1.2.1.1.2.1.2. PO Agreements
1.2.1.1.2.1.1. PO Placement
If PO negotiations with the supplier stumble, we Leverage existing PO agreements with prospective
could lose out of top-tier suppliers at a higher cost suppliers to reduce/eliminate negotiation time
If the material is out of stock or backordered by Place the PO within lead time to the purchase
more than 5 days, we will miss our finish date agreement terms and conditions
If the required software is not compatible with the Have IT perform a tech-check to ensure that the
existing PCs, the schedule could slip considerably necessary software are compatible