1) Executive summary………………………………………….
2) Project Charter. ……………………………………………….
3) Organization details. ……………………………………….
4) Scope statement/WBS. ……………………………………
5) Resource Breakdown Structure. ………………………
6) Risk Register. …………………………………………………..
7) Schedule. ………………………………………………………..
8) Project cash flow. ……………………………………………
9) Project Closure Remarks. ……………………………………………
Revision History
Date Description Author Version Comments
1
Executive summary
We are a pioneering technology leader that works closely with pharma, chemical,
agrochemical and food customers to create the future of industrial automation through
precision, innovation and customer insight. We design and deploy products and systems,
that are transforming manufacturing and process automation in globally sustainable ways.
Inspired by our legacy that spans across seven exciting decades, we continue to be driven
and defined by passion, perseverance and pursuit of perfection – to be problem solvers, risk
takers and true partners in the growth of all our stakeholders.
We are known for our values & employee friendly climate. However, the challenges are not
limited to the equipment they buy. Our solutions have to address their broader business
challenges: quality, people, efficiencies, ROI. When we propose a solution, our clients have
to feel comfortable that we know what we talking about and that we will give them the best
solution.
We have to know and understand processes, applications, and challenges. Our clients do not
want us to just build a mixer; they want us to know mixing. Similarly, we have to know
granulation, coating, drying and the other critical process unit operations. We learn their
entire process, the operating environment and all the factors affecting their manufacturing
operations.
2
Project Charter
BUSINESS CASE
PROJECT OBJECTIVES
KEY STAKEHOLDERS
PROJECT SUCCESS CRITERI
HIGH LEVELREQUIREMENTS
PROJECT RISKS
MAJOR MILESTONE
SUMMARY
BUDGET
HIGH-LEVEL ASSUMPTIONS, DEPENDENCIES AND CONSTRAINTS
ASSUMPTIONS
DEPENDENCIES
CONSTRAINTS
EXCLUSIONS
CORE TEAM & ORGANIZATION CHART
ASSIGNED PROJECT MANAGER
CORE TEAM
PROJECT SPONSER
STAKEHOLDER ANALYSIS
STAKEHOLDER REGISTER
Business Case
3
The project is about setting up of granulation suite at Aurobindo Pharma
(South Africa). Aurobindo Pharmaceutical being our old client the trust &
faith the client shows on us turn for repeatability of orders.
To deliver the 5-granulation line for South Africa project by 16th June 2020
compatible with SCADA (21 CFR part 11).
Project Objectives
• To manufacture the equipment as per the user requirement.
• To coordinate with internal team and meet the delivery timelines &
support their technically team to match their utility criteria.
• To create a user-friendly environment (Customer delight).
• To assist customers in resolving their queries related to online support
(SCADA) capture system through IT help-desk and technical support
(Customer Satisfaction).
Key Stakeholders
Technical Support Team (IT Support)
Documentation Team out sourcing if required.
Customer Engagement /awareness team.
PM Team
Project sponsors / Finance department
Procurement & Planning Team
Outsourced – IT Service Organization
External vendors: Manufacturers & Suppliers
Regulatory authorities
Auditors (Internal & External)
4
Project Success Criteria
To achieve the techno-commercial criteria & meet the delivery
timelines.
Liaising with expert vendors for the development of the SCADA system
linked with 21.
Milestones include set of tasks as per the timelines, achieving them on
time will meet the targeted delivery.
Repeatability of orders due the quality product & on time delivery up
roach.
Online technical support service will be added feature resulting in
uniqueness.
High-level Requirements
Business Requirements:
o To meet the client needs.
o Documentation to be as per regulatory norms.
o Customer should be able to purchase special printer which is
synchronized with software version for its audit trail & batch
report.
o Service should be reliable, secured, and easy to use.
Technical Requirements:
o The technical drawing & software version to be as per client
requirement (Validated plant).
o The technical parameters in the software to be followed as per
our requirement.
o The customer support should be available on time so that the
production of the client does not hamper.
5
Project Risks
Lead time for delivery of sub assembly parts.
Customer adaptability to the new requirement as per 21 CFR part 11
requirement.
Tight timeline should not hamper the quality of end product.
Major Milestones
Milestone 1: To achieve the technical approvals i.e. documentation & technical
drawing within 1-week time for the order release date.
Milestone 2: To coordinate with the internal team to achieve set task & the
delivery timeline i.e. 16 weeks from technical approval (16th June 2020).
Summary Budget
Summary Budget
INR _ Lakhs.
Factors/Considerations -
1. Complexity and the number of features in the granulation suite.
2. The manpower charge.
3. Technical document / drawing.
4. Development approach (up gradation in technology)
5. Number of platforms to be developed (SCADA etc.)]
6
High level constraints - Additional charges for development in SCADA
as per rising operator requirement.
High level dependencies – The available manpower to complete the
project.
Assumptions
Assumption Impact Strategy
Customers are tech-savvy. More customers will use the Promote SCADA system.
feature
Production batch are Efficient and effective Develop the system which is
successful. process of end product user friendly for order
(capsule). repeatability.
Dependencies
Dependency Impact Strategy
Software team The result of alarms, audit Visit the software house for
& batch report for timely update to maintain
production team. the timelines.
External Stakeholder Without the control panel, Encourage internal team to
AHU & scrubber we can’t pitch more for timeline.
execute the trails.
Constraints
Constraint Impact Strategy
Integration of new up Different platforms may Understand the user
gradation as pre-USER have security concerns as requirement & plan
requirement. well as higher turnaround accordingly to build a
time. software.
Charges for the Special Customer should get a Price the feature so that
Service reasonable trade-off customer feels the
between comfort and cost. advantage and company
also saves cost on process.
7
Exclusions:
Providing the requirement of client outside the scope.
Rising software changes after commissioning.
On-premise/Remote support.
Core Team
Project Sponsor
Mr. Ashish Banerjee & Mr. Subroto Banerjee – Business Partners & Directors.
Project Name – Manufacturing the granulation set-up for a R&D lab.
8
Project Scope Statement
We need to ensure all the required work and only the required work
necessary to complete till the project is accomplished. Any work that
does not support the needs of the project is out of scope & should not be
performed.
The scope statement will help us to make decision and the team can
communicate easy and also easy understanding for the stakeholders.
Daily updating the project status to client, if any delay reporting needed
ASAP to avoid the lag time.
9
Stakeholders:
Stakeholder Register: -
Dominant
Discretionary
Dangerous
Demanding
Core or Definitive
Dependent
Latent or Dormant
Non-Stakeholder
10
STAKEHOLDER ANALYSIS MATRIX
11
Auditors
SATISFIE
D Precise
Universal Ltd
engineering
Project sponsors
/ Finance
department Pilani
Customer
Procurement &
Engagement
Planning Team
/awareness team.
PM Team
Paras
Zabs Valves
Engineering
KEEP Technical
MONITOR
Documentation Support Team
(MINIMU INFORME
M Team D (IT Support)
EFFORT)
Outsourced – IT
Service
Organization
LOW HIGH
INTEREST
12
Organization Chart
13
To sound globally in pharmaceutical sector as a top manufacturer.
Being a reputed firm in manufacturing sector of pharmaceutical equipment's our main aim
is on time delivery of end product understanding the user requirement & urgency of
production at user end.
The finished product that we would deliver should provide us repeat order for
organizational growth.
However, the challenges are not limited to the equipment they buy. Our solutions have to
address their broader business challenges: quality, people, efficiencies, ROI.
When we propose a solution, our clients have to feel comfortable that we know what we
talking about and that we will give them the best solution.
We have to know and understand processes, applications, and challenges. Our clients do not
want us to just build a mixer; they want us to know mixing. Similarly, we have to know
granulation, coating, drying and the other critical process unit operations. We learn their
entire process, the operating environment and all the factors affecting their manufacturing
operations.
14
PLANNING FOR REVIEW ON PROJECT PLAN (MINDMAP)
Plan Review
Design approval.
Create O.A.
Invitation letter to all respected
Payment terms update.
authorities.
Complete conference review.
Verify date for other deliverables.
Provide PO.
Complete project plan
Email industry contacts.
Reserve resources
Send details to marketing Order exhibitor stands
Set up conference email address
Venue Procurement:
Identify suppliers
Send product specs
Receive quotes
AV Providers:
Shortlist suppliers Verify scope as per PO.
Select suppliers Check acknowledge/acceptance emails
Complete POs Send invites to email lists
Procurement/
Order summary review. Monitor the procurement flow w.r.t deadline:
Planning
Scope review. Client daily updates schedule planning.
Installation/engineer available Update resources received.
Timeline finalization. DQ, IQ & OQ date.
Create project plan. Work with marketing (if needed)
Evaluation if problem arise on Monitor documentation approval with stage wise flow.
Client conference date site.
confirmation. Project closure.
Closure date.
Overall review.
Project
Management
16
Cashflow in Project Management
The primary objective of the cash flow statement is to help management in taking a decision and making a plan
by providing current information on cash inflow and outflow of any accounting period.
A cash flow statement means statements relating to information regarding the inflow and outflow of cash.
Nowadays, in preparing financial statements, the cash flow statement is considered as an important element.
Generally, a cash flow statement is prepared for a particular period or a financial year.
Operations
Cash receipts from customers 693,200
Cash paid for
Inventory purchases (264,000)
General operating and administrative expenses (112,000)
Wage expenses (123,000)
Interest (13,500)
Income taxes (32,800)
Net Cash Flow from Operations 147,900
Communication plan
A communication plan is a policy-driven approach to providing stakeholders with information.
The plan formally defines who should be given specific information, when that information should be delivered
and what communication channels will be used to deliver the information.
The communication process is made up of four key components. Those components include encoding, medium
of transmission, decoding, and feedback. There are also two other factors in the process, and those two factors
are present in the form of the sender and the receiver.
Risk Register.
18
19
Work Breakdown Structure & Resource Breakdown Structure.
Work breakdown structure (WBS) is “a hierarchical decomposition of the total scope of work to be carried out by
the project team to accomplish the project objectives and create the required deliverables.” In the tree structure of
a WBS, project deliverables and activities are broken down into manageable parts, making it easier to estimate
required resources and costs, create a realistic schedule, and control each stage of a project. A work breakdown
structure is especially useful for bigger projects that involve many elements.
The representation of WBS & RBS is prepared via MS project software 2016.
20
Represented below is the RBS
Resource sheet:
21
Project Closure:
Timeline
22