To 17-06-2021

The Deputy Chief Engineer


Kerala State Electricity Board Ltd
Transmission System Operation, Kalamassery

Sir,
Sub- Request for extension of time limit for Completion of the Work”
Renovation of SLDC Office Building, Kalamassery.”

Ref:- WORK ORDER No. 28/2020-2021 Dated 28-01-2021


LETTER NO-CESO/TECH/TNMS/CIVIL/21-22/585 Dated 01-06-
2021

As per the above communication from your good office we are trying to
complete the work but due to the current pandemic situation we cannot
complete the above work on time, because of government restrictions,
shortage in availability of raw materials & Labour etc. So we humble request
your good office to grant us 60 days more time to complete the full work
and handover the site. We will assure that we will complete full work within
that period.

Expecting Yours Favorable Action


Yours faithfully
T P Subair