Agan Interior Design provides home and office decorating assistance to its customers.
In normal operation, an average of 2.5 customers arrive each hour. One design
consultant is available to answer customer questions and make product
recommendations. The consultant averages 10 minutes with each customer.
a. C
Poisson arrivals and exponential service times.
b. Se
an average of 5 minutes. Is this goal being met? If not, what action do you
recommend?
– The waiting time was greater than 5 minutes, thus the goal was not met.
Hence, the probable solution can be; first is to lessen the average time spent for
each customer, and second is to hire additional consultant.
c. If t
is the mean service rate? Will the service goal be met?
– The average service rate is 12 minutes; thus, the goal is still not met.
d. Sh
scenario.
– Yes, Agan should consider hiring a 2 nd consultant to lessen the time spent in
waiting and in also in their service.