Integrated wiring acceptance criteria

Project Manager
Device No Device Model
Full inspection & Methods of Defect
No Acceptance of the content and requirements Acceptance of result Remark
sampling Acceptance records
Test documentation, acceptance criteria, factory reports and other
0
preparation conditions have been ready
Data review □Yes □No □NA
Cable lashing acceptance criteria
Cable laying should naturally straight, shall not give rise to the
1 phenomenon of twisted, circular motion joints ,should not be subject to
external forces squeeze and damage.
Full inspection Visual □Yes □No □NA
The bunched cable must completely straightened out, there is not
2
crossover phenomenon which is obvious.
Full inspection Visual □Yes □No □NA
The bunched cable which laying on the cable tray and cabinnet
3
support should be a section of Circular or square
Full inspection Visual □Yes □No □NA
Excess cable tie required shear,spines is not allowed, avoid pricks
4 human or cable Full inspection Visual □Yes □No □NA
The position of the terminals of the power line must use the heat
5 shrinkable sleeve, ensure good insulation and beautiful appearance. Full inspection Visual □Yes □No □NA
Cabling acceptance criteria

1 Brand, type of integrated wiring should meet the bid requirements. Full inspection Visual □Yes □No □NA
2 The power socket can be inserted to power Full inspection Visual □Yes □No □NA
3 socket can avoid dust Full inspection Visual □Yes □No □NA
points corresponding table, test reports, system diagram consistent
4
with field
Full inspection Visual □Yes □No □NA
5 socket module must install the bottom box Full inspection Visual □Yes □No □NA
6 The the socket panel should be clearly identified; secured from fall off Full inspection Visual □Yes □No □NA
New hole in the wall after installation information panel, must
7 guarantee clean, without leaving the gap between the wall and the
panel.
Full inspection Visual □Yes □No □NA
Label acceptance criteria
Cable ends shall be fixed with a label ,shall be marked with a
1 number,The label should be used in difficult to damage, move off the
material,correct and accurate.
Full inspection Visual □Yes □No □NA
Each part of the system are set to the label by a unique identifier,
2
identifier label should be set to meet the design requirements.
Full inspection Visual □Yes □No □NA
Label paste should be consistent with the norms of the label types and
3
the label appearance is straight and neat.
Full inspection Visual □Yes □No □NA
Jacket cable should be earmarked identifier marked on the cable
jacket or jacket 300mm away from each end ,the termination point of
4
the cable should be set to private label with an identifier (100%
Full inspection Visual □Yes □No □NA
compliance)
Data room wiring acceptance criteria
The power cable and signal cable are laid on both sides of cabinet,and
1
bound on the support.
Full inspection Visual □Yes □No □NA
The rest should be hidden inside the cabinet except jumper joint part
2
on both ends.
Full inspection Visual □Yes □No □NA
3 The rack connection cable should accurately identify Full inspection Visual □Yes □No □NA
Supplier submit test reports of all information points, rectify the
Collected and file equipment
4 information points which do not meet the performance requirements
and give the reason
Full inspection Test Report □Yes □No □NA manufacturers commissioning reports

Wiring material brands meet the requirements of the tender, optical


Collected and file equipment
5 fiber connection test must meet all requirements (connectivity and
attenuation)
Full inspection Test Report □Yes □No □NA manufacturers commissioning reports

"The number of sampling network interface complies with the following


requirements, check the success rate of 100%
When the number of ports in the network within 500 requires sampling
Collected and file equipment
of 20% Test Report &
6
When more than 500 network port number to less than 10,000, you
Full inspection
Sampling □Yes □No □NA manufacturers commissioning
reports, and sampling
need to sampling 10%
When the network is greater than 10,000 more than the number of
ports needed sampling of 5%. "
Cable and fiber optic cable type, specifications and cable fire rating
7
should meet the design requirements.
Full inspection Visual □Yes □No □NA
Cable accompanying logo tag content should be complete, clear,
8 intact packaging should specify the models and specifications, cable
packaging and outer sheath is Intact.
Full inspection Visual □Yes □No □NA
Both ends of the optical fiber connecting devices face should be fitted
9 with a suitable protective cap. Fibre type should meet the design
requirements, and should be clearly labeled.
Full inspection Visual □Yes □No □NA
Cable laying should naturally straight, shall not give rise to the
10 phenomenon of twisted, circular motion, joint, should not be subject to
external forces squeeze and damage.
Full inspection Visual □Yes □No □NA
Cable should margin to accommodate the terminating detection and
change. Reserved length of twisted pair cable: in the work area should
be3cm ~~ 6cm ,the telecommunication room should be 0.5 ~ 2m, the
11 equipment should3m ~~ 5m; cable laying route should disk remain
and reserved length should be 3 ~~ 5m,if there is design
Full inspection Visual □Yes □No □NA
requirements ,should be reserved for the special requirements of the
length.
Unshielded four pairs of twisted pair cable bend radius should be at
12
least 4 times the diameter of the cable.
Full inspection Visual □Yes □No □NA
Four pairs of shielded twisted pair cable bend radius should be at least
13
eight times the cable diameter.
Full inspection Visual □Yes □No □NA
The trunk twisted pair cable bending radius should be at least 10 times
14
the cable diameter.
Full inspection Visual □Yes □No □NA
2-core or 4-core level of fiber optic cable bend radius should be
greater than 25mm; number of other core level fiber optic trunk cables
15
and outdoor fiber optic cable bend radius should be at least 10 times
Full inspection Visual □Yes □No □NA
the cable diameter.
The minimax distance is 10mm between twisted pair cable and
16
220VAC power cable
Full inspection Visual □Yes □No □NA
The minimax clear distance is 1m between cable and distribution box,
17 and 2m between cable and elevator、power room and air-conditioning Full inspection Visual □Yes □No □NA
room.
At the upper end of the vertical laying cable and at each interval of
1.5m vertical laying cables, cable trays should be fixed in the bracket
18
on the bridge; for horizontal laying cable , tail, corner, and each
Full inspection Visual □Yes □No □NA
interval at 5 ~ l0m should be fixed.
The cable should be bound in horizontal and vertical. Twisted pair
cable, fiber optic cable and other signal cable should be separately
bound according to the cable category 、number 、 diameter and
19
core number. The banding spacing should not be greater than 1.5m,
Full inspection Visual □Yes □No □NA
the spacing should be uniform, binding should not be too tight in order
to prevent cable damaged .
Terminating color should be consistent with the requirements of the
20 cable laying, the color should be consistent for termination point at
both ends of the cable olor
Full inspection Visual □Yes □No □NA
Pipe body of indoor metal pipe or plastic pipe should be smooth, no
21 scars and no distortion hole; pipe diameterand thickness shall meet
the design requirements (100% compliance)
Full inspection Visual □Yes □No □NA
Metal trays should be galvanized according to the project
22
environmental requirements. Plastic trays must be flame retardant
Full inspection Visual □Yes □No □NA
Various profiles of materials, specifications, models should be
23 consistent with the design documents, the surface should be smooth,
flat, without deformation and fracture.
Full inspection Visual □Yes □No □NA
All I/O's fluke test reports have been submitted, requiring all I/O to be
24
passed by the standard test of CAT6.
Full inspection Visual □Yes □No □NA
Is the damage to the building repaired? (a hole in the wall, a door, a
25
partition, etc)
Full inspection Visual □Yes □No □NA
Whether the site's garbage is cleaned up, the remaining material is put
26
up and handed over to the EEP HQ staff?
Full inspection Visual □Yes □No □NA

Acceptance Conclusion:

Representatives of
Date,
the construction compnay
Representatives of
Date,
the designment company

Representatives of
Date,
the implementation compnay
Cabinet installation project acceptance criteria
Project Manager
Device No Device Model
Full inspection & Methods of Acceptance of
No Acceptance of the content and requirements Remark Defect records
sampling Acceptance result
Collect the test document,
Device and system test document, acceptance criteria, the acceptance criteria, the factory
0 factory report and other preparation conditions have been ready Data review □Yes □No □NA report and installation manual
and other relevant documents
of the system
Cabinet installation inspection
Surface entire row of cabinets in the same plane, arranged neatly
1
close;
Full Inspection Visual □Yes □No □NA
2 Cabinet placement is consistent with the design drawings; Full Inspection Visual □Yes □No □NA
Cabinet ranks label is neat paste (if has the dashed box, must be
3
stuck in the dashed box)
Full Inspection Visual □Yes □No □NA
The cabinet surface and internal clean, no fingerprints, no dust,
4
no debris
Full Inspection Visual □Yes □No □NA
5 The floor gap around the frame should be blocked Full Inspection Visual □Yes □No □NA
The various parts of the cabinet and rack shall not be damaged
6
or, paint should not be shedding and scratches
Full Inspection Visual □Yes □No □NA
7 The cabinet and rack overall's grounding reliable connection Full Inspection Visual □Yes □No □NA
Cabinet installation on the wall must be safe and reliable.
8 Full Inspection Visual □Yes □No □NA
Cabinet internal inspection
Cabinet installation position is consistent with the design panel
9
diagram;
Full Inspection Visual □Yes □No □NA
The switch of front and rear door of the cabinet must be smooth,
10
not smooth on / off situation is not allowed;
Full Inspection Visual □Yes □No □NA
Whether the false panels and handle bar of the cabinets have
11
been installed
Full Inspection Visual □Yes □No □NA
12 The ground wire of cabinet door is connected reliable Full Inspection Visual □Yes □No □NA
Rack inlet and outlet should be closed strictly in accordance with
13
the cabinet instructions;
Equipment installation location inside the Cabinet is reasonable,
Full Inspection Visual □Yes □No □NA
easy to maintain. equipment installation firm .
14 Full Inspection Visual □Yes □No □NA
Check the cable inside the cabinet
Cabinet grounding cable and the line nose of power cable
compliant production specification. The joint portion must be
15
covered by the heat shrink tubing,and don't allowed to appear
Full Inspection Visual □Yes □No □NA
naked head of copper;
The line deduction of lashing cable must be cut square, leaving
16
no tip;
Sampling 10% Visual □Yes □No □NA

Acceptance Conclusion:

Representatives of
Date,
the construction compnay

Representatives of
Date,
the designment company

Representatives of
Date,
the implementation company
UPS Acceptance Criteria
Project Manager
Device No Device Model
Full inspection & Methods of
No Acceptance of the content and requirements Acceptance of result
sampling Acceptance
Equipment and system test documentation, acceptance criteria,
0
factory reports and other preparation conditions have been ready
Data review □Yes □No □NA
Inastallation Check
UPS equipment is clean, neat installation, connections are secure,
maintain space compliance with the design's requirements, UPS is
1
fixed on the basis of a screw.
Full inspection Visual □Yes □No □NA
Specifications and models of the UPS rectifier device, inverter
2
and static switching device accord the design's requirements
Full inspection Visual □Yes □No □NA
UPS cable and screw fastening, cable insulation layer without
3
damage
Full inspection Visual □Yes □No □NA
The accessible bare conductor of UPS shall be reliably grounded
4
(PE) or zero (PEN), and marks
Full inspection Visual □Yes □No □NA
Performance Check
The input and output phase sequence between the machines are Phase sequence
5
consistent
Full inspection
analyzer □Yes □No □NA
The resistance between each phase and active insulation
6
resistance of UPS should be greater than O.5MΩ
Full inspection Megger □Yes □No □NA
Technical parameters of UPS input, output voltage, frequency and
7
so on ,can accord product and design's requirements
Full inspection Test □Yes □No □NA
The switching time and switching action between the mains
8 electricity with bypass accord the product and design's
requirements
Full inspection Test □Yes □No □NA
The switching time and switching action between the mains
9 electricity with battery accord the product and design's
requirements
Full inspection Test □Yes □No □NA
The performance monitoring of local and remote interface are
10
normal
Full inspection Test □Yes □No □NA
UPS alarms including UPS online, a summary report of alarms,
battery discharge, bypass with load, static switch failure , inverter
11
failure, input breaker failure, output breaker failure, battery breaker
Full inspection Test □Yes □No □NA
failure, and so on. All of them work normal.

12 UPS parallel logic meet the requirements of design Full inspection Test □Yes □No □NA
Test report /
13 UPS steady running state meet the requirements of the customer Full inspection
factory report □Yes □No □NA
UPS transient running state meet the requirements of the Test report /
14
customer
Full inspection
factory report □Yes □No □NA

Acceptance Conclusion:

Representatives of
the construction company

Representatives of
the designment company

Representatives of
the implementation company
Defect
Remark
records

Mainly to verify the installation, wiring


and so on is correct.

Mainly to verify the installation, wiring


and so on is correct.

Mainly to verify the installation, wiring


and so on is correct.

Mainly to verify the installation, wiring


and so on is correct.

Mainly to verify the installation, wiring


and so on is correct.
Mainly to verify the installation, wiring
and so on is correct.

Mainly to verify the installation, wiring


and so on is correct.

Mainly to verify the installation, wiring


and so on is correct.

Mainly to verify the installation, wiring


and so on is correct.

Mainly to verify the installation, wiring


and so on is correct.

Date,

Date,

Date,
Battery System Acceptance Criteria
Project Manager
Device No Device Model
Full inspection & Methods of Acceptance of
No Acceptance of the content and requirements Remark
sampling Acceptance result
Equipment and system test documentation, acceptance criteria, factory
0
reports and other preparation conditions have been ready
Data review □Yes □No □NA
Inastallation Check

1 The batteries should be placed neatly in the battery racks Full inspection Visual / Measure □Yes □No □NA
2 The battery racks shoud be installed firmly Full inspection Visual / Wrench □Yes □No □NA
The capacity, quantity, specification and type of battery should meet the Visual /
3
requirements of design.
Full inspection
Factory report □Yes □No □NA
4 Cosmetic defects of batteries are not allowed. Full inspection Visual □Yes □No □NA
The positives and negatives should be connected correctly and with obviously
5
indentification .
Full inspection Visual □Yes □No □NA
The copper bars with insulation protection should connect batteries firmly
6
and reliably.
Full inspection Visual □Yes □No □NA
Performance Check

7 The voltage of battery should meet the requirement of design. Full inspection Test □Yes □No □NA Mainly to
verify the
Equal charge and floating charge performances should meet the need of Test report /
9
costomer.
Full inspection
Factory report □Yes □No □NA installation,
wiring and so
on is correct.
Test report /
10 Discharge performances should meet the need of costomer. Full inspection
Factory report □Yes □No □NA

Acceptance Conclusion:
Representatives of
Date,
the construction compnay

Representatives of
Date,
the designment company

Representatives of
Date,
the implementation company
Defect
records
AC Acceptance Criteria
Project
Device No

No

0
Indoor unit Inastallation Check
1
2 Cabinet
3
4
5 EC fan
6
7
8
Wet film
9
Humidfier
10
11
12
Compressor
13
14 Condensate
15 pump

16
Liquid level
17 detector
18
19 Water pan

20
Differential
pressure switch
21
22 Air filter
Outdoor unit Inastallation Check
1 The appearance is intact and free from scratches and paint flake-off
1 All fasteners are properly installed without stripping .The devaition of the screw locking force is wit hin ±10%
2 All cables are properly routed and all fixing points are scured .

3 The heat exchanger and pipes are in good condition .The heat exchanger fins are not pushed down.sufficient
solder is applied to the soldering points
4 All lables are peoperly attached to the specified area and free from devaition ,bubbles uneveness or dirt
5 The rotational direction , speed , and current of the fans are normal and no abnormal vibration or noise during
running
Pipeline inastallation Check
1 Ports are connected correctly. The pipelines have oil trap, inverted traps, gradients (of refrigerant pipes), and
pipe supports
2 The hose clamps and cable ties of the condensate water pipe are reliabely secured
3 All pipes are secured reliably and steadily
4 All pipes are wrapped with thermal insulation foam, and the insulation foam is intact
5 The water pipe joints are sealed by sealant
6 Check that the needle valve plug is secured (torque of 0.45±0.05 N•m), and valve bonnet is tightened
7 The pipes are not seriousy bent
Electrical inastallation Check
1 Cables are intact and not over-bent
2 No open or short circuits, or incorrect connections occur in electrical loops
The power cables for the indoor and outdoor units, signal cable, teamwork cable, and T/H sensor cable are
3
connected as required
4 The rated specifications of the upstream general circuit breaker meet the maximum current requirement
5 All cables, connectors, and screws are secured
6 Devices are properly grounded

Acceptance Conclusion:
AC Acceptance Criteria

Acceptance of the content and requirements

Equipment and system test documentation, acceptance criteria, factory reports and other preparation
conditions have been ready
Indoor unit Inastallation Check
The cabinet is installed properly, without any tilts
The cabinet is secured to the bottom base using bolts as required
The foreign matter inside the cabinet such as cable ties and stubs is cleaned up
The fan is secured
The fan has no foreign material inside
The fan blades rotate properly
The water inlet solenoid valve is secured reliably and steadily
The humidifier water pump is secured reliably and steadily
The wet film is secured reliably and steadily
The humidifier float is secured. The fasteners for the humidifier float are secured
Water inlet pipes are connected securely without leaks
The sheet metal for transporting the compressor is removed
The bolts on the compressor are tightened
The water inlet pipes and drainpipes of the water pump are securely connected without leaks
The condensate pump is securely connected to its base
The liquid level detector is secured
The fasteners for the liquid level detector are secured
The low liquid level detector functions flexibly
The foreign matter inside the water pan is cleaned up, and water pan filter is not blocked

The cable ties on the differential pressure tubes are secured

There is no foreign matter in the differential pressur tubes.The differntail pressure tubes ar
enot seriously bent
The air filter is correctly installed according to the air flow direction on the frame
Outdoor unit Inastallation Check

ppearance is intact and free from scratches and paint flake-off

steners are properly installed without stripping .The devaition of the screw locking force is wit hin ±10%
bles are properly routed and all fixing points are scured .

eat exchanger and pipes are in good condition .The heat exchanger fins are not pushed down.sufficient
r is applied to the soldering points

bles are peoperly attached to the specified area and free from devaition ,bubbles uneveness or dirt
otational direction , speed , and current of the fans are normal and no abnormal vibration or noise during
ng
Pipeline inastallation Check
are connected correctly. The pipelines have oil trap, inverted traps, gradients (of refrigerant pipes), and
supports
ose clamps and cable ties of the condensate water pipe are reliabely secured
pes are secured reliably and steadily
pes are wrapped with thermal insulation foam, and the insulation foam is intact
water pipe joints are sealed by sealant
k that the needle valve plug is secured (torque of 0.45±0.05 N•m), and valve bonnet is tightened
ipes are not seriousy bent
Electrical inastallation Check
s are intact and not over-bent
pen or short circuits, or incorrect connections occur in electrical loops
ower cables for the indoor and outdoor units, signal cable, teamwork cable, and T/H sensor cable are
ected as required
ated specifications of the upstream general circuit breaker meet the maximum current requirement
bles, connectors, and screws are secured
es are properly grounded

ce Conclusion:

Representatives of
the construction company

Representatives of
the designment company

Representatives of
the implementation company
nce Criteria
Manager
Device Model

Full inspection & sampling Methods of Acceptance Acceptance of result Remark Defect
records

Data review □Yes □No □NA


tallation Check
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA

Full Inspection visual □Yes □No □NA

Full Inspection visual □Yes □No □NA

Full Inspection visual □Yes □No □NA


stallation Check

Full Inspection visual □Yes □No □NA

Full Inspection visual □Yes □No □NA


Full Inspection visual □Yes □No □NA

Full Inspection visual □Yes □No □NA

Full Inspection visual □Yes □No □NA

Full Inspection visual □Yes □No □NA


llation Check
Full Inspection visual □Yes □No □NA

Full Inspection visual □Yes □No □NA


Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
Full Inspection visual □Yes □No □NA
allation Check

Date,

Date,

Date,