Professional Documents
Culture Documents
Project Proponent:
Environmental Consultants:
April, 2016
Environmental Impact Assessment for the proposed 5 x 800 MW Supercritical coal based Yadadri Thermal
Power Station at Veerlapalem village, Damarcherla Mandal, Nalgonda district, Telangana by M/s Telangana
State Power Generation Corporation Limited
Executive Summary
1.0 INTRODUCTION
The proposed project falls under ‘Category A’ of the EIA Notification, 2006 and
requires preparation of EIA report to obtain Environmental Clearance (EC) from the
MoEF&CC, GoI, New Delhi. The project proposal was considered by the Expert
Appraisal Committee - Thermal Power (EAC) in its 45th, 48th & 50th Meetings of the
EAC (Thermal Power) held during 29th - 30th October, 2015, 18th December, 2015
and 29th January, 2016.
Subsequently, the EAC, MoEF&CC, GoI, New Delhi has issued Terms of Reference
(ToR) vide letter No. J-13012/18/2015 - IA. I (T) dated 16th February, 2016 for
conducting EIA studies. The EIA studies were carried out as per the Standard ToR of
MoEF&CC Notification dated 10th April, 2015. The draft EIA report has been
prepared based on the ToR conditions for conducting Public Consultation, including
Public Hearing meeting. The final EIA will be submitted to MoEF&CC after
incorporation of deliberations of public hearing to obtain the EC.
The present proposal is to set up (5 x 800 MW) Super Critical Coal Based Yadadri
Thermal Power Station at Veerlapalem village, Damarcherla Mandal, Nalgonda
district, Telangana state. The coal requirement for the proposed power project based
on station heat rate of 2109.40 kcal/kwh, GCV of coal as 4550 kcal/kg and 85% PLF
is estimated as 13.81 MTPA. In line with the MoEF&CC guidelines for new Thermal
Power Projects, it is proposed to adopt closed circuit cooling water system deploying
natural draft cooling towers and draw only make up water requirement from the
source. The makeup and consumptive water requirement assessed as 9755 m3/hr
and will be sourced from Krishna river. The proposed site comprises of 75 % of
Three 275 m high stacks out of which two are double flue and one is single flue, will
be provided for the quicker and wider dispersion of the gaseous emissions with proper
control measures to minimize the stack emissions within the stipulated/permissible
limits prescribed by NAAQS.
The salient features of the project site are given in Table-1 and the salient features of
the power plant project are given in Table-2.
Item Description
(100 km) and State Highway No. 2 connecting
Hyderabad and Addanki.
Distance from highway 7 km
Environmental Sensitivity
Water bodies Krishna River about 3 km
Plant area falls under forest area and partly in
Forest Area patta lands. Forest Clearance is obtained vide Lr.
No. F.No. 8-07/2015-FC, dated: 7th July 2015.
Sanctuaries / National Parks None within the study area
Archaeological/ Historically None within the study area
Important Site
Seismic zone Seismic Zone – III as per IS 1893 (Part 1) 2002
Source: EIA studies, BALPL
The total extent of land for establishment of proposed power project is 2800 Acres
(Forest land is Ac. 2095.28 Gts, Patta Land, Government Land, Udfa patta Land and
D-Patta Land etc is Ac. 704.12 Gts). The proposed site comprises of 75 % of reserve
forest land and remaining land is mostly non-agricultural, uninhabitated, partly
agricultural, revenue land with isolated pockets of habitation. There are no historic
places in the vicinity. Plant area falls under forest area and partly in patta lands.
Forest Clearance is obtained vide Lr. No. F.No. 8-07/2015-FC, dated 7th July 2015.
The baseline study for the project was carried from 1st December, 2015 to 5th March
2016 as per the Standard ToRs published by MoEF&CC, GoI, New Delhi. The study
area for the primary field data collection for baseline studies has been considered as
10 km radius from the proposed project area as per EIA Notification, 2006. The
general location map of the proposed project is given as Figure 1 and the study area
map is given as Figure 2. The recent photographs of the site are provided in Figure
3.
The results were compared with NAAQS standard issued by MoEF&CC vide
Notification G.S.R 826 (E) dated 16th November, 2009 for Industrial, Residential,
Rural and Other Areas.
Particulate Matter: The PM10 concentration range was 19.9 – 66.4 µg/m3 for 24
hourly averages while PM2.5 concentration levels were in the range of 6.4 µg/m3
during the study period. At all ambient air quality locations, the PM10 and PM2.5 levels
recorded are within the prescribed standards of 100 µg/m3 and 60 µg/m3
respectively.
Not to scale
Figure 1: General Location Map of the Project Site
Executive Summary
Executive Summary
Gaseous Pollutants: SO2, NOx and NH3: The SO2, NOx and NH3 concentrations
were observed in the range of 5.1 – 24.6 µg/m3, 9.1 – 28.1 µg/m3 and 14.0-34.6
µg/m3 during the study period.
Ozone: The 8 hourly observed concentration of ozone ranged between 11.8 to 48.1
µg/m3, which were below the stipulated NAAQS.
Arsenic (As): Arsenic was not detected in the particulate matter of samples collected
during the season.
Nickel (Ni): Nickel was not detected in the particulate matter of samples collected
during the season.
The ambient noise level monitored during the season for residential, commercial,
industrial and silence zones revealed the following:
During the season, the noise level in the residential area during day time is ranging
between 48.8 - 51.2 dB(A) and the night time values are 40.8 – 44.1, which is below
CPCB range. In Commercial area, such villages Wazirabad, Adavi devulappalli and
Dameracherla have shown the maximum value of 62.3 dB(A) during day and 54.4 at
night. The CPCB value for commercial areas during day is 65 dB(A) and at night is 55
dB(A).
In Industrial areas, the maximum noise level value at the industrial area was 65.2
dB(A) which is below 75 dB(A) of CPCB standard. During night the value was 56.5
dB(A) safely below the CPCB value of 70 dB(A) during the study period.
In Silence zones, during day the maximum value recorded was 48.9 dB(A) at primary
school, Ragadappa. The night time maximum value was 39.7 dB(A) at Virappagudem.
Surface and ground water samples have been collected, analysed and analysis results
indicate no industrial contamination in this region. Physical parameters of water quality
for the studies carried out during the study period and the observations made are
discussed below:
Executive Summary
During the winter season, the analysis results indicate that the pH ranges in between
7.57 to 8.07, which is well within the specified standard of 6.5 to 8.5. Total Dissolved
Solids (TDS) concentrations were found to be ranging in between 492 to 772 mg/l.
During the season, the Total alkalinity and Total hardness is observed in between 115
to 250 mg/l and 145 to 380 mg/l respectively. Chlorides and Sulphates are observed to
be between 120 to 125 mg/l and 97 to 164 mg/l.
During the season, the Nitrates and Dissolved Oxygen observed in between 0.5 to 0.8
mg/l and 6.8 to 6.7 mg/l.
During the study period, the analysis results of ground water samples indicate that the
pH value was observed in between 7.57 to 8.35, Total Dissolved Solids levels were
observed as 492 mg/l near project site and high values of 968 mg/l near Veerlapalem
village.
During the winter seaon, the Total alkalinity and Total hardness is observed in between
115 to 375 mg/l, 145 to 480 mg/l. Chlorides and Sulphates are observed to be between
118 to 182 mg/l and 93 to 184 mg/l.
During the season, the Total Nitrates were observed in between 0.5 to 0.80 mg/l and
no traces of Dissolved Oxygen is observed. Oil & Grease is observed to be <1 mg/l.
The ground water quality conforms to drinking water standards IS : 10500 — 2003 (in
the absence of alternate source) with respect to physico-chemical parameters.
It has been observed that the pH of the soil ranged from 7.56 – 8.68 indicating that
the soils are neutral to alkaline in nature. The soil in the study area is predominantly
of sandy loam type. The Electrical Conductivity was observed in the range of 144-
683 S/cm.
The Nitrogen and Phosphorous values are in the range of 98-540 kg/ha and 10-20
kg/ha respectively. The Nitrogen and Phosphorous levels of the soils in the region
indicate that soils are sufficient for Nitrogen and less for Phosphorous levels. The
Potassium values range between 210-2832 kg/ha, which indicate that the soils have
sufficient quantity of Potassium. The soil from the study area shows good fertility due
to their NPK content.
Executive Summary
Using the standard land use classification system proposed by NRSC, five classes of
level I, eighteen of level II land use/land cover classes were identified and mapped
using satellite data in the present study. Subsequently land use/land cover map of
the study area was digitally composed in Arc View module and the final area
statistics was worked out and presented in Table 3.
Flora and fauna studies were conducted during study period to assess the existing
floristic and faunal components in study area. Core zone involves three forest
patches namely, Veerlapalem RF, Dilawarpur RF and Gangadevi Gattu RF. The
forest area consists of Southern Tropical Dry deciduous scrub forest and Thorny
forests of type 5A/C3/DS1 and 6A/C3/DS1. There are no any endangered/ rare /
unique species of flora and fauna in these Reserve Forests.
Overall 215 flora species has been reported from the buffer zone of the study area.
54 faunal species have been reported from the buffer zone which includes 25
species of birds, 10 species of mammals and 19 species of herpetofauna.
Executive Summary
Operation Phase
o Air Environment
The incremental concentration of the pollutants has been predicted using AERMOD
Version 8.2 dispersion model. The maximum incremental short term 24 hourly ground
level concentrations for Particulates, SO2, NOx and PM likely to be encountered
during the winter season are 6.77, 6.77 and 2.03 g/m3 respectively. The predictions
indicate that the PM, SO2, NOx concentrations are likely to be well within the prescribed
limit for residential and rural zone.
o Water Environment
The wastewater generated in the plant area will be utilized in various activities such
as ash/coal handling, fly ash conditioning, ash disposal, service water and greenbelt
development. The waste water emanates from the cation resin units in DM Plant are
generally acidic in nature and from the anion resin units are alkaline in nature. The
combined wastewater from the DM plant would be neutralised in a neutralising pit.
Executive Summary
The neutralized wastewater is expected to have suspended solids less than 5 ppm
and pH in the range of 6.5 to 8.5. This will also be led to the CMB.
The storm water in the project area will be collected through storm water drains and
Rain Harvesting System will be provided.
The main solid waste from the power plant complex will be the ash (fly ash and
bottom ash). The total ash generation from the proposed power plant will be about
3.9 MTPA. Out of this, the bottom ash will be about 0.59 MTPA and balance 2.37
MTPA will be fly ash. As per fly ash Notification, will be utilized 100% of the fly ash
generated from the proposed power plant by supplying to major cement Companies
located at a distance of about 200 km from the project site. Ash Management Plan
will be developed for 100 % utilisation of fly ash within the time period prescribed by
MoEF&CC. In ash disposal, HCSD method will be adopted. The ash will be conveyed
by pipeline to ash dyke in High concentration slurry form. The wastewater from the
guard pond will be sprinkled continuously to prevent fugitive dust. Under normal
condition there will not be water discharge from ash pond.
o Noise Environment
Acoustic enclosures will be provided wherever required to control the noise level
below 85 dB (A). Anywhere not possible technically to meet the required noise levels,
personal protection equipment will be provided to the workers. The wide greenbelt
around the plant will attenuate the noise level dissemination outside the plant
boundary.
o Greenbelt Development
Greenbelt of total 1225 acres will be developed in and around the plant site. In the
proposed greenbelt, trees will be planted with a density of 2500 trees/ha.
o Socio- Economics
The major economic impacts, which will accrue to the region, during the construction
phase and operation of the power plant, will be an increased availability of direct and
indirect employment. Local people will be benefited after commissioning of the
proposed project in terms of petty to major contractual jobs and associated business
establishments. Local youth will be given preference in employment during
construction and operational phase on the experience and qualification. In addition to
that several avenues of employment generation will be created due to proposed
power project.
Executive Summary
Ambient air quality monitoring on bi-weekly, 24 hours basis in the plant area and
in the surrounding villages;
Source emissions will be monitored on monthly basis. Automatic continuous
online monitoring system shall be installed in the stacks;
Water quality monitoring at surface water bodies and ground water in the
surrounding villages will be identified and monitored on the monthly basis;
All the effluents emanating from the plant should be monitored monthly for physio-
chemical characteristics. Heavy metals would be monitored on a quarterly basis.
Temperature of the hot water discharge should be monitored on hourly basis daily.
Similarly, the temperature at the discharge point in the drain should be monitored
on fortnightly basis;
The noise levels will be recorded in and around plant. The noise levels at
boundary of the plant will be recorded on monthly basis;
The soil quality will be monitored on six monthly basis for the fertility of the soil;
All the results will be compiled and thoroughly analyzed to assess the
performance of the power plant; and
The results will be reported on regular basis to the Regional office of MoEF&CC
and Telangana State Pollution Control Board (TSPCB).
Detailed risk assessment and disaster management studies have been carried out
and details are presented in the EIA report. Separate Hydro-geological study has
been undertaken by TSGENCO, summary of which is incorporated in the EIA report.
The detailed R&R study has been conducted and R&R award passed by the District
Collector, Nalgonda. An amount of Rs 285.81 Crores toward land compensation,
R&R package and other charges was deposited with District Collector, Nalgonda on
4th January 2016 towards an extent of Acres 854-32 Guntas of Patta land and Acres
920-25 Guntas of ROFR land. An amount of Rs. 198.59164 Crores was paid towards
cost of NPV of forest land and raising maintaining compensatory afforestation to an
extent of 4676 acres.
Executive Summary
In operation phase, the proposed project would require significant workforce of non-
technical and technical persons. Migration of persons with better education and
professional experience will result in increase of literacy in the surrounding villages.
During construction phase, the construction activities like site levelling, grading,
transportation of the construction material cause various impacts on the surroundings.
The activities like site development, grading and vehicular traffic contribute to increase
in PM and NOx concentration. The mitigation measures proposed to minimize the
impacts are:
The wastewater from vehicle and construction equipment maintenance centre will
contribute to oil and grease concentration. The mitigation measures proposed to
minimize the impacts are:
Executive Summary
Ecological Management
During operation phase, the impacts on the various environmental attributes should be
mitigated using appropriate pollution control equipment. The Environment Management
Plan prepared for the proposed project aims at minimizing the pollution at source.
Stack emissions from the proposed power plant will contribute to increase in
concentrations of NOx. The mitigative measures proposed in the plant are:
The project will source its entire water requirement from the Krishna river. The total
water requirement for the project is 9755 m3/hr. The project will not extract groundwater
and hence there will be no impact on ground water.
The wastewater generated in the plant area will be treated in the Effluent Treatment
Plant (ETP) and part of the wastewater will be utilized in various activities such as
cooling water make up, ash/coal handling, ash disposal, and service water and
greenbelt development. No discharge is envisaged into any surface river water
Bhagavathi Ana Labs Pvt Ltd (a Bureau Veritas Group Company)
Report Reference : IND.BH.41.15.0019/HSR 16/18
Environmental Impact Assessment for the proposed 5 x 800 MW Supercritical coal based Yadadri Thermal
Power Station at Veerlapalem village, Damarcherla Mandal, Nalgonda district, Telangana by M/s Telangana
State Power Generation Corporation Limited
Executive Summary
In the process, various equipment like pumps, cooling towers etc generate the noise.
The recommendations to mitigate higher noise levels are:
The ash generated in the plant will be supplied to identified cement industries for
consumption. The ash generated in the plant will be utilized in the brick/ cement
manufacturing industries to achieve 100% ash utilization as per Fly Ash Notification.
There are about 22 cement industries around proposed power plant site. Ash will be
issued to them for manufacturing of the cement as per their requirement.
The Sludge from sewage treatment plant will be dried and used as manure for
greenbelt maintenance. Canteen/sanitary waste will be composted and used as
manure for greenbelt development.
With the implementation of above precautionary measures, the impacts due to solid
waste disposal are insignificant on environment.
Executive Summary
9.0 SUMMARY
The proposed power project has marginal impacts on the local environment.
However, development of this project has certain beneficial impact/effects in terms of
bridging the electrical power demand and supply gap and providing employment
opportunities that will be created during the course of its setting up and as well as
during the operational phase of the project.