Professional Documents
Culture Documents
Project Brief
(Autumn 2021)
You will need to submit the report, all associated (Microsoft Excel) spreadsheets and
all HEC-HMS files. Submissions is via Turnitin in vUWS. Make only one submission
per team. If multiple submissions are made, only one of these submissions will be
selected at random and marked. Submission will be via Turnitin in vUWS.
Use the average of the last digits of your team members’ student ID to determine the
catchment to be used for the project.
For example,
• if the IDs of your team members are 12345678, 23456789 & 34567890, the
!"#"$
average of the last three digits is . % / = 5.67. Use catchment B for your
team project.
• If the IDs of your team members are 34567891, 56738491, 33567885 &
&"&"'"&
123454321, the average of the last four digits is . ( / = 2. Use catchment
A for your team project.
Estimates of all areas of the catchment can be made using either a software of your
choice or any other standard engineering method you are familiar with, including the
grid approach. An approximate estimate suffices - use the scale shown in the figure
(each grid is 1km x 1km) for estimation.
1
Catchment A
1000m
3 sub-catchments
1, 2, & Outlet are outlets of
the three sub-catchments
Centroid of the catchment
is at:
o
150 35’ E Longitude
o
33 35’ S Latitude
Catchment B
1000m
3 sub-catchments
1, & Outlet are outlets of
the three sub-catchments
Centroid of the catchment
is located at:
o
150 33’ E Longitude
o
33 31’ S Latitude
2
Catchment C
1000m
3 sub-catchments
1, & Outlet are outlets of
the three sub-catchments
Centroid of the catchment
is at:
o
150 35’ E Longitude
o
33 32’ S Latitude
Background
The project has been formulated to allow you to determine the differences in
catchment responses before and after development. The catchment currently is
undeveloped and one of the three sub-catchments is proposed for development. It is
up to your team to decide which sub-catchment you want developed. You will need
to identify the sub-catchment for development in your report.
Please note that the project has been formulated step-by-step (each task identified),
the final report will need to be in a technical report format.
3
Use the ARR Data Hub web site (https://data.arr-software.org/) to generate total
rainfall hyetograph for the storm generated in the above step. You will need to
include the total rainfall hyetograph, both table and histogram, in your report.
Extract the initial and constant loss values from the ARR Data Hub web site. Make
necessary adjustments and construct the rainfall excess hyetograph. You will need
to explain how you achieved your result and include this in your report. Graphical
representation suffices here.
For post-development condition, assume that both the initial loss and continuing
loss will be reduced by 50% for the sub-catchment you’re proposing to develop.
Remember you’re developing only one of the three sub-catchments, therefore loss
values and rainfall excess will change only for one sub-catchment.
You may then be required to convert thus generated 15-min unit hydrograph to
another duration unit hydrograph to meet the time interval of the rainfall excess
hyetograph. You may need to follow S-hydrograph method to achieve this
outcome.
Use of spreadsheet will save considerable time, as the process involves repetitive
computations. You will need to include your spreadsheet.
A 15-minute unit hydrograph for a catchment of 6km2 is given in the table below.
Time
(min) 0 5 10 15 20 25 30
Discharge
(m3/s) 0 0.54 1.76 3.28 3.75 3.36 2.55
Time
(min) 35 40 45 50 55 60 65
Discharge
(m3/s) 1.59 1.05 0.72 0.48 0.32 0.21 0.14
Time
(min) 70 75 80 85 90 95 100
Discharge
(m3/s) 0.09 0.06 0.04 0.03 0.02 0.01 0
Use the above 15-minute unit hydrograph to compute ordinates of the 15-min unit
hydrographs for your sub-catchments using the catchment area as the scaling factor.
4
For example, if the area of your sub-catchment is 3km2, each ordinate given in the
above table will be half of what’s listed. The resulting 15-minute unit hydrograph will
look like,
Time
(min) 0 5 10 15 20 25 30
Discharge
(m3/s) 0 0.27 0.88 1.64 1.875 1.68 1.275
Time
(min) 35 40 45 50 55 60 65
Discharge
(m3/s) 0.795 0.525 0.36 0.24 0.16 0.105 0.07
Time
(min) 70 75 80 85 90 95 100
Discharge
(m3/s) 0.045 0.03 0.02 0.015 0.01 0.005 0
Similarly, if the area of your sub-catchment is 12km2, each ordinate will be double of
what’s listed in the table. The resulting 15-minute unit hydrograph will look like,
Time
(min) 0 5 10 15 20 25 30
Discharge
(m3/s) 0 1.08 3.52 6.56 7.5 6.72 5.10
Time
(min) 35 40 45 50 55 60 65
Discharge
(m3/s) 3.18 2.10 1.44 0.96 0.64 0.42 0.28
Time
(min) 70 75 80 85 90 95 100
Discharge
(m3/s) 0.18 0.12 0.08 0.06 0.04 0.02 0
Note that you may need to generate up to 3 unit hydrographs (this will depend on the
areas of each sub-catchments).
Construct Dt-hr unit hydrograph (where Dt-hr is the time step of rainfall excess
hyetograph) from the 15-minute unit hydrographs generated for your sub-catchments.
You will need to use the S-hydrograph method to achieve this. You will need to explain
the process you followed in your report. Make sure to verify your results by checking
volumes after each computation.
5
Task 4. Construction of storm hydrographs
Construct the storm hydrograph for each sub-catchment using rainfall excess
(task 2) and respective Dt-hr unit hydrographs generated above (task 3). The 3
storm hydrographs you’ve generated are the responses at the outlet of respective
sub-catchments for the catchment in natural condition. Let us call it pre-
development storm hydrographs.
Your team will require to extract channel properties for routing the hydrographs
through channels using Muskingum routing method. For this, assume the
following.
Your team will need to discuss how you obtained these, include sample
calculations and show the final result (both table and figure). All computations will
be performed using a spreadsheet and the spreadsheet will also need to be
submitted.
6
Your team will then need to construct Dt-hr unit hydrograph (post-development)
for the sub-catchment being developed and use this to generate post-
development catchment response.
You will then need to propose a solution that will ensure that the peak of the post-
development hydrograph at the outlet does not exceed the peak of the pre-
development hydrograph at the outlet. You may have to design a reservoir
incorporating outlet structures to achieve this. If you’re to use this approach, you
will need to route the post-development hydrograph through the reservoir.
You will need to discuss your strategy, provide the size of the reservoir and the
details of outlet structures in your report.