Professional Documents
Culture Documents
Cost Engineering - L2
Cost Engineering - L2
CB 712 – E
By
Dr. Emad Fayez Gaid
Lecture 2
In small scope projects cost estimating and budgeting are very closely
linked and considered as a single process that can be performed by a single
person.
4/24/2021 Project Cost Engineering -CB 712-E -Dr. Emad Fayez 3
Cost Estimating
4
4/24/2021 Project Cost Engineering -CB 712-E -Dr. Emad Fayez
Cost Estimating
and during the preparation of the cost baseline detailed estimates are used.
summed to estimate the cost of the WBS work element. Costs are then
usually rolled up to estimate the total project cost in a manner like bottom-
estimated and rolled up, thus this method provides higher accuracy as
Pre-tendering Stage
Estimates in the pre-tendering stage are usually conducted for the owner
by owner’s staff and/or the consultant. With the initial stages of the
project, the owner needs to conduct a feasibility study and set a budget for
the project, even before any schematic designs are prepared. Conceptual
Tendering Stage
complete and submit a bid for the project, where a Detailed estimate
prepared.
Construction Stage
construction.
The output of the estimating process, may be used for many purposes such
as:
Parametric Method
costs.
Pricing, on the other hand, is adjusting the costs that have been applied for
specific project conditions, and commercial terms. Pricing includes
adjustments to cost to allow for overhead and profit, to improve cash flow.
The price reflected by a bid will include not only direct costs, but also an