Professional Documents
Culture Documents
Desk Engineer/Field
7 Ensure to isolate CPU O/L Oxygen dosing MIV at 3 mtr 3 mtr Engineer
Desk Engineer/Field
8 Open seal steam manual drain MIV at 8.5 mtr 8.5 mtr Engineer
Maintain seal steam temperature 280-290 ̊C (charge PRDS from Desk Engineer/Field
9 MS line in other unit to prevent from Steam extraction pressure 32 mtr
Engineer
ratio at higher load)
Ensure all MAL drains, HP & LP Flash tank drains manual isolating Desk Engineer/Field
10 4.5 mtr
valves are open. Engineer
22 Reduce the load up to 150 MW, Maintain MS Pressure about CCR Desk Engineer
100-120 kg/cm², by operating HP & LP Bypass
Reduce the load up to 120 MW, Maintain MS Pressure about
23 CCR Desk Engineer
100-120 kg/cm2, by operating HP & LP Bypass.
At about 120 MW load unload another TDBFP & put it on Desk Engineer/Field
24 barring. Ensure its barring speed in between 150-200 RPM. CCR Engineer
25 If any protection need to be check, then take follow up for this CCR SCE/UCE/Desk Engineer
31 Ensure all HP & LP Heaters extractions MOV closed in auto. CCR UCE/Desk Engineer
36 Ensure to close HPBP spray line, BD valve and manual isolating 8.5 mtr Desk Engineer/Field
valve. Engineer
Desk Engineer/Field
37 Ensure to isolate R/H Spray MIV from both TDBFP & both MDBFP 8.5 & 17 mtr
Engineer
Ensure to isolate both TDBFP warm up MOV (MDBFP Warm up Desk Engineer/Field
38 8.5 & 17 mtr
MOV also need to close in U#1) Engineer
Desk Enginner/Field
39 Maintain MOT Lube oil temp after cooler at about 46 ~ 50 ͦC. 8.5 mtr
Engineer
Ensure to stop one CEP after unit tripped, only one CEP kept Desk Engineer/Field
40 running. CCR Engineer
Ensure to stop one Condenser Vacuum pump (in case of two Desk Engineer/Field
41 vacuum pump running) CCR Engineer
Ensure to open all MIV'S & MOV'S of Unit flash tank & charge its Desk Engineer/Field
42 service waterr line CCR Engineer
Desk Engineer/Field
43 Ensure to open all MOV'S of steam drain flash tank/LPFT/HPFT CCR Engineer
Ensure to depressurize all HP/LP Heaters shells by opening Desk Engineer/Field
44 CCR
emergency drain valves to flash tank. Engineer
46 Ensure Generator circuit breaker is in local mode. 8.5 mtr SCE/Electrical Engineer
47 Ensure GCB Isolators are in open condition 8.5 mtr SCE/Electrical Engineer
48 Ensure to press the emergency push button of GCB 8.5 mtr SCE/Electrical Engineer
49 Ensure to close the door & provide lock on the door of GCB. 8.5 mtr SCE/Electrical Engineer
Desk Engineer/Field
51 Ensure to stop Hydrogen Drier, no need to isolate its MIV 8.5 mtr Engineer
52 Ensure to remove one CPU from service, only one CPU to be kept 0 mtr Desk Engineer/Field
in service. Engineer
Confirm with TMD team, is there any requirement of TDBFP Fast
53 CCR SCE/UCE
cooling. (For TDBFP Maintenance work)
UCE/Desk
In case of long shutdown, isolate Exciter cooler DMCW Isolation
54 8.5 mtr Engineer/Field
MIV Engineer
UCE/Desk
In case of long shutdown, isolate Hydrogen cooler O/L MIV
56 DMCW Side 8.5 mtr Engineer/Field
Engineer
Ask BMD, if hydro need to be performed then ask for continue
57 CCR UCE/Desk Enginner
vacuum pulling by opening MSSV, HPBP & LPBP.
Ensure Ammonia dosing system to be kept running at CPU O/L,
58 0 mtr Desk Engineer/Chemist
ask chemist to maintain the parameters.
After Main turbine Came on Barring gear, if No hydrotest Desk Engineer/Field
59 0 mtr
planned then kill Vacuum as per SOP. Engineer
Desk Engineer/Field
60 Ensure to isolate APH Soot Blowing MIV from APRDS. 32 mtr
Engineer
Desk Engineer/Field
61 Ensure to isolate Main turbine Gland seal MOV from APRDS. 32 mtr
Engineer
62 Ensure to isolate TDBFP AUX Steam MIV from APRDS. 32 mtr Desk Engineer/Field
Engineer
63 Ensure to isolate interconnection APRDS from Other unit. 32 mtr Desk Engineer/Field
Engineer
64 Ensure not to increase Deaerator temp, maintain D/A temp CCR Desk Engineer/Field
approx 110 ͦC. Engineer
65 Ensure to maintain Deaerator level about 500 mmwc. CCR Desk Engineer/Field
Engineer
Desk Engineer/Field
66 Ensure to reduce CW Interconnection valve from 100 % to 5% 0 mtr
Engineer
Ensure to stop one CW Pump (For 2 units three CW Pumps kept Desk Engineer/Field
67 CCR
running) Engineer
PRAYAGRAJ POWER GENERATION COMPANY LIMITED - 3X660 MW STPP
660 MW UNIT NO. # ___ DATE :-
TURBINE SHUT DOWN CHECKLIST
S No. Activity Description LOCATION RESPONSIBILITY REMARKS
Desk Engineer/Field
68 Ensure to reduce Condenser outlet valve from 60% to 10%. 0 mtr
Engineer
69 If Feed water not required in Boiler, Ensure to stop MDBFP. CCR UCE/Desk Engineer
PRAYAGRAJ POWER GENERATION COMPANY LIMITED - 3X660 MW STPP
660 MW Unit no. # ___ Date:-
BOILER SHUT DOWN CHECKLIST
S No. Activity Description LOCATION RESPONSIBILITY
Check if there is any Emergency shut down- Boiler tube leakage, major problems
2 in Turbine, Generator etc, Transmission constraints. CCR SCE/UCE
3 All coal bunkers should be preferably made empty before long shut down. Stop/ CCR SCE/UCE/CHP
regulate coal feeding to bunkers accordingly.
4 As soon as intimation received from management to shutdown the unit. Intimate CCR SCE/UCE/Commercial
SLDC about unit shutdown
Gradually reduce load to 360 MW & cut out 6 th & 5 th feeder, if coal mill A to F
running then first stop E & F Mill. (Ensure feeder & Mill empty) & mill (Reduce load Desk Engineer/Field
5 as per load requirements. Feed water, airflow, fuel flow, and steam temperature 24 mtr Engineer
should remain on automatic control)
6 Ensure to take one MDBFP in service & unload one TDBFP at about 360 MW. 17 mtr Desk Engineer/Field
Engineer
Ensure to start LRSB of Extended pass area, WSB & LRSB of the zone where BTL Desk Engineer/Field
7 Boiler
Suspected. Engineer
After 360 MW, Ensure to cut the coal from bottom Mill (Preferably bottom mill A &
8 CCR Desk Engineer/Field
B). Cut feeder & mill from bottom one by one. Ensure complete empting of mill &
Engineer
coal feeder by isolating Feeder inlet gate.
9 Ensure to maintain SH outlet temperature. Ensure closing of SH spray block valve/ 24 mtr Desk Engineer/Field
MOV/Control valves @ 30% BMCR (215 MW). Engineer
Desk Engineer/Field
10 Ensure warm keeping line NRV Bypass MIV is in close condition 32 mtr
Engineer
Desk Engineer/Field
11 Ensure Both HWL-1 & 2 Isolation MOV are in open condition. 14 mtr
Engineer
UCE/Desk
12 Ensure to take boiler in Wet mode at about 300 MW & start BCP as per procedure. CCR Engineer/Field
Engineer
UCE/Desk
13 Ensure to take Feed water 30% line at about load 300 MW. 17 mtr Engineer/Field
Engineer
Ensure to keep APH soot blowing continously during shut down of the unit to Desk Engineer/Field
14 avoid any fuel accumulation in APH. 14 mtr Engineer
UCE/Desk
Gradually reduce coal flow Keep 2 mill in service & adjacent oil gun in service. .
15 CCR Engineer/Field
Reduce load to 175 MW (Ensure Eco flow.)
Engineer
Slightly reduce the load up to 100 MW, Maintain MS Pressure with in the range of
16 CCR UCE/Desk Engineer
80-100 kg/cm2.
17 Ensure to trip the Boiler from Emergency push button on DCS/Desk. CCR UCE/Desk Engineer
18 Ensure to discharge all ESP Fields's. All CERM & EERM motors kept running. CCR UCE/Electrical Engineer
19 Ensure Boiler flash tank service water is in charged condition. CCR Desk Engineer/Field
Engineer
UCE/Desk
20 Ensure to check BTL either in SH/RH by operating HPBP. CCR Engineer/Field
Engineer/BMD
UCE/Desk
21 Ensure to stop one ID & one FD Fan CCR Engineer/Field
Engineer
Desk Engineer/Field
22 Ensure to run AC Scanner air fan in service. CCR Engineer
Desk Engineer/Field
23 Ensure to isolate LOTV/HOTV (main & bypass line) & Control valves. 24 mtr
Engineer
24 Ensure to isolate all MIV of Oil station line at 24 mtr. 24 mtr Desk Engineer/Field
Engineer
Desk Engineer/Field
25 Ensure to isolate all MIV of LONV/HONV at all elevations. 24 mtr
Engineer
26 Ensure to isolate all MIV of Atomising air/steam (AANV/ASNV) of all elevations. 24 mtr Desk Engineer/Field
Engineer
27 Ensure to establish Secondary air flow between 450 to 500 TPH & maintain CCR UCE/Desk Engineer
furnace draft -10mmwc with running ID Fan in auto.
28 Ensure not to exceed cooling down rate > 167 ̊C/hr of fluid temperature. CCR UCE/Desk Engineer
29 Ensure APH kept running, Emergency motor & Air motor available. CCR UCE/Desk Engineer
UCE/Desk
30 Ensure to isolate MSSV-1 & 2 in case of hot box up. CCR Engineer/Field
Engineer
Desk Engineer/Field
31 Ensure to open back pass rear & front header drains at 10 kg/cm² CCR
Engineer
Desk Engineer/Field
32 Ensure to open all vents when seperator pressure reached 5 kg/cm² CCR Engineer
Desk Engineer/Field
33 Ensure to empty Economizer hopper. CCR
Engineer/AHP
34 If APH need to be stopped, ensure APH Gas inlet temperature < 204 ̊C OR APH CCR UCE/Desk Engineer
hot element temp < 187 ̊C.
35 Ensure feed water temperature should not be less than 111 ̊Cthen the SST metal CCR UCE/Desk Engineer
temperature.
36 Before water washing, Ensure temp <= 55 ̊C metal temp achieved. CCR UCE/Desk Engineer
Ensure to kept run the BCP & BFP in service until the boiler water temperature is
37 reduced to 100 ̊C, keep the water level near normal in SST, adding make up water CCR UCE/Desk Engineer
required.
Ensure not to shut down the Scanner air fan, until the furnace temp has dropped
38 CCR UCE/Desk Engineer
below 149 ̊C.
39 Ensure to run the APH if fans are running, because deposit of fly ash in APH may CCR UCE/Desk Engineer
accumulate cause rotor unbalance.
NOTES:-
1 If required boiler to be draine make sure that BCP suction temp reduced to 93 deg.
2 When flue gas temp. at APH I/L reached 75 deg, stop FD fan and give clearance for water washing and during water washing ID fan Kept running
3 During Water washing Furnace draft in manual & presure maintain -10 MMWC
0 MW STPP
REMARKS
an Kept running