Mock Drill –220DC Failure Date: 04/12/2017

UNIT-5

Sequence of Activities TO BE DONE

Responsibility
Time Action taken

UCE observed both TDBFP recirculation valve got opened UCE


and 220vdc voltage became zero along with “220V DC
charger-1 &2 fail”.
Unit control engineer will inform to other desk engineer to UCE
start DG set from UCB. If not started, start from local.
Announce from local, DG Main/ Standby has started. Desk Engineer
Another Boiler desk engineer will go to Emergency Desk Engineer
switchgear.
Before making UES dead, Engineer will ensure whether AC Desk Engineer
SOP-2, HPCF-2, PW-2 has been changeovered from
Emergency bus.
Make UES dead and charge UES-A&B from DG Desk Engineer
Main/Standby
Start AOP-2, ACSOP-2, ACJOP-2, PW-2, HPCF-2 UCE
Ensure CW pumps are in unitized mode.(Interconnection UCE
valve to be closed)
Trip boiler from PB at desk, if not tripped UCE
Ensure turbine trips on MFT. UCE
Open 400KV breaker & Tie Breaker from Switchyard. UCE
Trip all HT drives from local.: Name* Desk engineer
Ensure closing of HOTV, LOTV and tripping of gravimetric Desk Engineer
feeders.
Observe turbine lub oil system and turbine speed. Desk Engineer
Isolate Seal Steam when vacuum deteriorates below -0.3, Desk Engineer
Close MS-1 & 2 and open MS Strainer drains to UFT.
Trip TDBFPs and isolate their steam, and ensure they come Desk Engineer
on barring.
Charge the emergency cooling of CC Pumps Desk Engineer