Pertamina (Persero) 080221 - Spherical Tank Terminal LPG Reff Jatim 1 - Tuban
Pertamina (Persero) 080221 - Spherical Tank Terminal LPG Reff Jatim 1 - Tuban
Pertamina (Persero)
PM LPG Facilities – Infrastructure Management & Project
Gedung Utama MOR III Lt. 9
Jl. Kramat Raya No. 59
Jakarta 10450, Indonesia Ref. No: 0511/JIQ/022021
M: 0812 422 34679 Quotation Date: 08-Feb-21
Valid Until: 08-Apr-21
Attn.: Mr. Mochamad Taufik Market Name: HPI
m.taufik@outlook.com CoU: NB
Revise: #0
No. of Volume DFT Spreading Rate Area Approx. Price/Ltr Price/M2 Total Packing
Location and
Preparation
Jotun Product coat Solid (mic) LF 35% (M2) Qty (Ltr) * IDR IDR IDR Size / Ltr Remarks
% M2/Ltr
I.2 Site painting for painting exclude 1course & Annular
Surface preparation: Sa 2½
Primer Penguard Express 1 74 75 6,4 23.923 3.732,14 140.000 21.841 522.499.600 5 & 20
Thinner No. 17 (± 10% ) 373,21 50.000 780 18.660.500 5 & 20
TOTAL DFT 75 22.621 541.160.100
I.3 Site painting for Intermediate & Topcoat
Surface preparation: Sa 2½
Primer Penguard Mid Coat , Buff 1 82 100 5,3 31.400 5.891,18 130.000 24.390 765.853.400 5 & 20
Thinner No. 17 (± 10% ) 589,12 50.000 938 29.456.000 5 & 20
Topcoat Hardtop XP, White 1 63 50 8,2 31.400 3.833,94 206.000 25.153 789.791.640 5 & 20
Thinner No. 10 (± 10% ) 383,39 50.000 611 19.169.500 5 & 20
TOTAL DFT 150 51.091 1.604.270.540
Notes:
- Quantity will be adjusted to nearest Jotun Standard packing size
- Please confirm for final colors. The prices for topcoats are for non-signal colors Sincerely Yours,
- Loss factor and Thinner consumption will vary depending on The application condition
- The prices above is based on calculation of 10% consumption of Thinners, and 35% Loss Factor of paint materials.