Professional Documents
Culture Documents
To cite this article: Wenchi Shou, Jun Wang, Peng Wu & Xiangyu Wang (2021)
Lean management framework for improving maintenance operation: development and
application in the oil and gas industry, Production Planning & Control, 32:7, 585-602, DOI:
10.1080/09537287.2020.1744762
CONTACT Jun Wang jun.wang1@deakin.edu.au School of Architecture and Built Environment, Deakin University, Geelong Waterfront Campus, 1,
Gheringhap Street, Geelong, Melbourne 3220, Australia
ß 2020 Informa UK Limited, trading as Taylor & Francis Group
586 W. SHOU ET AL.
in the process. The basic principle is to minimize unnecessary perspectives and focuses on variability based on which
production or operation to reduce process variability effective improvement plans could be established.
(Koskela 1997). The view of value generation focuses on ful- In order to address the research objective, after outlining
filling customers’ value. The concept investigates whether the literature review on the features of TAM projects and the
the task deployed is appropriate to capture the requirement challenges of lean application in TAM process management,
or not (Koskela 1997). this paper describes the design of the framework for a pro-
While the conventional project management methods duction-based view of project management based on the
consider project only based on transformation view by adaption of value stream mapping (VSM). Followed by a case
breaking down project work (Bertelsen and Koskela 2002), study to elaborates on the development and implementation
efforts were made to integrate the lean production manage- of the proposed lean management framework. Finally, the
ment theory which embraces the revolutionary concepts of contributions of this research in both managerial and prac-
flow and value into project management in industries, such tical aspects are summarised, report the limitations of this
as the construction industry (Pasqualini and Zawislak 2005; work and provide suggestions for future research.
Wu and Feng 2012; Ogunbiyi, Goulding, and Oladapo 2014),
and software development (McManus 2005; Leo n and Farris
2. Literature review
2011; Ali, Petersen, and De França 2015). The inclusion of
flow and value has also attracted much attention in TAM The basic philosophy of lean production is waste elimination
projects following the success in the construction and manu- and value creation for the customer (Hines, Holweg, and
facturing sectors (Abdulmalek and Rajgopal 2007; King and Rich 2004; Monden 1983; Womack, Jones, and Roos 1990).
King 2015; Shou et al. 2015; Sawhney, Kannan, and Li 2009; Lean production has been brought into the project manage-
Chowdary, Ojha, and Alexander 2018). However, the explor- ment area to form a strategy to copy with inefficiencies in
ation of lean production application in TAM projects has complex projects (Howell and Koskela 2000). Plant mainten-
mainly focussed on the benefits that can be achieved by ance is one of many types of the project-based production
assessing the maintenance process from value and waste system (Ballard and Howell 2003). Lean production shifts the
perspectives. Very few studies have systematically analyzed attention of maintenance improvement from the technical
lean transformation in TAM projects to manage variability, matters to the management side, which focuses on eliminat-
complexity and quickness by considering the uniqueness of ing the root causes of problems through team-based deci-
TAM projects (Shou et al. 2015). Abdulmalek and Rajgopal sions and implementation. According to McCarthy and Rich
(2007) have suggested that the application of lean produc- (2015) and Smith and Hawkins (2004), lean production imple-
tion in process industries is possible but the features such as mentation seeks to eliminate all forms of wastes such as
capacity focussed, high capital intensity, high volumes and extra inventory in the maintenance process. Reducing wastes
low flexibility make it impossible to borrow the lean concept in maintenance operation is the main feature that distin-
and implement directly. This leads to the research question: guishes the lean maintenance practice from a conventional
maintenance management practice (Smith and Hawkins
What is the appropriate framework for implementing the lean
2004). As shown in Table 1, synergistic objectives have been
production theory and tools to improve project management
performance in TAM projects? obtained by comparing the objectives of TAM and lean
maintenance. Therefore, it is beneficial to apply the lean
The research presented in this paper aims to develop a management theory to improve the efficiency of TAM in the
lean management framework for guiding lean production oil and gas industry.
applications in TAM projects in a structured way. The essen- The interaction between lean production and mainten-
tial principle in this paper, based on lean production theory, ance efficiency was investigated and is addressed via the
is that the performance of TAM project management can be applicability of lean principles into maintenance (Davies and
improved by recognizing value and managing flows. In light Greenough 2010; Baluch, Abdullah, and Mohtar 2012), lean
of this point of view, this paper presents production-based tools application with the prioritized maintenance strategies
view based on the lean principles and tools to determine the (Tendayi 2013; Youssouf, Rachid, and Ion 2014), and case
procedures and critical strategies to manage TAM projects studies of lean practices in maintenance management
cost-effectively. (Arslankaya and Atay 2015; Davies and Greenough 2003).
This paper seeks to contribute to the ongoing investiga- Meanwhile, the factors and parameters of maintenance oper-
tion on the lean transformation in complex TAM projects ations that are most effective in enhancing production to a
from TFV perspectives and to the capability of managing lean system have been proposed by Moayed and Shell
variability through the adoption of lean principles and tools. (2009). Some studies have also been made on a conceptual
In particular, this paper contributes to the field of knowledge framework such as lean enterprise architecture (Mathaisel
and practice by investigating the challenges of implementing 2005) and lean process structure (Mostafa et al. 2015).
lean in complex maintenance projects and understanding Moreover, several studies focussed on the effect of lean
how lean principles and tools can be used to establish struc- techniques on maintenance efficiency. Among lean tools,
tured improvement activities. This would have strong prac- VSM can be regarded as the most frequently applied lean
tical implementations for the management of complex technique for operation analysis in visualizing the entire
projects as it analyses efficiency from both value and waste maintenance process by representing material and
PRODUCTION PLANNING & CONTROL 587
Table 1. Comparison of the objectives of TAM and lean maintenance (Shou et al. 2015).
Objectives of lean maintenance Objectives of TAM
To visualise the maintenance flow from material and information perspectives To achieve higher corporate performance
To improve the process by applying lean techniques to shorten the lead time To improve the efficiency and the throughput of the plant by suitable
modifications
To make the plant safe to operate till the next TAM
To reduce routine maintenances costs
To upgrade the technology by introducing modern equipment
and techniques
To achieve zero waste by identifying the sources of waste To increase the reliability and availability of the equipment during operation
To achieve the best quality of workmanship
To translate the customer’s requirements into practice processes To modify the operating equipment to cope with the legal requirements and
or obligations, such as the environmental regulation(Ben-Daya et al. 2009)
information flows (Shou et al. 2015; Shou et al. 2014; fluctuation; how to simplify by identifying and removing
Sawhney, Kannan, and Li 2009; Kannan et al. 2007; Kasava NVA activities and constraints; how to cope with variability
et al. 2015; En–Nhaili, Meddaoui, and Bouami 2015). Shou caused by uncertain work scope and complex interfaces to
et al. (2020) proposed a classification system of value adding improve flow reliability.
(VA) and non-value adding (NVA) activities in TAM projects,
which contributes to accurate identification of value and
waste of adopting lean production. 3. The development of lean
However, some of the limitations of current research have management framework
been observed as well. The existing research works have The detailed analysis of existing research provides the sup-
been slightly limited in operational maintenance environ- porting elements for the development of the lean manage-
ments outside of the manufacturing context (Tendayi 2013). ment framework in TAM projects. Lean application is a
TAM is a duration-driven event as all the maintenance opera- process-based view that focuses on the analysis of the value
tions and measures have to be planned to fit into a very stream (Rother and Shook 2003). As an essential lean tech-
tight schedule to reduce economic loss due to non- nique to facilitate lean application and transformation, VSM
production (generally 3–4 weeks) (Bertolini et al. 2009). The is selected in this research. The lean application follows the
frequency of TAM is largely dependent on many variables systematic VSM implementation structure which includes tar-
such as the age and type of plant technology, the required get value stream selection, current state mapping and meas-
level of plant reliability, and the legal requirements associ-
urement, current state analysis, future state development,
ated with the operation (Ghazali and Halib 2011). As such, all
and action plan implementation (Rother and Shook 2003).
these variables results in unfixed plant items to be shut
The five-step framework is a continuous improvement loop
down and planned in an unroutine way. Every TAM is a new
that provides guidelines on streamlining the maintenance
project that has to be completed within the planned sched-
process in TAM projects, with an objective to minimize waste
ule. Therefore, the temporary nature has increased the risk of
and maximize planning and control efficiency.
efficient maintenance operation (Halib, Ghazali, and Nordin
2010). Besides, the scope of work involved in turnaround has
considerable variations and uncertainties due to the scope 3.1. Step 1: critical work scope selection
are loosely defined based on past turnaround experience,
inspection reports, operations requests and historical esti- The purpose of the first step is to select a critical work scope
mates, etc. (Lenahan 1999). Therefore, TAM is a high for current state mapping. The product family is a group of
demanding project, resources such as manpower, material, products with a similar production process. It is the standard
equipment, information, and techniques must be carefully unit for VSM analysis (Rother and Shook 2003). A TAM pro-
planned and adequately supported to avoid any inefficiency. ject usually consists of several work orders (WOs). The WO
The features of TAM projects, such as duration-driven, tem- based system in TAM is the guideline of ‘what’ to be
porary project, and dynamic project scope, different TAM involved in the maintenance project (Ben-Daya et al. 2009).
projects from any other maintenance projects. It argued that The resources required to facilitate the planning, execution,
more research should be conducted on lean practical appli- and control are included in WO, which also gives a detailed
cation in the maintenance operation. instruction of ‘how’ the work is carried out (Ben-Daya et al.
Moreover, the investigation of the specific TAM system 2009). The maintenance work included in one WO is divided
configuration and the conditions that disturb the effective into one or several work packages (WPs), which include all
application of lean production principles and tools in main- functions of the operation involved (Duffuaa and Ben-Daya
tenance operation is marginal. Previous research work has 2009). The WPs are scheduled by maintenance planners or
highlighted the impact of the features of the production pro- coordinators using network analysis in order to minimise
cess on the application of lean production (Shou et al. 2017). work completion time and shutdown periods (Ben-Daya
Even though several lean frameworks for maintenance man- et al. 2009). In addition, the WPs also include necessary infor-
agement have been proposed (Arslankaya and Atay 2015; mation related to ‘when’, that is, the time that WPs have to
Yile, XueHang, and Lei 2008), few initiatives have addressed be initiated or finished. Therefore, maintenance execution is
the issues such as how to stabilize workflow to reduce flow the processing of WP(s) by following the scheduled
588 W. SHOU ET AL.
procedures (Ben-Daya et al. 2009). According to this concept, extended project duration and the extended execution time
one WP can be regarded as one operation family. are proposed and calculated by the following equations:
The target product family is the WO with the shortest buf-
fer time in the planned schedule and it usually plays a crit- Extended project duration
ical role (i.e. is on the critical path) in the whole process. In ¼ LT of the actual process–LT of the planned schedule;
other words, it is the WO that has the highest risk of delay. If
there are more than one WPs included in the product family, Extended execution time
the critical family unit is the WP which has the longest ¼ Sum of CT of the actual process
scheduled operation time.
–Sum of CT of the planned schedule:
3.2. Step 2: current state mapping and measurement Two metrics are also proposed to measure the variations
in the process, which are processing time variation and the
The second step is related to the development of the current start time variation. These two metrics have been adopted
state map. In TAM projects, process mapping is a detailed by Wambeke, Hsiang, and Liu (2011) to study the variations
level of description of a maintenance workflow. Workflow
and relevant causes in construction projects. Table 2 shows
analysis focuses on exploring the answers in terms of value
the key metrics used to measure the effectiveness and effi-
creation and value evaluation in the TAM environment. Such
ciency of the TAM execution process.
analysis has two objectives: (1) to identify activities in critical
value stream; and (2) to develop feasible measurements for
the workflow performance measurement. 3.3. Step 3: waste analysis
The flows in the current state map are related to both
Step three is related to waste analysis, which aims to identify
material and information in a value stream. The lead time of
the maintenance execution not only depends on the flow of the root causes of the variations in the workflow. The con-
the physical operations related to materials, tools and equip- cept of root cause analysis, which aims to investigate the
ment, but also on the efficiency of information flow to meet schedule and the utilization of all relevant resources to
the maintenance needs. The physical flow comprises the reduce the variations, is the fundamental idea behind this
functional and logical operations conducted by the trading approach. At first, a cause and effect diagram is constructed
crew to complete the maintenance effectively. The informa- and used to identify possible reasons for variation (Ishikawa
tion flow is the interaction between the operations and the 1985), which may include system, environment, process,
resource supply which has a potential impact on oper- equipment and tools, labour force and materials and compo-
ational efficiency. nents. The six categories are briefly introduced below. A
Performance measurement is related to how value is eval- Focus group study is conducted to construct the ana-
uated and what types of waste can be identified. Based on lysis process.
the value and waste definition in (Shou et al. 2020), the man-
agement of workflow aims to identify and remove the waste System. It refers to the planning quality of the
that does not contribute to plant productivity or that leads WP, including:
to process variations. The variables in a TAM project can 1. the strict specification/method in the WP;
include weather, work process, material supply, work crew 2. the complexity of the activities in the WP; and
availability, neighbouring maintenance activities, and 3. constructability of the activities in the WP.
required resources and locations. The main assumption is Environment. It includes:
that the TAM project productivity and performance can be 1. External conditions, such as weather changes that
improved by reducing the variations in the process. may impact the maintenance execution;
Based on the objectives of the process improvement in 2. Internal site condition, such as the availability of
the TAM project, the performance of the TAM execution pro- workspace to perform the maintenance tasks (acces-
cess is measured by using the following metrics. The lead sibility, site congestion, etc.); and
time (LT) or cycle time (CT) in the planned and the actual 3. Internal location conditions, such as the efficiency of
operations are compared to reveal the productivity. The the working condition.
PRODUCTION PLANNING & CONTROL 589
Process. It refers to identifying the reasons that result in are ranked based on the amount of variation they caused.
inefficiency in physical and information flow. The identified causes are quantified based upon the magni-
This includes: tude of the wastes (measured in hours). Figure 1 illustrates
1. Prerequisite work. It refers to the work that has to be the framework of current state measurement and analysis in
completed before starting the subsequent activity. both steps 2 and 3.
Some examples are the quality assurance (QA)/quality
control (QC) inspection of the previous activities and
3.4. Step 4: future state improvement
the obtain of required permits to start the subse-
quent activity. The focus of this step is to optimize the current maintenance
2. Information flow, which includes coordination among process by selecting and adapting appropriate and relevant
the trading crew, between the superiors and the sub- lean tools to eliminate specific waste. The assumption in the
ordinates, as well as for instructions from TAM projects is that the capacity for waste elimination is lim-
the supervisor. ited due to its complexity and scale. Therefore, all the causes
Equipment and tools. This refers to the availability of the of variation cannot be eliminated simultaneously and priori-
equipment and the tools that are necessary for mainten- tization is necessary. Therefore, an impact/effort matrix is
ance execution. Such equipment and tools can include developed with the involvement of key participants to priori-
crane or forklift, rig, truck, hand tools, and personal pro- tize the causes of variation. This matrix is a tool to evaluate
tective equipment (PPE) several options by considering the impact of a variation and
Labour force. The availability of manpower has a signifi- the effort required to eliminate or minimize the variation. It
cant impact on the efficiency of maintenance execution. is a favourite tool for prioritizing the options when objective
Some examples are the efficiency of the labour (experi- data are not available. In this matrix, the impact is illustrated
enced, lack of skill, new employee) and late arrival to con- by five levels, namely low, minor, moderate, major and cata-
duct the activities. strophic. The effort is classified as rare, minor, moderate,
Materials and components. Some examples are: great and tremendous. The resulting prioritization is illus-
Movement or transportation of the material between the trated as low (L), moderate (M), high (H) and extremely high
site and the storage yard; (E), as shown in Table 3. The improvement will start from the
The arrival of material from suppliers; variations which have extremely high priority.
Size of the required materials and components; and The focus of future state map is to eliminate the root
Type of the required materials and components. causes of wastes and to link the value stream in a smooth
flow. In this study, the identified waste will be estimated and
In order to determine the main causes that led to the validated by experts to propose an achievable improvement
variation, the root causes of the processing time variation plan of the maintenance processes.
590 W. SHOU ET AL.
Table 3. Impact/effort matrix. management techniques using Primavera and SAP software.
Effort The shutdown was completed 1.5 h ahead of the target dur-
Rare Minor Moderate Great Tremendous ation. However, a cost overrun was observed due to the
Impact huge variations in the actual maintenance process from the
Low M M L L L
Minor H H M L L planned schedule.
Moderate E H H M L It is recommended that evidence and information
Major E E H M M
obtained through a case study be gathered from different
Catastrophic E E E H M
sources as a way to triangulate results (Yin 2013). It is argued
that much more reliable results can be produced by using
3.5. Step 5: action plan: 4D BIM for validating and the results from multiple methods to complement each
verifying the action plan other (Fellows and Liu 2015). In order to enhance the reliabil-
An action plan is undertaken to investigate the effect of the ity and validity, data is therefore collected from (1) a compre-
improvements proposed in the future state map before pro- hensive review of the documents of the selected
ceeding to the implementation. The evaluation of the lean maintenance project; and (2) VSM development workshop
initiatives proposed in the future state map is carried out by with key participants.
applying 4D BIM. BIM is emerging as a method of creating, The most critical work order that led to project overdue
sharing, exchanging and managing the information through- or cost overrun was identified and selected through:
out the project life cycle among all stakeholders (Wang, Sun,
et al. 2015; Wang, Zhang, et al. 2015). A 4D BIM model links Review of the work breakdown structure. The review was
the 3 D model to the fourth dimension of time (Shou et al. related to how many maintenance WOs and WPs have
2015). In the 4D model, the temporal and spatial aspects of been developed, what are the functional units in each
the project are inextricably linked, as they are during the WO and WP, and how many activities have been con-
actual construction process (Li et al. 2014). In the project ducted within WPs.
shaping stage, the 4D BIM is useful in communicating and Schedule and cost analysis for each WO. An analysis of
validating construction plans and processes, while during the buffer time, variations of scheduled duration, activities,
construction phase, it is helpful in identifying the errors in and resources that were related schedule and budget of
the logic of the schedule, potential time-space conflicts, and each WO were conducted.
accessibility issues (Chong et al. 2014; Chong et al. 2016). In Schedule of the project.
recent years, 4D BIM has been largely implemented in Work package. Activities conducted to finish a work pack-
building and infrastructure projects and has proven its capa- age were reviewed, which included quality management
bilities in planning simulation and optimization (Sacks et al. related activities, safety management activities, site logis-
2013; Zhang et al. 2013; Lee et al. 2016; Wang, Wang, tic management activities, administration activities and
et al. 2016). progress report activities.
Figure 2 presents the overall VSM-based lean manage-
ment framework. The second phase is the contribution of knowledge and
experience from experienced practitioners to streamline the
maintenance process and provide information which cannot
4. Case study be obtained from the analysis of documents. Similar to the
The case study method is used to illustrate the functionality research conducted by Wang, Shou, et al. (2016) and Shou
of the proposed framework. A case study allows the et al. (2020), the discussions with eight relevant TAM practi-
researchers to gain an in-depth understanding of the phe- tioners were carried out to map the current state process,
nomenon under investigation. The method of case study is verify information about maintenance execution for each
highly recommended for research where theories are at their process, and investigate the root causes of the waste. Table
formative stage (Eisenhardt 1989; Yin 2013). The use of a sin- 4 shows the experts’ background information. As can be
gle detailed case study has been widely accepted as a valid seen, the experts selected include the critical work crews
research method in the field of operational research involved in the selected TAM project.
(Robinson et al. 2012; Hicks et al. 2015; Wang, Shou, et al.
2016; Liu et al. 2013).
4.1. Step 1: critical work scope selection
The lean management framework was tested in a turn-
around project of a Liquefied Natural Gas (LNG) plant in Following the rules proposed in the framework, 18 WOs
Australia. The selected TAM project is a major shutdown con- were identified in the selected case. The WO of valve
ducted in 2016. The 28-day shutdown involved more than replacement was the target product family. There were 100
1000 functional units in two LNG trains. The scope of the valves that needed to be removed, refurbished, and installed.
maintenance work comprised a gas turbine major overhaul, Basic maintenance data were collected by researchers using
valve overhaul, internal tray modification and other shut- the proposed methods and then verified by focus
downs. The shutdown caused an operating loss of A$46.4 group discussion.
million and a capital expenditure of A$37.1 million. The pro- The maintenance workflow involved three stages: on-site
ject was planned and carried out using the classical project valve removal, off-site refurbishment, and on-site valve
PRODUCTION PLANNING & CONTROL 591
4D BIM simulation
installation. A total of 422 activities were identified and ana- repetitive activities were removed. In this study, the current
lyzed from this case. The replacement of the 100 valves fol- state focussed on analyzing the value and waste in on-site
lowed a similar process and most of the actions were production. Therefore, 27 operation activities were drawn in
repetitive. Finally, 42 activities were screened out after the current state map.
592 W. SHOU ET AL.
huge variation in the start time. The value of start time vari- differences between the CT and the PT in each activity in
ation revealed that most of the processes suffered from vari- the value stream were identified. Table 6 lists 18 individual
ous degrees of delay in starting. The analysis also showed causes that were identified which were distributed among
that the activities executed had a large tendency for the the 6 categories mentioned above.
delay in starting on time. Hence, the on-time start rate of The identified causes were quantified based upon the
the activities conducted in the same process was measured. magnitude of the wastes (measured in h). To determine the
It was observed that the percentage of on-time start activ- main causes that led to the variation, the root causes of the
ities was relatively low. For example, the percentage of on- processing time variation were ranked based on the amount
time start for break flanges was 11%. of variation they caused. Table 7 shows the top 10 causes
Secondly, the processing time recorded in the current for the processing time variation. The error of tools and
state map was the actual processing time taken, and the VA equipment used were ranked as no.1 among all the causes.
or the NVABN time was the planned processing time for A 10% error rate of the tools and equipment staging was
each process. The difference between the two values indi- observed. It led to 2.1 h of waste in the replacement proc-
cated the excess processing time. esses for every single valve. Permit issue/isolation was the
second main cause, with an estimated waste time of 1.5 h.
4.3. Step 3: waste analysis Delay of required material was the third cause with 1.4 h
identified as waste. The top six causes that led to the proc-
The waste analysis was then performed. First, the reasons essing time-variation could be categorized to three groups:
(root causes) leading to the fluctuating CT and the huge (1) extended processing time due to the unavailability of the
Table 5. The measurement. required resources to finish the tasks, such as labour (R8),
Difference
material and components (R3), tools and equipment (R1, R7),
Processing between and permit (R2); (2) processing time variation due to ineffi-
time varies CT and PT cient planning that, includes Rank 4, 5 and 6; and (3) envir-
Maintenance for each type for each type
Classification hours of activity of activity
onmental issues related to unavailable work front access (R9)
CT 77.5
and interface conflict (R10).
PT 49.15 The root causes of the starting time variation were also
VA – tool activities 35.94 7.66 16.85 examined using a similar approach. It was interesting to note
NVA but necessary 14.2 4.095 11.5
Waste in PT (total) 11.755
the great similarity with the causes of processing time vari-
Difference between 28.35 ation. The improvement in the future state would, therefore,
CT and PT (total)
focus on reducing the top 10 causes identified in processing performed by reducing the inefficient and redundant manage-
time variation. ment interfaces in the communication procedures among the
participants and the documentation process. The flowchart
technique was used to map the programme logic sequence
4.4. Step 4: future state improvement
of all the interfaces required. This technique has a high level
In this study, the identified waste was estimated and vali- of detail of the flows to identify the bottlenecks of the inter-
dated by experts to propose an achievable improvement face where the process can be improved. The complexity of
plan. The priorities emerged out of the impact/effort Matrix. the activity was measured by multiplying the number of work
Table 8 shows the priorities based on the impact/ teams by the number of interfaces in the process.
effort matrix. A process flowchart was drawn for each managerial pro-
The wrong permit issued, and the lack of prioritization of cess based on the information collected from both the inter-
valve isolations and the painting are the two causes that had view and the documents reviewed. The flowchart analysis
an extremely high priority. Delay due to the unavailability of included obtaining an understanding of the steps of a man-
materials required, administration work, crane and unskilled agerial process, identifying the risks and interfaces in the
workers were the four causes that also had a high priority. managerial process, understanding the individual’s view of
Unplanned work, unavailability of the work front access and the processes, analyzing the inefficient interfaces, and vali-
the interface conflict were the three causes with a dating by the business leaders.
medium priority.
4.4.1.2. Location-based operation levelling. The second
improvement aimed to reduce the flow fluctuation of the
4.4.1. Lean initiatives development
maintenance operations among distinct locations. According
Figure 4 shows the future state map. Three main lean
to Kenley and Sepp€anen (2006), the conventional scheduling
improvements were proposed.
technique is referred to as activity-based technique because
the management relies on the construction of a logical net-
4.4.1.1. Standardization. The first improvement strategy
work of activities. The waste, such as the idle times in the
focussed on identifying and removing the redundant interfa-
sequential activities (i.e. the time between the completion of
ces between the activities and standardizing the procedures
an activity and the start of the following activity), which is
in the workflows. The process of interface standardization was
caused by the fluctuations in the operation rates of the activ-
Table 8. The priority of causes elimination.
ities within different locations, cannot be observed and
solved in a linked network (Kenley and Sepp€anen 2006). The
Priority Causes
E 2, 4
methodology of location-based management was adopted
H 5, 3, 7, 8 to reduce such a kind of waste. The focus of location-based
M 9, 6, 10 scheduling is to track the continuity of the workflows of the
L N/A
resources as well as the value stream of the activities.
The underlying philosophy is to flow resources for produc- in Figure 5, the processing time of the activities con-
tion processes through locations to reduce the cycle time, as ducted for valve replacement was measured. It was
well as to use buffers to allow for variability. assumed that similar activities took the same processing
In this study, this location-based flow management phil- time. The activity in the process with the longest process-
osophy was combined and implemented with the concept of ing time was then identified and adjusted by considering
takt time to level the maintenance operation. Takt time plan- the feasibility of improving the production capacity. This
ning in the TAM project is the overall progress rate at which step was repeated until the maximum operating capacity
all the co-dependent flows in the maintenance execution are to complete the activity was reached. The adjustment
ideally moved. However, takt time is a customer-driven pull strategies included increasing the number of workers and
concept, and hence it would difficult to define the demand restructuring the activities to create a continuous flow. In
rate of workflow in the conventional push model of project addition, the operational capacities in different activities
management. The concept of production levelling proposed were balanced. The actions included providing time buf-
by Frandson, Berghede, and Tommelein (2013) in terms of fers to accommodate the production or decreasing the
the use of the takt time in the push model was adapted. The number of workers to extend the processing time. Finally,
identification of the uniform operation rate for TAM was the takt time for the production in the process was iden-
guided by the following processes: tified by referring to the processing time that could be
followed by most activities. For those activities where
Dividing maintenance processes: The first step was to div- there was a challenge to modify the capacities to get
ide the maintenance processes into several stages accord- them to match with the takt time, one solution was to
ing to functionality. Takt time was measured, for each use the controlled first-in-first-out (FIFO) to manage the
stage. This step was added to minimize the impact of the WIP inventory. FIFO lane could be applied to decouple
varied pace of the operations. In this case, the takt time consecutive activities with a huge capacity variation.
of the three stages was calculated separately. Another solution was to add a work team to reduce the
Zone definition: The second step was to divide the main- impact of the long production time. Time buffers were
tenance operations into zones. Each zone included the planned at the end of each completed process between
components served on by nearby facilities. In this case, the zones to absorb any variations. Once applied, the takt
the 100 valves were scattered at six different facilities and time for stages 1, 2 and 3 were 1.5, 0.8 and 1.2 h,
divided into four zones. The maintenance process was re- respectively.
organized so that the valve replacement started from the
valves in the same zone and the operations flowed from 4.4.1.3. Dynamic pull flow. The third improvement was to
one zone to another. propose a dynamic pull flow management to replace the
Workflow balancing: The third step was to refine the fixed maintenance schedule. In the conventional method, the
processing time of the maintenance executions. As shown maintenance process was managed by using a work break
Review
processing Delivery
Check
specifications dockets from
and
provided and third party
update
Yes
Specification update register specificat
Deliver
copy supplied ions to
Job approved from third Create job
to QA Review “WP
party? No inspection
operation register”
specifications record
provided and
update register Add
specific
Collate WP,
specificatio
job card &
Update daily n
Visual delivery
inspection Notification for Attach WP, requirement
inspection dockets
record inspection job cards & s to daily
required delivery inspection
dockets record
Complete
Update report
Close out &
inspection
notify
record in WP Collate all Finish
operation
Prepare quality documentation
report
Administ
Decision Administration
Documents Multi- ration
Process making activity
documents operation
Table 9. The comparison of the value in current state, future state and achieved state.
Future state value Achieved state value by 4D
Current state value (ideal value) BIM implementation Transformation rate
Criteria (a) (b) (c) ((a c)/ (a b) 100%)
Total CT (h) 77.5 48.05 50.25 93%
Total PT (h) 49.15 40.19 42.55 74%
The average percentage of 35% 65% 63% 93%
on time start (%)
VA ratio (%) 49.32% 60.37% 57.8% 77%
Number of interfaces 127 38 47 90%
effective the action plan has been. The average transform- Empirical evidence also showed that a systematic approach
ation rate in terms of the five criteria (i.e. total cycle time, to the lean theory and tools implementation is crucial to drive
total processing time, the average percentage of on-time the improvement of specific projects and address specific
start, VA ratio, and the number of interfaces) was 85%. problems (Vinodh, Ruben, and Asokan 2016; Okhovat et al.
2012). This research distilled the lean application in mainten-
ance projects and consolidated it into the VSM structure
5. Discussion which brought into focus the most crucial points for the for-
Although the lean theory and tools have a wide range of mulation of a logically sequenced lean implementation.
applications in maintenance projects, the best practice of lean Although the proposed lean management framework has
management requires further exploration owing to the differ- been generated and evaluated in the context of TAM projects
ences in the value streams. Research has suggested that the in the oil and gas industry, it does not exclude its use in other
application of lean management theory and tools should take industries. Further study is recommended to look at its applic-
into consideration the characteristics of the target-specific pro- ability to the other process industries.
duction environment (Shou et al. 2017). Current lean practices Moreover, this study relates 4D BIM to the lean initiative
are developed for the manufacturing processes. TAM is not a validation, which can contribute to the understanding and
repetitive production process but rather a project presenting implementation of the 4D BIM technology in the lean imple-
a unique work scope and context and follows a unique main- mentation. In the present study, simulation techniques, such
tenance process (Bevilacqua, Ciarapica, and Giacchetta 2009). as discrete event simulation, agent-based simulation, have
Although the lean theory and tools have been applied to been widely applied to facilitate the lean implementation.
managing projects in the housing construction (Yu et al. However, it is argued that the limitations, such as reliability
2009), the distinctive features hinder the application of the of the data provided for the simulation and visualisation of
lean experience in the maintenance stream. Thus, the pro- informational and functional characteristics of the specific
posed framework fulfilled the gaps in the application of lean processes, cannot be addressed (Solding and Gullander 2009).
practices in TAM projects. 4D BIM is an advanced method to simulate and visualize the
PRODUCTION PLANNING & CONTROL 599
changes and improvements in operational processes against By involving the participants during the process of the
variations. As 4D BIM is a means of information processing framework development and evaluation, we could, not only
with a time dimension, its introduction into the lean valid- help the project identify the most critical operational proc-
ation is a sensible effort. The framework developed here esses and the root causes of waste in these processes, but
explains how 4D BIM can facilitate the discussion of a feasible also convince them of the values of ‘embed and sustain’ sys-
and efficient lean initiative to achieve process improvement. tematic procedures within the routine improvement evalu-
ation. The case study discussed here, provided a useful
guideline for people in the industry to make decisions based
6. Conclusion, limitations and future
on ‘facts’.
research directions
There are potential limitations to this study. First, the
In this study, a lean management framework was proposed framework was tested by using a single representative case
and the effect of the proposed procedures and steps on the study. The selected case for validating the proposed frame-
maintenance operations was illustrated through a case study. work was relatively simple because only a repetitive process
The main contributions of the framework to the body of was investigated. Future studies should address this issue.
knowledge are threefold: First, it extended the lean applica- Second, the lean management framework developed should
tion beyond the manufacturing production management to a be evaluated and tested with more case studies in the oil
TAM process. In the current practice, the TAM project was and gas industry. This would help evaluate its wider applic-
treated as a collection of sub-campaigns using a conventional ability as well as create best practices for future implementa-
project management method. The conflict between the pre- tion of lean initiatives in TAM. A wider study provides
determined schedule and an unpredictable reality resulted in explanations on how the performance of TAM operation can
significant waste in the system. This research focussed on be improved through the application of the lean theory and
VSM, which is considered as one of the best tools for process the relevant lean tools. It is suggested that the selection of
improvements from a lean perspective. This paper explored lean production tools and techniques for project-based pro-
the major challenges in TAM and proposed a lean manage- duction context should be done with a comprehensive ana-
ment framework for utilizing VSM in a TAM setting. A critical
lysis. The review gives a general understanding of the
value stream was identified. Second, this work proposed a
features, pros, and cons of the selection and implementation
VSM application in the TAM execution process to achieve a
of lean tools and techniques for improving the process effi-
lean application in a practical way and improve workflow reli-
ciency in a TAM project. The development of lean applica-
ability and stability. It offered a structural way to choose the
tions in the oil and gas industry can be leveraged by
key-value steam of a complex TAM campaign and perform an
identifying the critical factors that affect the selection pro-
optimized analysis of the selected value stream. Location-
cess of appropriate lean production tools and techniques.
based levelling was used, in tandem with Takt time redesign
and pull planning rebuild, to control the variations and pro-
vide a predictable and stable flow of work trades. The evi- Disclosure statement
dence from the case study showed that the framework could
No potential conflict of interest was reported by the author(s).
achieve a better lean application and maintenance operation
performance. Each procedure in the framework has devel-
oped target interventions on key issues. Finally, the frame- Notes on contributors
work developed and presented in this research proposed
relations between lean practices and the project management
theory. There are many research efforts supporting the view Wenchi Shou, Ph.D., is a lecturer in the School of
Built Environment at Western Sydney University. Her
that the lean theories have positive effects on improving the
research interests are in value stream mapping, lean
traditional project management (Gabriel 1997; Howell and construction, Building Information Modelling, and
Ballard 1998). As suggested, the lean-based view of the man- simulation, exploring the application of digital lean
agement process highlighted the waste, which was invisible to improve construction and operation performance
in CPM or PERT analysis. Furthermore, the application of the across building, infrastructure, and oil and gas indus-
location-based levelling and pull flow addressed the chal- tries. As a Chief Investigator, she has obtained one
lenges posed by the variations by integrating the lean pull Australian Research Council Linkage project.
theory with the traditional push management system.
The findings of this study have practical implementations
as well. The proposed lean management framework provided Jun Wang, Ph.D., is a Lecturer in Construction
Management at Deakin University. His research inter-
detailed step-by-step instructions in terms of the lean appli-
ests focus mainly on leveraging emerging technolo-
cation in TAM. It has been found that the current practice of gies, such as Building Information Modelling, Internet
decision making for improvements relies on experience- of Things, Linked Data and Blockchain, to improve
based intuition (Gupta and Kumar 2012). The participants of construction and operation performance across the
this study admitted that they were reluctant to identify and building, infrastructure, and oil and gas industries. As
solve the problems in a systematic way; instead, they a Chief Investigator, he has been involved in two
Australian Research Council funded projects.
would come up with solutions based on their experience.
600 W. SHOU ET AL.
Peng Wu, Ph.D., is a Professor with the Department Bevilacqua, Maurizio, Filippo E. Ciarapica, and Gianluca Giacchetta. 2009.
of Construction Management, Curtin University. His “Critical Chain and Risk Analysis Applied to High-Risk Industry
research areas include sustainable construction, lean Maintenance: A Case Study.” International Journal of Project
production and construction, production and opera- Management 27 (4): 419–432. doi:10.1016/j.ijproman.2008.06.006.
tions management, and life cycle assessment. In Chong, Heap-Yih, Robert Lopez, Jun Wang, Xiangyu Wang, and Zeyu
2016, he received the Discovery Early Career Zhao. 2016. “Comparative Analysis on the Adoption and Use of BIM
Research Award from the Australian Research in Road Infrastructure Projects.” Journal of Management in Engineering
Council, which is a prestigious award to support 32 (6): 05016021. doi:10.1061/(ASCE)ME.1943-5479.0000460.
excellent basic and applied research by early career Chong, Heap-Yih, Jun Wang, Wenchi Shou, Xiangyu Wan, and Jun Guo.
researchers. 2014. “Improving Quality and Performance of Facility Management
Using Building Information Modelling.” Paper Presented at the
International Conference on Cooperative Design, Visualization and
Engineering, Seattle, WA, September 14–17.
Xiangyu Wang, Ph.D., is a Professor with the Chowdary, Boppana V., Kuldeep Ojha, and Arlene Alexander. 2018.
Department of Construction Management, and “Improvement of Refinery Maintenance and Mechanical Services:
Director with the Australasian Joint Research Centre Application of Lean Manufacturing Principles.” International Journal of
for Building Information Modelling, Curtin University. Collaborative Enterprise 6 (1): 20–36. doi:10.1504/IJCENT.2018.092082.
He is an expert and leading researcher on automa- Davies, C., and R. M. Greenough. 2003. “Testing Performance Measures
tion in construction. He received 5 Linkage grants, 5 within Maintenance, through Case Study Research into Lean Thinking
Discovery grants, and 1 Training Centre grant from Activities.” Accessed 24 March 2014. http://www.plant-maintenance.
Australia Research Council from 2013 to 2019. He is com/articles/Testing_Performance_Measures.pdf
on the Board of Directors and country representa- Davies, C., and R. M. Greenough. 2010. “Measuring the effectiveness of
tives of the International Society of Computing in Civil and Building lean thinking activities within maintenance.” Accessed 24 June 2013.
Engineering (ISCCBE) and International Association of Automation and www.plant-maintenance.com/articles/Lean_Maintenance.pdf
Robotics in Construction (IAARC), two most highly regarded academic Duffuaa, Salih O., and Mohamed Ben-Daya. 2004. “Turnaround
societies in Automation in Construction. Maintenance in Petrochemical Industry: Practices and Suggested
Improvements.” Journal of Quality in Maintenance Engineering 10 (3):
184–190. doi:10.1108/13552510410553235.
References
Duffuaa, Salih O., and Mohamed Ben-Daya. 2009. “Turnaround
Abdulmalek, Fawaz A., and Jayant Rajgopal. 2007. “Analyzing the Maintenance.” In Handbook of Maintenance Management and
Benefits of Lean Manufacturing and Value Stream Mapping via Engineering, edited by Mohamed Ben-Daya, Daoud Ait-Kadi, Salih O.
Simulation: A Process Sector Case Study.” International Journal of Duffuaa, Jezdimir Knezevic, and Abdul Raouf, 223–235. London:
Production Economics 107 (1): 223–236. Springer.
Ali, Nauman B., Kai Petersen, and Breno B. N. De França. 2015. Eisenhardt, Kathleen M. 1989. “Building Theories from Case Study
“Evaluation of Simulation-Assisted Value Stream Mapping for Software Research.” Academy of Management Review 14 (4): 532–550. doi:10.
Product Development: Two Industrial Cases.” Information and 5465/amr.1989.4308385.
Software Technology 68: 45–61. doi:10.1016/j.infsof.2015.08.005. En–Nhaili, Ahmed, Anwar Meddaoui, and Driss Bouami. 2015. “A New
Antunes, Ricardo, and Vicente Gonzalez. 2015. “A Production Model for Tool for Maintenance Performance Measurement Using Value Stream
Construction: A Theoretical Framework.” Buildings 5 (1): 209–228. doi: Mapping and Time–Driven Activity–Based Costing.” International
10.3390/buildings5010209. Journal of Process Management and Benchmarking 5 (2): 171–193. doi:
Arslankaya, Seher, and Hatice Atay. 2015. “Maintenance Management 10.1504/IJPMB.2015.068665.
and Lean Manufacturing Practices in a Firm Which Produces Dairy Fellows, Richard F, and Anita MM Liu. 2015. Research Methods for
Construction. John Wiley & Sons.
Products.” Procedia - Social and Behavioral Sciences 207: 214–224. doi:
Frandson, Adam, Klas Berghede, and Iris D. Tommelein. 2013. “Takt-Time
10.1016/j.sbspro.2015.10.090.
Planning For Construction of Exterior Cladding.” Paper presented at
Ashayeri, Jalal, A. Teelen, and W. Selenj. 1996. “A Production and
21th Annual Conference of the International Group for Lean
Maintenance Planning Model for the Process Industry.” International
Construction, Fortaleza, Brazil, July 31–August 2.
Journal of Production Research 34 (12):3311–3326.
Gabriel, Eric. 1997. “The Lean Approach to Project Management.”
Ballard, Glenn. 2000. The Last Planner System of Production Control.
International Journal of Project Management 15 (4): 205–209. doi:10.
Birmingham, UK: University of Birmingham.
1016/S0263-7863(96)00066-X.
Ballard, Glenn, and Gregory Howell. 1998. “Shielding Production:
Ghazali, Zulkipli, and Mohammed Halib. 2011. “The Organization of Plant
Essential Step in Production Control.” Journal of Construction
Turnaround Maintenance in Process-Based Industries: Analytical
Engineering and Management 124 (1): 11–17. doi:10.1061/(ASCE)0733- Framework and Generic Processes.” Journal of International Business
9364(1998)124:1(11). Management & Research 2 (3).
Ballard, Glenn, and Gregory Howell. 2003. “Lean Project Management.” Goldratt, Eliyahu M. 2017. Critical Chain: A Business Novel. New York, NY:
Building Research & Information 31 (2): 119–133. Routledge.
Baluch, Nazim Hussain, Che Sobry Abdullah, and Shahimi Mohtar. 2012. Gupta, Suprakash, and Uday Kumar. 2012. “An Analytical Hierarchy
“TPM and Lean maintenance-A Critical Review.” Interdisciplinary Process (AHP)-Guided Decision Model for Underground Mining
Journal of Contemporary Research in Business 4 (2):850–857. Method Selection.” Review of. International Journal of Mining,
Ben-Daya, Mohamed, Daoud Ait-Kadi, Salih O. Duffuaa, Jezdimir Reclamation and Environment 26 (4): 324–336. doi:10.1080/17480930.
Knezevic, and Abdul Raouf. 2009. Handbook of Maintenance 2011.622480.
Management and Engineering. Vol. 7. London: Springer. Halib, Mohammed, Zulkipli Ghazali, and Shahrina Md Nordin. 2010.
Bertelsen, Sven, and Lauri Koskela. 2002. “Managing the Three Aspects “Plant Turnaround Maintenance in Malaysian Petrochemical Industries:
of Production in Construction.” Paper presented at the 10th annual A Study on Organizational Size and Structuring
conference in the International Group for Lean Construction, Processes.” International Handbook of Academic Research and
Gramado, Brazil, August 6–8. Teaching. p. 55.
Bertolini, M., M. Bevilacqua, F. E. Ciarapica, and G. Giacchetta. 2009. Hicks, Chris, Tom McGovern, Gary Prior, and Iain Smith. 2015. “Applying
“Development of Risk-based Inspection and Maintenance Procedures Lean Principles to the Design of Healthcare Facilities.” International
for an oil Refinery.” Journal of Loss Prevention in the Process Industries Journal of Production Economics 170: 677–686. doi:10.1016/j.ijpe.2015.
22 (2):244–253. 05.029.
PRODUCTION PLANNING & CONTROL 601
Hines, Peter, Matthias Holweg, and Nick Rich. 2004. “Learning to Evolve: Monden, Yasuhiro. 1983. The Toyota Production System. Portland, OR:
A Review of Contemporary Lean Thinking.” International Journal of Productivity Press.
Operations & Production Management 24 (10): 994–1011. doi:10.1108/ Mostafa, Sherif, Sang-Heon Lee, Jantanee Dumrak, Nicholas Chileshe,
01443570410558049. and Hassan Soltan. 2015. “Lean Thinking for a Maintenance Process.”
Howell, Greg, and Glenn Ballard. 1998. “Implementing Lean Production & Manufacturing Research 3 (1): 236–272. doi:10.1080/
Construction: Understanding and Action.” Paper presented at the 6th 21693277.2015.1074124.
Annual Conference of the International Group for Lean Construction, Ogunbiyi, Oyedolapo, Jack Steven Goulding, and Adebayo Oladapo.
Guaruja, Brazil, August 13–15. 2014. “An Empirical Study of the Impact of Lean Construction
Howell, Gregory A., and Lauri Koskela. 2000. “Reforming Project Techniques on Sustainable Construction in the UK.” Construction
Management: The Role of Lean Construction.” Paper presented at the Innovation 14 (1): 88–107. doi:10.1108/CI-08-2012-0045.
10th Annual Conference of the International Group for Lean Okhovat, Mohammad Amin, Mohd Khairol Anuar Mohd Ariffin,
Construction, Brighton, Brazil, July 17–19. Taravatsadat Nehzati, and Seyed Ali. Hosseini. 2012. “Development of
IDC Technologies. 2008. Practice Shutdown and Turnaround Management World Class Manufacturing Framework by Using Six-Sigma, Total
for Engineers and Managers. Perth, Australia: IDC Technologies. Productive Maintenance and Lean.” Review of. Scientific Research and
Ishikawa, Kaoru. 1985. What is Total Quality Control? The Japanese Way. Essays 7 (50): 4230–4241.
Englewood Cliffs, NJ: Prentice Hall. Parida, Aditya, and Uday Kumar. 2009. “Maintenance Productivity and
Kannan, Soundararajan, Yanzhen Li, Naveed Ahmed, and Zeid El-Akkad. Performance Measurement.” In Handbook of Maintenance
2007. “Developing a Maintenance Value Stream Map.” Department of Management and Engineering, edited by Mohamed Ben-Daya, Daoud
Industrial and Information Engineering, The University of Tennessee Ait-Kadi, Salih O. Duffuaa, Jezdimir Knezevic, and Abdul Raouf, 17–41.
Kasava, Nithia Kumar, Noordin Mohd Yusof, Alireza Khademi, and London: Springer.
Muhammad Zameri Mat Saman. 2015. “Sustainable Domain Value Pasqualini, Fernanda, and PauloAntonio Zawislak. 2005. “Value Stream
Stream Mapping (SdVSM) Framework Application in Aircraft Mapping in Construction: A Case Study in a Brazilian Construction
Maintenance: A Case Study.” Procedia CIRP 26: 418–423. doi:10.1016/j. Company.” Paper presented at the 13th International Group for Lean
procir.2014.07.075. Construction Conference, Sydney, Australia, July 19–21.
Kenley, Russell, and Olli Sepp€anen. 2006. Location-Based Management for Robinson, Stewart, Zoe J. Radnor, Nicola Burgess, and Claire
Construction: Planning, Scheduling and Control. New York, NY: Worthington. 2012. “SimLean: Utilising Simulation in the
Routledge. Implementation of Lean in Healthcare.” European Journal of
King, Peter L., and Jennifer S. King. 2015. Value Stream Mapping for the Operational Research 219 (1): 188–197. doi:10.1016/j.ejor.2011.12.029.
Process Industries: Creating a Roadmap for Lean Transformation. New Rother, Mike, and John Shook. 2003. Learning to See: value Stream
York, NY: Productivity Press. Mapping to Add Value and Eliminate Muda. Cambridge, MA: Lean
Koskela, Lauri. 1992. Application of the New Production Philosophy to Enterprise Institute.
Construction. Vol. 72. Stanford, CA: Stanford University. Sacks, Rafael, Ronen Barak, and Biniamin Belaciano, Ury Gurevich, and
Koskela, Lauri. 1997. Lean Production in Construction. In Lean Ergo Pikas. 2013. “KanBIM Workflow Management System: Prototype
Construction, edited by Luis Alarcon. New York, NY: Taylor & Francis Implementation and Field Testing.” Review of. Lean Construction
Lee, Do-Yeop, Hung-lin Chi, Jun Wang, Xiangyu Wang, and Chan-Sik Journal 19–35.
Park. 2016. “A Linked Data System Framework for Sharing Sawhney, Rapinder, Soundararajan Kannan, and Xueping Li. 2009.
Construction Defect Information Using Ontologies and BIM “Developing a Value Stream Map to Evaluate Breakdown Maintenance
Environments.” Automation in Construction 68: 102–113. doi:10.1016/j. Operations.” International Journal of Industrial and Systems Engineering
autcon.2016.05.003. 4 (3): 229–240. doi:10.1504/IJISE.2009.023539.
Lenahan, Tom. 1999. Turnaround Management. Oxford, UK: Butterworth- Shou, Wenchi, Jun Wang, and Xiangyu Wang. 2018. “4D BIM for
Heinemann. Improving Plant Turnaround Maintenance Planning and Execution: A
Leon, Hilda C. Martınez, and Jennifer A. Farris. 2011. “Lean Product Case Study.” Paper presented at the ISARC 2018-35th International
Development Research: Current State and Future Directions.” Symposium on Automation and Robotics in Construction and
Engineering Management Journal 23 (1): 29–51. doi:10.1080/10429247. International AEC/FM Hackathon: The Future of Building Things,
2011.11431885. Berlin, Germany, Julu 20–25.
Li, Jian, Ying Wang, Xiangyu Wang, Hanbin Luo, Shih-Chung Kang, Jun Shou, Wenchi, Xiangyu Wang, Jun Wang, Lei Hou, and Martijn Truijens.
Wang, Jun Guo, and Yi Jiao. 2014. “Benefits of Building Information 2014. “Integration of BIM and Lean Concepts to Improve Maintenance
Modelling in the Project Lifecycle: Construction Projects in Asia.” Efficiency: A Case Study.” Review of. Computing in Civil and Building
International Journal of Advanced Robotic Systems 11 (8): 124. Engineering 2014: 373–380.
Liu, Shaofeng, Mike Leat, Jonathan Moizer, Phil Megicks, and Dulekha Shou, Wenchi, Jun Wang, Peng Wu, and Xiangyu Wang. 2020. “Value
Kasturiratne. 2013. “A Decision-Focused Knowledge Management Adding and Non-Value Adding Activities in Turnaround Maintenance
Framework to Support Collaborative Decision Making for Lean Supply Process: Classification, Validation, and Benefits.” Production Planning &
Chain Management.” International Journal of Production Research 51 Control 31 (1): 60–77. doi:10.1080/09537287.2019.1629038.
(7): 2123–2137. Shou, Wenchi, Jun Wang, Peng Wu, Xiangyu Wang, and Heap-Yih
Lutz, James D., and Adib Hijazi. 1993. “Planning Repetitive Construction: Chong. 2017. “A Cross-Sector Review on the Use of Value Stream
Current Practice.” Construction Management and Economics 11 (2): Mapping.” International Journal of Production Research 55 (13):
99–110. doi:10.1080/01446199300000003. 3906–3928. doi:10.1080/00207543.2017.1311031.
Mathaisel, Dennis F. X. 2005. “A Lean Architecture for Transforming the Shou, Wenchi, Jun Wang, Xiangyu Wang, and Heap-Yih Chong. 2015.
Aerospace Maintenance, Repair and Overhaul (MRO) Enterprise.” “An Application of Value Stream Mapping for Turnaround
International Journal of Productivity and Performance Management 54 Maintenance in Oil and Gas Industry: Case Study and Lessons
(8): 623–644. doi:10.1108/17410400510627499. Learned.” Paper presented at the 31st Annual ARCOM Conference,
McCarthy, Dennis, and Nick Rich. 2015. Lean TPM: A Blueprint for Change. Lincoln, UK, September 7–9.
Oxford, UK: Butterworth-Heinemann. Smith, Ricky, and Bruce Hawkins. 2004. Lean Maintenance: reduce Costs,
McManus, Hugh L. 2005. Product Development Value Stream Mapping Improve Quality, and Increase Market Share. MA, USA: Elsevier.
(PDVSM). Manual Release 1.0. Cambridge, MA: The Lean Aerospace Solding, Petter, and Per Gullander. 2009. “Concepts for Simulation Based
Initiative. Value Stream Mapping.” Paper presented at the Winter Simulation
Moayed, Farman A., and Richard L. Shell. 2009. “Comparison and Conference, Austin, TX, December 13–16.
Evaluation of Maintenance Operations in Lean versus Non-Lean Tendayi, Tinashe George. 2013. An Investigation into the Applicability of
Production Systems.” Journal of Quality in Maintenance Engineering 15 Lean Thinking in an Operational Maintenance Environment.
(3): 285–296. doi:10.1108/13552510910983224. Stellenbosch, South Africa: Stellenbosch University.
602 W. SHOU ET AL.
Utne, Ingrid, Lars Thuestad, Kaare Finbak, and Tom Anders Thorstensen. Crane Layout Planning.” Automation in Construction 59: 168–178. doi:10.
2012. “Shutdown Preparedness in Oil and Gas Production.” Journal of 1016/j.autcon.2015.05.006.
Quality in Maintenance Engineering 18 (2): 154–170. doi:10.1108/ Womack, James P., Daniel T. Jones, and Daniel Roos. 1990. Machine That
13552511211244193. Changed the World. New York, NY: Harper Perennial.
Vinodh, S., R. B. Ruben, and P. Asokan. 2016. “Life Cycle Assessment Wu, Peng, and Yingbin Feng. 2012. “Using Lean Practices to Improve
Integrated Value Stream Mapping Framework to Ensure Sustainable Current Carbon Labelling Schemes for Construction Materials—A
Manufacturing: A Case Study.” Clean Technologies and Environmental General Framework.” Journal of Green Building 7 (1): 173–191. doi:10.
Policy 18 (1): 279–295. doi:10.1007/s10098-015-1016-8. 3992/jgb.7.1.173.
Wambeke, Brad W., Simon M. Hsiang, and Min Liu. 2011. “Causes of Yile, Liu, Xu XueHang, and Zou Lei. 2008. “Lean Maintenance Framework
Variation in Construction Project Task Starting Times and Duration.” and Its Application in Clutch Maintenance.” Paper presented at the
International Conference on Information Management, Innovation
Journal of Construction Engineering and Management 137 (9): 663–677.
Management and Industrial Engineering, Taipei, Taiwan, December
doi:10.1061/(ASCE)CO.1943-7862.0000342.
19–21.
Wang, Jun, Wenchi Shou, Xiangyu Wang, and Peng Wu. 2016.
Yin, Robert K. 2013. Case Study Research: Design and Methods. Thousand
“Developing and Evaluating a Framework of Total Constraint
Oaks, CA: Sage publications.
Management for Improving Workflow in Liquefied Natural Gas
Youssouf, Ayadi, Chaib Rachid, and Verzea Ion. 2014. “Contribution to
Construction.” Construction Management and Economics 34 (12):
the Optimization of Strategy of Maintenance by Lean Six Sigma.”
859–874. doi:10.1007/s10098-015-1016-8. Physics Procedia 55: 512–518. doi:10.1016/j.phpro.2014.08.001.
Wang, Jun, Weizhuo Sun, Wenchi Shou, Xiangyu Wang, Changzhi Wu, Yu, Haitao, Tarry Tweed, Mohamed Al-Hussein, and Reza Nasseri. 2009.
Heap-Yih Chong, Yan Liu, and Cenfei Sun. 2015. “Integrating BIM and “Development of Lean Model for House Construction Using Value
LiDAR for Real-Time Construction Quality Control.” Journal of Stream Mapping.” Journal of Construction Engineering and
Intelligent & Robotic Systems 79 (3–4): 417. Management 135 (8): 782–790. doi:10.1061/(ASCE)0733-9364(2009)
Wang, Jun, Xiangyu Wang, Wenchi Shou, Heap-Yih Chong, and Jun Guo. 135:8(782).
2016. “Building Information Modeling-Based Integration of MEP Zhang, Sijie, Jochen Teizer, Jin-Kook Lee, Charles M. Eastman, and Manu
Layout Designs and Constructability.” Automation in Construction 61: Venugopal. 2013. “Building Information Modeling (BIM) and Safety:
134–146. doi:10.1016/j.autcon.2015.10.003. Automatic Safety Checking of Construction Models and Schedules.”
Wang, Jun, Xuedong Zhang, Wenchi Shou, Xiangyu Wang, Bo Xu, Mi Jeong Review of Automation in Construction 29: 183–195. doi:10.1016/j.aut-
Kim, and Peng Wu. 2015. “A BIM-Based Approach for Automated Tower con.2012.05.006.