You are on page 1of 16

Journal of Financial Management of Property and Construction

Volume 11, Number 2, pp75 - 90, August 2006


Printed in Great Britain

A model for integrating cost management and production plan-


ning and control in construction
ANDREA P. KERN
Universidade do Vale do Rio des Sinos (UNISINOS) Av. Unisinos, 950 - Bairro Cristo
Rei, CEP 93.022-000, Sao Leopoldo-RS, Brazil
CARLOS T. FORMOSO
Federal University of Rio Grande do Sul, Building Innovation Research Unit
(MORIE), Av. Osvaldo Aranha 99, 3o andar, CEP 90035-190. Porto Alegre-RS, Brazil
Summary
• Traditional cost management systems adopted by construction firms have many problems,
which are widely discussed in the literature: the information provided by them is usually too
late, and tends to be too aggregated and too distorted to be relevant for production management.
• The main objective of this research work is to propose a project cost planning and control
model for construction firms. This model aims to support the development of production
management systems, in which cost management and production planning and control can be
gradually integrated, in order to overcome the existing limitations of cost accounting systems.
• The scope of the model was limited to building projects carried out by small and
medium sized companies, involved in both product development and production.
The development of the model was based on the literature review and also on the re-
sults of nine empirical studies conducted in four different Brazilian construction firms.
• The model suggests the integrated application of three fairly well known cost management
techniques: operational cost estimating, S-curves and target costing. By using this set of tools,
it is expected that cost management will become more proactive, and able to deal with the
dynamic, uncertain and complex construction environment that exists in most projects. The
model was partially tested in two case studies, in which it provided key information for sup-
porting decision making related to design, production planning and contracts with suppliers.

Keywords: cost management, planning production control, cash flow, S-curves, opera-
tional cost estimating, target costing.

Introduction systems have three important consequences. Firstly,


these systems cannot provide accurate product cost:
costs are distributed to products in a simplistic and arbi-
Despite the environmental, managerial and technologi- trary way that usually does not represent the real demand
cal changes that have occurred in the last few decades, imposed by each product on the company’s resources
existing cost management systems tend to be very (Ostrenga et al., 1998). Secondly, such systems fail to
similar to the ones that have been used since the mid stimulate decisions that can affect the overall production
Twenties (Johnson and Kaplan, 1993). In the face of all result. Managers are sometimes encouraged to accom-
these changes, traditional cost account information has plish short-term goals by reducing expenses with train-
become mostly irrelevant and even dangerous for man- ing and investments, or even by increasing the level of
agerial purposes (Ploss, 1999; Kim, 2002). According inventory(Ostrenga et al., 1998). Although effective in
to Johnson and Kaplan (1993), such information tends the short term, these decisions can seriously affect future
to be too late, too aggregated and too distorted to be results (Goldratt and Cox, 1989). Finally, the cost man-
relevant for production management, since they are agement information provided by traditional systems is
generated mostly to satisfy fiscal and financial needs. of little help to managers in their effort to improve pro-
The drawbacks of the traditional cost management duction performance. Poor transparency allied with the

© Glasgow Caledonian University


76 A. P. Kern and C. T. Formoso

lack of timeliness makes cost information ineffective to Uncertainty, variability, interdependence and com-
help in the identification and elimination of waste. plexity play a key role in the construction environment,
Particularly in the construction industry, the exist- and a major challenge for production management sys-
ing gap between the available cost information and the tems is to eliminate or to reduce the impact of these
goals set to the business is pointed as being one of the characteristics (Koskela, 2000). Moreover, the uncer-
main faults of traditional cost management systems tainty related to the financial environment must also be
(Kim, 2002). Often construction cost control consists considered, regarding the significant amount of capital
basically of monitoring actual performance against cost required by construction projects (Barbosa and Pimen-
estimates and identifying variances. As a result, tradi- tel, 2001).
tional cost control systems have been much more useful According to Koskela (2000), management systems in
to manage contracts than production (Howell and Bal- construction tend to be ineffective due to the fact that the
lard, 1996). nature of the production processes involved is not prop-
This paper discusses traditional cost management erly taken into consideration. The same author suggests
practices in the construction industry and proposes a that a major underlying cause of the ineffectiveness of
project cost planning and control model for construc- production management is the fact that production is
tion companies. Cost planning and control is defined viewed as a transformation process, without explicitly
in this study as a managerial process that must be per- considering the non value-adding activities, which tend
formed in all project phases, involving different sectors to be neglected in production control despite their high
and other processes of a construction. Its main objec- impact in terms of cost. In fact, both cost estimates and
tive is to generate cost information to support decision- production plans for construction projects are typically
making related to production management in order to segmented in items that represent only value-adding
reach the goals set for the business, including decisions activities (Koskela, 2000).
related to finance, profitability, timing, and quality. In the case of cost estimating, the information pro-
This model aims to support the development of duced has the additional drawback that it is remotely
production management systems in which cost man- related to the way costs are incurred. Most cost meth-
agement and production planning and control can be ods adopted in the industry are strongly based on the
gradually integrated, in order to overcome the existing standard cost method, and tend to associate each cost
limitations of cost accounting systems. The scope of the item to a finished element, e.g. walls (m2), reinforced
model was limited to building projects carried out by concrete components (m3), windows (units), obtained
small and medium sized companies, involved in both from design drawings (Koskela, 2000). This makes
product development and production processes. The it difficult to examine accurately the effect of design
development of the model was based on the literature changes in production costs.
review and also on the results of empirical studies con- Moreover, although time is a factor of major impor-
ducted in four different Brazilian construction firms. tance in construction costs, traditional cost estimating
methods do not offer any reliable guidance for assess-
Cost estimating practices in the construction in- ing the impact of production duration on project costs
dustry (Kaka and Price, 1991; Turner, 1993; Navon, 1995).
Horngreen et al. (1990) argue that cost management
Differently from other industries, the product of the con- must not be isolated from other managerial functions,
struction industry product is one-of-a-kind and most of and should play a key role in the implementation of
the production takes place in a temporary environment, the company strategies. Kim (2002) suggests that cost
which is vulnerable to weather conditions. Thus, substan- management systems should involve a set of processes
tial changes often occur in the product and in construction required to ensure that a construction project is com-
methods during the design and production phases. These pleted within the approved budget, including cost esti-
limit the usefulness of the early cost estimates on which mating, cost control and cost projection. Navon (1995)
the business is based. points out that the proper consideration of the interac-
Due to the unique characteristics of the product involved, tion between cost and time in construction projects de-
specific information is necessary for each new project. pends on the integration of cost management systems to
This means that cost management models developed for production management.
industries in which processes are repetitive and relatively Therefore, cost management systems in construction
stable cannot be easily adapted to construction projects. must be dynamic, proactive and able to support differ-

© GCU Journal of Financial Management of Property and Construction, 11 (2)


A model for integrating cost management and production planning and control 77

-ent decision-making processes, in order to protect the The information produced by ABC cost systems can po-
business from the harmful effects of uncertainty. Their tentially increase process transparency, providing guid-
main objective should be to generate information to ance to identify non-value-adding activities (Marche-
support decision- making, mainly concerned with cost san and Formoso, 2001).
reduction, value improvement and financial manage- Notwithstanding the benefits of its application, ABC
ment. presents some drawbacks when compared to traditional
Considering this context, this study proposes a cost cost systems. Perhaps, the most important one is the
planning and control model that integrates the use of large amount of data usually needed in ABC systems.
three cost management techniques, which have been Indeed, according to some authors (Krieger, 1997), the
identified in the literature as potentially helpful for im- excessive level of detail is a major cause of unsuccess-
proving cost management in construction: operational ful ABC implementations. This problem can be even
cost estimating, S-curves, and target costing. These are worse in unstable and complex production systems,
described bellow. such as those observed in the construction industry
(Marchesan and Formoso, 2001).
OPERATIONAL COST ESTIMATING The idea of using operational cost estimating in this
research is to keep production into perspective during
The idea of using an operational approach for cost es- the estimating process. Thus, costs of non-value ac-
timating is not new. In the Sixties, Skoyles (1965) dis- tivities can be identified and estimated to some extent.
cussed a radical change in traditional cost estimating Moreover, the changes (i.e., design, production plan-
methods that had been proposed in the U.K., in which ning) that might occur after the initial cost estimate, due
a very detailed estimate of the project was produced to the uncertainty of the construction environment may
based on the early definition of construction methods. be taken into consideration.
This approach was not successful because it was con-
sidered to be too time consuming and also due the lack CASHFLOW S-CURVES
of knowledge on production methods by cost estimat-
ing professionals. It seems that the main difficulty for The S-curve is a fairly simple technique that presents
implementing such an approach was that the high level graphically the project cash-flow. It can be used to
of uncertainty and variability that exist in construc- forecast and control the use of resources throughout a
tion at the early project stages was neglected. Barnes project (Kim and Ballard, 2001). S-curves can be used
(1977) proposed a less radical approach to operational for simulating different scenarios, considering time and
cost estimating for construction projects, suggesting cost deviations, and also for summarising key informa-
the use of different cost drivers for estimating the cost tion for supporting decision making in different sectors
of resources, which were classified into fixed, quantity of a firm (Neale and Neale, 1989). Due to its simplicity,
based, time-based, and price-based. they can be used a visual device for displaying informa-
Activity-Based Costing (ABC) is a cost method that tion that is quickly understood in the working environ-
has been recently adopted in many industrial and serv- ment.
ice firms as a method to improve cost management in Although S-curves do not solve problems concerning
complex production systems. It is basically a two-stage limitations in cost estimating (Bazarra et al. 2000), this tool
approach for allocating indirect costs to products based is very useful for supporting production management since
on cost drivers of various levels (Kaplan and Cooper, it can be used for integrating information from production
1998). In the first stage, resource costs (labour, equip- plans and cost estimates (Kim and Ballard, 2001).
ment and power) are assigned to those activities per- S-curves are often used as both a cost and time con-
formed in the organisation. During the second stage, trol tool, by applying the earned value method (EVM).
activities costs are assigned to the cost objects based Kim and Ballard (2000) define EVM as a project control
on selected cost drivers (e.g., machine set-up, quality technique that provides a quantitative measure of work
inspection and material handling activities), which ex- performance: project progress is measured against an
press a causal relation between the activity demand and earnings plan. The entire project is divided into the vari-
the cost object considered (Ostrenga et al 1998). Besides ous types of work required, each with their own budget
the fact that ABC allows to directly trace manufactur- unit rates, with 100% corresponding to their aggregated
ing costs to products, it is also possible to determine the budgets. It involves a crediting of budget dollars or labour
costs related to product families, services and clients. hours as scheduled work is performed.

© GCU Journal of Financial Management of Property and Construction, 11 (2)


78 A. P. Kern and C. T. Formoso

However, this technique has been criticized by Kim process of product design (Cooper and Slagmulder,
and Ballard (2000): EVM is an effective tool only un- 1997).
der the limiting assumption that every activity or cost While target costing is focused in cost reduction dur-
account is independent. According to them, activities ing the design process, a similar technique, named kai-
should be considered as being dependent. Also, the au- zen costing, has been used during the production phase,
thors point out the work sequence can be manipulated with the main objective of reducing costs in order to
by managers, releasing work assignment to the field, achieve a pre-established target cost (Monden, 1999).
that are not shielded from uncertainty. A further prob- However, as in most construction projects, there is an
lem cited by Kim and Ballard (2000) is that with the overlap between the design and the production phases,
objective of making cost variance positive, managers this study proposes the use of target costing in the pro-
may try to decrease the actual cost of work performed duction phase, in construction companies that also get
as much as possible. The overload resulting from re- involved in the product development process.
duced capacity can make work flow less reliable, which
in turn can impact the performance of downstream pro- Research method
duction units.
This research project started in November 2001 and
TARGET COSTING ended in February 2005. Multiple case studies were the
research strategy adopted in this investigation. Com-
Target costing has been widely used by some leading pared to a single case study this creates a richer learning
industrial companies with the main objective of re- opportunity since the weaknesses of one study may be
ducing the final cost of the product in order to obtain compensated by the strengths of others. Moreover, de-
the expected profitability while ensuring satisfactory veloping an investigation in different organisational en-
quality levels (Maskell and Baggaley, 2003). It can be vironments creates favourable conditions for reflecting
described as a structured way of establishing the cost on the processes being investigated at a higher level of
and quality that must be achieved in the development abstraction.
of a product in order to reach the desired profitability Table 1 presents a brief description of the four compa-
(Cooper, 1995). nies involved in this study. They are all small and medi-
Target costing can be divided into two main steps. um sized companies, located in the Metropolitan Region
Firstly, a cost target should be established for the prod- of Porto Alegre, in the South of Brazil, and their main
uct, by subtracting the product’s desired profit margin business is to develop and construct building projects.
from its expected selling price. Secondly, the target cost The main criteria for choosing the companies were: (a)
of the product is distributed to its components, materi- their willingness to participate in this study; (b) they all
als or systems (Cooper, 1995). Differently from tradi- had fairly effective production planning and control sys-
tional cost estimating processes, cost is regarded as an tems; and (c) they were representative of different mar-
input and not as an outcome of the design process. By ket segments in Brazil. Three of the companies (A, B and
setting target costs based on market-driven selling prices, C) had been using for several years production planning
target costing transmits the cost pressure that is placed on and control systems strongly based in the Last Planner
the firm by the marketplace to everyone involved in the System for Production Control (Ballard, 2000).
Table 1: Brief description of the companies involved in this study
Company Number of direct Main market segment Turn-over
employees (US$/year)
A 14 Development and construction of 4,000,000.00
housing building projects for lower
middle class
B 136 Construction and refurbishment of 20,000,000.00
industrial buildings and hospitals,
including both the management of
the design and production processes
C 89 Development and construction of 4,600,000.00
social housing projects, and construction
and refurbishment of industrial buildings.
D 73 Development and construction of house 10,000,000.00
building projects for higher middle class

© GCU Journal of Financial Management of Property and Construction, 11 (2)


A model for integrating cost management and production planning and control 79

Figure 1: Overview of the research design

Figure 2: Brief description of the case studies carried out in the second and fourth tesearch stages

Figure 1 presents an overview of the research design, In the second stage, exploratory case studies were
including the main research questions, as well as the undertaken in three different construction projects, with
case studies and companies involved in each one of the the objective of defining the scope of the cost planning
four research stages. and control model and the role of the three cost man-
The first set of studies was focused on the cost man- agement tools (cash flow S-curves, operational cost es-
agement systems of each one of the four companies. timating and target costing). Based on stages 1 and 2
The aim was to understand the existing problems in the and also in the literature review, a project cost planning
cost management systems adopted by those firms. The and control model for construction companies was pro-
processes and sectors involved in cost management posed in the third research stage. Finally, the proposed
were investigated, as well as the main decisions made model was tested in two different projects in the fourth
by managers that were supported by cost information. research stage, in which the model was partially imple

© GCU Journal of Financial Management of Property and Construction, 11 (2)


80 A. P. Kern and C. T. Formoso

mented in two different projects. SECOND RESEARCH STAGE: CONTEXT


The main characteristics of the projects investigated EXPLORATION
in the second and fourth research stages are presented
in Figure 2. All three empirical studies carried out in the second stage
It is important to point out that the research strategy involved the combined implementation of cash flow S-
imposed some limitations in the scope of the model, curve and operational cost estimating as a mechanism
since its development was based on a set of case studies for integrating cost control into the production planning
in which changes in the cost management of construc- and control process. The S-curve was mainly used to
tion projects were implemented. The degree of innova- make cost projections, as well as to assess whether the
tion introduced by the model was to some extent lim- project cash flow was adequate. In Case Study 6, a tar-
ited by the success of the implementation process. get costing exercise was also carried out.
The main sources of evidence used in the case studies
were: (a) interviews with contract managers, produc- • Case Study 5
tion managers and cost estimators; (b) participant ob- Case study 5 involved an investigation on the cost man-
servation in cost management and production planning agement system of a low-income house-building project
meetings; (c) analysis of documents (e.g. production in which the houses were to be delivered in stages. Each
plans, cost estimates, etc.). stage consisted of ten terraced house blocks.
The S-curve was gradually introduced in the com-
Results pany with the aim of producing a reliable cost plan, in-
volving the following tasks:
FIRST RESEARCH STAGE: CONTEXT UN- (a) The cost estimate structure was changed so that
DERSTANDING each item of the bill of quantities had a correspond-
ing activity in the long-term production plan, i.e. an
The case studies conducted in the first research stage operational cost estimate for each production activity
indicated that the four companies had faced problems was produced. This task was jointly performed by the
that are relatively similar to those pointed out in the project production manager and the person responsible
literature. Although the companies had fairly organized for cost estimating;
project financial controls, their managers stated that (b) The project resources were divided into two cat-
there was a lack of cost information to support decision egories in order to simplify cost control. For the most
making related to design, production and contracts. expensive items, detailed information on labour and
All four companies had some kind of cost database, material costs, resource consumption and payment
but they faced difficulties in keeping it updated. Some dates were considered, while for the other items only
of the people interviewed pointed out that this is dif- a lump sum was estimated for each month. The pro-
ficult because it requires information from different duction manager and the person responsible of material
processes and sectors. Firm directors were particularly supply were in charge of this task;
dissatisfied with cost control due to the fact that the (c) Information on the expected monthly income pay-
information produced was usually late and too aggre- ments were provided by the financial sector of the com-
gated. pany;
Another important drawback was that in none of the (d) The cost plan was then produced combining in-
companies was production planning and control and formation from production plans, cost estimates, sched-
cost management integrated. In Companies A and C ule of material and labour payments, and income pay-
production managers were not involved in the project ments. This information was organised in a spreadsheet
cost management system at all. In Company B and and also displayed as project cash flow S-Curves (see
D, although the production managers were in charge example in Table 2); and
of both cost control and production management, they (e) The cost plan was updated every month, when a
dealt with them separately, since the information was new three-month look-ahead plan was produced.
available in two different information systems. The introduction of cost plans and S-curves demanded
changes in the information flow of the company. Differ-
ent sectors (production, cost estimating, material supply
and finance) started to be in charge of providing the infor-
mation that was necessary to keep the S-curve updated.

© GCU Journal of Financial Management of Property and Construction, 11 (2)


A model for integrating cost management and production planning and control 81

Table 2: Example of a cost plan from Case Study 5


Production planning activities Activity cost estimates January February March
Labour Material Labour Material Labour Material Labour Material
cost (R$) cost (R$) cost cost cost cost cost cost
Pile location 30,000,000 9,360,000 3,000,000 9,360,000 3,000,000 3,000,000
Formwork foundation beam 500,000 500,000
production
Formwork foundation beam 500,000 500,000
assembly
Steel reinforcement 600,000 3,633,320 600,000 3,633,320
preparation
Steel reinforcement assembly 600,000 600,000
Foundation beam concrete 600,000 3,164,000 600,000 2,000,000 1,164,000
Beam formwork removal 200,000 200,000
Plumbing kit assembly 600,000 3,055,000 600,000 3,055,000
Internal landfill 300,000 300,000
Concrete slab 1,500,000 1,500,000
Ground floor brick wall 3,600,000 4,116,280 3,600,000 4,116,280
Precast slab assembly 1,800,000 1,168,900 1,168,900
Electrical pipes 1,200,000 247,000 247,000
Slab reinforcement 300,000 998,850 998,850
Note: The financial figures have all been changed due to the need for confidientiality

Figure 3: Cost plans of project phases 1 and 3 in Case Study 5

Updated cost plans and S-curves were used for sup- production plan, was very time consuming. As in case
porting decisions that improved the cash flow from the 5, a more detailed operational cost estimate was pro-
project phase 1 to 3, as shown in Figure 3. Those de- duced for the most expensive items in order to make it
cisions were mostly related to changes in production easier to implement that tool.
plans and also in resource payment schedules, due to One of the problems faced by the construction firm
new agreements that were established with key suppli- was the relatively low profit margin that was expected
ers. after the initial production phases due to a cost overrun
in the foundation activities. For that reason the company
established some cost targets for the following stages,
• Case Study 6 with the aim of reducing the total project cost. Based on
Case study 6 involved an investigation on a much larger those cost targets, new design solutions and alternative
project than in Case 5. The project consisted of the con- production methods were investigated, which resulted
struction of two hospital buildings, and there was much in the renegotiation of contracts with some of the main
overlapping between the design and production phases. suppliers. Also, a spreadsheet for estimating overhead
Due to the size and complexity of the project, the imple- costs was developed by the firm, so that the impact of
mentation of S-curves for producing cost plans, based project duration on costs could be properly assessed.
on the existing cost estimates and the long-term Figure 4 presents the project cash flow after those

© GCU Journal of Financial Management of Property and Construction, 11 (2)


82 A. P. Kern and C. T. Formoso

Figure 4: Cost and revenue planning of hospital project studied in Case Study 6

Figure 5: Improvement in project cash flow in Case Study 7


changes were introduced, indicating the unfavourable into an operational cost estimate so that it could be
cash flow balance at the beginning of the project. used to produce cost plans. The application of S-curves
Although target costing was not fully implemented enabled managers to make some important decisions
in this project, in this case study it was possible to link related to changes in the sequence of production activi-
cost targets to S-curves, making it easier to assess the ties in order to improve the cash flow of the project.
impact of changes in design and construction methods Figure 5 compares the initial cash flow for one of
in the project cash flow, especially at the early project the projects (cash flow 1), and the one that was pro-
phases, based on a fairly operational cost estimate. duced based on the cost plan (cash flow 2), after some
changes were introduced in the long-term production
• Case Study 7 plan. It indicates that the project cash flow was sub-
Case study 7 involved the use of cash flow S-curves stantially improved.
during the conception phase of a low-income hous- In all three case studies the implementation of S-
ing project. Based on data from two similar previous curves provided some short term benefits for the compa-
projects, different cash flow scenarios were simulated nies in terms of supporting managers in their decisions,
considering changes in the long-term production plans. such as assessing economic and financial feasibility,
This also required the translation of cost information changing long-term production plans, and identif-

© GCU Journal of Financial Management of Property and Construction, 11 (2)


A model for integrating cost management and production planning and control 83

-ying the need of renegotiating contracts. Although • Cost planning and control systems
the initial translation of cost information into a proc- After costs have been estimated, they should be planned
ess based model was time consuming, those studies and controlled, according to pre-established cycles. Cost
indicated that it is feasible to gradually introduce an plans ought to be updated and changed whenever neces-
operational approach to cost estimating. This approach sary and situations that need special attention should be
includes gathering information from different sectors, highlighted. The cost plan must have an operational form,
focussing on high cost items, and making explicit some i.e. be easily related to production activities and resources
non-value adding activities, instead of adopting a high- – this was achieved to some extent in Case Studies 5, 6
ly centralised cost control approach mostly based on and 7. This is an important difference between this model
the standard cost method. and the traditional cost planning techniques (see, for in-
stance, Ferry and Brandon, 1984).
THIRD RESEARCH STAGE: MODEL PROPOSAL Figure 6 presents an overview of the proposed model. The
• Scope of the model cost planning and control process is divided into five activi-
In this study, the cost planning and control process was ties, similarly to the production planning and control model
divided into two subprocesses: cost estimating and cost proposed by Laufer and Tucker (1987): process preparation,
planning and control. information collection, plan preparation, information diffu-
The information generated in the cost estimating sub- sion, and process evaluation.
process at the early design stages should be used mostly “Process preparation” consists of defining how cost plan-
for supporting decisions related both to the initial ne- ning and control will be performed in each project, involving
gotiations with the client and suppliers and to the de- several decisions such as the role of each person or sector
sign process. This cost estimate must be seen as a target involved, tools to be used, and frequency of control cycles.
that may change over time, due to the dynamic nature “Information collection” typically involves gathering infor-
of most construction projects. It needs to be updated mation from different sources, such as design, contracts, pro-
whenever changes in design, production and contracts duction control, resource schedules, and cost database. Once
are made. For example, in Case Study 5 it was neces- the cost plan is prepared, the information produced must be

Figure 6: Cost estimating and planning and control stages.

-sary to search for new design solutions and alternative disseminated to different users in order to guide the nec-
production methods due to the need of reducing the re- essary actions to be carried out.
maining project costs. It was a kind of partial applica- Further information needs to be collected and used for
tion of target costing in which the cost targets for some updating the cost plans. Some information collected dur-
building elements had to be reduced after the produc- ing the project can also be used for updating the cost data-
tion phase had started. base of the company. At the end of the project, the cost
plan ning and control process must be evaluated so
that this process can be improved in future projects.

© GCU Journal of Financial Management of Property and Construction, 11 (2)


84 A. P. Kern and C. T. Formoso

• Cost planning and control tools They were also in charge of an overall financial control
Figure 7 illustrates how cash flow S-curves, operational of the project, the only kind of cost control that existed
cost estimating, and target costing are integrated in the in the company.
model. Target costing should be used to support early The cost-estimating department was in charge of
project decisions related to design, supply chain, and estimating direct costs, including the updating of the
production system design. Such decisions must take into existing cost database, while overhead costs were es-
consideration the target cost established for the project timated by the company directors. The focus of the
at the cost estimating sub-process. An operational cost production managers was to keep production on time
estimating approach must be used, based on informa- and the material supply department was responsible for
tion from design, production plan and contracts with purchasing materials demanded by production manag-
suppliers, so that the impact of decisions concerned ers. Therefore, the production, material supply and cost
with design and construction methods on project costs estimating sectors were not well integrated, and did not
and duration can be properly assessed. get involved in major project decisions, such as choos-
S-curves play a central role in the cost planning and ing suppliers and defining long-term production mile-
control sub-process, from the early stages of the project stones.
throughout the design and production stages. It demands According to one of the directors, there was a general
information from different sectors, such as cost esti- dissatisfaction in the company with cost management
mating, production management, and material supply. since there was very little cost information available
Target costing can also be used during this sub-process, that could support timely production management deci-
if there is an overlap between design and production sions. Cost control had a reactive character, meaning
phases, as it was undertaken in Case Study 6. that cost deviations were detected too late and it was
difficult to spot the main causes of deviations. In fact,
FOURTH RESEARCH STAGE: MODEL EVALUATION the company had faced financial losses in one previous
• Case study 8 low-income house-building project.
Before this study was conducted, cost management In this case study, the cost planning and control mod-
in Company C, was mostly carried out by the firm el was partially implemented in three different projects
direct-ors, who also supervised cost estimating ac- that had just started. For each of those projects, an ini-
tivities. tial cost estimative had been produced and the contract

Figure 7: The integration of target costing, operational cost estimating and cash flow S-curves

© GCU Journal of Financial Management of Property and Construction, 11 (2)


A model for integrating cost management and production planning and control 85

had already been signed with the National Savings Several production management decisions were based
Bank based on that document. It was not possible to on this new control cycle, mostly related to changes in
implement target costing because the design was com- resource schedules and production plans. According to
pleted and there was not much flexibility for introduc- the firm director, such decisions were based mostly on
ing changes. the S-curve shape rather then on detailed information
At the beginning of the study several meetings were on activity durations or cost estimates.
held, involving one of the firm directors, the research This integration of cost management and production
team and representatives of the cost estimating depart- planning and control was made possible due to the fact
ment, material supply department and production man- that some important changes that were made in the cost
agers. In these meetings, the necessary information flow estimates, in which a more operational approach was
for carrying out the cost planning and control process incrementally introduced, based on previous projects.
was defined. This was made easier because a separate cost data-
The production manager assumed the role of collect- base was created specifically for low-income housing
ing the required information and preparing the cost plan projects.
using S-curves. The project cost plans were presented The implementation of the model resulted in a much
and discussed every two weeks in a meeting by every- broader involvement of different sectors in cost man-
one involved in the process, forming the cost planning agement, as shown in Table 3.
and control cycle. People from different sectors became engaged in dif
Table 3: Organizational change due to the model implementation.
Activities Directors Production Cost estimating Material supply
managers department department
Before the implementation

Cost estimating Estimating Estimating Estimating


overhead direct cost direct costs
of the model

Cost database Database updating


Cost control Overall financial
control
Decision-making Major cost related
decisions

Cost estimating Estimating Estimating Estimating Analysis of database


After the implementation of the

overhead direct cost direct costs regarding market


Database updating Analysis of the Database updating prices of resources
database regarding
production aspects
model

Cost planning Overall financial Cost planning Provide information Provide


control for cost estimating information of
payment dates
Cost control Proactive control Proactive control Proactive control
in real time in real time in real time
Main decisions Major cost Production Decisions related Decision related
involved related decisions management cost to estimating process to material supply

Such control cycle was strongly linked to the look- -ves, as shown in Figure 8, pointing out the items for
ahead (medium-term) production planning level, in which it was still possible to negotiate price and pay-
which constraints should be identified and removed. ments with suppliers. ferent activities, such as data
The main focus of this discussion was the results collection, and database updating, and started to get
achieved so far, in terms of time and cost deviations, involved in the decision-making process. Moreover,
and the resources to be purchased within the medium- systematic cost planning and control cycles were in-
term plan horizon. troduced, allowing managers to make timely decisions,
Based on a suggestion of the material supply manag- rather than simply obtaining late information on cost
er, direct costs were divided into two categories: com- deviations. According to one of the company directors,
mitted and not-committed. This enabled the amount of these changes in cost management has decisively con-
resources to be purchased to be visualised in the S-cur- tributed for the success of the three projects that were

© GCU Journal of Financial Management of Property and Construction, 11 (2)


86 A. P. Kern and C. T. Formoso

investigated in this case study – all of them had a much project, and the design had not been fully conclud-
better financial performance (profit margin around 8%) ed.
than the previous one (profit margin around –7%). The client commissioned the architectural and struc-
tural designs, which were developed to the sketch design
• Case Study 9 level. The project consisted of a reinforced concrete struc-
Since 2002, Company B has been seeking to improve ture, steel roof, and brick walls.
its cost management system because the firm directors Company B took part in a competitive bidding, in which
realized that some important projects were not so suc- several other construction firms had participated. Both tar-
cessful in terms of profitability as expected. They also get costing and operational cost estimating techniques were
realized that the company had not been very successful used as a basis for the formulation of the proposal.
in terms of winning contracts. According to some direc- The target cost was initially based on a previous
tors and production managers, a major cause for those similar project and also on the available design. Based
problems was that prices were not adequately formulated on this information the final price of the project was es-
in the cost estimating process. tablished, and the target cost resulted from the subtrac-
Due to those problems the company changed its bid- tion of the profit margin expected by the firm directors.
ding strategy. Instead of bidding for several price requests After establishing the project target cost, directors and
from potential clients, the company decided to focus its the contract manager (who had experience in similar
efforts only on projects that had the potential of becomi- projects) established the target-costs for the main sub-

Figure 8: S-curves developed by Company C in Case Study 8


-ing very profitable. It means that when the company systems involved and estimated the overhead costs with
decided to make a proposal for a project, a thorough support from the cost estimating sector.
analysis of design, and client requirements was un- For the negotiation with subsystem suppliers, an opera-
dertaken, in order to develop new solutions in col- tional approach to cost estimating was adopted, in which
laboration with some key suppliers. The aim was to a unit price was initially established for each of them, e.g.
make a proposal in which the cost was reduced and foundation (m3), reinforced concrete pre-cast structure
the value for the client increased. Before that change (m3), steel roof structure (m2).
in the bidding strategy, the firm used to make an ef- Once the project started and the main suppliers were con-
fort for developing new solutions, but only after the tracted, some collaborative design meetings were carried
contract was signed. out for developing the detail design. Those meetings in-
Case study 9 was carried out on the refurbish- volved not only designers but also a client´s representative
ment of an industrial building for a steel mill. The and suppliers, and were chaired by production managers
complexity of this project is much related to the fact from Company B. They jointly develop design solutions
that this building was inside an industrial site that re- and production methods, aiming to meet requirements
mained in operation. Moreover, the project duration from both the client and the production system. The use of
was relatively short (six months) for the size of the target costing by Company B is illustrated in Figure 9.

© GCU Journal of Financial Management of Property and Construction, 11 (2)


A model for integrating cost management and production planning and control 87

Figure 9: The implementation of target-costing in Case Study 9.

Table 4: Total cost reduction from new engineering solution in Case Study 9
Description Client New design Cost reduction Solution
design
Overhead costs R$ 61.11
Preliminary services R$ 53.54
Foundation R$ 56.98 R$ 48.00 18.71% Beams elimination
Concrete structure R$ 205.96 R$ 174.49 17.96% New modularisation: elimination of column
Walls R$ 87.74
Concrete floor R$ 67.37
Windows/doors R$ 58.42
Roof R$ 475.32 R$ 417.20 13.92% New structure conception
Painting R$ 22.27
Sanitary installation R$ 9.85
Total R$ 1,098.47 R$ 1,000.00 9.85%
Note: The financial figures have all been changed due to the need for confidentiality

The most important changes introduced in the project Discussion


consisted of a new conception of the foundations, re-
inforced concrete structure and roof steel structure, re- The cost planning and control model that was proposed
sulting in a reduction of 9.85% of the total estimated in this investigation is based on the simultaneous use
costs, as shown in Table 4. of different cost modelling principles, according to the
The new conception of the roof structure resulted in type of resource that is considered. For instance, the
a reduction of 37% of the steel weight. The subsystem standard cost method approach may be effective for es-
supplier, which was hired by the construction firm, timating the cost of some materials. By contrast, the
played a key role in developing this new solution. Also, overhead costs were classified in three different catego-
some major changes were made in the concrete struc- ries as suggested by Barnes (1977): fixed, time-based
ture. The pre-cast concrete supplier proposed a different and price-based. Labour costs in most companies are
column modularisation, increasing the beam span from mostly related to the market price of subcontracted
5 to 10 metres. This was possible because fibre-cement work, rather than on standard cost based productivity
roof tiles were used for cladding and gypsum plaster- rates. If a construction component is purchased as a
board for the internal walls, instead of ceramic brick- subsystem, then there is usually an existing cost model
walls, reducing the total load. Moreover, due to those for estimating its purchasing cost (that often includes
changes, the foundation structure was also reduced. design, materials, prefabrication and installation work).
This allows making explicit the cost of some non-val-

© GCU Journal of Financial Management of Property and Construction, 11 (2)


88 A. P. Kern and C. T. Formoso

-ue-added activities, especially those related to over- -ease value for the client. This technique can be used
head. Therefore, by keeping production into perspec- in different phases of the project, from the early stages
tive during the estimating process it is possible to take through to design and production stages.
into consideration to some extent the nature of the pro-
duction process and its impacts on the final cost of the Conclusion
project.
Of course, an operational approach for cost estimat- Existing literature suggests that one of the main factors
ing would demand a substantial change in the project that contribute to the poor performance of traditional
cost structure, and tends be more time consuming, due cost management systems is the fact that they do not
to the wider range of data that need to be dealt with. take into consideration the nature of the product and the
However, the case studies carried out in the second and production processes involved, due to the conceptual
fourth stages of this research indicated that this prob- basis on which these are founded.
lem can be minimized when all relevant sectors of the This assumption was confirmed by the case studies
company are involved in this task, and also if the initial carried out in this study. All companies were dissatisfied
cost estimate is based on a production plan. with their cost control systems, which did not provide
The cost planning and control cycle must be short timely information that could be used for improving
enough so that it generates timely information that sup- the performance of their production systems. The main
ports decision-making in real time. Due to the complex causes of the ineffectiveness of such systems were the
and dynamic environment of most construction projects, separation between cost management and production
cost information needs to be updated frequently. This planning and control.
will also demand the participation of different sectors This paper has proposed a cost planning and control
of the company. It is also necessary to focus cost con- model, which was developed and tested in several em-
trol on the high cost items, in order to reduce the effort pirical studies conducted in different small and medium
needed. A Pareto diagram is useful for selecting them. sized construction companies from the South of Brazil.
S-curves should be also used for forcasting the project The proposed model is strongly based on the integration
cash flow by updating payments and revenue dates, as of production planning and control and cost estimating.
it was undertaken in case studies 5 and 7. Such simula- It proposes that costs should be planned and control-
tions can be useful to support negotiations with suppli- led in fairly short cycles, from the early project stages,
ers in terms of payment dates and prices, as well as to throughout the design and production phases, involving
decide about changes in production plans, in order to information from different sectors of the company.
improve the project cash flow. The model suggests the integrated application of three
The integration of cost management and production fairly well known cost management techniques: opera-
control, which was based in the Last Planner System, tional cost estimating, S-curves and target costing. By
minimized some of the drawbacks of the Earned Value using this set of tools, it is expected that cost manage-
Method. The way S-curves is suggested to be used is ment will become more proactive, and able to deal with
strongly based on the integration of production plan the dynamic, uncertain and complex construction envi-
with cost estimatiing. It must take into consideration ronment that exists in most projects. However, due to
activities packages from production long-term plan, the unique character of each project, the way in which
to minimise the problems related to EVM technique this set of tools is used may vary considerably.
discussed in Cash flow S-curves item. For example, by The partial implementation of the model in two case
using work packages from production long-term plan, it studies had positive impacts in the performance of tho-
should be consider the dependence of activities. -se projects. It provided key information to support de-
Moreover, due to the strong link between production cision making related to design, production plans and
management and cost planning and control, this study contracts with suppliers.
suggests that production managers should be in charge of The implementation of the model made also a con-
both processes, as it happened in the case studies carried tribution in terms of increasing process transparency,
out in the second and fourth research stages. making visible some important problems to the people
Target costing may be used as a reference for introduc- in charge of decisions earlier than before. A major ob-
ing changes in the project, such as proposing new design stacle for its implementation was the inadequacy of the
solutions, devising alternative production methods, and existing cost database and the ineffective flow of infor-
renegotiating contracts, in order to reduce costs or incr- mation among different sectors of the companies.

© GCU Journal of Financial Management of Property and Construction, 11 (2)


A model for integrating cost management and production planning and control 89

Finally, some additional studies are suggested for fur- Gower, Aldershot.
ther developing the proposed cost planning and control Horngreen C.T, Foster, G, and Srikant, M.D. (1990)
model: Cost accounting: a managerial emphasis. 7th
(a) Investigating the full implementation of target-cost ed. Englewood: Prentice-Hall.
ing and value analysis in construction projects, espe- 148.
cially in low costing house-building projects, in which Howell, G. and Ballard. G (1996) Can project controls
the available resources for generating value are scarce; do its job? Proceedings, Annual meeting of the
(b) Investigating the use of the model to support pro- International Group of Lean Construction. Bir
duction management considering a multi-project envi- mingham. www.iglc.net, [Accessed in May,
ronment; 2006].
(c) Devising computer systems for cost management Johnson, H.T and Kaplan, R.S. (1993) Cost & Manage
that allow the use of the proposed tools and also the de- ment Accounting: Relevance Lost A Critique.
centralization in data collection and processing, as well Rio de Janeiro: Campus
as in decision-making. Kaka, A. and Price, A.D.F. (1991) Relationship be
tween value and duration of construction
Acknowledgements projects. Construction Management and Eco
nomics, 9(4), 383-400.
The authors would like to thank FINEP – Financiadora Kaplan, R and Cooper, R. (1998) Custo & Desempen
de Estudos e Projetos and UNISINOS – Universidade ho: administre seus custos para ser mais com
do Vale do Rio dos Sinos for sponsoring this research petitivo. São Paulo:Futura.
study, and also the construction companies that took Kim, Y. (2002) The implications of a new production
part in this project. paradigm for project cost control. Berkeley,
149f. PhD Thesis, University of California.
References Kim, Y. and Ballard, G. (2001) Earned value method
and customer earned value. Journal of Con
Ballard, H.G. (2000) The last planner system of pro struction Research, 3(1), 55-66.
duction control. Birmingham. PhD Thesis, Kim, Y. and Ballard, G. (2000) Is the earned-value
Faculty of Engineering, The University of Bir method an enemy of work flow? Proceedings,
mingham. Annual meeting of the International Group of
Barbosa, P.S.F and Pimentel, P.R. (2001) A linear pro Lean Construction. Brighton, www.iglc.net.
gramming model for cash flow management in [Acessed in May2006].
the Brazilian construction industry. Construc Krieger, J. (1997) Establishing activity-based costing:
tion Management and Economics, 19(5), 469- Lessons and Pitfalls. Newspaper Financial Ex
480 ecutives Quarterly, 3(4), 14-17.
Barnes, N.M. (1977) Cost modeling – an integrated ap Koskela, L. (2000) An exploration towards a produc
proach to planning and cost control. Engineer tion theory and its application to construction.
ing and Process Economics, (2), 24-51. PhD Thesis, Technical Research Centre of Fin
Bazarra, G., Back, E. and Mata, F. (2000) Probabilis land – VTT. Helsinki.
tic monitoring of project performance using S- Laufer, A. and Tucker, R.L. (1987) Is construction
curves. Journal of Construction Engineering project planning really doing its job? A criti
and Management, March/April, 126(2), 142- cal examination of focus, role and process.
Cooper, R. (1995) When lean enterprise collide – com Construction Management and Economics,
peting through confrontation. Harward Busi 5(3), 243-266.
ness School Press. Boston, Massachusetts. Marchesan, P.R.C and Formoso, C.T. (2001) Cost man
Cooper, R and Slagmulder, R. (1997) Target costing agement and production control for construc
and value engineering. Productivity Press, tion companies. Proceedings, International
Montvale, New Jersey. Group for Lean Construction Conference, Sin
Ferry, D. J and Brandon, P.S. (1999) Cost planning of gapore, 291-303
buildings. 7th Edn. Great Britain: Blackwell. Maskell, B. and Baggaley, B. (2003) Lean manage
Goldratt, E.M and Cox, J. (1989) The goal: A process ment accounting. Available in: www.maskell.
of On-going Improvement. Revised Edition, com. [Acessed in October, 2005].

© GCU Journal of Financial Management of Property and Construction, 11 (2)


90 A. P. Kern and C. T. Formoso

Monden, Y. (1999) Sistema de redução de cus


tos: cus to-alvo e custo kaizen. Porto Alegre:
Bookman.
Navon, R. (1995) Resource-based model for automatic
cash-flow forecasting. Construction Manage
ment and Economics, 13(6), 501-510.
Neale, H.and Neale, D. (1989) Construction planning.
London: Thomas Telford Ltda, 160p.
Ostrenga, M. et al. (1998) The Ernst & Young guide to
total cost management. 13 ed. Rio de Janeiro:
Record.
Ploss, G.W. (1999) Cost accounting manufacturing:
dawn of a new era. Production Planning and
Control, 1(1), 61-68
Skoyles, R. (1965). Operational bills: a critical appre
ciation. The Quantity Surveyor, 21, 117-120.
Turner, J.R. (1993). The handbook of project based
management: improving the process for
achieving strategic objective. McGrow-Hill.
England.

© GCU Journal of Financial Management of Property and Construction, 11 (2)

You might also like