LITERATURE REVIEW ON CONCURRENT ENGINEERING AND ITS

IMPLEMENTATION
Gopa Bhattacharyya Choudhury 1 Dr. Sumati Sidharth2 Dr. Nilesh Ware3
1
Student, Dept of Technology Mgmt., DIAT, Pune
2
Professor, Dept of Technology Mgmt., DIAT, Pune
3
Professor, Dept of Technology Mgmt., DIAT, Pune
Email: gopa_drdo@rediffmail.com

Abstract— This literature study is a review of work published in various journals on ‘Concurrent Engineering & Its
Implementation’, between 1990 and 2020.This study intends to serve three major goals. It shall be useful to the
researchers or scholars who are interested in understanding the recent trends in the area of CE. This study shall also be
useful to businesses / industries, as it intends to enlighten on the various approaches for successful implementation of CE
for realization of business benefits. This study shall will also attempt to identify the different factors which play a major
role in implementation of concurrent engineering in a product development scenario.
.
Keywords: Concurrent Engineering, Product Life Cycle, Product and Process development
the ways of its implications in determining new product
I. INTRODUCTION development success.
In the competitive environment prevalent in the current
times, managing a 'Project for New Product Development'
faces many challenges, which needs to be optimally II. STATE OF DEVELOPMENT (1990-2000)
addressed. While necessary efforts must be taken to
R.A.Sprague; K.J.Singh; R.T. Wood (1991) Concurrent
continuously to meet the increasing expectations of customers
Engineering, an integrated design approach that considers,
and remain competitive, it also imperative to manage the
from outset, all elements of the product life cycle from
product development process in such a manner so as to ensure
conception through disposal, including quality, cost, schedule,
that the newly developed products are globally competitive in
and user requirements, is examined.
terms of the prevailing expectations of customers most
J.Michael, O'Flynn,M. Ahmad (1991) The manufacturing
effectively.
sector has experienced significant changes over the past
Literature indicates that Concurrent Engineering practices
twenty years. Companies are becoming more international and
have contributed in increasing new product development
are facing increased competitive challenges. Because of this,
efficiency and effectiveness by introducing a higher degree of
and owing to higher customer expectations, there are greater
integration between areas and departments –notably product
demands on product quality, functionality, aesthetics,
and process design. This concept enables teams to work with
reliability, and flexibility. In addition, product life cycles have
each other concurrently, optimize the design and development
reduced which has led to shorter time periods in which to
processes with respect to different lifecycle issues and
recover costs. There is a greater pressure on design teams to
enhance the quality of product and launch products in the
develop products in shorter time periods as profits have been
market with the least lead-time.
shown to be very sensitive to time to marker (TTM). Many of
In this research, an attempt will be made to explore and
the above factors are directly influenced during product
identify the critical success factors affecting acceleration of
development and therefore the approach adopted during this
new product development process in the context of Indian
phase of product life cycle, can have major impact on
Defense Research Organizations and see how concurrent
profitability. This paper defines the simultaneous or
engineering can play a role in integrating these activities so as
concurrent engineering (CE) approach to product
to shorten the Project Life Cycle for new product
development, and the benefits of adopting it, versus the
development.
traditional sequential engineering approach.[8]
Presently, new product design & development challenges
M.Lawson,H.M.Karandikar (1994) The use of CE as the
are immense and are related with complexity of products,
defacto methodology for product development has become a
geographically located design teams, growing needs of rapid
reality. However CE programs implementers and practitioners
fulfillment of customer requirements/demands, earning
have reported widely varying results. The results of a survey
revenue by capturing market share at an early stage etc. In
of an industrial organizations implementing or considering
such situations, business oriented organizations are looking
implementation of CE are presented in this article. The
for; faster design & product development with enhanced
difficulties in quantifying the benefits of CE are highlighted
manufacturing capacity & capability, by improving revenue
here.
from lifecycle efficiency. Many marketing activities
Klaus Pohl,Stephan Jacobs (1994) Concurrent
influences the new product development process, particularly
engineering requires the cooperation of people coming from
different phases of the engineering process. Traceability
between the different views (products), which exist in such supplier-networks can therewith be established
cross-functional teams, is essential for enabling mutual instantaneously.[15]
understanding. Moreover, the different views must be related R. Smith (1997) this paper explores the history of the ideas
to each other and must be presented in a suitable way to behind concurrent engineering from the end of the 19th
support finding and resolving of inconsistencies, conflicts, and Century until the 1960s. Concurrent engineering is the
different opportunities. We have developed and implemented relatively recent term that is applied to the engineering design
a concurrent engineering environment, called PRO-ART, philosophy of cross-functional cooperation in order to create
which is based on four main ideas.[11] products that are better, cheaper, and more quickly brought to
Victor J B J Paashuis,(1995) This paper looks into the use market. The principles of concurrent engineering that are
of concurrent engineering (CE) in new product development traced by this paper are: manufacturing and functional design
(NPD) processes. To this end presents an NPD strategy constraints need to be considered simultaneously; combining
framework, which is derived from an operations strategy of people with different functional backgrounds into a design
framework filled out with integration mechanisms decision team is a useful way to combine the different knowledge
alternatives. The framework focuses on cross-functional co- bases; engineering designers must bear in mind customer
operation, inter-functional communication.[13] preferences during the design process; and time to market is
J.G.Bennett, T. Lamb (1996) this paper reports on a SP-8 an important determinant of eventual success in the market.
Panel project to analyses the application of Cein US. None of these principles is by itself surprising; concurrent
Shipbuilding and to perform a pilot implementation of CE. engineering has led to their propagation to many people and
Within a US Shipyard firms in the engineering world. The author has examined the
Hu Yongtong; Liu Ping;Yan Yuhong;Zheng Danian; engineering literature in order to locate the existence of similar
Ma Changchao;J.Bode;Ren Shouju (1996) The concurrent themes in published engineering thought. All of these themes
design of a product involves the cooperation of many have recurred often in the literature. Concurrent engineering
functions such as manufacturing ,logistics, marketing, and can be seen therefore as a summary of best practice in product
sales. It can be represented as a multi agent system with each development, rather than the adoption of a radically new set of
agent representing a kind of expertise. Each agent has its own ideas. The paper suggests some reasons that concurrent
evaluation criteria and egoistic goals. Decision making leads engineering ideas may not have been adopted more widely.
to problems typical for concurrent engineering, in which all A.S. Pillai, V.N.Lal, K.S. Rao. (1997) The Indian Guided
related processes are simultaneously taken into consideration. Missile Programmer may be the first in the country to adapt
Geritz,William, (1996) Unification of design, process for the philosophy of concurrent engineering (CE) for the
obtaining significant gain in productivity and profitability. development of high-technology weapon systems. The
Dr. K..S. Panwar & H. Driva (1996) This paper presents a management of IGMDP took enormous risk and proceeded
holistic approach to concurrent engineering and its with the concurrent development of the technology, the
implementation which is under development by the PACE product, as well as the establishment of production facilities.
consortium. PACE stands for 'Practical Approach to During the implementation of this concurrent development
Concurrent Engineering'. It is a pan-European project and production process, a number of hurdles have been
consisting of a consortium of eight partners. The most well- encountered which further led to the development of new
known existing models are reviewed, examined and critiqued. ideas, tools and techniques to realize the weapon systems in
[9]
shorter time frames. The net result of these efforts is not only
Robert de Graaf , Luuk Kornelius (1996) Concurrent the saving in time from the design of weapon systems to their
Engineering (CE) is mostly applied within an organization. induction, but also the build-up in technological confidence
Due to the focus at core competencies, suppliers need to be that swept through all those organizations that participated in
involved. Focusing on core competencies requires this programmer. This paper presents the experiences of the
manufacturers to involve suppliers in the development of Indian Guided Missile Programmer in implementing the
complex products, especially in electronic design. various concurrent engineering practices.
Consequently, an inter-organizational approach is necessary to Peter E D Love,A Gunasekaran (1997) The construction
reduce throughput-time, improve quality, and lower costs. industry has been suffering from low productivity and poor
Analysis of a European PCB supplier’s difficulties in performance in an attempt to improve its performance,
implementing CE, with the Readiness Assessment for industry practitioners and researchers have looked at the
Concurrent Engineering (RACE), led to a maturity model for manufacturing industry as a point of reference and a source of
supplier involvement in electronic design. This framework’s innovation. Consequently, the industry has acquired and
first step is effectuation of basic CE principles within the adapted the CE approach to manufacturing, to construction .
organization, which has been recommended for the PCB The motivation for importing a CE approach to construction is
supplier. Further progress requires customer involvement, presented in this paper.
ultimately leading to virtual customer-supplier-teams striving D.Sobek,A.C.Ward,J.K.Liker (1999) How Toyota's
end-user satisfaction, supported by enhanced, Ethernet-based product design and development process helps find the best
application tools. The lack of customer effort, to achieve Inter- solutions and develop successful products.
Organizational CE, proved to be the major road-block for the J.D. Owens and J.Davies (2000) In order to achieve a
PCB supplier. Nevertheless, suppliers have a strong successful new product, and certainly the successful
competitive edge, since they are capable of entering customer- implementation of a new product into a company, it is
necessary to have a structured and documented approach to introduced KCs considerations into their product development
new product development, therefore providing a clear road practices. This paper presents a holistic framework of KCs
map for the development of new products. This review methodologies and practices through the PLC and summarizes
highlights the NPD process, from concept to customer, and the the fundamentals of KCs including their definition and
key drivers for success.[20] classification. [33]
R. Badham,P.Couchman, M. Zanko (2000) This article E. Stevans,H. Karkkainen and H Lampela (2009) Virtual
addresses the conditions necessary for firms to implement teams consisting of participants from many geographically
concurrent engineering successfully. Although there has been distant subunit, or even belonging to many organizations and
considerable interest in concurrent Engineering since the late communicating mainly through ICT, are used for the purpose
1980s, and many books and articles have been published on of sharing development costs and shortening the time to
this approach to product innovation, there is still some market. This paper analyses how a VT may facilitate or
confusion about the concept, and the issues associated with its prevent learning, knowledge generation, and ideation
successful implementation remain largely unsearched. This processes in New Product/Service Development. [5]
article seeks to add to the body of knowledge in these areas by A. Hambali, S.M. Sapuan, N. Ismail, Y. et al (2009)
drawing on recent Australian Surveys and on the findings of Examination of key concepts and tools in CE .[45]
four case studies of the introduction of concurrent engineering M.Antaki,A. Schiffauerova,V. Thomson (2010) The
in Australian firms. [1] performance of new product development (NPD) is greatly
affected by communication strategy and the information
III. STATE OF DEVELOPMENT (2001 -2010) technology tools used to support the strategy. A number of
users of NPD processes claim that an adequate communication
A. Portioli-Staudacher,H.Van Landeghem, C.E. Redaelli strategy decreases their product cycle time and cost. However,
(2003)The concept of concurrent engineering (CE) has been the problem with evaluating the impact of information transfer
known for quite a while now, and it has been widely is that no one has ever specifically measured how performs
recognized as a major enabler of fast and efficient product and communication strategies are, or how effective
development. This paper examines the extent to which CE information tools are. In this paper, a model has been
best practices, as obtained from a broad literature review, are developed to evaluate communication strategies. The result
being used effectively in companies. Companies both in indicates that a shorter, more efficient communication process
Belgium and in Italy were investigated using a CE compliance reduces time and effort, and that a shift towards formal
checklist. The paper comments on usage patterns in both methods and passive information tools (computer based
countries and compares them. Specific information per sector systems) results in more effective and easier coordination as
is also included. Finally, the positive impact of formal CE well as better integration.[4]
programs is proven by the data.[10] ZHANG Qingshan,WANG Zhihui (2010) Support
Holger Ernest (2003) The continuous development and environment for ensuring consequent production of the
market introduction of new products ca be an important product, and guidance and provide a reference for companies.
[46]
determinant of sustained company performance. For
approximately 30 years, conceptual and empirical research has R.Cooper, E.J.Kleinschmidt (2010) The main factors
been undertaken to identify the critical success factors of new impacting success at the project and the firm levels are
products. This paper reviews the findings of empirical work identified on the basis of numerous empirical studies. The
into the success factors of new product development (NPD). factors at the project level are a unique superior product,
E. Cengiz, H Ayyildiz, F Kirkbir (2005) New product strong market orientation, global orientation, pre-development
development is essential for outstanding corporate work, early product definition, project team organization, and
performance and research about what leads to new product leveraging core competencies. Differences in factors for
success has been carried out for both good and services highly innovative versus incremental projects are discussed.
frequently. Despite extensive documentation on how to The main factors for success at the business level are the right
achieve success, NPD remains a high risk venture. Critical organizational culture, an innovative strategy, resource
success factors that affect new product performance. commitment, top management support, portfolio management,
N.Bhuiyan, V.Thomson, D.Gerwin (2006) Pdt and a multistage, disciplined, new product development
development managers need a single well defined process process. Details of these factors are provided and their
with clear ownership and goals. [32] application in Industry is outlined. Performances differences
PM Wognum, R Curran et al. (2006) Study of different between highly successful projects and business and less
fields will be identified for present and future application and successful ventures are described. [18]
development, and reference will indeed be made to the Dag Raudberget (2010) Objective research to investigate
potential importance of CE as a disciplinary. [44] whether Set-Based Concurrent Engineering concepts can
L.Y.Zheng,C.A.Mc Mohan,L.Li,L.Ding,J Jamshidi increase the effectiveness and the efficiency of the
(2008) KCs play a significant role in product life cycle development process. [43]
management(PLM) and in collaborative and global product
development. Over the last decade, KCs methodologies and III. STATE OF DEVELOPMENT (2011 -2020)
tools have been studied and practiced in several domains of
the product life cycle, and many world class companies have
X. Hu,J.Hu,A. Sekhari,Y. Peng and Z.Cao (2011) Due to Menenti, Zuidema (2012) Impactful behavior can lead to
the increased complexity of engineering products and design impactful result in product development. [36]
processes, concurrent engineering practices still face A.A. Ashaab,M. Golob,U.M. Attia,M. Khan, J. Parsons,
enormous challenges. Design teams often provide the A. Andino (2013) This article presents a transformation
knowledge involving multiple disciplines in natural language process towards lean product development in an aerospace
at conceptual design stage. As a result, conflicts often arise industry. The transformation was achieved in two main stages:
during communications. To increase the efficiency of design the first was to integrate the principles of set based concurrent
process, it is necessary to avoid interpretation conflicts. This engineering into an existing product development model of an
article presents a system framework to resolve terminology aerospace company. This stage included defining activities
conflicts.[6] and associated tools. The second stage was to implement the
S. Gedell,M. T. Michaells and H. Johannesson (2011) developed modeling a research based industrial case study, a
The seamless co-development of products and production helicopter engine in this case. Three main outcomes were
systems is still an unresolved challenge. Undoubtedly, realized from this work. First, it presented an industrial case of
progress has been made through the proposal and application lean transformation in product development, where the
of new methodologies in the collective of concurrent leanness of an existing model was enhanced by embedding set
engineering. Still, there is a gap between modeling approaches based CE principles. Second, the developed model was
in product development and in production system design. This structured into a set of well-defined activities and associated
gap is an obstacle, especially if many interdependencies exist tools that were previously scattered or redundant. Finally, the
among the constituents of products and production systems.[7] developed model was trailed in an industrial project of a
Sofuoglu, Ecehan (2011) It explains new product helicopter engine, tested to evaluate its value in enhancing the
development methods by applying it, gives the tools for it, innovation level and reducing risk.[3]
compares the CE with Sequential Engineering (SE).[34] B. Felekoglu, A.M. Maier, J. Moultrie (2013) Effective
Nadia Bhuiyan (2011) The purpose of this paper is to interaction across organizational boundaries is a critical
propose a framework of critical success factors, metrics, and success factor in new product development (NPD).However;
tools and techniques for implementing metrics for each stage few studies have investigated how different mechanisms
of the new product development process.[35] enable effective interaction across organizational and
C.E. Levandowski,D. Corin-Stig, D.Bergsjo,A. particularly hierarchical boundaries. [37]
Forslund,U. Hogman, R.Soderberg and H Johannesson SandipBasu, Nabarun Biswas, Supriya Naha Biswas and
(2012) Reusing design knowledge is a key concept, whether Sweta Sarkar (2013) Recognizes concurrent engineering as
manifested as reusing parts, ideas, concepts, or technologies. the way of achieving long-term sustainability in this highly
This article describes processes and information technology competitive business climate. [38]
solutions for holistically working with both technology Ricky Luppino, M. Reza Hosseini and Raufdeen
platforms and product platforms. [2] Rameezdeen (2014) a definition of the effective methods of
Alireza Aslani, Petri Helo,Marja Naaranoja (2012) The risk management in R&D projects has remained elusive.
development of successful new products is today of challenge Similarly, there have been calls to devise effective risk
to most consumer product companies. They have to short their management methods in R&D projects. To develop this area
response time, pushing their development processes to move further, the purpose of this study is twofold. First, it validates
faster while keeping on competitive prices and quality. These the veracity of claims about the urgency of introducing
caused companies are forced to find effective and innovative effective methods of risk management to R&D projects in
approaches as work methods to overcome to pressures. South Australia based on nine unstructured interviews with
Concurrent Engineering (CE) is one of the approaches to experts. Second, the study presents the outcomes of two case
address these managerial and manufacturing dilemmas in new studies that deployed the extended version of the failure mode
product projects. The basic premise of CE revolves around and effect analysis, namely, the RFMEA method in a South
team working. However, most of the managers especially Australian organization, to investigate how the method can
project manager’s face with problems when they want to facilitate the identification of effective contingency plans to
promote teamwork culture, especially in conditions that the mitigate high-priority risks. The findings showed that the
project faces with complicated problems. In this condition, a RFMEA method would be effective for project managers in
creative team consists of members from different levels of the dealing with risk management issues in R&D projects. The
organizational hierarchy must be shaped. There are always discussions presented will provide guidelines for practitioners
barriers in group meetings that influence growth and diffusion in the industry. [17]
of creative solutions and would be reduced by using creativity M. Tshiki (2015) Critical Success Factors (CSFs) have
and innovation techniques. The first purpose of this study is to been defined as characteristics, conditions or variables that can
identify the effective criteria in success of creative meetings in have a significant impact on the success of a project when
CE projects. Next, the prioritization of each factor has been properly sustained, maintained or managed.[39]
analyzed and ranked respectively. Finally, based on the results M. Graner,M. Behr (2015) The purpose of this paper is to
of previous research of the authors, the useful group creativity analyse the use of methods in new product development and
and innovation techniques related with team work meetings in their impact on product success.[40]
CE projects have been ranked by using the Analytic Hierarchy Angappa Gunasekaran (2017) Concurrent Engineering
Process (AHP) approach.[4] (CE) is a systematic approach to the integrated, simultaneous
design of both products and their related processes, including
production. A number of research reports are available in the
literature to deal with CE and its applications in manufacturing
industries. However, the application of CE in Process
Industries (PI) has not received enough attention from
researchers and practitioners for improving productivity and
quality. To use CE effectively in process industries requires
accuracy of data and a common architecture. In PI, the
products are processed with minimal interruptions in any one
production run or between production runs of products that
exhibit process characteristics, such as liquids, fibers, powders
and gases. The general characteristics of this industry add
value to materials by mixing, separating, forming, or chemical
reactions. PI often initiates their flow with only a few raw
materials and subsequently process a variety of blending and
respiting operations. Nevertheless, there are many common
characteristics such as material and information flow between
manufacturing and PI. This indicates the application areas of
CE in PI and hence to improve the competitiveness of PI in
terms of flexibility and responsiveness. An attempt has been
made in this paper to study how CE can be utilized to design
products, production system, and production planning and
control (PPC) system for improving productivity and quality
in PI.[12]
Aniket Bipin, Pratik, Vipul (2017) This paper intend to
carry a review of the concurrent engineering in various
sectors, and the traditional methods as well as development of
new products by advanced method based on a new approach.
[41]

S. Pretorius,H.Steyn,T.J.Bond (2017) Appropriate


balance of leadership styles
Cezar-Petre Simion (2018) The article aims to analyze the
main features of the risk management process in R & D
projects in Romanian organizations. In the article, the risk
management process in the projects carried out by the
Romanian organizations is surprised at all stages: risk
identification, risk analysis and project risk response.
Organizational risk management influences the way in which III. CONCLUSION
risk identification and analysis are integrated into the
management of R & D projects. The level of residual risk This paper focuses only on the literature review of
during the project implementation period depends on how previously published studies. The findings of this study the
project managers address the identification of risks in the concurrent Engineering has been a topic of interest since the
initial stages of their preparation. In most projects, resources late 1980s. There is still some confusion about the concept,
are not allocated to team members with exclusive risk and the issues associated with its successful implementation.
management responsibilities, but they are usually assumed by This article seeks to add to the body of knowledge in these
the project manager.[16] areas by drawing on recent Australian Surveys and case
R.Cooper (2019) Why are some new products so studies of concurrent engineering in Australian firms.
successful and some companies outstanding performers in new Concurrent engineering practices still face enormous
product development? This article identifies success factors challenges. Virtual teams are used to share development costs
from numerous research studies into NPD performance in and shortening the time to market. To increase the efficiency
Industry. Three categories of success drivers have been of design process, it is necessary to avoid interpretation
defined.[19] conflicts. This article presents a system framework to resolve
terminology conflicts. It defines the simultaneous or
concurrent engineering (CE) approach to product
development.
Concurrent engineering is a systematic approach to the
integrated, simultaneous design of both products and their
related processes, including production. To use CE effectively
in process industries requires accuracy of data and a common
architecture, writes the authors. The authors develop a a survey in Italy and Belgium” Robotics and
concurrent engineering environment, called PRO-ART, which Computer-Integrated Manufacturing, Vol 19(3)
is based on four main ideas. 11. Klaus Pohl,Stephan Jacobs “Concurrent Engineering:
The development of successful new products is today of Enabling Traceability and Mutual Understanding”
challenge to most consumer product companies. Due to focus Concurrent Engineering: Research and Applications
at core competencies, suppliers need to be involved. An inter- (CERA)
organizational approach is necessary to reduce throughput- 12. Angappa Gunasekaran “Concurrent engineering: A
time, improve quality, and lower costs. competitive strategy for process industries” Journal
of the Operational Research Society, Vol 49 (2017)
13. Victor J B J Paashuis, “Organizing for Concurrent
REFRENCES Engineering: An Integration Mechanism Framework”
Integrated Manufacturing Systems, Vol 8 (2012)
1. R. Badham, P. Couchman, M. Zanko “Implementing 14. Alireza Aslani, Petri Helo,Marja Naaranoja
Concurrent Engineering” Human Factors & “Development of Creativity in Concurrent
Ergonomics in Manufacturing, Vol 10(3), pp-237- Engineering Teams” American Journal of Industrial
249 (2000) and Business Management, Vol 2
2. C.E. Levandowski,D. Corin-Stig, D.Bergsjo,A.
Forslund,U. Hogman, R.Soderberg and H 15. Robert de Graaf , Luuk Kornelius “Inter-
Johannesson “An integrated approach to technology organizational concurrent engineering: a case study
platform and product platform development” in PCB manufacturing” Journal of Computers in
Concurrent Engineering Research and Applications, Industry, Vol ( 30) (1996)
Vol 21(1),pp 65-83 (2012)
3. A.A. Ashaab,M. Golob,U.M. Attia,M. Khan, J.
16. Cezar-Petre Simion “Risk Management In Research-
Parsons, A. Andino “The transformation of product
Development (R & D) Projects Carried Out By
development process into lean environment using set-
Romanian Organizations” journal of Research on
based concurrent engineering: A case study from an
Trade, Management and Economic Development
aerospace industry” Concurrent Engineering
Volume 5, Issue 2 (2018)
Research and Applications, Vol 21(4),pp 268-285
17. Ricky Luppino, M. Reza Hosseini and Raufdeen
(2013)
Rameezdeen “Risk Management In Research And
4. M.Antaki,A. Schiffauerova,V. Thomson “The
Development (R&D) Projects: The Case Of South
Performance of Technical Information Transfer in
Australia” Asian Academy of Management Journal,
New Product Development” Concurrent Engineering
Vol. 19, No. 2, 67–85 (2014)
Research and Applications, Vol 18(4),pp 291-301
18. R.Cooper, E.J.Kleinschmidt “Success Factors for
(2010)
New -Product Development” Wiley International
5. E. Stevans,H. Karkkainen and H Lampela
Encyclopedia of Marketing (2010)
“Contribution of virtual teams to learning and
19. R.Cooper “The Drivers of Success in New Product
knowledge generation in innovation related projects”
Development” Industrial Marketing Management,
International J Product Development, Vol 8 (2009)
Vol 76, pp 36-47 (2019)
6. X. Hu,J.Hu,A. Sekhari,Y. Peng and Z.Cao “A Fuzzy
20. J.D. Owens and J.Davies “The importance of New
Knowledge Fusion Framework for Terms Conflict
Product Development Process: Getting Started”
Resolution in Concurrent Engineering” Concurrent
Conference Paper (2000)
Engineering Research and Applications, Vol 19(1),pp
71-84 (2011)
7. S. Gedell,M. T. Michaells and H. Johannesson 21. R.A.Sprague; K.J.Singh; R.T. Wood “Concurrent
“Integrated Model for Co-Development of Products Engineering in Pdt Development” IEEE Design and
and Production Systems - A Systems Theory Test of Computers, Vol 8, Issue 1, (1991)
Approach” Concurrent Engineering Research and
Applications, Vol 19(1),pp 71-84 (2011) 22. M.Lawson,H.M.Karandikar “A Survey of Concurrent
8. J.Michael, O'Flynn,M. Ahmad “The concurrent Engineering (CE)” Sage Journal, (1994)
engineering approach to product development”
Journal of Electronics Manufacturing, Vol 01(02),pp 23. J.G.Bennett, T. Lamb “CE: Application and
97-104 (1991) Implementation for US Ship Building” Journal of
9. Dr. K..S. Panwar & H. Driva “Concurrent Ship Production,Vol 2, Issue 2 (1996)
Engineering: From Concept to Implementation”
Proceedings of International Conference on Agile 24. Hu Yongtong; Liu Ping;Yan Yuhong;Zheng Danian;
Manufacturing (1996) Ma Changchao;J.Bode;Ren Shouju “A multiagent
10. A.Portioli-Staudacher,H.Van Landeghem, C.E. system for the support of CE” IEEE International
Redaelli “Implementation of concurrent engineering: Conference on Systems,Man and Cybernetics.
Information Intelligence and Systems (1996)
25. Geritz,William, “The Project Manager for CE” Cost 39. M. Tshiki “CSFs for IF construction pjts in South
Engg, Vol38,Iss 12 (1996) Africa” Journal of Civil Engg, Vol 23,Issue 6, July
2015
26. R. Smith “Historical Roots of Concurrent Engg
Fundamentals” IEEE Transactions on Engg Mgmt, 40. M. Graner,M. Behr “Method application in NPD and
Volume 44 (1997) the impact on Product Success” Intl Journal of
Innovation and Technology Management, Vol 12, Iss
27. A.S. Pillai, V.N.Lal, K.S. Rao. “CE Experiences in 4,2015
High Tech Defence Projects” IJTM, Vol 14,Iss 6-8
(1997) 41. Aniket Bipin, Pratik, Vipul “Concurrent Engineering:
A Review” Volume 4, Issue 5, May 2017 IRJET
28. Peter E D Love,A Gunasekaran “CE in Construction (2017)
Industry” Sage Journals, (1997)
42. S. Pretorius,H.Steyn,T.J.Bond “Exploring project
29. D.Sobek,A.C.Ward,J.K.Liker “Toyota's Principles of related factors that influence leadership style and
Set Based C Engg” MIT Sloan Mgmt Review their effect on project performance : a conceptual
(1999) framework” South African Journal of Industrial
Engg,Vol 28,Iss 4,2017
30. Holger Ernest “Success Factors of New Product
Development: A review of the Empirical Literature” 43. Dag Raudberget “Practical Applications of Set-Based
International Journal of Management Concurrent Engineering in Industry” Strojniški
Review/Volume 4, Issue 1 (2003) vestnik - Journal of Mechanical Engineering
31. E. Cengiz, H Ayyildiz, F Kirkbir “Critical success 56(2010)11
factors in new product development” Ataturk
University (2005) 44. PM Wognum, R Curran et al. “Concurrent
32. N.Bhuiyan, V.Thomson, D.Gerwin (2006) Engineering - Past, Present and Future” Proceedings
“Implementing CE” Industrial Research Institute of the 2006 conference on Leading the Web in
RTM,Vol49,Iss 1, 2006 Concurrent Engineering

33. L.Y.Zheng,C.A.Mc Mohan,L.Li,L.Ding,J Jamshidi 45. A. Hambali, S.M. Sapuan, N. Ismail, Y. et al “The
“Key Chareacteristics Management (KCM) in Important Role of Concurrent Engineering in Product
product life cycle: A survey of methodologies and Development Process” Pertanika J. Sci. & Technol.
practices” Jornal of Engineering Manufacture, Vol 17 (1): 9 – 20 (2009)
222, Iss 8,2008
46. ZHANG Qingshan,WANG Zhihui “Organization of
34. Sofuoglu, Ecehan “Different Approaches to Concurrent Product Development” IEEE 2010
Concurrent Engineering” Bogazici University,
October (2011)

35. Nadia Bhuiyan “A framework for successful new


product development” Journal of Industrial Engg and
Mgmt, Vol 4, No 4 (2011) 

36. Menenti,Zuidema “Measurable Acceleration in


innovation processes by managing behaviour”
Innovation Symposium, 2012

37. B. Felekoglu, A.M. Maier, J. Moultrie “Interactions


in NPD” Jornal of Engg and Tech Mgmt, Vol30,Iss
4,2013

38. SandipBasu, Nabarun Biswas, Supriya Naha Biswas


and Sweta Sarkar “A study on concurrent
engineering-based design and product development”
Vol.2, No.1, February 2013, International Journal of
Recent Advances in Mechanical Engineering
(IJMECH)