Project: Chainpal Br.

No: ROB Ch: Chainpal


Width of carriage way 7.5 m Bed block & dirt wall Fly wing No No
Road width including shoulders 11.23 m Top width of dirt wall 0.4 m 3 m
Skew angle 35.401944444 Deg Bottom width of dirt wall 0.4 m 2 m
Levels Thickness of bed block 0.6 m 0.6 m
Top of formation level 80.14 m 0.3 m
Ground level 71.92 m Abutment data
Top of foundation level 71.35 m Design material RCC
RCC Pedestals
Thickness of wall at bed block 1.325 m Shorter dimemsion 750 mm
Super structure Earth side batter 2 Longer dimension 950 mm
Type of super structure Conc.girder
Conc.girder Height from bottom of bed block to batter 0 m Thickness 150 mm
Height of super structure 1.75 m Span side batter 25
Clear span 32 m Height from bottom of bed block to batter 0 m Seismic Zone III
Effective span 33.794 m Grade of concrete M30
M30
Over all span including long. cantilever 34.294 m Percentage of steel Fe415 0.8 % To Standard Data >>

Expansion and other clearence 0.025 m Foundation data Safe in stability


Bearing Type of foundation Single rectangular
Single rectangular Factor of safety against OT 4.59
Type of bearing ElastomericElastomeric
bearing bearing Width Height Factor of safety against sliding 2.04
No of bearings on each abutment 4 nos Length of heel slab 0.75 3.25 m Safe in foundation pressure
Thickness of bearing 80 mm Length of toe slab 0.75 1.75 m Max. foundation pressure 33.764 t/sqm
Shorter dimension of bearing in plan 450 mm Thickness of footing 0.75 1.25 m Min. foundation pressure 14.506 t/sqm
Longer dimension of bearing in plan 650 mm m #VALUE!
Loading Depth of foundation is safe Bending comp. Stress in co ### t/sqm
Class of loading 70R
70R t Dia of main reinforcement 32 Comp. stress in steel ### t/sqm
Dead load from super structure 450 t Dia of distribution reinforcement 12 Tensile stress in steel ### t/sqm
Programmed at Centralised Design Section of S E Railway, Chandrasekharpur, Bhubaneswar. By: P C Dash, J.E.(works) and K.P.Dash, J.E.(works)
Chainage Chainpal
Date & time 8/5/2021 7:42
Geometry of abutment
Length of abutment 13.777 m
Top width of abutment 1.325 m
Earth side batter 0
Height from bottom of bed block to batter 0 m
Span side batter 0
Height from bottom of bed block to batter 0 m
Total height of abutment 80.14 - 71.35 8.79 m
Height of super structure 1.75 m
No of pedestals 4
Shorter dimension 0.75 m
Longer side of pedestal 0.95 m
Height of pedestal 0.15 m
Thickness of bearing 0.08 m
Height of dirt wall 1.75 + 0.08 + 0.15 1.98 m
Top width of dirt wall 0.4m
Bottom width of dirt wall 0.4m
Width of bed block (( 34.294-32 )/2 + 0.025) * 0.815 + 0.4 1.355 m
Thickness of bed block 0.6m
Height of abutment up to bottom of bed block m
8.79 - 1.98 - 0.6 6.21 m
Height of triangular wedge on earth side
6.21 - 6.21 0m
Bottom width of earth side wedge
0/0 0m
Height of triangular wedge on span side
6.21 - 6.21 0m
Bottom width of span side wedge
0/0 0m
Bottom width of abutment
1.325 + 0 + 0 1.325 m
Cross section at cut off level
13.777 * 1.325 18.255 sqm
Section modulus at cut off about long. Axis of abutment
13.777 * 1.325 ^ 2 / 6 4.031 cum
Section modulus at cut off about trans. Axis of abutment
1.626 * 11.23 ^ 2 / 6 34.167 cum
Length of fly wing = 0 m
Height of fly wing at support = 0 m
Height of fly wing at free end = 0 m
Thicknessof fly wing = 0 m
Unit weight of abutment material 2.5 t/sqm
Forces and moments calculated at centroid of area at top of foundation
1 Self weight
Dirt wall
13.777 * 1.98 * ( 0.4 + 0.4 ) / 2 * 2.5 27.278 t
Long. Eccentrity
0 + 1.355 - 0.2 - 1.325 / 2 0.493 m
Pedestal
4 * 0.75 * 0.95 * 0.15 * 2.5 1.06875 t
Long. Eccentrity 0.2345 m

Bed block
13.777 * 1.355 * 0.6 * 2.5 28.002 t
Long. Eccentrity
0 + 1.355 / 2 - 1.325 / 2 0.015 m

535393980.xls 08/05/202107:42:40
Z 0.16
Sa/g 2.5
I 1.5
R 2.5
ah 0.12
av 0.06
l 3.239700296102
3.652222780306
1 Load from super structure
Horizontal seismic force in long/trans direction 54 t
Lever arm 7.915 m
Vertical seismic force 27 t
Lever arm 0.2345 m
2 Seismic effect of live load
I ) in longitudinal direction 20 t
II ) in transverse direction 3t
Lever arm 7.04 m
3 Seismic effect of dead load from sub-structure
Dirt wall
Horizontal force 3.27336 t
Lever arm 7.8 m
Vertical force 1.63668 t
Lever arm 0.493 m
Bed block
Horizontal force 3.36024 t
Lever arm 6.51 m
Vertical force 1.68012 t
Lever arm 0.015 m
Abutment wall
Horizontal force 34.00824 t
Lever arm 3.105 m
Vertical force 17.00412
Lever arm 0m

Dynamic incrememnt of earth pressure due to scemic force


0.29915063 0.30366964 0.3037
0.29915063 0.30366964 0.3037
0.29915063 0.30366964 0.3037

Intensity at the bottom of dirt wall


0.3037 * 1.9 * 1.98 1.143 t/sqm
Total active earth pressure on dirt wall corresponding to triangular pressure diagram
0.5 * 1.98 * 1.143 * 13.777 15.59 t
Dynamic increment 2.715 t
Horizontal component 2.659 t
Lever arm 6.21 + 0.6 + 0.5 * 1.98 7.8 m
Vertical component 0.549 t
Lever arm 1.325 / 2 - 0 - 5 * 0 0.6625 m
Intensity at top of bed block
0.3037 * 1.9 * 1.98 1.143 t/sqm
Intensity at bottom of bed block /starting of batter
0.3037 * 1.9 * ( 1.98 + 0.6 ) 1.489 t/sqm
Total active earth pressure on bed block corresponding to rectangular pressure diagram
1.143 * 0.6 * 13.777 9.448 t
Dynamic increment 1.645 t
Horizontal component 1.611 t
Lever arm 6.21 + 0.5 * 0.6 6.51 m
Vertical component 0.333 t
Lever arm 1.325 / 2 - 0 0.6625 m
Total active earth pressure on bed block corresponding to triangular pressure diagram
0.5 * ( 1.489 - 1.143 ) * 0.6 * 13.777 1.43 t
Dynamic increment 0.252 t
Horizontal component 0.247 t
Lever arm 6.21 + 0.5 * 0.6 6.51 m
Vertical component 0.051 t
Lever arm 1.325 / 2 - 0 0.6625 m
Intensity at starting of batter/bottom of bed block
0.3037 * 1.9 * ( 1.98 + 0.6 ) 1.489 t/sqm
Intensity at top of foundation
0.3037 * 1.9 * ( 1.98 + 0.6 + 6.21 ) 5.072 t/sqm
Total active earth pressure on abutment wall corresponding to rectangular pressure diagram
1.489 * 6.21 * 13.777 127.392 t
Dynamic increment 22.245 t
Horizontal component 21.785 t
Lever arm 0.5 * 6.21 3.105 m
Vertical component 4.498 t
Lever arm 1.325 / 2 - 0 / 2 0.663 m
Total active earth pressure on abutment wall corresponding to triangular pressure diagram
0.5 * ( 5.072 - 1.489 ) * 6.21 * 13.777 153.272 t
Dynamic increment 26.65 t
Horizontal component 26.099 t
Lever arm 0.5 * 6.21 3.105 m
Vertical component 5.389 t
Lever arm 1.325 / 2 - 0.5 * 0 0.663 m

Seismic effect on Weight of foundation


Horizontal seismic force 32.67732 t
Lever arm 0.625 m
Vertical seismic force 16.33866 t
Lever arm 0m

Active earth pressure on foundation due to seismic force

Angle af inclination to vertical 0


0.29915063 0.30366964
Coefficient of earth pressure 0.3037
Intensity at top of foundation 5.072 t/sqm
Intensity at bottom of foundation 5.793 t/sqm
Total earth pressure on foundation due to rectangular stress diagram
5.072 * 1.25 * 13.777 87.34618 t
Dynamic increment 15.20618 t
Horizontal component 14.89202977588 t
Lever arm 0.625 m
Vertical component 3.074956804044 t
Lever arm 3.163 m
Total earth pressure on foundation due to triangular stress diagram
0.5 * 0.721 * 1.25 * 13.777 6.208260625 t
Dynamic increment 1.191260625 t
Horizontal component 1.166649921172 t
Lever arm 0.625 m
Vertical component 0.240893831602 t
Lever arm 3.163 m

Forces and moments at cut off level due to seismic forces


Horizontal in longitudinal direction Horizontal in transverse direction Vertical effect
H Force Lever arm Moment Force Lever arm Moment V Force Lever arm Moment
Super structure 54.00 7.92 427.41 54.00 7.92 427.41 27.00 0.23 6.33
Sub-structure
Dirt wall 3.27 7.80 25.53 3.27 7.80 25.53 1.64 0.49 0.81
Bed block 3.36 6.51 21.88 3.36 6.51 21.88 1.68 0.02 0.03
Abt wall 34.01 3.11 105.60 34.01 3.11 105.60 17.00 0.00 0.00
Dynamic incrementof earth pressure
Triangular on dirt wall 2.66 7.80 20.74 0.55 0.66 0.36
Rect on bed bloak 1.61 6.51 10.49 0.33 0.66 0.22
Triangular on bed bloak 0.25 6.51 1.61 0.05 0.66 0.03
Rect on bed abt wall 21.79 3.11 67.64 4.50 0.66 2.98
Triangle on abt 26.10 3.11 81.04 5.39 0.66 3.57
Live load seismic 15.36 6.44 98.93 3.00 7.04 21.12
Total at cut off level 162.40 860.86 97.64 601.53 58.14 14.34

50% Vertical live load effect with transverse eccentricity 1.16 54.53 47.22 0.23 11.07

r1 Vertical effect
r2 Horizontal effect in longitudinal direction
r3 Horizontal effect in transverse direction
Vertical load Long force Long moment Trans force Trans moment
1 Normal case 855.601 308.317 1254.471 0.000 0.000
2 50% Live load vertical effect 47.216 54.534
3 +r1+ 0.3r2 + 0.3r3 58.141 48.721 272.595 29.293 180.460
4 -r1 + 0.3r2 + 0.3r3 -58.141 48.721 272.595 29.293 180.460
5 +0.3r1 + r2 + 0.3r3 17.442 162.405 865.161 29.293 180.460
6 -0.3r1 + r2 + 0.3r3 -17.442 162.405 865.161 29.293 180.460
7 +0.3r1 + 0.3r2 + r3 17.442 48.721 262.559 97.642 601.533
8 -0.3r1 + 0.3r2 + r3 -17.442 48.721 262.559 97.642 601.533

1+2+3 960.958 357.038 1527.066 29.293 234.994 #VALUE!


1+2+4 844.676 357.038 1527.066 29.293 234.994 #VALUE!
1+2+5 920.259 470.722 2119.632 29.293 234.994 #VALUE!
1+2+6 885.375 470.722 2119.632 29.293 234.994 #VALUE!
1+2+7 920.259 357.038 1517.030 97.642 656.067 #VALUE!
1+2+8 885.375 357.038 1517.030 97.642 656.067 #VALUE!

Horizontal in longitudinal direction Horizontal in transverse direction Vertical effect


H Force Lever arm Moment Force Lever arm Moment V Force Lever arm Moment
Rectangular on foundation 14.89 0.63 9.31 14.89 0.63 9.31 3.07 3.16 9.73
Triangular on foundation 1.17 0.63 0.73 1.17 0.63 0.73 0.24 3.16 0.76
Weight of foundation 32.68 0.63 20.42 32.68 0.63 20.42 16.34 0.00 0.00
Total 80.25 50.15 80.25 50.15 35.75 9.73
Seismic effect of all forces up to cut off level except live load calculated at CG of foundation
162.40 1063.87 97.64 723.59 58.14 57.94
Total seismic effect at CG of foundation
242.65 1114.02 177.89 773.74 93.89 67.67
Stability
1) Sliding
Total vertical force 2009.25 t
Total horizontal force 708.24 t
FS against sliding 1.276637684026
2) Over turning
Overturning moment 2737.37 tm
Resisting moment 7447.774570795 tm
FS against overturning 2.720779384906

Foundation pressure
Addl pressure r1+0.3r2+0.3r3 6.138965718318
0.3r1+0.3r2+r3 8.705649900577
0.3r1+r2+0.3r3 13.8738747755
Critical 13.8738747755

Max foundation pressure 47.6378747755


Min foundation pressure 0.6321252245
Distance between two successive 70R trains 90 m
Distance between two successive Class A or 20 m
70R tracked
Over all width of track 2.9 m Class of loading
Width of each Track 0.84 m Criticality of tracked, wheeled o
Length of track 4.57 m No of traffic lanes
Total load of one track 70 t No of trains
Total load of track1 70 t First train load
Total load of track2 0 t Second train load
CG of total load from head of trac 2.285
Maximum support reaction 65.26691 t Maximum suport reaction
Minimum edge distance
Less than 5.5m width of carriage 0.6 m
More than including 5.5m 1.2 m
Distance between two vehicles 2.4 m

70R wheeled
Over all widht of wheeled vehicle 2.79 m
Width of wheel 0.86 m
Contact length along span 0.61 m
Load Distance
8 0
12 3.96
12 1.52
17 2.13
17 1.37
17 3.05
17 1.37
100 13.4
17 0 8 0
17 1.37 12 3.96
17 4.42 12 5.48
17 5.79 17 7.61
12 7.92 17 8.98
12 9.44 17 12.03
8 13.4 17 13.4
0 103.4 0 103.4
0 104.77 0 107.36
0 107.82 0 108.88
0 109.19 0 111.01
0 111.32 0 112.38
0 112.84 0 115.43
0 116.8 0 116.8
Load from 100 t 100
Load from 0 t 0
CG of loads 5.1238 m 8.2762
Max suppor84.83814 t 75.50985

Minimum edge distance


Less than 5.5m width of carriage 0.6 m
More than including 5.5m 1.2 m
Contact length along span 0.61 m
Distance between two vehicles 2.4 m
70R Bogie
Over all width of wheeled vehicle 2.79 m
Width of wheel 0.86 m

Load
20 0
20 1.2
Maximum support reaction
39.28981 t
Minimum edge distance
Less than 5.5m width of carriage 0.6 m
More than including 5.5m 1.2 m
Contact length along span 0.61 m
Distance between two vehicles 2.4 m

Class A
Over all width of vehicle 1.8 m
Width of wheel 0.5 m
Load Distance
2.7 0
2.7 1
11.4 3.2
11.4 1.2
6.8 4.3
6.8 3
6.8 3
6.8 3
55.4 18.7
Load1 6.8 0 2.7 0
Load2 6.8 3 2.7 1
Load3 6.8 6 11.4 4.2 11.4 0
Load4 6.8 9 11.4 5.4 11.4 1.2
Load5 11.4 13.3 6.8 9.7 6.8 5.5
Load6 11.4 14.5 6.8 12.7 6.8 8.5
Load7 2.7 17.7 6.8 15.7 6.8 11.5
Load8 2.7 18.7 6.8 18.7 6.8 14.5
Load9 0 38.7 0 38.7 0 34.5
Load10 0 41.7 0 39.7 0 35.5
Load11 0 44.7 0 42.9 0 38.7
Load12 0 47.7 0 44.1 0 39.9
Load13 0 52 0 48.4 0 44.2
Load14 0 53.2 0 51.4 0 47.2
Load15 0 56.4 0 54.4 0 50.2
Load16 0 57.4 0 57.4 0 53.2
First train 55.4 55.4 50
Second trai 0 0 0
CG of load 9.703971 8.996029 5.7136
Max support reaction 39.49185 40.65241 41.54643
Edge distance for all widths 0.15 m
Contact length along span 0.25 m
Distance between two vehicles-
-For less than 5.5m width 0.4 m
-For 7.5m and above 1.2 m
Class B
Over all width of vehicle 1.8 m
Width of wheel 0.38 m
Load Distance
1.6 0
1.6 1
6.8 3.2
6.8 1.2
4.1 4.3
4.1 3
4.1 3
4.1 3
33.2 18.7
Load1 4.1 0 1.6 0
Load2 4.1 3 1.6 1
Load3 4.1 6 6.8 4.2 6.8 0
Load4 4.1 9 6.8 5.4 6.8 1.2
Load5 6.8 13.3 4.1 9.7 4.1 5.5
Load6 6.8 14.5 4.1 12.7 4.1 8.5
Load7 1.6 17.7 4.1 15.7 4.1 11.5
Load8 1.6 18.7 4.1 18.7 4.1 14.5
Load9 0 38.7 0 38.7 0 34.5
Load10 0 41.7 0 39.7 0 35.5
Load11 0 44.7 0 42.9 0 38.7
Load12 0 47.7 0 44.1 0 39.9
Load13 0 52 0 48.4 0 44.2
Load14 0 53.2 0 51.4 0 47.2
Load15 0 56.4 0 54.4 0 50.2
Load16 0 57.4 0 57.4 0 53.2
First train 33.2 33.2 30
Second trai 0 0 0
CG of load 9.671084 9.028916 5.738667
Max support reaction 23.69891 24.32979 24.9056
Load12
Edge distance for all widths 0.15 m
Contact length along span 0.2 m
Distance between two vehicles-
-For less than 5.5m width 0.4 m
-For 7.5m and above 1.2 m
Class of loading 70R
Criticality of tracked, wheeled or bogie Wheeled to be examined from all cases
No of traffic lanes 1
No of trains 1
First train load 100
Second train load 0

Maximum suport reaction 84.838 t


Shear
IS 456
Table-17: Permissible shear stress in concrete(N/sqmm)
100Ast/bd Grade of concrete
M15 M20 M25 M30 M35 m40
0.25 0.22 0.22 0.23 0.23 0.23 0.23
0.5 0.29 0.3 0.31 0.31 0.31 0.32
0.75 0.34 0.35 0.36 0.37 0.37 0.38
1 0.37 0.39 0.4 0.41 0.42 0.42
1.25 0.4 0.42 0.44 0.45 0.45 0.46
1.5 0.42 0.45 0.46 0.48 0.49 0.49
1.75 0.44 0.47 0.49 0.5 0.52 0.52
2 0.44 0.49 0.51 0.56 0.54 0.55
2.25 0.44 0.51 0.53 0.55 0.56 0.57
2.5 0.44 0.51 0.55 0.57 0.58 0.6
2.75 0.44 0.21 0.56 0.58 0.6 0.62
3 0.44 0.51 0.57 0.6 0.62 0.63
Table-18 :Maximum shear stress(N/sqmm)
Grade M15 M20 M25 M30 M35 m40
Permissible shear 1.6 1.8 1.9 2.2 2.3 2.5
Design bond stres 1 1.2 1.4 1.5 1.7 1.9

SBC 0.04*Fc

IRC 21, Table 6 :Basic permissible stresses in concrete


Properties/PermissiblM15 M20 M25 M30 M35 m40
Moduluss of elasticit 20 25 28 31 33 36
Permissible direct c 3.8 5 6.2 7.5 8.5 8.5
Permissible bending 5 6.7 9.3 10 11.5 11.5
Permissible tensile s -0.14 -0.17 -0.2 -0.23 -0.25 -0.25
7 day modulus of rup 2.1 2.4 2.7 3 3.2 3.4
Shear stress tco(MPa) 0.28 0.34 0.4 0.45 0.5 0.5
IRC 21, Table 7
Fe415 Tension, shear or flexure 200 MPa
Direct compression 170 MPa
Table of wind pressure and wind velocities Zone factor
Height Velocity Pressure Zone Zone factor
80 40 II 0.1
2 91 52 III 0.16
4 100 63 IV 0.24
6 107 73 V 0.36
8 113 82
10 118 91 Importance factor
15 128 107 Important 1.5
20 136 119 Other Brid 1
25 142 130
30 147 141
40 155 157
50 162 171
60 168 183
70 173 193
80 177 202
90 180 210
100 183 217
110 186 224

Conversion factor from deg. to radian 0.017453


Zone factor