Professional Documents
Culture Documents
College of Engineering
Surveying Department
Construction Surveying
Introduction
©2019
Yousif Y. Zaia
The University of
Duhok
Construction surveying Surveying Engineering
Construction staking may consist of Rough Grade Staking to map the general location on
improvements at a site, or precise Site Layout Surveys for actual construction purposes.
Rough Grade Staking Rough Grade Staking defines the location of the site improvements
with their respective reference to the location and final grade elevation. This is done for
the construction of slopes, building outlines, parking lots and roadways, and enables the
contractor to grade and prepare the site for the next sub-contractor to commence his
work.
The University of
The role of the Land Surveyor in Construction Staking Duhok
Surveying Engineering
Site Layout Staking Once the site has received inspection and approval from the local
agency, the contractor can move right into the various stages of construction of the
underground utilities, retaining walls, buildings, site lighting and parking lot or street
paving.
This Site Layout Staking phase typically begins with those features that are underground
such as sanitary sewer lines, storm drain lines, water lines, electrical lines etc. Once all
underground utilities are installed the above ground features are staked for construction.
The building corners are staked along with any interior grid lines throughout the building,
as well as onsite items such as fire hydrants, curb and gutter, walls/planters, catch basins
and area drains.
The University of
Duhok
Types of Construction Projects
Surveying Engineering
Listed below are the types of construction projects that depend a great deal on the
construction surveyor or engineering surveyor for the successful completion of the project:
1. Streets and highways 12. Storm and sanitary sewers
2. Drainage ditches 13. Water and fuel pipelines
3. Intersections and interchanges 14. Piers and docks
4. Sidewalks 15. Canals
5. High- and low-rise buildings 16. Railroads
6. Bridges and culverts 17. Airports
7. Dams and weirs 18. Reservoirs
8. River channelization 19. Site grading, landscaping
9. Sanitary landfills 20. Parks, formal walkways
10. Mining—tunnels, shafts 21. Heavy equipment locations (millwright)
11. Gravel pits, quarries 22. Electricity transmission lines.
Layout equipment The University of
Total stations are the predecessor of robotic total stations. They cost much less to purchase
and are widely used by contractors. Like robotic total stations, data collectors provide the
information needed for plotting points. Total stations' primary drawback is that two people are
needed to operate them: one at the instrument and one at the rod.
Digital levels still are used primarily by surveyors. They gather very precise elevations over
long, level routes. Sometimes the rods used have barcodes instead of numbers, so the
instrument reads the barcode to determine elevation.
Laser levels remain the workhorse of the construction industry and just about every contractor
uses them to set elevations or to guide equipment. Newer models automatically level
themselves, are easier and faster to use, and are less expensive than earlier models.
The University of
Survey Control Points Duhok
Surveying Engineering
A Survey Control Station (also known as a Standard Survey Mark - SSM) is a permanent
point of known Reduced Level (height) and Horizontal Position (Latitude and Longitude
or Easting and Northing).
A Standard Survey Mark is normally a brass plaque set in concrete, such as the one below
These stations are usually positioned below ground level to protect them from being
accidentally or purposely destroyed. An identification plaque is located nearby so that it
can be easily found.
The University of
Duhok
Protecting Survey Control Stations Surveying Engineering
After the control point has been placed in the ground, four further pegs or metal rods are
placed so that there is a peg on each side of the control point. If a string is placed across each
of the opposing recovery marks, they will intersect directly over the nail in the survey peg. If
the control point is destroyed, it can be replaced by using the recovery marks.
The University of
Horizontal control surveys use any of a variety of measuring and positioning techniques
capable of providing appropriately precise results; such surveys can be tied into
(1) state or provincial coordinate grids,
(2) property lines,
(3) roadway centerlines, and
(4) arbitrarily placed baselines or grids.
When using positioning satellites to establish or re-establish ground positions, the always-
available satellite systems themselves can be considered as a control net—thus greatly
reducing the need for numerous on-the-ground reference stations. At present, the only fully
deployed satellite-positioning system is the United States’ Global Positioning System
(GPS); the Russian system, called GLONASS, is about halfway to full deployment; and others
plan to have positioning systems deployed within the next five or ten years—for example,
Europe’s Galileo System, China’s Compass System, and an Indian positioning system.
The University of
Road Construction
The University of
Duhok
Surveying Engineering
All roads consist of a carriageway and a drainage system. Set out below is a cross section of
a typical road.
The University of
Duhok
Parts of a Road Surveying Engineering
Batter
A batter is the artificial side slope of the road
formation from the road to the natural surface.
From the natural surface it can be upward for an
area of fill or downward for an area of cut.
Traffic Lanes
The traffic lanes are that part of a road where
vehicles would normally drive. This will
vary in width, depending on the number of
lanes to the road. A lane is the portion of
road that is allocated for the use of a single
line of vehicles moving in the same
direction.
The University of
Duhok
Shoulders Surveying Engineering
The shoulders of a road are the widths of
carriageway between the outer edges of
the traffic lanes and the verge. The primary
purpose of the shoulders is to provide stability
to the roads, and to act as a safety strip or
emergency stopping space for vehicles.
Pavement
The pavement is the portion of the road, excluding the shoulders, placed above the sub-grade
to support and form a running surface for vehicles. The pavement is made up of the sub-base,
the base and the surface course. The pavement is designed to distribute the weight of vehicles
and to provide a durable wearing surface.
The University of
Duhok
Surveying Engineering
Carriageway
The carriageway is the portion of the road intended for use by vehicles, and includes the
shoulders. It can be of single, double or multi-lane construction.
Formation Width
The formation width is that part of the road bounded by the batters on either side. It includes
the traffic lanes, shoulders and the verges on both sides of the road.
The University of
Duhok
Surveying Engineering
Verge
The verge is that portion of the road that is
between the shoulders and the batters. It is
unpaved and forms the transition between the
roadway and the batter.
Embankments
An embankment is a section of road that has been built up above the natural surface of the
surrounding area. This requires soil being brought in to increase the height of the road
formation.
The University of
Duhok
Surveying Engineering
Cuttings
A cutting is a section of road that has been cut out of the ground so that the road is below
the natural surface of the surrounding area. This requires soil to be removed to decrease
the height of the road formation.
The University of
Duhok
Road Drainage Surveying Engineering
A road will be damaged unless the moisture content of the soil is adequately controlled. The
removal of water from a road is important so that the movement of traffic along the road during
periods of rain is not impeded. To achieve this a wide variety of systems is used.
Camber
Camber is the convexity of a road, meaning that the center, or crown, of the road is higher than
the sides. This means that water will drain from the center to either side of the road.
The University of
Duhok
Surveying Engineering
Cross fall
Cross fall is the straight slope of the road from
one side to the other. Normal practice is for cross
fall to be used on single lane roads, side hill roads
and where it is necessary to drain water to one
side only.
Catch Drain
A catch drain is a drain constructed along the
high side of a road or embankment outside the
batter to intercept surface water. The drain
should be as near as possible to the top of the
cutting, and channel the water into culverts or
natural water courses wherever possible.
The University of
Duhok
Surveying Engineering
Culverts
Culverts are pipes or enclosed channels used to convey water from one side of the road to
the other side, under the formation level. Drains are designed to run into a culvert on the
uphill side of the road and away from the road on the down hill side of the road.
The University of
Pegging and Leveling a Section of Road Duhok
Surveying Engineering
Once the initial decision has been made to construct a road, the surveyor will visit
the area and make a detailed map of where the road will be constructed. From this
map the tentative location of the centerline of the road is determined.
After the location of the road has been decided on, the surveyor will again visit the
area and commence pegging the centerline of the road.
The University of
Having determined the location for the centerline, the surveyor then designs the curves to
connect the straight portions into the final road.
The surveyor must now place pegs along the entire length of the centerline of the road.
The University of
Duhok
Chainage Pegs Surveying Engineering
The surveyor will start placing pegs along the centerline of the road at even intervals, starting
at the first point of the road and continue for the entire length, including around the curves.
These pegs are called chainage pegs.
The most common interval for chainage pegs is 20m although 25m is also used. Each peg is
referenced as a distance from the start, with the start point being chainage 00m. This means
that each peg along the length of the centerline of the road will have a unique reference.
The normal peg used for a chainage peg to indicate the centerline is a 25mm x 25mm
wooden peg, painted white on the top half. These pegs are not permanent, but rather will be
removed once the construction work starts. Each peg would be protected by placing a
survey stake next to it, with flagging, so that they can easily be seen.
The University of
Duhok
Offset Pegs Surveying Engineering
Once the centerline pegs have been positioned, the surveyor will then position two pegs each side
of each centerline peg. These pegs are placed at right angles from the centerline pegs and at an
even interval from the centerline. The distance from the centerline will depend on the type of road
being constructed, but the more common distances are 10m and 20m or 20m and 40m out.
The offset pegs are best positioned using an optical square, tape and range pole. There is no need
to place a survey stake next to each peg, as they can easily be replaced and only an approximate
position for each is necessary.
Like the chainage pegs, the offset pegs are usually 25mm x 25mm survey pegs, painted white at
the top.
The University of
Duhok
Surveying Engineering
b = Road base or
Road width or b
Formation width.
w1 , w2 = Side width or w1 w2
w =w1 +w2 = width of ground Center line
level.
The University of
Duhok
Surveying Engineering
Method of Measurement Cross Sectional Area
Measurements of Area of
Cross Section
w1 w2 b
m
1 1
h m h
b w1 w2
1:k
w1 w2
w2 w1
1:k
m
1 h
b
The University of
Duhok
Surveying Engineering
Solution:
The University of
w1 w2 b
hl 1 h hr
m m
hl 1 h hr
w1 w2
b
The University of
OR Known Grade Line (Two Grade Line 1:k or 1:L)
Duhok
Surveying Engineering
1:L
1:k m
h 1
b
1
m h
1:k 1:L
w1 w2
1
m h
1:k 1:L
w1 w2
Example: Find the cross sectional area shown in Figure below: The University of
Duhok
Surveying Engineering
Solution
12
h = 31.5 - 29.2 = 2.3,
El. 31.5
hl = 31.5 - 26.4 = 5.1,and
1 1
w1 = (b/2) + m*hl = (12/2) + 4 * 5.1 = 4 4 hr
hl El. 29.2
26.4
El. 26.4 w1 20
4 Sections Part in Cut and Part in Fill The University of
Duhok
Surveying Engineering
1:n
h
1:m
1:k
w2 w1
Fill Cut
Note : When the cross section is in fill at the center line, instead of being in cut as shown in figure,
then the following modified formula obtain:
The University of
Duhok
Surveying Engineering
Example: A road has a formation width of 15m and side slope of 1 vertical to 1 horizontal in cut
and 1 vertical to 2 horizontal in fill. The original has a cross fall of 1 vertical to 5 horizontal. If the
depth of excavation at the center line is 1m. Calculate the side widths and areas of cut and fill.
Solution:
The University of
An irregular cross section as shown in Figure Duhok
below, the area of this type of section can be b Surveying Engineering
determined by dividing the section into
trapezoidal and triangle. However, the most
efficient procedure is to use the coordinates h hr
hl
method. For Example.
w1 w2
X1 X2 X3 X4 X5 X1 (X2,Y2) (X3,Y3)
Y1 Y2 Y3 Y4 Y5 Y1
1
m
(X1,Y1) (X4,Y4)
(X5,Y5)
The University of
Duhok
Volume from Cross Section Surveying Engineering
Computation of Volume The University of
Duhok
Trapezoidal Rule Surveying Engineering
Simpson’s Rule
Where:
A1, A2, A3, ……An-1,An=are areas of cross section.
D1, D2,……Dn-1,Dn=are the horizontal distances
between the successive cross section.
The University of
Duhok
A1 A2 An
volume v L
n
The University of
Duhok
Surveying Engineering
Where:
A1 = 1st cross-section area
A2 = 2nd cross-section area
L = length of cut or fill
V = volume of cut or fill
The University of
Duhok
Example: Calculate the volume of earth required to form the Surveying Engineering
embankment shown in figure
The University of
Duhok
Surveying Engineering
The width of a certain road at formation level is 9.50 m with side slopes 1 in 1 for cut and 1 in 2 for
filling. The original ground has a cross-fall of 1 in 10 in embankment. While in cut sections the
original ground surface has three different levels as shown in table.
St. R C L
2+50 106.0 106.4 105.7
3+00 105 105.9 105.5
3+50 106.8 105.3 105.3
Mass Haul Diagram The University of
Duhok
Surveying Engineering
Shows two curves:
A continuous curve representing
the profile of the existing grade.
A continuous curve representing
the accumulated volume of earth
work plotted against the linear
profile of the roadway.
Tells Us:
1. Quantities of Materials to cut and fill
2. Average Haul Distances
3. Types of Equipment that should be
considered
4. Mass diagrams are also extremely
useful in determining the most
economical distribution
Definitions Related To Mass Diagrams:- The University of
Duhok
Surveying Engineering
1000
V
o 500 Mass Diagrams are plotted from the
l
u 0 Earthwork Volume
m
e
- 500
- 1000
2 + 00 4 + 00 6 + 00 8 + 00
Station Numbers
Duhok
1000
V 500
o
l 0 Station Mass
# Ordinate
u
-m
350 1 + 00 - 350
e - 500
- 1000
1 + 00 2 + 00 4 + 00 6 + 00 8 + 00
Station Numbers
The University of
Duhok
Surveying Engineering
1000
Station Mass
V 500 # Ordinate
o
l 2 + 00 - 700
u 0
m
e - 500
- 700
- 1000
2 + 00 4 + 00 6 + 00 8 + 00
2 + 00
Station Numbers
The University of
Duhok
Surveying Engineering
1000
V 500
o
l Station Mass
u 0 # Ordinate
m
e - 500 3 + 00 - 700
- 1000
2 + 00 4 + 00 6 + 00 8 + 00
Station Numbers
The University of
Duhok
Surveying Engineering
1000
V 500
o
l 0
u
m
e - 500
- 1000
2 + 00 4 + 00 6 + 00 8 + 00
Station Numbers
The University of
Duhok
Surveying Engineering
1000
V 500
o
l 0
u
m
e - 500
- 1000
2 + 00 4 + 00 6 + 00 8 + 00
Station Numbers
The University of
Duhok
Surveying Engineering
1000
V 500
o
l
u 0
m
e
- 500
- 1000
2 + 00 4 + 00 6 + 00 8 + 00
Station Numbers
The University of
Duhok
Surveying Engineering
1000
NODE 1
V 500
o
l 0
u
m
e - 500
- 1000 NODE 2
2 + 00 4 + 00 6 + 00 8 + 00
Station Numbers
The University of
Duhok
Surveying Engineering
1000
Final Position
Final Position indicates if the
V 500 project is predominately cut or fill.
o
l 0
u
m FILL CUT
e - 500
In a Node, the volume
of cut is equal to the
- 1000 volume of fill.
Shows the transition
from cut to fill.
2 + 00 4 + 00 6 + 00 8 + 00
Transition Point - Where the Mass
Diagram Line changes direction. Station Numbers
The University of
Duhok
Surveying Engineering
50
50
2 + 00 4 + 00 6 + 00 8 + 00
Station Numbers
The University of
Duhok
Example 1 :- for the tabulated data below, draw the mass Surveying Engineering
haul diagram assuming an bulking factor 20% :-
Distance
Distance
(m) (m)Cut volume
Cut volume
Fill volume
Fill volume Fill Fill
(10%)(10%) Accumula.
Accumula.
(𝒎𝟑 )(𝒎𝟑 ) (𝒎𝟑 (𝒎
) 𝟑) (fill*1.1)
(fill*1.1) Volume
Volume
0 0 7.2 7.2 0.00.0
20 20 19.0 19.0 7.27.2
40 40 42.0 42.0 26.2
26.2
60 60 15.5 15.5 68.2
68.2
80 80 3.0 3.0 83.7
83.7
96 96 0.480.48 0.528
0.528 86.7
86.7
100 100 25.025.0 27.5
27.5 86.172
86.172
120 120 8.0 8.0 8.8 8.8 58.672
58.672
140 140 13.513.5 14.85
14.85 49.872
49.872
160 160 17.717.7 19.47
19.47 35.022
35.022
180 180 15.615.6 17.16
17.16 15.552
15.552
200 200 9.1 9.1 10.01
10.01 -1.608
-1.608
220 220 2.752.75 3.025
3.025 -11.618
-11.618
240 240 -14.643
-14.643
The University of
Duhok
Surveying Engineering
The University of
Duhok
Example 3 :- given the following data, complete the
Surveying Engineering
earthworks using shrinkage of 90% then prepare the M.H.D
and find the following:
a. Limited of economical haul.
b. Free-haul volume
c. over-haul volume
d. Waste volume
e. Borrowing volume
given the cost of Over-Haul = 30 $ / cubic meter
Cost of borrow = 120 $ / cubic meter
Free haul distance = 200 m
Stat. 1 2 3 4 5 6 7 8 9 10 11
Cut 1100 1300 1500 1500 350 300 1400
Fill 250 1300 1500 1300 1000 200
The University of
Fill Corrected Cumulated
Station Cut m3 Cut Duhok
m3 fill Volume
Surveying Engineering
0
1 1100 1100
1100
2 1300 1300 2400
Route Surveying
( Horizontal and Vertical Curves)
The University of
Duhok
Introduction Surveying Engineering
3. Detailed Surveying Precise instruments are used for setting out center
line stations for the chosen location and several
cross sections are set out along the center line,
Maps and sketches are drawn using large scale
(1:1000-1:2500) or larger with a contour interval
of 1-2 m.
The University of
Duhok
Surveying Engineering
Vertical curves
Horizontal curves
Types of Horizontal Curves The University of
Duhok
Horizontal Curves Surveying Engineering
Lemniscate Curve
Terminology of Horizontal Circular Curves The University of
Duhok
Surveying Engineering
• Curves are designated by their radius (R) or their degree of Curvature (D°).
The offsets from tangents may be calculated and set to get the required curve. The offsets can be
either radial or perpendicular to tangents.
(i) Radial offsets: Referring to Fig., if the center
of curve O is accessible from the points on
tangent, this method of curve setting is possible.
(ii) Perpendicular offsets: If the center of a circle is not visible, perpendicular offsets from
tangent can be set to locate the points on the curve.
Example 1: Duhok
Surveying Engineering
Two roads having a deviation angle of 45° at intersection point are to be joined by a
200 m radius circular curve. If the chainage of intersection point is 1839.2 m, calculate
necessary data to set the curve by radial and perpendicular offsets from every full
station of 30 m along tangent.
R = 200 m △ = 45°
The University of
Duhok
Surveying Engineering
Chainage of T1 = 1756.36 m
The University of
Duhok
Surveying Engineering
Chainage of T1 = 1756.36 m
The University of
c- Offsets from the chord produced Duhok
Surveying Engineering
This method is very much useful for setting long curves. In this method, a point on the curve
is fixed by taking offset from the tangent taken at the rear point of a chord.
The University of
Example 2: Duhok
Surveying Engineering
Two roads intersect at chainage of 1000 m. The deflection angle being 30ᵒ. Calculate all
necessary data for setting out a circular curve of radius 200 m by method of offsets from
the chord produced, take a peg interval of 20 m.
The University of
Duhok
Surveying Engineering
The University of
d- Successive Bisection of Chord Duhok
Surveying Engineering
In this method, points on a curve are located by bisecting the chords and erecting the
perpendiculars at the mid-point. Referring to Fig.
Similarly
Example 3: Duhok
Surveying Engineering
Use data of example 1, set out the curve using successive bisection of chord method.
The University of
The horizontal curve below has a deflection angle (13° 16′), radius
(600m) and P.I station (27+45.75), stakeout the curve use 25m
station.
The University of
Duhok
Surveying Engineering
The University of
Duhok
Surveying Engineering
The University of
Duhok
Surveying Engineering
P.C. 26+75.94 00° 00′ 00″ 00° 00′ 00″ 0.00 0.00
P.E. 28+14.87 00° 42′ 36″ 06° 38′ 00″ 14.87 138.93
The University of
Duhok
Surveying Engineering
The University of
Duhok
Curves and Coordinates
Surveying Engineering
a. Coordinate Equations
The equations below are general equations for computing coordinates using direction and
distance from a known point
Curve point coordinates can be computed using these equations from a base point. Since the
radial chord method uses the BC as one end of all the chords, it can also be used as the base
point for coordinate computations.
The University of
Duhok
b. Computation Process
Surveying Engineering
Assuming we start with the tangents and PI, then fit a curve, the general process is as follows:
The width of a certain road at formation level is 10 m with side slopes 1 in 1 for cut and 1 in 2 for
filling. The original ground has a cross-fall of 1 in 10 in cut. While in embankment sections the
original ground surface has three different levels as shown in table. Work out the following:
St. R C L
0+00 72.45 71.15 71.65
0+50 70.90 71.25 71.50
1+00 70.85 70.85 70.60
The University of
Quiz #2 Duhok
Surveying Engineering
A tangent with a bearing of N 85° 55′ 30″ E meets another tangent with a
bearing of S 75° 34′ 30″ E at PI station 1590.25 m and they connected by a
simple circular curve. The design showed that a building obstructs the line of
sight of the driver as shown in figure. Use Deflection Angles and Chords
method, stakeout the curve every 50 m station.
Vertical Curves The University of
Duhok
Surveying Engineering
The University of
Duhok
Surveying Engineering
• If two given grades are to be connected by a vertical curve, then either r or
L must be assumed and the other value is computed .
• When a vertical curve is laid out so that V lies mid way between the two
ends of the curve measured horizontally, the curve is an equal-tangent
parabolic vertical curve.
EVC
Y g2
BVC V
g1
L/2 L/2 X
L
The University of
Duhok
Surveying Engineering
sag
+r
-g1 +g2
-r
summit
sag +g2
+r
+g1
-r
summit
The University of
Vertical curves by equation of parabola (analytical Duhok
method) Surveying Engineering
Y EVC
g2
BVC V
g1
L/2 L/2 X
L
The University of
Vertical curves by equation of parabola (analytical Duhok
method) Surveying Engineering
The University of
Vertical curves by equation of parabola (analytical Duhok
method) Surveying Engineering
The University of
Example: Duhok
Surveying Engineering
g1=+1.25% and g2=-2.75% intersect at station 18+00 , elevation of
V=686.1, length of v. curve = 600 .
Compute Elevation of BVC
Elev. Of EVC
Elev. Of all full stations .
BVC EVC
18+00
16
19 20
17
15+00 21+00
The University of
Duhok
Surveying Engineering
The first step in setting out a roadway is to establish the center line. In order to achieve this, the
coordinates of all points of change of direction must be obtained from the development plan.
Figure below is a skeletal layout of the roadway R1-R4.
The coordinates of starting point R1,
finishing point R4 and intersection
point X1 must be scaled as accurately
as possible from plan or obtained
from a CAD version of the plan.
The coordinate values are shown in
table
Point E (m) N (m)
R1 47.00 106.70
X1 69.00 128.70
R4 107.00 91.80
The University of
1- Setting out the roadway as a traverse. Point C (Survey St.), R1, X1, R4, and F are treated as
points of a traverse survey and are set out by angles and distances using theodolite or total
station. The chosen instrument is set up in turn on each of the points and the traverse is closed
on point F.
This method takes time and assistants have to be skilled, particularly if distances are to be set out
by tape. However, the method is self-checking in that the survey finishes on the known
coordinates of point F and any errors are therefore detected.
2- Setting out coordinates by radiation. The coordinates of points R1, X1 and R4 are set out
directly from some convenient survey point, probably B, using total station instrument and
prism.
This method is speedy and an unskilled assistant may be employed to handle the prism. The
disadvantage is that the points are unchecked and errors are not noticed till later, resulting in
more expenditure.
The University of
Duhok
c- Setting out the road as a traverse Surveying Engineering
The traverse, as already explained, comprises the points C, R1, X1, R4, F.
i- The coordinates of points R1, X1 and R4 are shown in the previous table. (The coordinates of
points C and F are already known.
ii- Calculate the bearing and distance of the lines C-R1, R1-X1, X1-R4, and R4-F, as shown in table.
1- The theodolite or total station is set up at survey station C and back sight is taken to station
B with the instrument reading zero degree.
2- The horizontal circle is set to read 154ᵒ 38′ 34″; thus the theodolite now points towards
station R1.
3- The assistants set the tape along this line C-R1 and measure 6.488 m horizontally, this
establishing point R1.
4- The theodolite is removed to station R1, back sight to station C and procedure described
above is repeated, with the next set of data.
5- The setting out is continued to reach peg F.
The University of
d- Setting out by coordinates Duhok
Surveying Engineering
When calculating setting out distances, the plan distance is always produced. However, on the
ground it is often difficult to measure distances horizontally; hence the ground slope along the
line being set out has to be found and the plan distance amended.
Setting out building and engineering works, using total station instrument, has therefore become
standard practice on construction sites, since those instruments allow horizontal distances to be
set out without difficulty.
Using EDM methods requires that the coordinates of every proposed point be determined,
usually by calculation.
METHOD 2
The most frequently used method of slope measurement in construction surveying involves
measuring the slope distance, determining the slope angle, and calculating the horizontal
distance. The horizontal distance can be calculated by multiplying the slope distance by the
Cosine of the slope angle.
The University of
Duhok
Surveying Engineering
Suppose one needs to determine the horizontal distance between Points A and B. Using a
slope angle of 6° 25′ 21″ and a slope distance of 73.84 m.
Slope stakes are set to mark the intersection of the proposed side slope and the original ground
or “catch point”. Slope stakes may be placed prior to the contractor clearing and grubbing as a
way to establish the clearing limits. The slope staking procedure should be discussed with the
contractor and the earthwork superintendent prior to beginning earthwork operations so all
personnel are aware of how the slope stakes are marked and read.
In this example we are going to slope stake the 2:1 back slope on the right side of the typical
section shown in figure.
First the elevation at the toe of the slope we are staking must be determined. These
elevations are typically determined prior to going out in the field. Performing these
calculations beforehand will greatly speed up the slope staking process once in the field. The
process is as follows:
The University of
Duhok
Surveying Engineering
1) To calculate the elevation at the toe of slope we must first determine the elevation at centerline.
Centerline elevations are determined by using the plan and profile sheets. For this example, we
will assume a centerline elevation of 6550.00 and use the typical section in figure.
a) First, convert the -2.0% cross slope to decimal form by dividing by 100, -2.0% / 100 = -
0.02 ft./ft.
b) Next calculate the difference in elevation between the centerline and the shoulder by
multiplying the horizontal distance by the -0.02 ft./ft., 20 ‘ x -0.02 ft./ft. = -0.40
d) Repeat this process from the shoulder to the toe of the slope.
c) Subtract this difference from the centerline elevation to calculate the elevation at the
shoulder. 6550.00 – 0.4 = 6549.60.
2) Once the toe of slope elevation is determined we are ready to set up the level and begin
slope staking.
a) First set up the level in a convenient location where a back sight to an existing benchmark
can be seen as well as the probable location of the catch point.
b) Then determine an H.I
The University of
Duhok
Surveying Engineering
3) Once an H.I. is determined, calculate the difference between the H.I. and the finished grade
at the toe of slope. 6555.30 – 6547.60 = 7.7. This difference is called the Grade Rod. This
calculation is done only on paper and is not actually a shot taken with the level. Figure below
shows a graphical representation of a Grade Rod. By determining a Grade Rod we will be
able save time by using the difference in rod readings to slope stake rather than having to
convert them to elevations first.
The University of
Duhok
Surveying Engineering
4) Once the Grade Rod is determined we can begin taking shots in the approximate location
of the catch point, several attempts may be necessary.
5) While measuring the distance from centerline, take a F.S. in the approximate location of
the catch point. This is called the Ground Rod. For our first attempt we read a -3.2 on the
level rod at a distance of 35’ from centerline. See figure.
The University of
Duhok
Surveying Engineering
6) The difference between the Grade Rod and the Ground Rod will either be a cut or fill. This
cut or fill is multiplied by the slope and added to our reference offset to determine the
horizontal distance from centerline.
The Reference Offset is the horizontal distance from centerline of the roadway to the beginning
of the slope being staked. This offset represents the horizontal distance that remains unchanged
regardless of where the catch point is staked. In some cases this distance may remain the same
between several typical sections. In our example, it is the toe of slope on the right side 28’ from
centerline. This offset See figure below.
The University of
Duhok
Surveying Engineering
7) Using the formula above, we can perform the calculations for our first attempt as follows:
a) First calculate the cut or fill. For our example 7.7 is subtracted from 3.2 this equals a fill of 4.5.
b) Next calculate our distance by multiplying the fill by the side slope. 4.5 x 2 = 9.0.
c) Then add this distance to the reference offset. 28’ + 9.0’ = 37.0’.
d) Our calculated distance is then compared to the actual distance we measured. Our measured
distance of 35’ is not equal to our calculated distance of 37’. If they were the same, a slope stake
would be set. But, since they are not, the process is repeated at a new distance from centerline
until the measured distance matches the calculated distance.
The University of
Duhok
Surveying Engineering
8) For our second attempt we will move further out from centerline and repeat the process. Try
a rod reading of -2.3 at a distance of 40’ from centerline. See figure
28’ + (7.7 - 2.3) x 2 = 38.8’, this is not equal to 40.0’, try moving closer.
The University of
Duhok
Surveying Engineering
9) For our third attempt try a rod reading of -2.7 at 38’ from centerline. See figure
28’ + (7.7 - 2.7) x 2 = 38’, this is equal to 38’. A stake would then be set at this point.
Setting slope stakes is a process of trial and error; several shots at different distances from
centerline are generally required to set slope stakes
The University of
Duhok
Surveying Engineering
Setting out of building foundation trenches is the process of laying down the excavation line
and centerline on the ground based on the foundation plan. The setting out process is also
called as ground tracing that is performed before commencing the excavation process.
Once the design of foundation is complete, a setting out plan or foundation layout is prepared
for a suitable scale and the plan is dimensioned accordingly.
Once the design of foundation is complete, a setting out plan or foundation layout is prepared
for a suitable scale and the plan is dimensioned accordingly. Procedure and requirements in
setting out foundation trenches are explained below.
The basic steps involved in setting out the foundation trenches are:
1 9
Setting Out Building on Ground The University of
• Using Coordinates Duhok
Surveying Engineering
Setting out points using coordinates has become standard practice on construction sites.
Setting out by EDM methods requires that the coordinates of every proposed point be
determined, usually by calculation. The coordinates of the point are compared with those of
the setting-out control station and the horizontal distance and bearing between the two are
computed. The proposed point is then set out from the control station.
Setting Out Building on Ground The University of
• Using Coordinates Duhok
Surveying Engineering
Figure above shows the plan of an industrial estate where the coordinates of survey station
ABCD and E have been determined. A large rectangular building X is to be set out on the estate.
Since the building quite far removed from the survey point, a control station closer to the
building would usually be established. The coordinates of the station, often called free station,
are determined either by intersection or by resection.
First, the topographic detail is collected using total stations set up at various control points
(preliminary survey). The detail is then transferred to the computer (and adjusted, if
necessary), and converted into Y, X, and Z coordinates. Various programs can then be used to
design the proposed road. When the proposed horizontal, cross-section, and profile alignments
have been established, the proposed coordinates (Y, X, and Z) for all key horizontal and vertical
(elevation) features can be computed and stored in computer files. The points coordinated
include top-of-curb and centerline (CL) positions at regular stations, as well as all changes in
direction or slope. Catch basins, traffic islands, and the like are also included, as are all curved
or irregular road components.
The University of
Duhok
Surveying Engineering
The computer files now include coordinates of all
control stations, all topographic detail, and (finally) all
design component points. Control point and layout
point coordinates (Y, X, and Z) can then be uploaded
into the total station. The layout is accomplished by
setting the instrument to layout mode, then setting up
at an identified control point, and properly orienting
the sighted instrument toward another identified
control point. Second, while still in layout mode, and
after the first layout point number is entered into the
instrument, the required layout angle or azimuth and
layout distance are displayed. To set the selected
layout point from the instrument station, the layout
angle (or azimuth) is then turned (automatically by
motorized total stations) and the distance is set by
following the display instructions (backward/forward,
left/right, up/down) to locate the desired layout point.
When the total station is set to tracking mode, the
surveyor can first set the prism close to target by rapid
trial-and-error measurements.
The University of
Duhok
Surveying Engineering
Verticality Survey
The University of
Checking Verticality Duhok
Surveying Engineering
In figure below an office block rises to a height of five stories and the columns must be
checked at every storey for verticality.
The University of
The Importance of a Verticality Survey Duhok
Surveying Engineering
Put simply, a Verticality Survey checks to see whether a building, structure or even a
retaining wall is completely vertical or leans towards one direction or another.
All project managers know the importance of an accurate Measured Building Survey, however
Verticality Surveys can often be overlooked.
A Verticality Survey can be undertaken either during the construction phase of a new build
or post construction for as-built reports, and can be carried out both internally and
externally.
Checking verticality works would encounter during building construction at several stages such
as during installing vertical formworks of columns and transferring levels up successive floors
of multi storey structures. Various methods which to control or check verticality works during
building construction are discussed.
1. Plumb-bob technique
2. Spirit level
3. Theodolite
4. Optical plummet
The University of
1. Plumb-Bob Technique Duhok
Surveying Engineering
This tool is appropriate for controlling verticality of small scale works for example
checking formworks and door frames. If spirit level is employed for approximate
checks, then it is required to check the verticality with more accurate technique.
The University of
3. Theodolite Method Duhok
Surveying Engineering
•After Theodolite set up accurately the laser beam will be turned on and focused it to the steel tape which
is held to the formwork.
•Take the reading of the steel tape through the telescope.
•Take the readings of two positions at the same level on both top and bottom levels of the formwork. By
taking two readings at the same level any curvature on the surface can be identified
The University of
4. Optical Plummet Method Duhok
Surveying Engineering