Materials Inventory as of second week (Monday):
REINFORCEMENT STEEL BARS
6M – D16mm ………………………………………………………………………………………………………………………………..19pcs
CONCRETE HOLLOW BLOCKS
5’’ CHB ……………………………………………………………………………………………………………………..……..287pcs
CEMENT (BAGS)
Holcim Cement (40kg) ……………………………………………………………………………………………………….…….…12 bags
MISCELLANEOUS ITEMS
#16 G.I Tie Wire ………………………………………………………………………………………………………………………...+/- 5kgs
14’’ Cutting Disc .…………………………………………………………………………………………………………………………….1 pc
EQUIPMENT
Shovel …………….………………………………………………………………………………………………………………………….... 3 pcs
A-Frame (1-bagger) Concrete Mixer .…………………………………………………………………………………………… 1 unit
14’’ Metal Cut-off Saw ……………………………………………………………………………………………………………..… 2 units
Circular Saw (Wood) ……………………………………………………………………………………………………………………. 1 unit
2
DECEMBER 7, 2020 (Monday)
Weather Condition: Sunny
Attendance:
NAME DESIGNATION STATUS
PAUL FOREMAN PRESENT
IAN STEELMAN PRESENT
VAL STEELMAN PRESENT
DAN CARPENTER PRESENT
HENRY CARPENTER PRESENT
ALEX LABOR PRESENT
RENE LABOR ABSENT
KEN LABOR PRESENT
KEVIN LABOR PRESENT
ROMEO MASON (RESCUE) PRESENT
BOY MASON (RESCUE) ABSENT
NOTE: w/ 2-man rescue from Tam-awan project.
Work done:
Excavation at basement floor
Installation of beam reinforcements
Hauling of cement and R.S.B
Bending of steel for beam reinforcements
Deliveries/Expenses/Purchases:
20 bags of Northern Cement (40kg)……………………………………………………..…………………………………..4200php
30 pcs of 6M – D10mm R.S.B …………………………………………………………………………………………………..3780php
Delivery Fee ……………………………………………………………………………………………………………………………….400php
Water Bill ………………………………………………………….……………………………………………..….………………...11980php
TOTAL = 20,360php
Materials used:
REINFORCEMENT STEEL BARS