Weekly

Construction
Report – Second Week
December 2020

4-STOREY DORMITORY
HONEYMOON ROAD, BAGUIO CITY

1
Materials Inventory as of second week (Monday):
REINFORCEMENT STEEL BARS
 6M – D16mm ………………………………………………………………………………………………………………………………..19pcs
CONCRETE HOLLOW BLOCKS
 5’’ CHB ……………………………………………………………………………………………………………………..……..287pcs
CEMENT (BAGS)
 Holcim Cement (40kg) ……………………………………………………………………………………………………….…….…12 bags
MISCELLANEOUS ITEMS
 #16 G.I Tie Wire ………………………………………………………………………………………………………………………...+/- 5kgs
 14’’ Cutting Disc .…………………………………………………………………………………………………………………………….1 pc
EQUIPMENT
 Shovel …………….………………………………………………………………………………………………………………………….... 3 pcs
 A-Frame (1-bagger) Concrete Mixer .…………………………………………………………………………………………… 1 unit
 14’’ Metal Cut-off Saw ……………………………………………………………………………………………………………..… 2 units
 Circular Saw (Wood) ……………………………………………………………………………………………………………………. 1 unit

2
DECEMBER 7, 2020 (Monday)
Weather Condition: Sunny
Attendance:
NAME DESIGNATION STATUS
PAUL FOREMAN PRESENT
IAN STEELMAN PRESENT
VAL STEELMAN PRESENT
DAN CARPENTER PRESENT
HENRY CARPENTER PRESENT
ALEX LABOR PRESENT
RENE LABOR ABSENT
KEN LABOR PRESENT
KEVIN LABOR PRESENT
ROMEO MASON (RESCUE) PRESENT
BOY MASON (RESCUE) ABSENT
NOTE: w/ 2-man rescue from Tam-awan project.
Work done:
 Excavation at basement floor
 Installation of beam reinforcements
 Hauling of cement and R.S.B
 Bending of steel for beam reinforcements
Deliveries/Expenses/Purchases:
 20 bags of Northern Cement (40kg)……………………………………………………..…………………………………..4200php
 30 pcs of 6M – D10mm R.S.B …………………………………………………………………………………………………..3780php
 Delivery Fee ……………………………………………………………………………………………………………………………….400php
 Water Bill ………………………………………………………….……………………………………………..….………………...11980php
TOTAL = 20,360php
Materials used:
REINFORCEMENT STEEL BARS
 6M – D10mm ………………………………………………………………………………………………………………………………..20pcs