HEAD OFFICE : MEDAN BRANCH OFFICE : BANDA ACEH

Jl. DR. TD. Pardede No.6, Medan – 20153 Jl. Daud Beureueh No. 101 Kuta Alam

Telp. (061) 4152269 Banda Aceh


PT Bima Golden Powerindo
energize your world Fax. (061) 4151991

Planing Tim pelaksana


No : 2 1.khalid perkasa
Date : 1/2/2018 2.muhajir
Start : 3/2/2018
Finish :
13/02/2018 SCHEDULE PEKERJAAN
Arrive :
25/02/2018
Site : blangkejeren TROUBLESHOOTING UNIT 5 MITSUBISHI S16R-PTA Sn 17105 (engine burn out) AND COMTEST UNIT 1 MITSUBISHI S16R-PTA Sn 16992 (AFTER T.O)

DATE LIMIT DAY ADD BALANCE OVERTIME


NO JOB DESCRIPTION CLARIFICATON OVER ACCESSION OVERTIME DESCRIPTION JOB TARGET OVERTIME PERSON
START FINISH ACCESSION TARGET ACCESSION WORK DAY DATE IN OUT COUNT
(n) (s) (f) (a) (j) t=(f-s) a1=(a-s) a2=(f-s) b=(bup+t-a+a2) (c ) (d) (i) (o) c1=(o-i) (o1) (t1) (p)
(Date) (Date) (Date) (Description) ( Day) ( Day) ( Day) ( Day) (Description) (Date) (Time) (Time) (Hours) (Description) (Description) (Name)
TAHAP ESTIMASI BESERTA PEMBONGKARAN ENGINE #5
*buka housing turbo sisi L 2 pcs 03/02/18 14:00:00 18:00:00 04:00:00 *buka turbo 2pcs sisi L khalid,muhajir,anil,ali
*buka pipe turbo sisi L *buka air cooler 2 pcs Lembur hari sabtu
*buka pipe outlet
*buka pipe intake before air cooler
*test kebocoran air cooler 2 pcs 04/02/18 08:00:00 19:00:00 11:00:00 *test kebocoran air cooler 2 pcs Lembur hari minggu Khalid,muhajir,anil ali
*buka cover crocker case 1 s/d 16 *buka cover crocker case 1 s/d 16
*Buka cover crank case 1 s/d 16 *Buka cover crank case 1 s/d 16
1 03/02/18 05/02/18 05/02/18 2 2 0 0
*pengechekan ruang bakar *pengechekan ruang bakar
*pengechekan all dinding liner *pengechekan all dinding liner
*Cabut injector 16 pcs *Cabut injector 16 pcs
*buka rocker arm 3 pcs *buka rocker arm 3 pcs
*Buka rocker case 3 pcs *Buka rocker case 3 pcs
*Cabut cyl head 3 pcs *Cabut cyl head 3 pcs
*Cabut piston 3 pcs *Cabut piston 3 pcs
TAHAP PEMASANGAN ENGINE #1
*Buka all pipeing acssesoris injection pump sisi L dan R
*Buka all bolt injection pump sisi L dan R
*Buka injection pump sisi L dan R
*pemasangan injection pump calibrasi dari BWTC sisi L dan
R
*Pemasangan pipe acsesoris injection pump
*Test pressure injector engine #5
*Pengisian air battery engine #1
2 05/02/18 06/02/18 07/02/18 *pengisian air radiator #1 1 2 1 0 *waiting injector dari BNA
*pengisian oli engine #1 *repair injector 16 pcs engine #5 BKJ
*pemasangan all fuel filter
*pemasangan air filter
*pemasangan v-belt altenator
*Connect battery
*pemasangan injector 16 pcs
*Pengikatan bolt nut
*pemasangan cover cyl head

TAHAP COMTEST ENGINE #1 08/02/18 17:00:00 03:00:00 09:59:59 *pengambilan data comtest #1 memonitoring engine dan khalid,muhajir,anil
record data engine
*Test crank engine #1 09/02/18 17:00:00 02:00:00 09:00:00 *monitoring comtest engine #1 khalid,muhajir,dodi,zoelhelmi
*Test running rpm bertahap
*Simulasi sensor
*Safety device
*test sincrone
*Buka cover cyl head 8 pcs
3 08/02/18 10/02/18 10/02/18 2 2 0 0
*Cabut injector 8 pcs
*Pengechekan pressure ulang
*pemasangan kembali injector 8 pcs
*Pengikatan bolt nut
*lanjut comtest unit #1
*running Rpm 1500 rpm
*load sistem 900 kw

Page 1 of 4
HEAD OFFICE : MEDAN BRANCH OFFICE : BANDA ACEH

Jl. DR. TD. Pardede No.6, Medan – 20153 Jl. Daud Beureueh No. 101 Kuta Alam

Telp. (061) 4152269 Banda Aceh


PT Bima Golden Powerindo
energize your world Fax. (061) 4151991

Planing Tim pelaksana


No : 2 1.khalid perkasa
Date : 1/2/2018 2.muhajir
Start : 3/2/2018
Finish :
13/02/2018 SCHEDULE PEKERJAAN
3 08/02/18
Arrive : 10/02/18 10/02/18 2 2 0 0
25/02/2018
Site : blangkejeren TROUBLESHOOTING UNIT 5 MITSUBISHI S16R-PTA Sn 17105 (engine burn out) AND COMTEST UNIT 1 MITSUBISHI S16R-PTA Sn 16992 (AFTER T.O)

DATE LIMIT DAY ADD BALANCE OVERTIME


NO JOB DESCRIPTION CLARIFICATON OVER ACCESSION OVERTIME DESCRIPTION JOB TARGET OVERTIME PERSON
START FINISH ACCESSION TARGET ACCESSION WORK DAY DATE IN OUT COUNT
(n) (s) (f) (a) (j) t=(f-s) a1=(a-s) a2=(f-s) b=(bup+t-a+a2) (c ) (d) (i) (o) c1=(o-i) (o1) (t1) (p)
(Date) (Date) (Date) (Description) ( Day) ( Day) ( Day) ( Day) (Description) (Date) (Time) (Time) (Hours) (Description) (Description) (Name)

TAHAP CLEANING ENGINE #5 10/02/18 14:00:00 17:00:00 03:00:00 *cleaning block dudukan liner
*Cabut liner 3 pcs *pemasangan liner 3 pcs
*cleaning carter oli *cleaning housing air cooler khalid,muhajir,ali
*Cleaning block
*buang oli carter
*Buka filter oli
4 10/02/18 12/02/18 12/02/18 *Cleaning gasket air cooler 2 2 0 0 11/02/18 08:00:00 18:00:00 10:00:00 *Cleaning gasket air cooler Lembur hari sabtu dan minggu khalid,muhajir,anil,bastian tanjung
*cleaning rocker case 3 pcs *cleaning rocker case 3 pcs
*cleaning housing air cooler *cleaning housing air cooler
*cleaning cyl head 3 pcs *cleaning cyl head 3 pcs
*Cleaning block keseluruhan *Cleaning block keseluruhan
*Overhoul piston 3 pcs dan pemasangan yang baru *Overhoul piston 3 pcs dan pemasangan yang baru

PM 50 HOURS ENGINE #1
*Buka all cover cyl head
*buang oil carter
*pergantian all filter
5 14/02/18 15/02/18 15/02/18 *cleareance valve inlet dan exhaust 1 s/d 16 1 1 0 0
*perbaikan joint fleksibel yang bocor
*Pemasangan kembali all cover
*lanjut comtest unit #1

TAHAP PEMASANGAN ENGINE #5 16/02/2018 08:00:00 17:00:00 09:00:00 *Pemasangan rubber housing air filter
*Pemasangan rubber housing air filter *Pengechekan all dinding liner Khalid,muhajir
*Pengechekan all dinding liner *Pengetesan kebocoran
*Pengetesan kebocoran *Pemasangan cover crankcase 1 s/d 16 Hari libur
6 15/02/18 17/02/18 17/02/18 *Pemasangan cover crankcase 1 s/d 16 2 2 0 0 *Pemasangan all pipeing injection pump sisi L dan R
*Pemasangan all pipeing injection pump sisi L dan R *Cleareance valve cyl head 6,8,15
*Cleareance valve cyl head 6,8,15

COMTEST DAN DOKUMENTASI #5


*Pemasangan pipe pressure no 4
*Pemasangan all filter
*pengisian oli engine #5 *engine gagal sincrone

*Pasang air filter *Kondisi motor fan 1 pc bermasalah tidak dikerjakan secara
paralel
*Running test 1500 rpm *Kondisi exhaust manifold ubnormal
*lanjut comtest unit #5 *terlambat disupport
*load sistem 700 kw
*Pengukuran Kabel motor fan
*Pengukuran kabel contactor dan over load
*pergantian overload dan contactor dari engine #6
7 17/02/18 19/02/18 21/02/18 *Load sistem engine #5 2 4 1 -1

*buka housing racor dan pergantian dengan yang baru


*Buka pipe fuel system overflow sisi L dan R
*Buka cover exhaust
*buka pipe outlet

Page 2 of 4
HEAD OFFICE : MEDAN BRANCH OFFICE : BANDA ACEH

Jl. DR. TD. Pardede No.6, Medan – 20153 Jl. Daud Beureueh No. 101 Kuta Alam

Telp. (061) 4152269 Banda Aceh


PT Bima Golden Powerindo
energize your world Fax. (061) 4151991

Planing Tim pelaksana


No : 2 1.khalid perkasa
Date : 1/2/2018 2.muhajir
Start : 3/2/2018
Finish :
13/02/2018 SCHEDULE PEKERJAAN
Arrive :
25/02/2018
Site : blangkejeren TROUBLESHOOTING UNIT 5 MITSUBISHI S16R-PTA Sn 17105 (engine burn out) AND COMTEST UNIT 1 MITSUBISHI S16R-PTA Sn 16992 (AFTER T.O)
7 17/02/18 19/02/18 21/02/18 2 4 1 -1

DATE LIMIT DAY ADD BALANCE OVERTIME


NO JOB DESCRIPTION CLARIFICATON OVER ACCESSION OVERTIME DESCRIPTION JOB TARGET OVERTIME PERSON
START FINISH ACCESSION TARGET ACCESSION WORK DAY DATE IN OUT COUNT
(n) (s) (f) (a) (j) t=(f-s) a1=(a-s) a2=(f-s) b=(bup+t-a+a2) (c ) (d) (i) (o) c1=(o-i) (o1) (t1) (p)
(Date) (Date) (Date) (Description) ( Day) ( Day) ( Day) ( Day) (Description) (Date) (Time) (Time) (Hours) (Description) (Description) (Name)
*pergantian rubber clamp pipe outlet
*comtest engine #5
*Monitoring engine #5 BKJ
*Serah terima engine #5 BKJ

Page 3 of 4
HEAD OFFICE : MEDAN BRANCH OFFICE : BANDA ACEH

Jl. DR. TD. Pardede No.6, Medan – 20153 Jl. Daud Beureueh No. 101 Kuta Alam

Telp. (061) 4152269 Banda Aceh


PT Bima Golden Powerindo
energize your world Fax. (061) 4151991

Planing Tim pelaksana


No : 2 1.khalid perkasa
Date : 1/2/2018 2.muhajir
7 17/02/18
Start : 3/2/2018
19/02/18 21/02/18 2 4 1 -1
Finish :
13/02/2018 SCHEDULE PEKERJAAN
Arrive :
25/02/2018
Site : blangkejeren TROUBLESHOOTING UNIT 5 MITSUBISHI S16R-PTA Sn 17105 (engine burn out) AND COMTEST UNIT 1 MITSUBISHI S16R-PTA Sn 16992 (AFTER T.O)

DATE LIMIT DAY ADD BALANCE OVERTIME


NO JOB DESCRIPTION CLARIFICATON OVER ACCESSION OVERTIME DESCRIPTION JOB TARGET OVERTIME PERSON
START FINISH ACCESSION TARGET ACCESSION WORK DAY DATE IN OUT COUNT
(n) (s) (f) (a) (j) t=(f-s) a1=(a-s) a2=(f-s) b=(bup+t-a+a2) (c ) (d) (i) (o) c1=(o-i) (o1) (t1) (p)
(Date) (Date) (Date) (Description) ( Day) ( Day) ( Day) ( Day) (Description) (Date) (Time) (Time) (Hours) (Description) (Description) (Name)

TAHAP PEMASANGAN ENGINE TROUBLE SCRAP LINER #5


*Pasang air cooler 2 pcs
*Pasang piston 3 pcs
*pengikatan torsi bolt conrod
*Cleaning ulang carter oli
*Pasang cyl head 3 pcs
*Pengikatan torsi bolt cyl head
14 12/02/18 14/02/18 14/02/18 0 2 2 -1
*Pasang rocker case
*Pasang rocker arm
*pengikatan torsi bolt rocker arm
*pasang injector 15 pcs
*Pemasangan pipe intake before air cooler
*Pasang pipe water sisi R dan L
*Pasang caseing turbo sisi intake compress

14 14/02/18 14/02/18 14/02/18 ADDITIONAL WORK 0 0 0 -1

NOTE: SIGH IN 56 khalid


56 muhajir
35 anil
9 dodi
PERSON OVERTIME
ACKNOELEDGE APPROVED
18 ali
ACCUMULATION 12 17 4 -1 OVERTIME RANGE 56 jam 10 bastian tanjung
PERFORMANCE EFISIENSI 94.12% SITE MANAGER/ KORDA TECHNICAL MANAGER 9 zoelhelmi