Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 1 of 14
NCR PROCEDURE
CLASS : 1
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 2 of 14
REVISION REVISION
SHEET SHEET
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
1 X 31
2 X 32
3 X 33
4 X 34
5 X 35
6 X 36
7 X 37
8 X 38
9 X 39
10 X 40
11 X 41
12 X 42
13 X 43
14 X 44
15 45
16 46
17 47
18 48
19 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 3 of 14
COMMENT TABULATION
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 4 of 14
TABLE OF CONTENTS
1. INTRODUCTION............................................................................................................................. 5
1.1 Plant Description ................................................................................................................... 5
1.2 Project General Description and Purpose .......................................................................... 5
2. DOCUMENT SCOPE ...................................................................................................................... 7
3. REFERENCE DOCUMENT ............................................................................................................ 7
3.1 Company Specification......................................................................................................... 7
3.2 International Code and Standard ......................................................................................... 7
3.3 COMPANY Supplied Document ........................................................................................... 7
3.4 Project Document.................................................................................................................. 7
4. DEFINITIONS ................................................................................................................................. 8
5. DUTY AND RESPONSIBILITY....................................................................................................... 8
5.1 QA/QC Manager .................................................................................................................... 8
5.2 QC Inspector ......................................................................................................................... 9
5.3 Work Site Fabrication Manager ........................................................................................... 9
5.4 OFFSHORE CONSTRUCTION MANAGER .......................................................................... 9
5.5 CONSTRUCTION Superintendent ....................................................................................... 9
5.6 CONSTRUCTION Supervisor ............................................................................................... 9
6. PROCEDURE OF NON CONFORMITY ....................................................................................... 10
6.1 Identification of the non conforming product.................................................................. 10
6.2 Preparation of the non conformance report (NCR) ......................................................... 10
6.3 Implementation of Corrective Action ............................................................................... 10
6.4 Verification of Corrective Action / CLOSE OUT NCR ...................................................... 11
7. ATTACHMENT ............................................................................................................................. 11
Attachment 1 : Non Conformance Flow Chart ......................................................................... 12
Attachment 1 : Non Conformance Report ................................................................................ 13
Attachment 2 : Non Conformance Summary Report ............................................................... 14
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 5 of 14
1. INTRODUCTION
1.1 Plant Description
Bekapai is a COMPANY’s oil field located at offshore area in the Mahakam delta (East
Kalimantan) with water depths 30 – 40 meters and located about 40 kilometers south east of
the Senipah terminal.
COMPANY continues to develop of mature Bekapai offshore oil filed which was discovered in
1972 and start to production in 1974, with current facilities are:
Nine (9) satellite wellhead platforms & inter-platform pipelines;
Production (BP) & LQ platforms;
12” export pipeline to Senipah Terminal (BP1-SNP);
12” export pipeline to Peciko field SWP-K (BA-SWPK).
All effluents from satellite platforms are transported to BP1 and BA in order to have gas-oil-
water processing unit (separation, pumping, compression, and oily water treatment).
Production fluid from Bekapai field is routed to two (2) locations; multiphase production (mostly
gas and oil) is exported to Senipah Terminal (TPA) via 12” BP1-SNP pipeline and gas
production is exported to Peciko Field via 12” BA-SWPK Pipeline. The network of BEKAPAI
Platforms is shown in figure below.
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 6 of 14
BE & BH Platform
Project Purpose
Increase oil and gas reserves recovery by Reserve: 22.1 BcfGas & 2.8 MbblOil +
Condensate
Drilling of 5 new wells from existing BE & BH platforms, with :
- Modification of the existing BE & BH
- Reuse of existing 6" pipeline from BE to BG (3.6 km) & 6" pipeline from BH to BG (1.9 km)
- Modification and integration work at the BA, BG & BP platforms
-
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 7 of 14
2. DOCUMENT SCOPE
Purpose of this document is to describe the required Non conformance report to deliver the
Bekapai 3 Surface Facilities Modification and Dogleg Installation (EPCIC) project. This is
required in order to prove that the work is carried out properly accordingly to the applicable
Code / Specification.
3. REFERENCE DOCUMENT
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 8 of 14
4. DEFINITIONS
4.1 Non-conformance:
Any defect, flaw, damage, inferior quality of material equipment or deviation of work performed
out of specifications, drawings or any other contractual documents or
A deviation from a quality system element of the contractor or a departure from determined
criteria independent from contractual requirements, resolution of the nonconformity includes
application of existing procedures or
A deviation from work procedures or instructions which have been accepted by the COMPANY,
or a departure from determined criteria inherent to the contractual requirements, this
nonconformity might requires informing or obtaining the COMPANY 's advising/review for the
proposed corrective action
Solutions of any non-conformities such as rework, repair, scrap, use as is or rejected made by
Project Manager with advise from Construction Engineering based on Codes or Specification and
shall be approved by Company can give other solution
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 9 of 14
Inform to Construction Supervisor and Foreman about deviations, defects or non conformance
performed during monitoring or related to welding fabrication activities and give advice or input
to Welder, Foreman to minimize any problem on the fabrication.
5.2 QC Inspector
Initiates Non-Conformity Report (NCR) based on finding by CONTRACTOR or COMPANY's
Quality Notification that classified as requiring NCR follow up.
Follows up and ensures that the corrective action task has been effectively implemented or
performed.
Finally, close any non – conformities report.
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 10 of 14
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 11 of 14
7. ATTACHMENT
Attachment 1 : Non Conformance Flow Chart
Attachment 1 : Non Conformance Report
Attachment 2 : Non Conformance Summary Report
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 12 of 14
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 13 of 14
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
BEKAPAI - 3
Revision Index
Surface Facilities Modification and Dogleg Installation
(EPCIC) Rev Status
Contract No. 4500010835
NCR PROCEDURE 0.1 IFC
Project : NCR No :
Client : Location :
Reference Document
Reported by :
Document yang relevan
Position :
Sign :
Root Cause
:
Masalah Utama
Corrective Action
:
Tindakan Perbaikan
Corrective Action By :
Date : Signature :
Position :
Target Closed Out Date :
Verification :
Verification By :
Date : Signature :
Position :
Preventive Action :
Tindakan Pencegahan
Final Disposition :
Other
Closed out by :
Status Closed Out Date :
Nama :
Position : ON TIME
OVERDUE
Sign : Date :
AR-QC-NCR-08/19
Contract : 4500010835
Document Number
ID-BKP-SOME-2009-504005
NCR PROCEDURE
Revision: 0.1 Status : IFC
Document Type : REP System/Subsystem : N/A Discipline: QUA Date : 12 – 08 - 2021
Originator Document No : N/A Page 14 of 14
This document is the property of PT Pertamina Hulu Mahakam and shall not be disclosed to third parties or reproduced without permission
of the COMPANY. Electronic Filename: ID-BKP-SOME-2009-504005_rev0.1.pdf
Revision Index
BEKAPAI - 3 Surface Facilities Modification and Dogleg Installation (EPCIC)
Contract No. 4500010835 Rev Status
Client : Location :
TOTAL 0 0 0