Professional Documents
Culture Documents
EIA Consultant:
Contents
1 INTRODUCTION .......................................................................................................................................... 8
3.1 BACKGROUND AND SALIENT ENVIRONMENTAL FEATURES OF THE STUDY AREA .......................................35
3.1.1 Environmental Setting and Salient Environmental Features of the Project Area ....................35
3.1.2 Site Connectivity ................................................................................................................................38
3.1.1.1 ARCHAEOLOGICAL PROTECTED AREAS ..............................................................................................38
3.1.3 Existing Sources of Pollution ...........................................................................................................38
3.2 PHYSICAL ENVIRONMENT..............................................................................................................................43
List of Tables
List of Figures
Figure 2.1: Project Location TOPO Map .....................................................................................15
Figure 2.2: Project Location on Google Image...........................................................................16
Figure 2.3: Plant Boundary of Proposed plant ...........................................................................17
Figure 2.4: Key Plan of Project Site ...........................................................................................20
Figure 2.5: Proposed Plant Lay Out Along with Existing Facilities ..............................................22
Figure 2.6: Process Flow Chart ..................................................................................................28
Figure 2.7: Process Description of Project .................................................................................29
Figure 2.8: Design of Mounded Storage Bullet ..........................................................................29
Figure 3.1: Environmental setting of the 10 Km radius of the plant site ....................................37
Figure 3.2: Google view of Gidha Industrial Area (BIADA) viewing project site and nearby
industries ...........................................................................................................................39
List of Annexure
1 INTRODUCTION
This chapter provides background information of the project, LPG market scenario in the
target region, location of the proposed project, the scope of EIA study as per approved
terms of reference from Expert Appraisal Committee (Industry), Ministry of Environment and
Forests,, methodology adopted for EIA study and structure of the report.
Liquefied Petroleum Gas (LPG) is an essential commodity and the HPCL’s LPG Bottling
Plant at Arrah is responsible for meeting the needs of consumers based in the district of
Bhojpur and surrounding districts. The Bulk/packed LPG needs of Commercial and
Industrial establishment of this region is also catered by the Plant. Presently, the bottling
requirement of the Plant is around 300 MT per day as dictated by the Market Demand
and the storage capacity is 1000 MT providing only 2.5 days coverage. Any disruption in
bulk supplies from the existing supply sources is bound to affect the bottling and will
create backlog in the market. This issue will be addressed adequately by the proposed
mounded storage facility of 1500 MT storage capacity.
terms of any eventuality is only 2.5 days and this will further shrink with the ever
increasing market demand for this essential commodity.
To have adequate coverage to take care of any supply issues and ensure nil backlog in
the market at all times, it has been envisaged to install 3X500 MT (1500 MT) capacity
LPG Mounded storage facility. The Mounded storage method is the latest technology
available for the storage of bulk LPG, which is the safest mode and eliminates the
hazards associated with the traditional above ground storage bullets.
From the point of view of having adequate supplies of LPG in the market and for making
storage operations safer and eliminating all the environmental aspects, it is proposed to
undertake the project inside the existing premises as cited above.
Time frame and the type of impacts will be different for these phases of the project.
In this section, Environmental setting of the existing plant and details of proposed
facilities will be defined. The description also gives details of effluents
(gaseous/liquid/solid/noise) generation sources. Coverage on environmental setting of the
existing plant in terms of site details, project description, products, its storage, existing
pollution control devices/measures, emission summary, hazardous waste / chemicals
management, etc. will be described.
IDENTIFICATION OF IMPACTS
In order to identify the impacts comprehensively, all the activities associated with the
proposed project during the construction as well as operational phase are identified and
listed. The environmental impacts associated with the proposed project on various
environmental components such as air, water, noise, soil, flora, fauna, land,
socioeconomic, etc. has been identified using Impact Identification Matrix.
BASELINE DATA COLLECTION
Once the affected environmental parameters are identified, various environmental
parameters of concern are identified to establish its baseline quality. M/s Kamal Enviro
Private Limited, Gurgaon, Haryana (A NABL recognized Laboratory) was entrusted for
carrying out environmental baseline data collection during October 2016–December
2016. Data thus collected has been utilized here to establish baseline quality of various
environmental parameters.
ENVIRONMENTAL IMPACT PREDICTION & EVALUATION
In this part of the report, the sources of emissions (Gaseous, Liquid, Solid, Noise) due to
the proposed activities will be identified and based on their emission loads their impacts
are to be predicted. Such predictions are then superimposed on baseline quality
(wherever there is an additional impact) and quantitative/qualitative assessments have
been made for the impacts and synergistic impact is evaluated using the matrix method.
The resultant matrix attempts to give an objective assessment to identify the mitigation
measures needed for abatement of various impacts.
In order to mitigate or minimize the negative impacts (if any) of the proposed project, an
effective EMP is delineated. Therefore, in the final part of the report, the planning and
implementation of various pollution abatement strategies including the proposed
monitoring/surveillance network has been described. Detailed Environment Management
Plan (EMP) with specific reference to details of air pollution control system, water &
wastewater management, monitoring frequency, responsibility and time bound
implementation plan for mitigation measure is formulated.
Chapter-1: Introduction
This chapter provides background information of the proposed refinery LPG Handling
facility, scope, frame work & methodology of the study.
This chapter presents the details of the proposed project in terms of location, project
configuration of existing and proposed, utilities & offsite, description of the resources
required and emissions, solid waste and wastewater anticipated to be generated.
This chapter describes the existing baseline status of environment components collected
in a pre-defined study area based on primary and secondary data collection.
This chapter describes the potential impacts of the proposed project and evaluates their
significance based on parameters such mathematical models were used to quantify the
intensity and spatial extension of the impacts. Impact avoidance and mitigation measures
are delineated.
This chapter indicates the justification for selection of project sites within existing LPG
bottling plant.
This chapter describes the details of the monitoring schedule to be implemented for
checking the effectiveness of mitigation measures. It covers the parameters and its,
frequency.
This chapter assesses the potential risks involved in the construction and operation of
proposed facilities from this project and also provides broad guidelines for updating
existing Disaster Management Plan (DMP) of proposed plant.
This chapter presents the details of direct and indirect benefits due to proposed project.
This chapter describes the existing environmental management system, existing CSR,
impact analysis & mitigation measures for various components of environment. It also
includes organizational structure and resources planned for implementing the mitigation
measures and monitoring schedule.
This chapter contains the details of various functional areas in which the consultant is
expertise as per Quality Council of India (QCI) to conduct Environment Impact
Assessment (EIA) studies as per the MoEFCC Guidelines.
2 PROJECT DESCRIPTION
This chapter deals with the details of the proposed additional mounded storage for LPG Bottling
plant; Location Consideration, Technology Description, Raw material Requirement and its source,
Process flow diagram, Environmental Pollution Control measures etc.
2.1.1 Connectivity
Nearest railway station : Kulhariya Railway Station- 3 KM (S); Arrah Railway Junction, 8.93
km (SW)
Nearest highway: NH-30 (250 m)
Nearest Airport: Jay Prakash International Airport, Patna 45 km (E)
Two LPG vapor compressors each coupled to a flame-proof motor have been installed for
loading/unloading of LPG vapor, based differential pressure mechanism. The maximum
discharge pressure of these compressors is 11.5 kg/cm2g.
Proposed Project is for installation of three Mounded LPG Storage vessel (3X500 MT)-
Proposed in phase II
Proposed project is housed at existing HPCL facility in Bhojpur, Bihar for Installation of 3x500
MT (1500 MT) capacity LPG Mounded Storage Vessel (MSV) facility. Details of Existing and
proposed facility is given as below:.
Figure 2.5: Proposed Plant Lay Out Along with Existing Facilities
storage tank and the vapours from the compressor are discharged into the tank truck
above the liquid.
For proper unloading of tank truck pressure should be maintained 2 kg/cm² above the
storage tank pressure depending upon the distance between the tank truck and the
storage tank, the design of the piping system and the height of the storage tank
compared to tank truck. If the pressure differential is too low, unloading will be slow. If
the differential is too high, the excess flow check valve in the tank truck liquid pipeline
will close and unloading would stop.
Care must be exercised to see that the pressure created within the tank truck does not
approach or exceed the setting of the safety relief valve within.
After all the liquid LPG has been decanted from the tank truck, the vapour remaining in
the TT shall be recovered by operating 4 way valve and thereby connecting the suction
of the compressor to the vapour connection of the tank truck and the discharge of the
compressor is connected to the receiving storage tank.
These vapours should be discharged below the liquid level in the receiving tank to
hasten the liquefaction and to prevent the development of excessive pressure. When the
tank truck pressure has been reduced to 1.5 kg/cm² stop the compressor and close all
valves.
Evacuate liquid and vapour from unloading lines by venting into vent lines. When it is
ensured that shut-off valves are closed tight, disconnect unloading arms /hoses. After
disconnection, plug the unloading arm / hoses.
The master switch shall be put off immediately after parking the truck in position. No
electrical switch on the truck shall be turned “on” or “off” during the transfer
operation.
No repairs shall be made on the truck while it is in the loading area.
New tank trucks vessels or vessels received after repair shall be purged before
loading.
It is recommended that the receiving vessel having a pressure of less than 1
Kg/sqcm should not be filled. Such vessel should be checked for oxygen
content/explosive mixture and purged, if necessary.
Venting and purging of LPG during transfer operation normally should not be carried
out in open atmosphere. It should be piped to a suitable flare system. Where such
facility does not exist, vent pipes shall be provided to carry the vented product to a
safe distance and released at a height not less than three meters above the highest
point of any building, shed or structure within 15m radius. Snuffing steam facility may
be provided for the vent line.
Filling/transfer operations should be stopped immediately in the event of –
Uncontrolled leakage occurring
A fire occurring in the vicinity
Lightning and thunder storm
35Kg/47.5 Kg are also filled up thru 4 nos Static Filling Scale. Filled cylinders are
delivered only to the authorized LPG distributors. Drivers of the trucks carrying LPG are
having valid license and are having training in safety & fire fighting procedures. The total
storage facility will be protected with following Fire Protection System.
Mounded vessel is storage vessel sited above ground and completely covered by a
mound of earth or similar inert material except for nozzles, manhole covers, inspection
covers fitted on vessel (s). The mechanical design of storage vessel shall be based on
following considers.
ASME SEC VIII or PD -5500 or equivalent duly approved by chief Controller of
Explosives, A single code shall be adopted for design, fabrication, inspection and
testing.
The specific consideration shall give to
a) Internal vapour and hydraulic pressure
b) External loadings on the vessel
c) Internal vacuum
Material: Material of construction shall conform to above design code. ASTM A 516 Gr.
70 (IT) or SA 537 C II(IT) or PD: 5500 or equv. Material shall be used.
Radiography: Full
Stress Relieving: 100% irrespective of thickness
Earthquake pressure: as per IS: 1893
The recommended design pressure and temperature shall be treated as minimum
requirement and other design consideration and statutory requirements shall also be
considered.
Construction Methodology
Mounded vessels shall be placed on a firm foundation and installed so as to prevent
movement or floatation. The sub-soil water, rain water or any other surface water should
not be allowed to percolate into the mound. The foundation should be constructed such
that in the longitudinal direction of a vessel slope of at least 1:200 is maintained to
facilitate draining of the vessel.
Site conditions and soil mechanics shall be deciding factors for selection of the type of
foundation in a given situation. The preferred type of foundation is a continuous sand
bed, supporting the vessel over its full length. The foundation shall have sufficient load
bearing capacity and all the factors affecting the foundation shall be considered while
designing the same.
The sand bed beneath the vessel shall be adequate elevation not less than
760millimeter (mm) to facilitate drainage from liquid outlet pipe by gravity. Proper
provision shall be made for encountering the consequences of the settlement of the
vessel. The surrounding of the bottom connection should be filled with such material that
can absorb such settlement.
The mound shall protect the vessel from the effects of thermal radiation and shall be
sufficiently robust to remain in place in the event of Jet flame impingement.
Mound shall be of earth, sand or other non-combustible, non-corrosive material such as
Vermiculate or Perlite and shall provide at least 700mm minimum thickness of cover for
the vessel.
The mound surface shall be protected against erosion by rain or wind by providing a
suitable cover or prefabricated stone, open concrete tiles etc
Water ingress into the mound shall be minimized by providing impervious layer or
suitable material. Proper drainage and slope on top of the mound shall also be provided.
Longitudinal axis of vessels in a mound shall be parallel to each other with ends in line.
The valve and appurtenances of mounded vessels shall be accessible for operation or
repair, without disturbing the mound.
Provision shall be made to monitor the settlement of the mound/vessels by providing
permanent reference points. A minimum of three reference points shall be provided to
ascertain uniform/differential settlement and also identify possible vessel bending (one
each near the vessel ends and one in the middle)
Provision shall be made for inserting portable CuSO4 reference electrode on top of the
mound for measurement of PSP at 12’O clock position of the vessel. This shall be
protected to prevent water ingress in the mound.
Production Process
Questions
Storage Vessels-
Bullets-2X500=1000 MT
LPG Pump &
Compressor
8 Bay TT Gantry
Filling Equipment
24 Head carousel-2 nos.
Empty
cylinder
LPG Liquid QC
Equipment
LPG vapor Filled cylinder
5 dispatch to markets
SAFETY PHILOSOPHY
Codes and standards which are generally followed for LPG installations are as follows:
HPCL has an ETP of 4KLD capacity. Main treatment is removal of oily material. Treated
effluent is utilized in green belt development.
The other sources of waste water are from the existing canteen facilities and office
building whose quantity remains unaffected due to proposed project. The waste water is
being diverted in soak pits and some quantity is being reused for gardening and other
activities.
Employment Generation (Direct and Indirect) due to project Common User LPG plant a
project of HPCL will generate indirect employment for local people. It will also generate
ancillary business to some extent for the local population.
Note –The manpower requirement is given in combined way for operation in two shifts,
general shift and idle night shift.
This Chapter describes the baseline environmental conditions around the project site for various environmental
attributes, viz., and physical, biological and socio-economic, within the 10 km radial zone, which is termed as the
study area. Topography, soil, water, meteorology, air, noise, and land constitute the physical environment,
whereas flora and fauna constitute the biological environment. Demographic details and occupational pattern in
the study area constitute socio-economic environment. Baseline environmental conditions are based on the field
studies carried out during the study period October’ 2016 to December 2016 (Post Monsoon) at and around the
proposed site and through secondary data collected from published sources.
The Salient Environmental Features of plant site within 500m, 2 Km and 10 Km radius is
summarized at Table 3.1.
Environmental setting of the 10 Km radius of the plant site is presented at Figure 3.1. Site
photographs are presented in Figure 3.2.
Figure 3.2: Google view of Gidha Industrial Area (BIADA) viewing project site and nearby industries
The study period and methodology for primary data collection is followed as per the
CPCB guidelines in line with TOR prescribed by SEAC, Bihar. Summary of monitoring
plan with sampling testing methodology followed is summarized in Table 3.2.
Environment monitoring location map given in Figure 3.3.
1
CGWA Bhojpur
2
The satellite Imagery of Indian Remote Sensing Satellite (IRS- ID, sensor P6, LISS III) of 24 m resolution was used. The Swath of
the imagery is 141 Km x 141 Km. Band used are 4, 3, 2 and 5. LANDSAT imagery of 30 meter resolution and 185 x 185 km swath is
also used for the comparative and overall analysis of the area. LISS III imagery and LANDSAT 4-5 TM imagery were used for the
complete coverage of the study area
under dry river bed, 2.52 % of the land is open shrub land, 1.76 % is under vegetation and
rest in other uses. (Refer Figure 3.5 and Table 3.3).
Figure 3.4: Graph Showing Land Use of the Study Area (10 km Radius)
Project site
Project site
Physical characteristics of soil greatly influence its use and behavior towards plant
growth.
Soil Texture
The mineral components of soil are sand, silt and clay, and their relative proportions
determine a soil's texture. Properties that are influenced by soil texture, include
porosity, permeability, infiltration, shrink-swell, water-holding capacity, and susceptibility
to erosion. The soil in which neither sand & silt nor clay predominates is called "loam".
The mineral constituents of a loam soil might be 40% sand, 40% silt and the balance 20%
clay by weight. Soil texture affects soil behavior, in particular its retention capacity for
nutrients and water. Texturally the soils of study area are observed as Sandy Loam and
Sandy Clay Soils.
Bulk Density
Bulk density of soil relates to the combined volumes of the solids and pore spaces. Soil
with a high pore space with loose solid particles will have lower bulk density than those
that are more compact and have less pore space. This is directly related to the movement
of air and water through soil thus affecting the productivity. The bulk density of the soils
was found in the range of 1.35 to 1.49-gm/cm³.
Water Holding Capacity
Water-holding capacity is usually defined as the amount of water that soil can hold. Soil
that have fine particles are able to hold more water than coarse soils while rock
fragments cannot hold any water and contribute negatively to soil water-holding capacity.
The type and composition of soil are the controlling factors in this case. Water Holding
Capacity of study area soils was observed as 28.2 to 32.4%.
Permeability
Permeability is the measure of the ability of a soil to transmit water under a unit hydraulic
gradient. For a particular soil, it represents its average water transmitting properties,
which depends mainly on the number and the diameter of the pores present. The results
show Permeability values were found to vary from 0.19 to 2.02-cm/hr under Sandy Loam
and Sandy Clay textured soil in the study area.
Chemical Characteristics of Soil
Soil Reaction Classes and Critical Limits for Macro & Micro Nutrients in Soil
According to Soil Survey Manual (IARI, 1970), the soils are grouped under different soil
reaction classes viz; extremely acidic (pH<4.5), very strongly acidic (pH 4.5-5.0 ), strongly
acidic (pH 5.1-5.5), moderately acidic (pH 5.6-6.0), slightly acidic (pH 6.1-6.5), neutral
(pH 6.6-7.3), slightly alkaline (pH 7.4-7.8), moderately alkaline (pH 7.9-8.4), strongly
alkaline (pH 8.5-9.0).The soils are rated as low (below 0.50 %), medium (0.50-0.75 %)
and high (above 0.75 %) in case of organic carbon, low (<280-kg/ha), medium (280 to
560-kg/ha) and high (>560-kg/ha) in case of available Nitrogen, low (<10-kg/ha), medium
(10 to 25-kg/ha) and high (>25-kg/ha) for available Phosphorus, low (<108-kg/ha),
medium (108 to 280-kg/ha) and high (>280-kg/ha) for available Potassium and low (<10-
mg/kg), medium (10-20-mg/kg) and high (>20-mg/kg) for available Sulphur (Singh et.al.
2004, Mehta et. al.1988). Critical limits of Fe, Mn, Zn, Cu and B, which separate deficient
from non-deficient soils followed in India, are 4.5, 2.0, 0.5, 0.2 and 0.5-mg/kg
respectively. (Follet & Lindsay-1970 and Berger & Truog-1940)
Soil Reaction (pH)
Soil pH is an important soil property, which affects the availability of several plant
nutrients. It is a measure of acidity and alkalinity and reflects the status of base
saturation. The soil pH ranges from 7.32 to 7.55, thereby indicating the soils are neutral
to slightly alkaline.
Organic Carbon
The effect of soil organic matter on soil properties is well recognized. Soil organic matter
plays a vital role in supplying plant nutrients, cation exchange capacity, improving soil
aggregation and hence water retention and soil biological activity. The Organic Carbon
content of soil varied from 0.49 to 0.68 %( 0.85 to 1.17% as Organic Matter) thereby
implying that soils are medium in organic content.
Macronutrients
Nutrients like nitrogen (N), phosphorus (P) and potassium (K) are considered as primary
nutrients and sulphur (S) as secondary nutrient. These nutrients help in proper growth,
development and yield differentiation of plants and are generally required by plants in
large quantity.
Available Nitrogen
Nitrogen is an integral component of many compounds including chlorophyll and enzyme
essential for plant growth. It is an essential constituent for amino acids which is building
blocks for plant tissue, cell nuclei and protoplasm. It encourages aboveground vegetative
growth and deep green color to leaves. Deficiency of nitrogen decreases rate and extent
of protein synthesis and results into stunted growth and develop Chlorosis. Available
nitrogen content in the surface soils ranges between 235.2 & 278.4-kg/ha, thereby
indicating that soils are low in available nitrogen content.
Available Phosphorus
Phosphorus is an important component of adenosine di-phosphate (ADP) and adenosine
tri-phosphate (ATP), which involves in energy transformation in plant. It is essential
component of deoxyribonucleic acid (DNA), the seat of genetic inheritance in plant and
animal. Phosphorous take part in important functions like photosynthesis, nitrogen
fixation, crop maturation, root development, strengthening straw in cereal crops etc. The
availability of phosphorous is restricted under acidic and alkaline soil reaction mainly due
to P-fixation. In acidic condition it gets fixed with aluminum and iron and in alkaline
condition with calcium. Available phosphorus content ranges between 24.8 & 32.2-kg/ha,
thereby indicating that soils are having medium to high available phosphorus.
Available Potassium
Potassium is an activator of various enzymes responsible for plant processes like energy
metabolism, starch synthesis, nitrate reduction and sugar degradation. It is extremely
mobile in plant and help to regulate opening and closing of stomata in the leaves and
uptake of water by root cells. It is important in grain formation and tuber development and
encourages crop resistance for certain fungal and bacterial diseases. Available
potassium content in these soils ranges between 256.4 & 295.2-kg/ha, thereby is
indicating that the soils are medium to high in potassium content.
Micronutrients
Proper understanding of micronutrients availability in soils and extent of their deficiencies
is the pre-requisite for efficient management of micronutrient fertilizer to sustain crop
productivity. Therefore, it is essential to know the micronutrients status of soil before
introducing any type of land use.
Available Manganese
Manganese is essential in photosynthesis and nitrogen transformations in plants. It
activates decarboxylase, dehydrogenize, and oxides enzymes. The available manganese
content in surface soils was recorded as 13.6 to 18.2-mg/kg, as the critical limit of
available manganese is 2.0-mg/kg.
Available Zinc
Zinc plays role in protein synthesis, reproductive process of certain plants and in the
formation of starch and some growth hormones. It promotes seed maturation and
production. The available zinc in surface soils of the study area ranges from 12.2 to 21.0-
mg/kg. As per the critical limit of available zinc (0.5-mg/kg), most of the study area soils
are sufficient in available zinc in the vicinity of the project.
Available Boron
Boron increases solubility and mobility of calcium in the plant and it act as regulator of
K/Ca ratio in the plant. It is required for development of new meristematic tissue and also
necessary for proper pollination, fruit and seed setting and translocation of sugar, starch
and phosphorous etc. It has role in synthesis of amino acid and protein and regulates
carbohydrate metabolism. The available boron content in the soils ranges from <0.1 to
0.52-mg/kg. The critical limit for deficiency of the available boron is 0.5-mg/ kg.
As per the above mentioned detailed soil descriptions indicate medium fertility status or
agricultural potential of soil.
3.5 Meteorological Data
The meteorological parameters play a vital role in transport and dispersion of pollutants in
the atmosphere. Historical meteorological data were obtained from climatological tables
pertaining to Patna (as the nearest representative IMD station) for the period 1974-1990
and is summarised in Table 3.6.
time. The summary of the met data is summarized in Table 3.7. Wind rose diagram of site
is shown in Figure 3.7.
Table 3.9: Ambient Air Quality Monitoring Results for PM2.5 and PM10 (24-hour
average)
Location PM2.5 (g/m³) PM10 (g/m³)
Code Location
Min Max Mean 98% tile Min Max Mean 98% tile
AAQ-1 Project Site 27 58 42 56 68 128 98 126
AAQ-2 Gidha Industrial 32 75 51 74 75 168 119 167
Area
AAQ-3 Gidha Village 26 48 39 48 64 92 83 92
AAQ-4 Sakdi Village 20 39 32 39 53 87 76 87
AAQ-5 Kultharia 18 34 26 33 48 72 63 71
AAQ-6 Koilwar 23 46 34 45 56 85 74 84
AAQ-7 Birampur Village 22 34 27 34 50 76 64 76
AAQ-8 Purdilganj 20 42 32 42 56 80 70 80
Village
60
50
40
30
20
10
0
Kultharia
Gidha Industrial Area
Project Site
Koilwar
Stand. Limits
Sakdi Village
Birampur Village
Purdilganj Village
Gidha Village
PM 2.5 (µg/m³) Max PM 2.5 (µg/m³) Min PM 2.5 (µg/m³) Mean Standards 24 Hours Avg.
PM10 (µg/m³): The highest PM10 levels were found at Gidha Industrial area (168 µg/m³)
and lowest PM10 level at Kultharia (48 µg/m³) were observed at purdilganj While the
mean conc. of all location ranges between 63-119 µg/m³. The PM10 level in all the
monitoring locations is within permissible limit i.e. NAAQMS level 100 µg/m³
140
120
100
80
60
40
20
0
Kultharia
Koilwar
Stand. Limits
Project Site
Gidha Industrial
Birampur Village
Sakdi Village
Purdilganj Village
Gidha Village
Area
SO2 (µg/m³): The highest SO2 level were found at two locations Project site, Gidha
industrial area (9.6 µg/m³) and lowest SO2 level were observed also at four locations (4
µg/m³) while the mean conc. of all location ranges between 6.1-7.6 µg/m³. The SO2 level
in all the monitoring locations is within permissible limit i.e. NAAQMS level 80 µg/m³.
70
60
50
40
30
20
10
0
Kultharia
Koilwar
Purdilganj Village
Gidha Village
Sakdi Village
Gidha Industrial Area
Stand. Limits
Project Site
Birampur Village
SO2 (µg/m³) Max SO2 (µg/m³) Min SO2 (µg/m³) Mean Standards 24 Hours Avg.
NOx (µg/m³): The highest NOx level were found at Gidha industrial area (21.6 µg/m³) and
lowest NOx level were observed at Sakdi village (9.0 µg/m³) while the mean conc. of all
location ranges between 13.6 – 17.2 µg/m³. The NOx level in all monitoring location are
under permissible limit i.e. NAAQMS level 80 µg/m³
90
80
Concentration in µg/m3
70
60
50
40
30
20
10
0
Kultharia
Koilwar
Stand. Limits
Project Site
Gidha Industrial
Birampur Village
Purdilganj Village
Sakdi Village
Gidha Village
Area
NOx (µg/m³) Max NOx (µg/m³) Min NOx (µg/m³) Mean Standards 24 Hours Avg.
CO is below detection limit at all the locations except around Gidha industrial area and
varies between 0.14 to 0.40 µg/m³ HC. NMHC, VOC and HC- were found below detection
limit.
3.7 AMBIENT NOISE QUALITY
The noise level in study area was measured at eight locations. As mentioned earlier a
sound level meter has been used to measure noise levels as instant values which are
integrated over a given period to give Leq values as a weighted average. At each
location, readings were taken at uniform interval of. 5 seconds over a period of 10
minutes per hour for twenty-four hours’ period, with further divisions of day and night
noise as per CPCB guidelines (between 6.00 A.M to 10.00 P.M and between 10.01 P.M to
5.59 A.M representing day and night period noise levels).
3.7.1 Noise Levels in the Study Area
Ambient noise measurement was taken at 8 locations within 10 km area of the project
site. Noise monitoring location and noise results for day time and night time is presented
in Table 3.10and Table 3.11 respectively.
mg/l 3111B
15 Calcium as 54 48 84 88 APHA- 75/200
Ca mg/l 3500B
16 Magnesium 11.8 9.7 8.7 9.7 APHA- 30/100
as Mg mg/l 3500B
17 Cadmium as <0.01 <0.01 <0.01 <0.01 APHA- 0.003/No
Cd mg/l 3111B relaxation
18 Copper as <0.01 <0.01 <0.01 <0.01 APHA- 0.05/1.5
Cu mg/l 3111B
19 Nickel as Ni <0.01 <0.01 <0.01 <0.01 APHA- 0.02/No
mg/l 3111B relaxation
20 Lead as Pb 0.023 0.018 0.020 0.039 APHA- 0.01/No
mg/l 3111B relaxation
21 Mercury as <0.001 <0.001 <0.001 <0.001 APHA- 0.001/0.001
Hg mg/l 3112
22 Chromium <0.05 <0.05 <0.05 <0.05 APHA- 0.5/No
(Total as Cr) 3111B relaxation
mg/l
23 Arsenic as <0.025 0.04 <0.025 <0.025 APHA- 0.01/0.05
As mg/l 3114
24 Phenolic <0.001 <0.001 <0.001 <0.001 Part 43 0.001/0.002
compound
mg/l
25 Total Nil Nil Nil Nil APHA- Nil
Coliform 9230B
MPN/100ml
Source: Kamal Enviro & Food Lab Pvt. Ltd., Gurgaon-Haryana
Samples for bacteriological analyses were collected in sterilized bottles. The water
samples were examined for physico-chemical parameters and bacteriological
parameters. Samples were analyzed for various parameters using the CPCB’s DBU
Criteria. The name of sampling locations is presented in Table 3.16. The analysis results
of surface water are presented in Table 3.16.
3500B
16 Cadmium as Cd mg/l <0.01 <0.01 <0.01 <0.01 APHA-
3111B
17 Copper as Cu mg/l <0.01 <0.01 <0.01 <0.01 APHA-
3111B
18 Nickel as Ni mg/l <0.01 <0.01 <0.01 <0.01 APHA-
3111B
19 Lead as Pb mg/l <0.01 <0.01 <0.01 <0.01 APHA-
3111B
20 Mercury as Hg mg/l <0.001 <0.001 <0.001 <0.001 APHA-3112
21 Chromium (Total as Cr) <0.05 <0.05 <0.05 <0.05 APHA-
mg/l 3111B
22 Arsenic as As mg/l <0.025 <0.025 <0.025 <0.025 APHA-3114
23 Oil & Grease mg/l 2.7 2.8 4.2 4.8 Part -39
24 Chemical Oxygen Demand 14 16 22 20 Part -58
as COD mg/l
25 Bio- Chemical Oxygen 3.6 4.1 5.7 5.4 Part -44
Demand as BOD (for 3
Days 27 ˚C) mg/l
26 Dissolved Oxygen mg/l 4.8 4.7 4.0 3.8 APHA
27 Total Coliform MPN/100ml 3210 3400 4230 4120 APHA-
9230B
Source: Kamal Enviro & Food Lab Pvt. Ltd., Gurgaon-Haryana
Deciduous, Littoral and Swamp Forest, and Tropical Dry Deciduous Forests. The forests
are dominated by Tropical Dry Deciduous Forests which accents for 84.66% followed by
Tropical Moist Deciduous Forests (8.81) and Tropical Wet Evergreen Forests (1.22).
Littoral and Swamp Forests accounts to 0.24%. Tree cover and plantation occupying
7.06% of the forest cover.
The proposed project area in Bhojpur districts has deciduous type of forest. The project
area does not encounter with any kind of recorded forests such as Reserve Forest,
Protected forest or un- classed Forest (declared Protected under “ The Indian Forest Act,
1927”) and “Forest (Conservation) Act, 1980 with Amendments Made in 1988”.
3.9.1 Study Area and Sampling Locations
The study area has been marked as 10 km radial distance from the plant boundary. The
study area around the project site mainly comprises of terrestrial ecosystem (agricultural
land, wasteland and barren land) and aquatic ecosystem (Rivers, Canals, etc.).
Topography of the study area is generally plain areas. Study area is surrounded by rain
fed double crop agricultural land.
3.9.2 Methodology adopted for the Survey
To achieve the above objectives a detailed study of the area was undertaken in 10 km
radius area from proposed plant boundary as centre. The different methods adopted were
as follows:
Generation of primary data by undertaking systematic ecological studies in the area; and
Discussion with local people so as to elicit information about local plants, animals and
their uses.
cumini, Tamarindus indica, Phoenix sylvestris etc. The shrubby vegetation is mainly
comprises of Anona squamosa, Prosopis julifera, Zyziphus species , Calotropis
procera.,Lantana camara, Lawsonia inermis, Narium indicum etc. The dominant herbs in
ground vegetation are Achyranthes aspera, Argemone mexicana, Datura metal, Cassia
tora, Parthenium hysterophorus, Sida rhombifolia, Solanum nigram, Ipomea cornia etc.
list of the flora observed /reported during the field survey is presented in Table 3.19.
Terrestial Fauna: To study the diversity of fauna, information is collected form secondary
sources. Secondary data was collected from the forest department and from previous
studies done in the area to establish baseline study for distribution of wild animals in the
study area. No wild mammals sighted during the field surveys but local people and
secondary data reported some of the animals visiting the project area.
Existing and proposed traffic due to the project: The details of the existing load and
proposed load due to the project is describes in Table 3.22.
The plant is located almost 250 m from the National Highway – Arrah-Danapur (NH-30).
The plant site is well connected to the NH-30 by 9 m wide road. Total inward and outward
material movement shall be done through trucks. As estimated above total inward and
outward truck movement will be 344 (172x2) which is equal to 1032 PCU/day. So about
1032 PCU/day traffic shall be added in the existing traffic load due to the proposed
project. Which mean hourly traffic will be around 43 PCU/hr. The NH-30 is multilane (2-
lane) of very good design (1.5 m hard shoulders) and its capacity is 20000 PCU per day
as per IRC specification (IRC64-1990). Considering total material transport from HPCL
plant the existing highway is adequate to bear the additional PCU without any issue.
3.11 Demographic and Socio-Economic Features
Demography is one of the important indicators of environmental health of an area. It
includes population, sex ratio, number of households, literacy & literacy rate, population
density, etc. In order to assess the Demographic & Socio-economic features of the area,
Census data of 2011, for the concerned District Bhojpur, in Bihar State was compiled and
placed in the form of tabulation and graphical representation.
As per the census records 2011, Bhojpur district of Bihar has a population of 2,720,155
persons. The district has a population density of 1,136 inhabitants per square kilometer.
Its population growth rate over the decade of 2001-11 was recorded as 21.27%. Bhojpur
district has a sex ratio of 900 females for every 1000 males and a literacy rate of 72.79%.
Child (0-6 year’s age) sex ratio was also observed as 918 female children for every 1000
male children in the district. Languages include Bhojpuri, a tongue in the Bihari language
group with almost 200 000 000 speakers, according to the study of 'Times of India Daily'
written in both the Devanagari and Kaithi scripts. Hindi, Urdu. As per the census records
2011, mainly about 92.3% Hindu, 7.25% Muslims and 0.45% other (Christian and Sikh)
religions were recorded in the district. (Source-
https://en.wikipedia.org/wiki/Bhojpur_district,_Bihar).
Population Distribution in the Study Area
As per the census records 2011, the total population of the study area was recorded as
555971 persons of one hundred fourteen (114) revenue villages including two (02) towns
named Arrah (M Corp.) and Koilwar (NP) respectively of Bhojpur District. All the revenue
villages/towns are under Shahpur, Arrah, Barhara, Koilwar & Udwant Nagar tehsils
respectively of Bhojpur District of Bihar State. Total number of ‘Households’ was recorded
as 85114 in the 10-km radius study area. Male-female wise total population was recorded
as 294317 males and 261654 females respectively. About twelve (12) villages are
recorded as uninhabited villages in the 10km radius study area
House- Population SC ST
Village holds P M F M F M F Tehsil
Jamira 2058 13891 7345 6546 1167 1071 1 1
Pipra 385 2392 1265 1127 468 415 1 1
Piraunta 609 3887 2135 1752 419 320 0 0
Chatarsainpur 433 3049 1645 1404 196 157 0 0
Bheldumra 202 1424 751 673 196 190 0 0
Mohanpur 110 861 440 421 125 107 0 0
Ramsara Chandar Uninhabited village
Chur
Santpur Uninhabited village
Alimullah Chak Uninhabited village
Singhi Tola 128 813 452 361 241 180 0 0
Arrah 39274 261430 138804 122626 13418 12056 499 457
(M Corp.)
Sarangpur 438 2805 1464 1341 136 133 0 0
Makhdumpur 453 2988 1575 1413 281 257 0 0
Dumra
Saidpur 220 1479 782 697 63 58 0 0
Balua 308 2457 1294 1163 5 4 105 98
Mirza Beg 68 483 242 241 7 11 7 6
Mathaulia 232 1521 809 712 160 149 0 0
Garaiyan 1 2 2 NA
Basantpur 540 3323 1788 1535 385 344 0 0
Rokaiya Chak Uninhabited village
Mahkampur Bara 307 3023 1629 1394 380 319 207 182
Jadopur 99 590 317 273 19 23 0 0
Agarpura 101 738 370 368 79 77 0 0
Babhangawan 382 2731 1463 1268 301 244 0 0
Chatar 387 3408 1818 1590 465 430 0 0
Rampur 270 1944 1051 893 178 158 0 0
Kazi Chak 224 1349 736 613 170 150 0 0
Matukpur 404 2724 1426 1298 144 127 0 0
Deorath 107 645 343 302 143 126 0 0
Ram Shahar 601 4337 2364 1973 399 297 1 0
Gangauli 20 101 56 45 9 7 0 0
Keshopur 171 1153 609 544 0 0 0 0
Semaria Pararia 876 5433 2792 2641 259 222 0 0
Bakhorapur 682 4903 2616 2287 461 382 0 0
Milki Mir Chhaka Uninhabited village
Lauhar 371 2503 1355 1148 317 281 0 0
Karja 356 2306 1221 1085 148 115 0 0
Turki 119 730 320 410 143 162 0 0
Pharna 589 3850 2013 1837 388 319 0 0
Gyanpur 386 2381 1299 1082 155 128 0 0
Milki 218 1748 956 792 164 150 0 0
Panditpur 136 877 466 411 118 114 0 0
Paiga 538 3456 1845 1611 458 413 12 12
Gunri 2169 13910 7393 6517 856 761 87 92
Amma Narbirpur 284 1945 1031 914 19 12 0 0
Kaem Nagar 1338 8554 4542 4012 1249 1110 1 1
House- Population SC ST
Village holds P M F M F M F Tehsil
Koilwar (NP) 2893 17725 9382 8343 1042 943 18 12
Kulharia 1157 7201 3781 3420 632 541 0 1
Sakaddi 1181 8294 4383 3911 628 551 0 0
Giddha 856 5634 3033 2601 1093 891 0 1
Chanda 505 2804 1527 1277 313 258 1 1
Sirari Chak Uninhabited village
Kazi Chak 278 1669 890 779 81 68 1 0
Chhitampur Uninhabited village
Sadasibpur Urf Uninhabited village
Sabdalpur
Sirpalpur 363 2140 1154 986 207 167 0 1
Mahui 69 378 198 180 19 13 0 0
Kishunpura 358 2165 1194 971 118 74 0 0
Golakpur 295 1778 936 842 100 94 0 0
Jamalpur 732 4876 2527 2349 503 454 1 1
Mana Chak 117 979 519 460 0 0 0 0
Pachaina 318 1971 1043 928 175 172 0 1
Jalpura 192 1071 595 476 17 18 0 0
Khesrahiya 249 1490 791 699 267 227 0 0
Mohaddi Chak 373 2472 1317 1155 226 212 0 1
Deoria 119 806 418 388 5 6 0 0
Babhnauli 75 464 236 228 0 0 0 0
Daulatpur 565 3568 1867 1701 27 17 0 0
Pachrukhia 344 2214 1189 1025 43 33 0 0
Kamalu Chak Uninhabited village
Rajapur 421 3043 1581 1462 42 53 0 0
Manikpur 597 3859 2021 1838 157 133 4 1
Dumaria 229 1398 710 688 158 146 0 0
Sirpalpur 182 1269 681 588 209 188 0 0
Bhopatpur 160 1001 504 497 246 238 0 1
Mohkampur 221 1429 759 670 121 98 1 1
Chandwa 256 1672 897 775 237 171 0 0
Mathurapur 288 2126 1146 980 51 37 0 0
Chandi 1054 5953 3092 2861 455 449 113 97
Guri 130 865 441 424 35 32 0 0
Kusihan 155 913 481 432 297 272 0 0
Khangaon 1784 10711 5617 5094 843 781 49 51
Bhadwar 1241 7807 4104 3703 575 513 10 9
Farhangpur 571 3119 1654 1465 434 378 0 2
Bahiyara 397 2250 1200 1050 244 193 0 0
Dhandiha 226 1278 663 615 31 32 0 0
Jogta 899 6378 3273 3105 263 251 0 0
Suraudha Uninhabited village
Purdilganj 176 1279 673 606 32 37 0 0
Haripur 477 2859 1494 1365 299 279 2 1
Mokhalsa 627 3108 1689 1419 509 426 0 0
Kiratpura 886 4999 2626 2373 696 592 117 94
Songhatta 499 2849 1513 1336 78 72 0 0
Mirapur Uninhabited village
House- Population SC ST
Village holds P M F M F M F Tehsil
Imadpur Uninhabited village
Gorhna 260 1488 757 731 152 150 6 9
Milki 167 1344 715 629 72 57 0 0
Diliya 122 836 446 390 0 0 0 0
Birampur 235 1370 696 674 160 168 0 0
Doghra 605 4108 2154 1954 600 550 101 80
Kauriya 300 2208 1152 1056 145 123 2 0
Dhanpura 245 1686 869 817 56 57 0 0
Madain 203 1264 589 675 62 70 0 0
Sundarpur 7 38 24 14 22 14 0 0
Ratanpur 179 943 499 444 221 195 0 0
Bhakura 463 2835 1450 1385 244 225 1 3
Lodipur 134 784 389 395 124 126 0 0
Total 85114 555971 294317 261654 39695 35254 1403 1268
Source-Census of India 2011
Sex Ratio
The ‘Sex Ratio’ of the study area is a numeric relationship between females and males of
the area and bears paramount importance in the present day scenario where the un-
ethnic pre-determination of sex and killing of female fetus during pregnancy is practiced
by unscrupulous medical practitioners against the rule of the law of the country. It is
evident that by contrast the practice of female foeticide is not prevalent in the study area.
As per the census records 2011, the entire study area is falling in Bhojpur district of Bihar.
The ‘Sex Ratio’ was observed as 900 females per 1000 males in the District. The same
was recorded as 889 females for every 1000 males in the study area. Child sex ratio (0-6
years); girls per 1000 boys in the District and study area was also observed as 918 & 902
respectively.
The village wise male-female population distribution for the entire study area is depicted
and shown by graphical representation in Figure 3.9.
Total Population
600000
500000
400000
300000
200000
100000
0
Total Population Male Population Female Population
Total Population
Total SC Population
80000
60000
40000
20000
0
Total SC Population Male SC Population Female SC Population
Total SC Population
Total ST Population
3000
2000
1000
0
Total ST Population Male ST Population Female ST Population
Total ST Population
400,000
350,000
300,000
250,000
200,000
150,000
100,000
50,000
0
Total Male Female Total Male Female
Literates Literates Literates Illiterates Illiterates Illiterates
The majority of people in rural sector are farmers (cultivators) & agricultural labors which
indicates dominant agricultural economy. A small segment of population is engaged as
household industry worker. But in urban sector the existing scenario is completely
reversed as most of the people there are engaged in non-agricultural activity especially in
local hotels/restaurants and as drivers and some people also operates their
vans/jeeps/cars as tourist vehicle.
Annual income helps in identifying families below poverty line. During the field surveys,
income of a household through all possible sources was recorded. Agriculture and allied
activities were reported to be the major source of income followed by non-farm wage
labor, business, government service and private service. The other important sources of
income include government pension and income from selling of fodder.
3.11.2 Workers Scenario
Occupational Pattern was studied to assess the skills of people in the study area.
Occupational pattern helps in identifying major economic activities of the area. The main
and marginal workers population with further classification as casual, agricultural,
households and other workers is shown in Table 7.3. In the study area the Main and
Marginal Workers population was observed as 109104 (19.6%) and 42626 (7.7%)
respectively of the total population (555971) while the remaining 404241 (72.7%) persons
were recorded as non-workers. Thus it implies that the semi-skilled and non-skilled work-
force required in study area for the project is available in aplenty. Graphical
representation of Workers Scenario is given below as Figure 3.13.
Distribution of work participation rate of the study area population is shown in Table 3.26
as follows;
Workers Scenario
Main Workers
19.6% Marginal
Workers
7.7%
Non-Workers
72.7%
MAIN_CL_P
15.8%
MAIN_AL_P
MAIN_OT_P 21.8%
57.5%
MAIN_HH_P
4.9%
MARG_OT_P
37.8%
MARG_AL_P
45.1%
MARG_HH_P
8.0%
Non-Workers Population
450000
400000
350000
300000
250000
200000
150000
100000
50000
0
Total Non-Workers Male Non-Workers Female Non-Workers
Non-Workers Population
pass through the district. The district has been fairly rich in road communication for a long
time.
The development of the means of communication has had a great impact on the trade
and commerce of the district. The district may now be said to be fairly well-connected by
Road and Rail. Arrah town is the hub of commercial activities of the district. In Bhojpur
district, trade consists mainly of export of pulses, rice, castor seed, milk products and
vegetables and import of cotton textiles, iron and steel products, cement, coal and
consumer goods.
Apart from Post &Telegraph (P & T) services, transport is the main communication
linkage in the study area. Only thirty one (31) villages are being served with Post Office
facilities in the rural parts of the study area. Rests of the villages are depending upon
these villages and towns of the study area. The study area has average rail and road
network, passes from the area. Nearest town is Arrah (MC) at about 10-km away from the
project site in the South-West direction with respect to the proposed project activities.
The district is served by East Central Railway. Arrah, the District Headquarters, is on the
main line of Eastern Railway. It enters the district at Koilwar on the East and moves via
Buxar to Moghalsarai on the West. A new Broad-gauge rail line is being constructed
between Arrah and Sasaram. The East Central rail line also passes across the District
HQ and most of the villages availing this facility through the nearest railway station.
Nearest Railway Station is Arrah Railway Junction, at about 10km away in South-West
direction w.r.t., the proposed project site.
The district of Bhojpur is not served by any regular air service. Jai Prakash International
Airport is about 45-kms away from the proposed expansion site in East direction. National
Highway (NH-30) is about 250m away from the proposed site. Pucca road facility is
available for about seventy nine (79) villages (69.3%) of the study area. As per the
compiled census 2011 data on amenities availability, out of the total one hundred
fourteen (114) revenue villages/towns of the study area, only ten (10) villages (8.8%) are
served with Railway Station facility in the study area; remaining villages are depending
upon the same villages and towns of the area having such facility. Sixteen (16) revenue
villages have navigable waterways facility in the study area. The villages in the study area
which do not have such facility can reach within 5 to 10-km range. Mainly Six (06) Towns
named Shahpur, Arrah, Koilwar, Behea, Piro, and Arwal are available within the distance
range of 2 to 25-kms from the villages of the study area.
3.11.10 Banking Facility
The study area has almost all the schedule commercial banks with ATM facility at urban
areas and the district HQ.
Banking facility is available only in 85 villages (8.5%) out of 997 inhabited villages in the
district. Among the C.D. Blocks, Koilwar has the maximum proportion of villages having
banking facility with 18.3% and Agiaon has the minimum proportion of villages having
banking facility with 1.49%.
Mahui 63 0 10 2 51 10 0 7 1 2
Kishunpura 281 53 33 7 188 384 97 107 5 175
Golakpur 264 82 16 46 120 283 58 157 33 35
Jamalpur 980 138 404 12 426 410 36 264 18 92
Mana Chak 209 189 0 5 15 1 0 0 0 1
Pachaina 504 201 201 13 89 42 3 28 0 11
Jalpura 256 160 63 1 32 10 6 3 0 1
Khesrahiya 264 80 141 2 41 103 1 68 0 34
Mohaddi Chak 524 208 221 14 81 76 0 74 0 2
Deoria 135 49 8 7 71 248 2 71 1 174
Babhnauli 39 30 3 3 3 210 11 47 148 4
Daulatpur 484 74 174 20 216 276 30 171 17 58
Pachrukhia 517 37 79 10 391 40 2 23 0 15
Kamalu Chak Uninhabited village
Rajapur 389 65 85 60 179 388 96 77 73 142
Manikpur 892 405 190 29 268 504 65 219 45 175
Dumaria 152 64 34 0 54 145 0 136 0 9
Sirpalpur 300 46 124 3 127 79 3 41 13 22
Bhopatpur 155 22 70 1 62 57 0 35 0 22
Mohkampur 178 58 14 1 105 172 10 134 8 20
Chandwa 241 124 53 6 58 130 2 87 1 40
Mathurapur 303 21 14 2 266 530 8 8 4 510
Chandi 1220 289 344 24 563 283 16 198 7 62
Guri 240 79 110 6 45 49 13 19 7 10
Kusihan 293 38 204 15 36 30 1 22 0 7
Khangaon 2534 1112 992 25 405 545 73 340 101 31
Bhadwar 1429 353 599 48 429 567 78 366 18 105
Farhangpur 698 107 543 14 34 739 28 694 2 15
Bahiyara 612 61 223 15 313 87 1 60 8 18
Dhandiha 102 72 0 0 30 294 3 283 1 7
Jogta 1854 940 760 13 141 1067 144 830 22 71
Suraudha Uninhabited village
Purdilganj 278 7 181 13 77 55 2 34 6 13
Haripur 496 150 196 13 137 333 6 151 38 138
Mokhalsa 175 3 76 5 91 738 12 439 37 250
Kiratpura 853 208 409 20 216 424 14 312 28 70
Songhatta 470 101 162 17 190 304 9 253 10 32
Koilwar
Bhopatpur 1 1 0 0 0 0 0 0 2 2 1 1 2 2 2 2 1 2 2 1 1 2 1 2 1 2 2 (16km)
Koilwar
Mohkampur 1 0 0 0 0 0 0 0 2 2 1 1 2 2 2 2 2 2 2 1 1 2 1 2 1 2 2 (14km)
Koilwar
Chandwa 1 0 0 0 0 0 0 0 2 2 1 2 2 2 1 2 1 2 2 1 1 2 1 2 2 2 2 (16km)
Koilwar
Mathurapur 1 1 0 0 0 0 0 0 2 2 1 1 2 2 1 2 2 2 2 1 1 2 1 2 1 1 2 (16km)
Chandi 1 1 1 0 0 1 0 0 2 2 1 1 2 2 1 2 1 2 2 1 1 1 1 1 1 1 1 Koilwar (7km)
Koilwar
Guri 0 0 0 0 0 0 0 0 2 2 1 2 2 2 2 2 1 1 2 1 1 2 1 2 2 2 2 (14km)
Koilwar
Kusihan 1 0 0 0 0 1 0 0 2 2 1 2 2 2 2 2 1 1 2 1 1 2 1 2 2 2 2 (14km)
Khangaon 7 3 2 1 1 1 1 1 2 2 1 1 2 2 1 2 1 2 2 1 1 1 1 1 1 1 1 Koilwar (9km)
Bhadwar 3 1 1 0 0 1 0 0 2 1 1 1 2 2 1 2 1 2 2 1 2 2 1 2 1 1 1 Koilwar (9km)
Farhangpur 1 1 0 0 0 0 0 0 2 2 1 1 2 2 2 2 2 2 2 1 1 1 1 2 1 1 1 Koilwar (6km)
Bahiyara 2 0 0 0 0 0 0 0 2 2 1 1 1 2 2 2 2 2 2 1 2 1 1 2 1 1 1 Koilwar (8km)
Dhandiha 2 1 2 0 0 0 0 0 2 2 1 2 1 2 1 2 2 2 2 2 2 1 1 2 1 1 1 Koilwar (2km)
Koilwar
Jogta 3 1 1 1 0 1 0 0 2 2 1 1 1 2 2 2 2 2 2 1 1 1 1 2 2 2 2 (15km)
Suraudha Uninhabited Village
Purdilganj 1 1 0 0 0 0 0 0 2 2 1 2 2 2 2 2 2 2 2 1 1 2 1 2 1 1 2 Koilwar (9km)
Haripur 1 1 0 0 0 0 0 0 2 2 1 1 2 2 1 2 2 2 2 1 1 2 1 2 1 2 2 Koilwar (3km)
Mokhalsa 1 0 0 0 0 1 0 0 2 2 1 2 2 2 2 2 1 2 2 1 1 2 1 2 1 2 2 Koilwar (8km)
Kiratpura 1 0 0 0 0 1 0 0 2 2 1 1 2 2 2 2 1 2 2 1 1 2 1 1 1 2 2 Koilwar (8km)
Songhatta 1 1 0 0 0 0 0 0 2 2 1 2 2 2 1 2 1 2 2 1 1 2 1 2 1 1 1 Koilwar (6km)
Mirapur Uninhabited Village
Imadpur Uninhabited Village
Gorhna 1 1 0 0 0 0 0 0 2 2 1 1 1 2 2 2 2 2 2 1 1 2 1 2 1 1 1 Arrah (3km)
Milki 1 0 0 0 0 1 0 0 2 2 1 1 2 2 2 2 1 2 2 1 1 2 1 2 1 1 1 Arrah (12km)
Diliya 1 0 0 0 0 0 0 0 2 2 1 2 2 2 2 2 2 2 2 1 1 2 1 2 1 1 2 Arrah (5km)
Birampur 2 1 0 0 0 0 0 0 2 2 1 1 1 2 2 2 2 2 2 2 1 2 1 2 2 2 2 Arrah (13km)
Doghra 2 1 0 0 0 0 0 0 2 2 1 2 2 2 2 2 2 2 2 1 1 2 1 2 1 2 2 Behea (4km)
Kauriya 1 1 0 0 0 1 0 0 2 2 1 1 2 2 2 2 2 2 1 2 2 2 1 2 2 2 2 Behea (10km)
Dhanpura 1 1 0 0 0 0 0 0 2 2 1 2 2 2 2 2 2 1 1 1 2 2 1 2 2 2 2 Piro (15km)
Madain 1 0 0 0 0 0 0 0 2 2 1 1 1 2 2 2 1 2 2 2 1 1 1 2 2 2 2 Piro (10km)
Sundarpur 0 0 0 0 0 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 2 2 2 2 Piro (9km)
This chapter details the inferences drawn from the environmental impact assessment of the proposed
project. It describes the overall impacts of the plant activities and underscores the areas of concern, which
need mitigation measures.
4.1 General
The anticipated impacts of the proposed LPG storage and bottling facilities at Gidha
Industrial Growth Centre, Village Gidha, Arrah, Dist: Bhojpur, Bihar on environment have
been evaluated and predicted based on the information collected at the site and the
information provided by the HPCL.
The environmental impacts can be categorized as either primary or secondary. Primary
impacts are those which are attributed directly by the construction and operation of the
project, secondary impacts are those which are indirectly induced and typically include the
associated investment and changed patterns of social and economic activities by the
construction and operation of proposed facilities.
There is no sensitive location of ecological, historical or strategic importance around the
HPCL’s proposed LPG storage and bottling facilities. Therefore, no such impact is
anticipated during construction and operation phases of proposed LPG storage and
bottling facilities.
The proposed LPG storage and bottling facilities would create impact on the environment
in two distinct phases:
Terrestrial Ecology,
Aquatic Ecology,
Demographic and Socio-economic.
The details of the activities of the proposed LPG storage and bottling facilities during
construction and operation phases are described in the following sections:
These emissions will result in temporary degradation of air quality, primarily, close to the
working environment affecting employees. Dust and other emissions are not likely to
spread in vicinity of site and surroundings.
The excavated of the earth from proposed LPG storage and bottling facilities during
construction will result in emission of suspended particulate matter (SPM). However, the
suspended particulate matter (SPM) rise in the ambient air are coarse in size and will
settle within a short distance closed to the construction site. Therefore, dust and gaseous
emissions due to construction activities at proposed LPG storage and bottling facilities are
not likely to affect the surrounding.
Hence, the impacts on the ambient air quality during construction phase will be temporary
and reversible in nature for short duration and it is restricted to short distance only.
Mitigation Measures
Construction materials will be fully covered during transportation by road to the
project site.
Dust suppression systems (water spray) will be used as per requirement at the
construction site.
Construction area will be cordoned off by tin sheets up to about 3 m height.
Earth moving equipment, typically with a grader blade and ripper were used for
excavation work.
Construction vehicles and machineries will be maintained properly and “Pollution
under Control” certificate will be kept up-to-date and checked.
Mixing of cement with other building materials will be done at isolated place.
Operation Phase
During the normal operation of the proposed LPG storage and bottling facilities, there will
be no continuous source of air emissions. Hence, the impact on ambient air quality will be
insignificant during operation phase.
During operation phase, intermittent gaseous emissions are anticipated from DG sets
which will be operated during grid power failure at proposed LPG storage and bottling
facilities. DG sets will be fitted with stack of sufficient height as per CPCB guidelines to
achieve natural dispersion of pollutants.
During receipt of LPG through bullet tankers and distribution of LPG cylinders, increase in
vehicular emissions is anticipated due to bullet truck and Cylinder truck movement. As an
estimate 86 trucks will be reaching proposed LPG plant for unloading of LPG and
distribution cylinders to authorized dealers in the area. To control vehicular emissions,
truck/tankers engaged in bulk LPG transportation and distribution of LPG cylinders will
essentially have Pollution under Control Certificate (PUCC) to minimize vehicular
emissions. It will be ensured at the gate of HPCL LPG plant gate. Therefore, during
operation phase the impacts on the ambient air quality shall be insignificant.
Mitigation Measures
DG sets will be fitted the stacks of sufficient height as per CPCB guidelines to achieve
natural dispersion of exhaust gases.
Compulsory Pollution Under Control Certificate (PUCC) for bullet trucks and cylinder
trucks to minimize vehicular emissions
Overall impact of proposed LPG storage and bottling facilities in the study area will be
positive and beneficial in long term, as distribution of LPG cylinders will replace or
minimize use of traditional fuels, such as, wood, coal, petroleum oils and subsequently
improvement in ambient air quality of the area will be observed.
The average ambient noise level at the boundary walls of the proposed LPG storage and
bottling facilities, as monitored during baseline data generation are in the range of 40.9 to
51.8 dB(A). At the proposed LPG storage and bottling facilities, pumps, DG sets, fire
pumps, unloading bays and cylinders truck and bullet tankers will be major source of
noise generation. The noise levels from these sources shall be in the range of 70 to 80 dB
(A). DG sets will be intermittent source of noise generation and will be operated only
during grid power failure. To control noise levels, DG sets have been provided with
acoustic enclosures and anti vibration pads.
Hence, anticipated impact of noise generation from proposed expansion project of LPG
storage and bottling facilities during operation phase will be limited within the boundary.
Mitigation Measures
Noise levels from proposed LPG storage and bottling facilities will not reach its
boundary.
DG sets room will be acoustically treated to control noise levels as per CPCB
guidelines.
Ear muff and ear plugs will be provided to operators while working DG sets
rooms/high noise areas.
very small and obtained from ground water. Therefore, no significant impact is anticipated
on surface and ground water resources of the area during construction phase.
Mitigation Measures
Use of water was minimized during construction phase.
Drainage channels and storm water drains have already been constructed at the
site.
Operation Phase
For normal operation of LPG storage and bottling facilities, no process water is required.
Howeverafter proposed expansion project about 5 KLD of water will be required for
cylinder washing, obtained from ground water. For domestic purpose only 3 KLD water will
be required at the proposed LPG storage and bottling facilities.
Mitigation Measures
Treated waste water from washing will be reused for washing purpose or for
horticulture purposes to minimize the use of fresh water.
Water Quality
Construction Phase
During construction phase of LPG bottling plant, small quantity of metal cuttings, soil
debris, etc will be generated as waste which will be cleared after construction activity was
over and same were disposed in environmental safe manner. Therefore, no significant
impact could be observed on ground and surface water quality of the area during
construction phase.
Mitigation Measures
The excavation work will be carried out during non-monsoon season.
All the debris generated from construction site will be collected and disposed
suitably.
A sediment trap provided to prevent the discharge of excessive suspended solids
with water.
An oil trap will be provided in the drainage line to prevent contamination by
accidental spillage of oil and contamination of water.
To prevent contamination from accidental spillage of fuel oil, the storage areas will
be bunded and cleaned at regular intervals.
Sewage generated from the site will be treated in septic tank followed by soak pit
Operational Phase
During operation of proposed LPG plant, no process effluent will be generated. For
washing of cylinders approx 5 KLD water will be required. Waste water generated from
cylinders washing will be collected in settling tank. Treated water from clarifier will be
reused for cylinders washing purpose.
Little quantity of contaminated water will be drained from LPG tankers during unloading
and mounded bullets regularly. The effluents will be sent to 4KLD ETP for treatment
(mainly oil) and treated effluents will be used for green belt development.
During operation the proposed LPG storage and bottling facilities, 3.0 KLD sewage will be
generated, which will be disposed through septic tank followed by soak pit. Hence, during
the operation of the proposed LPG storage and bottling facilities, no impact is anticipated
on water quality.
Waste water generated from cylinders washing will be collected in settling tank and
dosed for flocculation of suspended particles. Treated water from clarifier will be
reused for cylinders washing purpose.
Proper collection and disposal of solid and hazardous waste to be generated from
proposed LPG storage and bottling facilities
4.2.6 Soil
Impact on Soil
Construction Phase
During the construction of LPG bottling plant, construction wastes such as excavated soil,
debris, some pipes/ metal waste and very small amount of oil & grease will be generated.
These wastes will be disposed-off properly in environmentally sound manner.
Mitigation Measures
Construction debris, fuel, oil drums, used grease cartridges will be collected and
disposed of properly;
Lubricating waste oil will be collected separately in drums and same was handed
over to waste oil recyclers as authorized by BPCB as per CPCB guidelines.
All solid wastes will be cleared after construction activities.
Operational Phase
During operation of proposed LPG storage and bottling facilities, no process waste will be
generated in any form. It is estimated that about 17.0 kg (28 Company employ and 139
contract employee-Per capta 100 gm) municipal solid waste may be generated by
workers, canteen and truck drivers. Municipal solid waste generated from proposed LPG
storage and bottling facilities will be segregated in the form of recyclable waste,
biodegradable waste and non bio-degradable wastes. Recyclable waste including paper,
plastic, etc will be sent for recycling. Biodegradable waste will be used for composting at
the LPG plant to produce manure for green belt.
Occasionally, used oil will be generated from DG sets and engines maintenance, which is
categorized as Hazardous Waste as per Hazardous Waste (Management, Handling and
Tran boundary Movement) Rule 2008. The used oil at the LPG bottling plant will be stored
in containers and handed over to MoEF&CC/Bihar State Pollution Control Board approved
Used Oil recyclers for recycling purpose. Some sludge will be generated from ETP which
will be suitably disposed off.
Hence, no significant impact is anticipated on soil of the area and at proposed LPG
storage and bottling facilities.
Mitigation Measures
Municipal solid waste generated from the proposed LPG bottling plant will be
segregated in the form of recyclable waste, biodegradable waste and non bio-
degradable wastes. Recyclable waste including paper, plastic, etc will be sent for
recycling.
Biodegradable waste will be used for composting to produce manure for green belt.
Sludge will be generated from septic tank, which will be used as manure for green
belt.
Sludge from ETP will be suitably disposed off.
Used oil will be collected separately in drums and sold to MOEF&CC/BPCB
authorized used oil recyclers for recycling.
No impact is envisaged on aquatic ecology from the operation of proposed LPG storage
and bottling facilities during construction or operational phases as there is no water body
in the vicinity of the proposed plant.
Construction Phase
The construction of proposed expansion project will be carried out at the existing LPG
storage and bottling facilities at industrial plot. Therefore, socio-economic impacts linked
to the acquisition of land will not come.
The proposed expansion project of LPG storage and bottling facilities will generate direct
and indirect employment opportunities during the construction phase. About 50 local
skilled, semi-skilled and unskilled labourers got employment in the construction activities.
This will be a moderate positive impact of the proposed LPG storage and bottling facilities.
The construction of the proposed LPG storage and bottling facilities will have beneficial
impacts as some local unskilled, semiskilled and skilled persons will get direct or indirect
employment.
Since the immigration of work force during construction of proposed LPG storage and
bottling facilities will be insignificant, the social impacts on literacy, health care, transport
and housing facilities and cultural aspects will also be insignificant.
Operational Phase
The major positive socio-economic impact will be observed in the form of the following:
Reduction of Emissions: The proposed LPG storage and bottling facilities will ensure
availability of LPG for domestic and industrial establishments in the region which will help
in minimization of use fossil fuel (petrol, HSD, furnace oil, etc), coal, wood, etc.
Consequently, it will help in maintaining cleaner environment in homes due to reduction in
emissions.
Improved Health Conditions: Use of LPG as a cleaner fuel will also create healthy
environmental conditions and help in uplift of socio-economic conditions of people of the
region.
4.3 Conclusions
In view of the above facts and figures, it may be concluded that the proposed expansion
of LPG storage and bottling facilities at Gidha Industrial Growth Centre, Village Gidha,
Arrah, Dist: Bhojpur, Bihar, shall not result in any adverse environmental impacts on
physical features, water, noise and air environment, biological and socio-economic
environment. The proposed LPG storage and bottling facilities shall generate additional
direct/indirect employment and indirect service sector enhancement in the region and
would help in the socio-economic upliftment of the state as well as the local area. The
proposed LPG storage and bottling facilities will make available LPG as a cleaner fuel and
will subsequently create healthy environmental conditions, which will result in uplift of
socio-economic conditions of people of the region.
This Chapter provides an alternative analysis, including site and technology, considered
for the proposed expansion project.
5.1 General
The analysis of alternative is the process of comparing potential impacts and mitigation
options of a series of alternative location, technologies, operation to identify optimal
alternatives that meets national legislation. These alternatives can include variations in
layout, alternative engineering process, routing, linear facilities and screening of material
suppliers to select those with appropriate environmental and risk management system.
5.2 Alternate Technology
The proposed expansion project is coming in existing plant area inside the Gidha
industrial area, BIADA, Dist-Bhojpur, Bihar. HPCL LPG Bottling plant, proposal to
construct additional 3 x 500 MT mounded storage vessels for storage of LPG within the
existing premises. HPCL has mastered the art and technology of installation of Mounded
Bullets. The LPG department of marketing division of HPCL has earned a good credential
for installation of Mounded bullets.
5.3 Alternative Site
Since, existing land is having sufficient space for construction of additional three
mounded storage vessels within available site at Gidha industrial area, BIADA, Dist-
Bhojpur, Bihar. Hence no alternative site selection is considered. Major Factor involved in
the selection of site are listed below
The proposed project is addition of Mounded LPG Bullets (3 nos.along with
associated facilites) to the existing LPG Bottling Faicity at Gidha.
The project site is in industrial area
Site is connected with National Highway (NH-30) for easy transport of product.
Site is near to railway station.
There is no forest or eco sensitive area within the 10km of project site
The site is located near high demand area.
There is no likelihood of any residential development in the vicinity of the proposed
bulk LPG storage and bottling facilities.
Possible mutual aid in emergency will be available in the industrial area.
Adequate availability of land within the proposed bulk LPG storage and bottling
facilities for future expansion.
Owing to the various advantages listed above, Gidha Industrial Growth Centre, BIADA,
Dist-Bhojpur, Bihar was chosen forbthe proposed expansion project.
6.1 General
It is essential that an effective environmental monitoring plan be designed and followed
during operation phases.
The objectives of environmental monitoring plan for proposed bulk LPG storage and
bottling facilities are:
To verify the results of the impact assessment study in particular with regards
to proposed pipeline;
To follow the trend of concentration values of the parameters which have
been identified as critical;
To check or assess the efficiency of the mitigation measures; and
To ensure that new parameters, other than those identified in the impact
assessment study, do not become critical through the proposed expansion
project of bulk LPG storage and bottling facilities.
The environmental monitoring is the primary tool for assessing the prevailing quality of
air, water, noise, land etc. The environmental monitoring helps in suggesting and taking
corrective course corrections, monitored parameters are exceeding. The monitoring of
various environmental parameters for ambient air quality, water quality, noise levels, and
soil quality will be carried out on a regular basis at and around the proposed bulk LPG
storage and bottling facilities to ascertain the following:
Pollution caused due to operations within the proposed bulk LPG storage and
bottling facilities.
Change in environmental quality within and outside the proposed bulk LPG
storage and bottling facilities
To assess environmental impacts after operation of proposed bulk LPG
storage and bottling facilities.
Evaluate the efficiency of pollution control systems installed.
Any Hazard / risk to plant and surrounding area.
The environmental monitoring shall be periodic and comply with the promulgated
standards. The frequency of monitoring of various environmental components and
frequency to be monitored is given in Table 6.1.
6.2 Environmental Monitoring Schedules
Ambient air quality parameters suggested during operation phase of the proposed bulk
LPG storage and bottling facilities, are Particulate Matters (PM2.5), Particulate Matter
(PM10), Nitrogen Dioxide (NO2), Hydro Carbon (HC), Sulphur Dioxide (SO2) and Carbon
Monoxide (CO). These are to be monitored at designated locations starting from the
commencement of construction activities. Data should be generated 24 hourly during
operation phase at identified locations in accordance to the National Ambient Air Quantity
Standards. During operation phase, there will not be any major source of air emissions
except DG sets and vehicular emissions through LPG road bullet tankers and cylinder
trucks approaching for loading of LPG. Six monthly ambient air quality monitoring should
be carried out at boundaries of proposed LPG plant for Particulate Matters (PM2.5),
Particulate Matter (PM10), Nitrogen Dioxide (NO2), Hydro Carbon (HC), Sulphur Dioxide
(SO2) and Carbon Monoxide (CO). Six monthly monitoring should be done for Total
Hydrocarbons in LPG Bullet tanker unloading areas and LPG cylinder truck parking
areas.
Table 6.1: Environmental Monitoring Plan for Proposed LPG Bottling Plant
Environmental Project Duration /
Parameter Standard Location Implementation Supervision
Component stage Frequency
LPG Unloading
HC in HPCL
Facilities
LPG Plant -- Six Monthly
LPG Truck
Area
Bullet
At boundary wall
Ambient Air PM2.5, PM10,
in upwind and
SO2, NO2, National
down wind Continuous 24-
CO & HC on Ambient
direction at hourly once in a
Boundary of Quality
boundary of bulk month
HPCL LPG Standards
LPG storage and Environmental
plant bottling facilities Cell of HPCL or
Operation As per IS: MoEF&CC/ HPCL
Phase 10500 for As Water NABL approved
relevant quality bulk LPG storage Monitoring
Water Quality parameters standards and bottling Once in a year agency
facilities
in (IS 10500)
consultation
with BPCB
At propose LPG
bottling plant
As per
Noise Level LPG Unloading 24-hourly
Noise National
Facilities Measurement,
Measurements in dB (A) Noise
standards LPG Truck once quarterly.
Tanker Parking
Area
7 ADDITIONAL STUDIES
This Chapter provides the details about the Risk Assessment, Disaster Management
Plan (DMP) and on-site emergency plan as proposed for the proposed expansion project.
carried out by HPCL at Plant.
7.1 General
HPCL LPG plant at Patna receives LPG from HMEL Bathinda refinery, HPCL
Visakhapatnam, GAIL petrochemical plant in Pata (UP) and HPCL Haldia through road
Tankers of 17 or 18 MT capacity. Eight unloading bays are provided for transfer of LPG
from the road tankers to storage bullets.
7.2 Hazard and Operability Study (HAZOP)
HAZOP study is to carefully review a process or operation in a systematic manner to
determine whether deviations from the design or operational intent can lead to
undesirable consequences. This technique can be used for continuous or batch
processes and can be adopted to evaluate written procedures. The HAZOP team lists
potential causes and consequences of the deviation as well as existing safeguards
protecting against the deviation. When the team determines that inadequate safeguards
exist for a credible deviation, it usually recommends the action be taken to reduce the
risk.
Objective of QRA:
• To identify, quantify and assess the risk from the facility from the storage and
handling of chemical products
• To identify, quantify and assess the risk to nearby facilities / installations.
8 PROJECT BENEFITS
This Chapter provides the benefits to the community in vicinity as well as to the region
on the whole that are associated with the project. It also envisaged the Corporate Social
Responsibility and Community Development activities undertaken by HPCL, Patna and
proposed CSR-CD plan.
The proposed LPG bottling plant will be helpful in ensuring availability of LPG for
domestic and industrial establishments which will help in minimization of use fossil fuel
(petrol, HSD, furnace oil, etc), coal and wood. It will, therefore, help in maintaining cleaner
environment due to reduction in emissions. Use of LPG by domestic and industrial users
will also help in reduction in generation of green house gases responsible for global
warming.
8.4 Other Tangible Benefits
The proposed LPG bottling plant shall create tangible benefits as described below:
This Chapter provides mitigation and control measures to attenuate and/or eliminate
environmental impacts, which are likely to be caused by the proposed project. An
Environmental Management Plan (EMP) has been developed to mitigate the potential
impacts and to strengthen the beneficial impacts during the construction and operation
phase.
9.1 General
The objective of the environmental management plan (EMP) is to identify administrative
aspects for ensuring that mitigation measures are implemented and their effectiveness is
monitored. The EMP focuses on direct impacts, which are identified as having the
potential to cause significant impacts on the environment and identifies:
• Specific measures that will be taken to prevent, reduce or manage the adverse
environmental impacts during construction and operation; and
• Where it is not possible to specify these at this stage, the level of environmental
performance that will be expected during the operation.
9.2.2 Sanitation
Adequate and suitable sanitary facilities will be provided to maintain proper standard of
hygiene for construction workers during working at the site.
TOTAL 18.00
YEAR I II III IV V TOTAL
Provision in Lakh 4.0 4.0 3.5 3.5 3.0 18.00
The fire fighting detection and prevention system in the storage & handling area comprise
of the following:
The plant is equipped with fire fighting facilities as per OISD 144.
Two fire water tanks of total capacity of 5085 KL have been installed. This will take acre
of proposed additional mounded bullets.
Safety Organization
The Fire and Safety Department will be under the control of trained and responsible
officer.
All the officers and staff of the proposed LPG bottling plant will be trained for combating
fire and use of safety equipment.
Security
The following security arrangement will be provided within proposed LPG Bottling Plant
The facilities are guarded round the clock by efficient security personnel. They
prevent any unauthorized entry inside the plant.
3.0 m high boundary wall with 0.6m barbed wire fencing has been provided around
the installation to resist any unauthorized entry.
Safety & Environmental Audit
In view of the high hazard potential of LPG, extreme cares will be taken to maintain the
safety needs of the LPG installation. Safety audits will be carried out regularly by a
multidisciplinary team. The safety audit will include operating procedures, housekeeping,
provision of fire fighting and safety gadgets, mock drills etc.
Occupational Safety and Health
Safety Department in the proposed LPG plant will be looked after the occupational safety
aspects of the workers. HPCL will follow OISD-166 to maintain occupational health and
safety of the employees and workers. Workers will be well informed about the preventive
measures and safe operating practices to be followed for various types of job. Training
courses will be organized for the workmen and the officers before they are put on the job.
Contractor's labourers will also be trained and educated to ensure safe operating
practices for the jobs.
Tool & Tackles
In LPG installation, it is customary to use non-sparking type tools (spanners, wrenches
etc). Electrical hand tools like torches; lamp etc. to be used in the hazardous area should
be flame proof type. All tools should be of approved quality and make and will be
purchased with test certificates.
Preventive Maintenance & Planned Inspection
To facilitate inspection and maintenance service in planned manner, a schedule will be
made for jobs to be done daily, weekly, bi-weekly, monthly, half yearly and yearly. The
record of the jobs done will be kept properly. The inspection & maintenance schedule will
be done as per the directive & procedure lay down by OISD as well as instructions of
suppliers and OEM. The planned inspection will also include statutory inspection of
pressure vessels, storage tanks, safety valves, etc.
Safety, Health & Environmental Policy of HPCL
HPCL is committed to conduct business with strong environment conscience ensuring
sustainable development, safe workplaces and enrichment of quality of life of employees,
customers and the community. HPCL believes that good SH&E performance is an
integral part of efficient and profitable business management.
Establish and maintain good standards for safety of the people, the processes and
the assets.
Comply with all rules and regulations on Safety, Occupational Health and
Protection.
Plan, design, operate and maintain all facilities, processes and procedures to
secure sustained Safety, Health and Environmental Protection.
Remain trained, equipped and ready for effective and prompt response to
accidents and emergencies.
Welcome audit of our SH & E conduct by external body, so that stakeholder
confidence is safeguarded.
Adopt and promote industry best practices to avert accidents and improve our
S,H&E performance.
Remain committed to be a leader in Safety, Occupational Health and
Environmental Protection through continuing improvement.
Make efforts to preserve ecological balance and heritage.
9.4 Environment Management Cell
Organising Essay Competition at Local School to promote Tree Plantation on eve of World Environment Day 5th
Tree Plantation on eve of World Environment Day 5th June’15 Tree Plantation on eve of Climate Change Awareness Week
25th Oct’15 to 1St Nov’15.
As per HPCL CSR policy for Social development activities in terms of Skill Development /
Empowerment, Education/Literacy Enhancement, Healthcare/ Medical facility, Drinking
water/ Sanitation, Community Development etc. HPCL kept at provision of 2.5% (55.0
Lacs) of investment cost (22.0 Crores) and it will use in 5 years by the HPCL.
The present report is based on the work carried out by M/s. EQMS INDIA PVT LTD on
Environmental aspects as well as baseline data collection carried out by them only.
The EIA report contains in depth study on environmental quality and Environmental
Management Plan to mitigate the impacts including Rapid Risk Assessment and Disaster
Management Plan. The project is technically, environmentally and socioeconomically
viable and is beneficial at local level, state level and national level.
10.1 Management of Releases of Pollutants
HPCL is committed to the guidelines and standards given by CPCB, Ministry of
Environment and Forest (MoEF), Bihar Pollution Control Board. The design of the project
activities will be done according to the guidelines of CPCB to keep atmospheric
discharges in air, water and land below the stipulated levels during normal operation.
This is achieved by proposed elaborate treatment for active gaseous waste, active liquid
and solid waste before discharges. Some amount of conventional pollutants like dust and
gaseous pollutants are produced or a short construction period, for which proper
management plan has been prepared. The conventional pollutants releases from the
plant during operation stage will be insignificant.
Onsite recycle/reuse potential of treated water for dust suppression at sites, watering
greenbelts and/or flushing of toilets will be assessed and optimal recycling will be done.
The soak pit and septic tanks at the construction sites will be designed in accordance
with the relevant Indian Standards considering peak load. Noise pollution will be reduced
by development of different barrier i.e. acoustic covering of noise generation machineries,
specially designed building in which the plant is enclosed. Occupational exposure of
noise will be reduced by providing protective gadgets to the workers working in the high
noise zone.
10.2 Risk Assessment
Rapid Risk Analysis has been performed and it documents the consequence results with
hazard to create awareness about the extent of impact.
10.3 Corporate Social Responsibility of HPCL, Village Gidha, Arrah, Dist: Bhojpur,
The policy of HPCL towards social welfare and community development aims at
strengthening the bond between project authorities and local population in the vicinity of
project. In line with this policy, HPCL planned to implement social and community welfare
11 DISCLOSURE OF CONSULTANT
This chapter, provide brief introduction of the consultancy organisation along with details of
accreditation of consultant with QCI-NABET. Lists the Functional Area Experts (FAEs) who
have worked in the preparation of EIA/EMP Report also given.
EIA Coordinator:
I, S.K.Jain, hereby confirm that the above-mentioned experts the EIA/EMP REPORT
Expansion of LPG Mounded Storage Facility at HPCL, Gidha Industrial Growth Centre,
Village Gidha, Arrah, Dist: Bhojpur, Bihar. I also confirm that the consultant organization
shall be fully accountable for any mis-leading information mentioned in this statement.
Signature:
Name: S.K.Jain
7. Details of the storage and technical specifications Details are given in section 2.4
with safety aspects & standards. and page no 29 to 31.
Detailed land use pattern
section 3.3 and Figure 3.3:
8. Site details including satellite imagery for 5km Land use Map of 10 Km Area
around the site by delineating land use pattern. around Project Site Page no
43 to 45. Land Use & Satellite
image enclosed in Annexure II.
Land use pattern section 3.3
Land use along with maps (By using satellite
and Figure 3.3: Land use Map
9. imagery data) & cropping pattern, vegetation, of 10 Km Area around Project
Flora & Fauna. Site Page no 43 to 45.
Detailed Environmental Setting
and Salient Environmental
10. Details within 500m with respect to all Features of the Project Area in
establishments/railway line /habitation etc. 500 Mt is given in section 3.1.1
& page 39 to 42 of chapter 3.
Table 3.1 and Page no 36.
Demographic and Socio-
Economic Features given in
11. Demography & Socio-economics of the area. Chapter 3 Section 3.11, page
no 72 to 96.
Baseline 3 Months of Monitoring AAQ data
12. (except monsoon) for air, water and soil for 8
locations. Chapter 3; Section 3.6 Air
environments, 3.6.1 Selection
Ambient Air Quality Monitoring for PM2.5, PM10, of Monitoring Stations, 3.6.2
i) SO2, NOx, CO and other parameters relevant to Analysis of Ambient Air
the project shall be collected. Quality, 3.6.3 Page no 54 to 58
ii) Background levels of hydrocarbons (methane &
non-methane HC) and VOCs.
Chapter 3 Section 3.4 Soil,
3.4.1 Sampling and Analysis,
iii) Soil sample analysis. 3.4.2 Soil Characteristics Page
no 47 to 51
Details are given in Section 3.8
iv) Baseline underground and surface water quality in Ground and Surface Water
the vicinity of Project. Quality Of chapter 3. Page no
60 to 65
Section 3.5 Meteorological
v) Climatology & Meteorology including wind speed, Data Of chapter 3. Page no 51
wind direction, temperature, rainfall etc. to 53
3.7 Ambient Noise Quality,
3.7.1 Noise Levels in the Study
vi) Measurement of Noise levels. Area 3.7.2 Observation of
Ambient Noise Quality in
chapter 3. Page no 58 to 59
Details are given in different
Details of water consumption and source of water section 2.3.1 Water Source
supply, waste water generation, treatment and water consumption Resource
13.
utilization of treated water generated from the optimization/ recycling and
facilities and effluent disposal. reuse envisaged in the project
of Chapter 2. Page no 30
14. Detailed solid waste generation, collection, Section 2.6.3 Solid and Liquid
segregation, its recycling and reuse, treatment Hazardous Waste , 2.6.1
and disposal. Waste Water generation &
Management plan, 2.6.3 Solid
& Hazardous waste generation
& Management plan of chapter
2. Page no 33.
Detailed impact assessment is
15. Assessment of impact on air, water, soil, given in chapter 4 Page no 97
solid/hazardous waste and noise levels. to105
Section 69.3 LPG Leak
Details of proposed preventive measures for Detection Mechanism of
16.
leakages and accident. chapter 9 page no 111. 9.3.8
HSE in Section 9.5 Page 126
17. Adequate width of approach road to avoid Project site approximate 300
congestion and to have safe exit in emergencies. Mt National highway.
Detailed environmental
18. Environment Management Plan. management plan given in
chapter 9. Page no 117 to 128
Figure 2.6: Process Flow
Chart, Figure 2.7: Process
Details on list of hazardous chemicals to be stored Description of Project, Tanker
19. along with storage quantities at the facility, their Unloading Operation, 2.1 Page
category (as per MSIHC Rules), MSDS. no 14 to 25 Safety precautions
during loading / unloading
operations
Raw material in form of LPG
will be supplied by road
through anyone or all sources
20. Mode of receiving hazardous chemicals in viz. HMEL, Bhatinda refinery,
isolated storages and mode of their dispatch. HPCL Vishakha LPG Terminal,
IPPL Haldia, GAIL Auriya, &
IOCL Barauni.
Proposed plant layout with
21. Layout plan of the storage tanks and other existing and proposed details
associated facilities. in figure 2.5 of Page No 22.
Details on types and specifications of the storage
facilities including tanks, pumps, piping, valves, Details are given in Table 2.1:
22. flanges, pumps, monitoring equipments, systems No. of Storage Tanks &
for emissions control safety controls including Capacity in chapter 2.
relief systems.
Details are given in 2.1.3
Arrangements to control loss/leakage of Safety precautions during
23. chemicals and management system in case of loading / unloading operations
leakage. & LPG leak maintenance given
in section 6.3 page no 111.
24. Risk Assessment & Disaster Management Plan.
i) Identification of Hazards HPCL carried out detailed
ii) Consequence Analysis Quantitive Risk assessment
and report is attached as
iii) Risk Assessment & proposed measures for Risk
Annexure XI.
Reduction.
iv) Action Plan for fire fighting facility as per OISD Emergency Response &
Disaster Management
117 norms.
Planning (ERDMP) report is
v) Details of domino effect of the storage units in an attached as Annexure XII.
isolated storage facility.
vi) Onsite and offsite emergency preparedness plan.
Emergency Response &
Details of proposed occupational Health
Disaster Management
25. Surveillance program for the employees and other Planning (ERDMP) report is
labour. attached as Annexure XII.
Traffic study of the area, type of vehicles, 3.10 Traffic Study, Table 3.22
frequency of vehicles for transportation of and Table 23: Existing and
26.
materials, additional traffic due to proposed Propose Traffic of Project page
project, parking arrangement etc. no 70 to 72.
Detailed environmental
27. Environmental Monitoring Programme. monitoring programme is given
in chapter 6.
HPCL, as a responsible
Corporate Citizen, has
practiced the CSR model of
"Creating Shared Values", by
Adequate funds (at least 2.5% of the project cost)
reaching out to the
shall be earmarked towards the Enterprise Social
stakeholders, community and
Commitment based on Public Hearing issues and
society who are directly or
28. item-wise details along with time bound action
indirectly involved in its
plan shall be included. Socio-economic
business operations. Detailed
development activities need to be elaborated
Table 9.2: CSR Activity and
upon.
Budget & Demographic and
Socio-Economic Features
given in 9.8 Page no 128 to
129
Any litigation pending against the project and/or
29. any direction/order passed by any Court of Low No litigation is pending
against the project if so, details thereof.
A tabular Chart indicating point-wise compliance TOR Compliance enclosed as
30.
of ToR. an annexure III.
The following general points should be noted:
i) All documents should be properly indexed, page Compiled
numbered.
Baseline data collected from
ii) Period/date of data collection should be clearly October 2016 to December
indicated. 2016
iii) Authenticated English translation of all material Agreed, all the documents are
provided in Regional Languages. given English language.
The letter/application for EC should quote the Ref No 302 dated 13/07/2016,
iv) SEIAA, Bihar file No. And also attach a copy of letter enclosed as an annexure
the letter. II.
The copy of the letter received from the SEAC,
Copy of TOR letter enclosed
v) Bihar should be also attached as an annexure to as an annexure II.
the final EIA/EMP Report.
The final EIA/EMP report submitted to the SEIAA,
Bihar must incorporate the issues in this letter.
vi) The index of the final EIA/EMP Report must TOR Compliance enclosed as
indicate the specific chapter and page no of the an annexure III.
EIA/EMP Report where the above issues have
been incorporated.
While preparing and submitting the EIA report, the
instructions for the proponents and instructions for
the consultants issued by MoEF & CC Vide O.M.
Detailed EIA report along with
vii) No. J-1103/41/2006-IA.II (I) dated 4th August, additional study enclosed as
2009; O.M. No. J-1105/333/2009-IA.II (M) dated an annexure.
25th Feb 2010 and J-11013/41/2006-IA.II (I) dated
5th October, 2011, which are available on the
website of this Ministry should also be followed.
These ‘ToRs’ should be considered for the preparation of EIA/EMP report. Relevant information
as per the General Structure of EIA Notification, 2006.
The consultants involved in the preparation of EIA/EMP report after accreditation with Quality
Council of India/National Accreditation Board of Education and Training (QCI/NABET) would
need to include a certificate in this regard in the EIA/EMP Reports prepared by them and data
provided by other Organization(s)/Laboratories including their status of approvals etc. In this
regard circular No. B No. J-11013/77/2004-IA (II(I) dated 2nd December, 2009 available on the
Ministry’s Website http://www.moef.nic.in may be referred.
Annexure IV
:
Land Allotment Details
Annexure V
:
License from Department of Labour
Annexure VI
:
NOC from Pollution Control Board (Air/Water)
Annexure VII
:
Authorization Letter from to occupier or operator for
handling the hazardous waste
Annexure VIII
:
Baseline Monitoring Data
Annexure IX
:
Hazard and operability study (HAZOP)
HAZOP STUDY REPORT OF HPCL PATNA LPG
EQMS INDIA
BOTTLING PLANT FOR PROPOSED NEW LPG
DATED 04.10.2016
HPCL LPG MOUNDED BULLETS
BOTTLING PLANT
Revision-0,
Dated 04.10.2016
HAZOP STUDY REPORT OF HPCL PATNA LPG
EQMS INDIA
BOTTLING PLANT FOR PROPOSED NEW LPG
DATED 04.10.2016
HPCL LPG MOUNDED BULLETS
BOTTLING PLANT
TABLE OF CONTENTS
REVISION – 0
04.10.2016
Caution Note & Liability: The consulting services conducted by EQMS India Private Ltd (the
“Company”) were performed in good faith using generally accepted guidelines, standards,
and/or practices, which the Company considers reliable. Although the Company performed
its consulting services pursuant to reliable and generally accepted practices in the industry,
the Company does not guarantee or provide any representations or warranties with respect
to HPCL PATNA, (Arrah, District- Bhojpur). LPG Bottling Plant (the Client)’s use, interpretation
or application of the findings, conclusions, and/or suggestions of the consulting services
provided by the Company. Moreover, the findings, conclusions, and the suggestions resulting
from the consulting service are based upon information provided by the Client. EQMS does
not hold any liability with respect to interpretation or application of the consulting services
provided by the Company for this assignment / report. No responsibility, whatsoever it may
be is assumed by company for any injury and /or damage to persons or property as a matter
of products liability, negligence, or otherwise, or from any use or operation of any methods,
products instructions or ideas contained in the material of the report. Client is advised to
review the actual text of applicable legislation for analysis & ensuring compliance.
2.0 INTRODUCTION
2.1 INTRODUCTION
Hindustan Petroleum Corporation Limited (HPCL) headquartered in Mumbai and
employing around 11000 people is a Public Sector Undertaking (PSU) and also a
Navaratana Company. HPCL is among the few Indian representatives in the Fortune
500 companies.
HPCL operates in the Indian Oil & Gas Industry through different verticals. The
company’s infrastructure includes petroleum refineries, import facilities, cross-country
pipelines, petroleum product terminals, petroleum depots, liquefied petroleum gas
(LPG) bottling plants & storage facilities, lube-blending plants, petroleum retail outlets,
and Aviation Turbine Fuel (ATF) service facilities. Thus it is engaged in the business of
Refining, Storing, Marketing and Distribution of all kinds of petroleum products. Its
refineries are located at Mumbai and Visakhapatnam. In both the refineries, it
produces a host of petroleum products, such as Motor spirit, Naphtha, High speed
diesel, kerosene, liquefied petroleum gas, automotive and industrial lubricants, ATF,
FO, LSHS and other heavy distillates and distributes the same through its widespread
retail network so as to reach out to its customers.
During the year (2014-15), HPCL’s refineries at Mumbai and Visakhapatnam
maximized crude processing, this resulted in achieving a combined refining output of
16.18 million tonnes with a capacity utilization of 109%.
The refineries have been benchmarked by an international agency for various
performance parameters. The refineries also in the year (2014-15) achieved a highest
ever combined distillate yield of 77.5%, by improving the yields of value-added
products. Both the refineries are recipients of numerous awards in recognition of
their efforts in the field of energy conservation, environment and safety. Both the
Refineries have grown over the years and maintained their capacity utilization above
109% of their installed capacity. HPCL has equity participation in ONGC’s Mangalore
Refinery & Petrochemical Ltd and HMEL’s Guru Govind Singh Refineries Ltd.
To-day, Liquefied Petroleum Gas (LPG) has become the single most popular house hold
clean fuel. During the year 2014-15, 380 new retail outlets were commissioned; taking
the total number to 13233 retail outlets. A record number of 120 retail outlets were
modernized with an outlay of Rs. 234 Crore. HPCL released 41.9 lakh new connections
of HP GAS through a network of 3952 LPG distributors, achieving a total customer base
of over 47.1 million domestic LPG consumers. HP Gas reaches the customer after
through checking at every stage right from bottling to distribution.
In order to meet the increasing demand for LPG fuel, HPCL is making continuous effort
to increase the capacity of HPCL Bottling Plant situated at Gidha Industrial Growth
Centre, Village Gidha, Arrah, District Bhojpur(Near Patna), in its existing two LPG
storage and bottling plants (500 MT each with Total capacity of 1000MT). As part of
this program, HPCL plans to increase the capacity of its unit in Arrah, District Bhojpur
by installing 03 more mounded LPG bullets of 500 MT each for increasing total LPG
filling capacity from 300 MT per day to 700 MT per day, thereby improving more LPG
distribution in that area.
At present, at HPCL PATNA (Gidha, Arrah) LPG Plant with current storage capacity, the
number of bottling days for which the bulk will last is only 03 days on basis of double
shift bottling operation. The storage capacity augmentation would increase the
number of bottling days to about total 05 days on the basis of double shift bottling
operation. In order to meet the requirement of LPG cylinders in all the districts falling
under Patna LPG Regional Office, HPCL proposes to augment the storage and bottling
capacity of LPG at HPCL Patna Plant by installing 03 nos. of Mounded Storage Vessels
of 500 MT capacity each and additional 04 Tank Truck unloading gantries.
Being a Company committed to high standards of safety management, HPCL have
engaged the services of EQMS India Private Limited, Delhi to carry out detailed Hazard
& Operability (HAZOP) Study to identify the hazards involved in the LPG storage and
handling systems and ensure that all necessary protective measures are incorporated.
EQMS is a pioneer in process safety consultancy in India and has conducted over
various EIA Study/ Approval, HAZOP studies, QRA study, Preparation of ERDMP and
safety audits for various plants during the last 12 years.
2.2 This report has been prepared after the HAZOP study was conducted by Head-process
Safety Consultant from EQMS based along with the Sr. Official from HPCL Patna LPG
Bottling Plant on information and drawings furnished by HPCL
EQMS is thankful to HPCL-LPG Bottling Plant, PATNA (Arrah, District Bhojpur) for
extending the opportunity to participate in this assignment and trusts that the HAZOP
study report would be helpful in achieving high level of process safety management
right from the initial engineering stage of Proposed LPG Mounded Bullets for LPG
Handling System in the Bottling Plant.
telescopic conveyor before going for filling. The segregated cylinders are stacked
separately and the same undergoes testing/repair.
Tank Lorry Filling Shed
A Eight bay Tank Lorry Decantation/Filling Shed (TLD) will be provided to load LPG
from Tank Trucks to Storage Vessel (Bullet).
LPG Pumps and Compressor House
Two vertical can type pumps have been installed to pump liquid LPG from storage
vessels to carousel and One Vertical can type pump is used for loading the LPG tank
Trucks. These pumps have been provided with pop-action valves on discharge lines
and are coupled to flame proof motors.
LPG Pumps
LPG Size of Size of MOC
Motor Purpose
Pump Pump Suction Discharge
Capacity (Bottling/ TT
Capacity Type Pipe Pipe
(KW) Loading)
(M3/Hr) (mm) (mm)
200 NB 150 NB ASTM A
Cylinder
50 Vertical 22 (6 (6 216 Gr
Filling
inches) inches) WCB
200 NB 150 NB ASTM A
Cylinder
50 Vertical 22 (6 (6 216 Gr
Filling
inches) inches)) WCB
200 NB 150 NB ASTM A
Cylinder
150 Vertical 75 (6 (6 216 Gr
Filling
inches) inches) WCB
200 NB 150 NB ASTM A
Cylinder
150 vertical 75 (6 (6 216 Gr
Filling
inches) inches)) WCB
LPG Compressors
Reciprocating ASTM A
Tanker
192 Horizontal 75 100 NB 80NB 216 Gr
Unloading
type WCB
Two LPG vapor compressors each coupled to a flame-proof motor have been installed
for loading/unloading of LPG vapor, based differential pressure mechanism. The
maximum discharge pressure of these compressors is 11.5 kg/cm2g.
The total capacity of the LPG storage with the additional 03 new Mounded Bullets will
be 2500 MT.
Addition of new mounded bullets only will also greatly improve the safety aspects of
LPG storage.
Following actions are taken to draw the LPG Liquid/Vapor from LPG Road tanker
Vapor line valve of Bullets to suction of the Compressor are kept opened
Vapor Inlet line of the Road Tanker is made opened and liquid line from tanker line is
lined up to Inlet Header to Bullet
The compressor is started to Suck vapors from the Bullets which is compressed and
send to tankers
Tanker liquid is displaced with vapor in which the liquid LPG in turn sent to Bullet
After complete unloading of liquid, compressor is used to draw residual vapor from
Road tanker and sent to vapor phase of bullet through vapor line
The liquid LPG is pumped from the bullets and sent to LPG Bottling section (Carousel).
At present, the no. of days cover for LPG filling with present storage capacity is 03 days on the
basis of double shift bottling operation. The capacity augmentation would increase the no. of
days cover to about 05 days on the basis of Double shift bottling operation.
MANUFACTURING PROCESS
LPG is received from Road Tankers and transferred to a storage vessel (LPG Mounded Bullet).
The LPG stored in the vessel is pressurized to about 7 kg/sq.cm. The LPG pressure is boosted
to about 12-13.5 kg/sq.cm and sent to integrated carousel machine (LPG filling area) through
pipe lines using an LPG Pump.
The LPG cylinders are washed with multiple forced jet of water to remove mud, dirt, stains,
etc., from the outer surfaces. Subsequently the cylinders coming out of washing unit are dried
by blowing the air on the sides and top surfaces of the cylinders as they move.
Measured quantity of LPG is filled into cylinders at the filling shed under pneumatic control.
The Purging Unit which is on-line equipment creates a vacuum in the first stage and fills
LPG vapor in the second stage in new / hot repaired empty cylinders. PVC seal crimping
unit/Hot air sealing unit crimps the PVC cap and seal around the cylinder valve as a final
operation on the filled LPG cylinder.
Auto cap fixer fixes safety caps on to the valve of LPG cylinders.
Filled cylinders are subjected to 100 % weight check, presence and effectiveness of ‘O’ ring
inside cylinder valve and checks for leak and bung leak. Tamper proof seals are fixed on the
valves of sound cylinders. These cylinders are loaded to stake trucks and dispatched to
various markets. Cylinder movement inside the Plant is achieved using chain conveyors driven
by electrical motors through worm gear reducers/planetary gear reducers.
LPG is filled in the cylinders from 14.2 kg weight to 19.0 Kg Weight ( as per requirement) in
the integrated carousel machine and filled cylinders after leak testing, weight testing and
fixing safety caps are stacked in the filled cylinder shed near the delivery end as per rules laid
down by OISD/Gas Cylinder Rules, 1981. Commercial cylinders of capacity 35Kg/47.5 Kg are
also filled up thru 4 nos Static Filling Scale. Filled cylinders are delivered only to the authorized
LPG distributors. Drivers of the trucks carrying LPG are having valid license and are having
training in safety & fire fighting procedures. The total storage facility will be protected with
proper following Fire Protection System.
(a) Fire Hydrant System for total facility.
(b) Supplementary protection of bullets by medium facility of water spray system hooked
up with fire detection system.
(c) Provision of Fire Extinguishers as per requirement of OISD and TAC.
Fire protection facilities has been provided as per OISD-144.
Existing water storage capacity and fire pumps will be augmented as per OISD
to meet the requirement of the plant post-augmentation.
Safety distances between facilities and new proposed LPG Bullets will be
provided as per PESO/ OISD norms.
Entire Fire hydrant/ Hazard Control and detection system has been made to
meet OISD-144 standard. Total 02 fire water tanks of total capacity 5000 KL
have been installed. This storage Capacity will take care for fire fighting for 03
(500MT each) Mounded LPG Bullets.
Hydrant ring main system around the new Bullets will be provided with fire
hydrant points and monitors as per requirements of OISD. The Mounded
Bullets will also be provided with a fire hydrant system all around and water
sprinkler system as required, in addition, adequate numbers of portable fire
extinguishers of dry chemical type will also be provided.
Mock fire drills are conducted at regular intervals and the observations are
recorded. Personnel intended to operate the plant are well qualified and well
trained. Plant operations are supervised by a responsible Officer. The working
personnel are well informed and well trained for fire hazards and fire fighting
systems. Bottling Plant security system has been so envisaged to ensure strict
compliance of safety requirements and to take up prompt and proper action in
case of any emergency.
The first node is selected and applicable deviations from design intent are taken up
one by one. For each deviation first all possible causes are identified by brainstorming
among the HAZOP study team members. For equipment in batch operation,
deviations for each stage of the batch are to be studied separately.
The consequences of the deviations are then analyzed. In this context, consequence
represents the result of deviation not taking credit for safeguards provided in the
system. If the consequence is not significant, the cause is not taken up further in the
study.
It is important to ensure that the causes are identified within the node under Study,
whereas the consequences may occur anywhere in the plant. This procedure helps to
minimize confusing repetition and maintain focus.
The safeguards provided in the system are reviewed to ensure their adequacy. If
found necessary the HAZOP study team then formulates necessary recommendations,
which may consist of improvement in procedures, changes in the hardware or
additional safety devices depending on the level of risk involved.
The above procedure is continued till all the nodes and deviations are completed. All
the recommendations of the HAZOP study are compiled into an action report. These
recommendations need to be further subjected to engineering review and
management approval before implementation.
The HAZOP study procedure is illustrated in the following diagram.
4.2 HAZOP study for the HPCL LPG storage and Bottling Plant at PATNA was conducted by
EQMS during the period 13th September, 2016 to 14th September, 2016. The HAZOP
study team consisted of the following members:
EQMS
1. Mr. Tarun Kanti Roy –Head, Process Safety Consultant, EQMS, Delhi
HPCL LPG PLANT, PATNA
1. Mr. Anil Kaushik – Sr. Plant Manager, HPCL LPG Plant, Patna (Arrah)
2. Mr. Amar Kumar - Manager (Projects), HPCL Patna LPG Plant.
3. Mr. Hari Prasad Guchait - Dy. Manager (Projects) HPCL LPG Patna.
4. Mr. Rakesh Kumar Singh –Safety Officer- HPCL LPG Plant Patna.
The HAZOP WORKSHEET was further reviewed by above Official of HPCL PATNA LPG
Bottling plant thoroughly, for finalizing the worksheet and recommendations.
4.3 The following points are to be noted regarding the deviations, causes, consequences,
safeguards and recommendations considered in the HAZOP study.
Deviations:
A master list of deviations is used for the HAZOP study. For each Node, the
appropriate deviations are selected from this master list and included in the
worksheets. Deviations which are not applicable or those without significant
consequence are indicated in the worksheet.
Causes:
Causes are generally identified within the limits of the Node. However, care is taken to
consider consequences within and outside the Node. This procedure minimizes
repetition without limiting the coverage in HAZOP study.
Most often the cause for deviations such as more flow, less/no flow, high level, low
level etc. is malfunction of basic process control. Malfunction may occur in the
transmitter or control valve.
Control valve malfunction may lead to more opening, less opening or closing of the
valve. However, the transmitter which functions normally will generate necessary
alarm.
If the deviation is due to malfunction of transmitter, the control valve will move to the
wrong position (more open or less open), but alarm generated by the transmitter will
not be available, as the transmitter has malfunctioned.
Therefore, only the more opening or closing/ less opening of control valve due to
transmitter malfunction is recorded as cause for the deviation in HAZOP worksheet.
Other causes such as pump stoppage, blockage etc. are also recorded.
Consequences:
Though causes are considered within a Node, consequences applicable within and
outside the Node are taken into account. Due care is taken to identify hazardous
consequences such as leak, fire, explosion, toxic release, injury etc.
Safeguards:
The safeguards considered are as follows:
Equipment design features including design pressure, design temperature,
material of construction, etc, as per OISD-150
Process control instrumentation (unless the malfunction of the instrument is
the cause for the deviation)
Safety relief valve
Dyke containment systems
Procedural controls (SOP, operating instructions, checklists, periodic analysis,
testing etc.)
Process Alarms:
Alarms generated in the control system are normally considered as safeguards unless
the alarm is generated by the transmitter, malfunction of which is cause for the
deviation. Modern control systems have provision to configure high & low alarms for
all parameters.
The alarm system is to be carefully defined to avoid excessive alarm overload which
may cause problem to the operator during plant upset conditions. Alarms should be
provided only when there is well-defined operator response to the alarm and
sufficient time is available for corrective action. The alarm system definition is to be
carried out at appropriate stage of detailed engineering.
In this HAZOP study, the availability of transmitters with indication in control system is
understood to provide necessary alarm function.
General:
The HAZOP study is based on the following premise:
The plant will have effective process safety management system including
process safety information, MSDS, operation & maintenance manuals, safety
work permit system, inspection/ testing procedures, training, procedures for
modification, incident reporting & investigation, periodic safety audits.
4.4 The piping and instrumentation diagrams (P&IDs) were considered for this HAZOP
study are listed in the Table below.
4.5 All the lines and equipment in the sections are covered in HAZOP Nodes.
4.6 The summary of recommendations arising out of the HAZOP study is presented in the
next chapter.
Detailed Hazop study work sheets are enclosed in Annexure – 1.
P&I Diagrams with Nodes marked are enclosed in Annexure – 2
Hazop Attendance Sheet are enclosed in Annexure-3
5.1 The recommendations arising out of the HAZOP study are summarized in the following
Section. Remarks explaining the purpose of the recommendation are indicated for
each recommendation for ready reference.
It is to be noted that implementation of the HAZOP study recommendations should be
preceded by thorough engineering and management review and approval procedures.
5.2 Summary of HAZOP study recommendations
(a) The proposed Mounded Bullets of 500 MT each should be erected and
installed strictly as per the design and safety standard mentioned in OISD-150.
(b) A control room provides an effective centralized control system in the plant. It
is recommended to provide a proper control room in the plant area for housing
the instrument panels, alarms from fire & gas detection system, emergency
push button and communication equipment.
(c) Recommendation mentioned as per the Nodes as mentioned below.
Node 101: Liquid LPG from Road Tanker to LPG Bullet
(1) Before start of unloading of LPG tanker, the position of Manual vent valve/ Pop
action vent Valve should be checked. This should be included in SOP.
(2) Earthing strips made of Copper jumper strips are to be provided across flanges
to avoid hazard from static charge accumulation in piping and LPG storage tank
( OISD-144- 6.15-viii) Regular checking of resistance of earthing connections
and earth pits are to be made and a record is to be maintained
(3) The design vapor pressure of the bullet should be 14.5 Kg/cm2g (1.42 MPA) at
the top of the vessel (as per IS : 4576 or IS :14861 ) at 55 0C.- OISD-150 -5.1(iii)
(4) Continuous monitoring of Roto gauge Level indicator should be done during
unloading of LPG from LPG Road Tanker
(5) Pressure Safety valve/ PSV is to be provided at compressor discharge suitably
(6) The testing of each Pressure safety valve of compressor discharge line should
be done once in a year
(7) Design pressure of LPG tanker and set pressure of SRV at compressor
discharge is to be checked
(8) It is to be ensured that LPG unloading arm fitted with tanker shall be provided
with breakaway couplings. Only approved type Loading arm shall be of
provided and be tested as per OEM recommendations (OISD-144-6.3)
(9) Thermal Pressure relief valve provided in long pipes 80-LPG-l-131-A should be
checked regularly.(-OISD-144-9.5.5/e and also OISD-STD-132 on "Inspection of
Pressure Relieving Devices)" valve is to be provided in long pipes having
isolation valves at both ends (OISD-144-6.9)
(25) One Push Bottom as provided in Tanker unloading area should be provided in
Bullet area also, so that any leakage from the flange connection can be taken
care immediately
(26) The flange joints of the valves used in LPG system shall either have spiral
wound metallic gaskets or ring joints (OISD-144-6.2.2 )
(27) Sight Glass has been provided in the LPG unloading line to see flow of LPG to
Bullet. There is every possibility of breakage of side glass and LPG liquid may
spill at nearby area which may create fire and explosion. Generally this side
glasses are used to see the flow. Though In P&D Side Glass has not shown .But
if the sight glass have been kept and it breaks then somebody with all safety
measure has to go to the top of the Tanker to close the Tanker outlet Valve
which may be unsafe for the operator who will attend the leakage.
Management may review the provision of Side glass in pipelines.
Node: 102 -LPG Vapor from LPG Bullet to Suction of LPG Vapor Compressor
(28) Pressure Indication at Compressor suction and discharge does not shown in the
P&ID. Pressure indicator is to be provided at the suction and discharge side of
each Compressor
(29) One Alarm May be provided in Compressor House to actuate at the time of low
suction/ discharge pressure of Compressor. The working of Alarm should be
checked regularly.
(30) Pressure safety valve testing should be incorporated in maintenance
schedule.PSV should be tested once in year (OISD-144-9.5.5.e)
(31) Temperature indicator in Cooling water line should be provided
(32) Regular checking at a definite interval should be made, for activation of
Sprinklers with the help Quartz bulb and Deluge Valve for LPG compressor area
and road tanker area
(33) Specify procedure is to be made for keeping valve at before the PSV always
open & Locked, except when the PSV is removed for maintenance
(34) During any maintenance job in any flange of liquid /vapor line, the area should
not have ignition source near the flange. The line is to be purged properly with
the help of Nitrogen. Spark proof tools should be used during opening of the
flange. The safe opening procedure and procedure for attending maintenance
job should be specified in SOP.
(35) Presently no Nitrogen Connection is available at PATNA Plant. Generally
Nitrogen Cylinders are used to purge the vapor line in LPG plant. One nozzle
with valve for Nitrogen connection in the Bullet should be made permanently,
so that Nitrogen hose can be connected from the Nitrogen Cylinder to purge
the Bullet. The Nozzle should have double isolation valves, NRV and spectacle
blind. So Nitrogen Cylinders are to be arranged
(36) PSSR system should be followed for first start up of new Mounded Bullets and
piping connection.
Node-104- Mounded LPG Bullets (LPG Storage Vessel)
(37) (a) The pressure indicator provided in the top of the Bullet should be based on
Differential pressure transmitter. (b) The set pressure of PSV should be 12.5
Kg/Cm2 g (Compressor normal discharge pressure is 11.0 Kg/Cm2)
(38) As per OISD-150 -8.1 Automatic fire detection and /or protection (Fixed)
system based on heat detection through thermal fuses/ quartz bulbs/ EP
detectors shall be provided above the each Bullet. Sensors shall be installed at
all critical places as mentioned in OISD-150-8.1
(39) As mentioned in OISD-150-4.1a.The area at the which, the location of
Mounded Bullet is made, should be cleaned completely from tree, stump, root,
bush, combustible material and other objectionable matter
(40) We may consider low pressure alarm in each Bullet to control low temperature
in Bullet as well as in connected piping.
(41) Regular checking of Sprinklers is to be done for their working on auto mode.
(42) Gas detectors are also to be checked regularly. A schedule is to be made in this
respect.
(43) As per OISD-144, 6.2.3, the storage vessel shall have minimum two
independent level indicators and one independent high level switch. High level
alarms shall be set at not more than 85% level of the volumetric capacity of the
vessel.
(44) High level switch shall be interlocked with closure of ROV and compressor
shutdown.
(45) In a different interval the LPG product should be tested (mainly presence of
Butane & Condensate)
(46) In a different interval the LPG product should be tested (mainly presence of
propane & Condensate)
(47) Written procedure for draining water from LPG bullet should be available, as
serious accidents may occur due to mal-operation for water draining from LPG
bullet. Water may freeze and block the line and valve. The arrangement
provided for draining water from bullet for safety is to be checked. Water
freezing in the drain pipe may prevent the valve from closing and LPG will be
released after the ice melts
(48) Specify procedure for keeping the valve at the outlet of PSV always open,
except when the PSV is removed for maintenance.
(49) Nitrogen connection (Nozzle for Connection) in liquid inlet line of each bullet
with double isolation valves, NRV and spectacle blind should be provided for
purging the system. Nitrogen Cylinders are to be arranged for safe purging of
Bullets
(50) To avoid external corrosion of Mounded Bullet, provision of cathode
protection system for mounded bullets is to be made.(OISDstandard-150
Annexure-I)
(51) Provision of instrument air receiver/ emergency power back up connection
during power failure. Instrument Air Compressor should take start immediately
through DG set.
(52) Nitrogen connection is to be made at LPG inlet Pipe to each bullet. Proper SOP
is to be made for attending start up & shut down of LPG Bullet system.
(53) Safety (HSE) is prime concern during handling of LPG. So for running LPG
handling system safely , always we have to check the following with respect to
OISD standards
Fire protection system
Spacing of equipment/ buildings
Access/ approach roads
Emergency response system
(54) Fire Protection System should always be in healthy condition. Particularly,
Fire water storage level
DG operated Fire Pumps on auto mode
Fire Hydrant net work
Fire sprinkler system on auto mode
All ROV in Auto mode.
Fire Extinguisher at proper place to extinguish small Fire
Node-105 - Liquid LPG from mounded Bullet to Suction of LPG Pump for LPG Bottling
Plant
(55) Minimum circulation line should be provided in all Liquid LPG centrifugal
Pumps.
(56) One Pressure Gauge should be provided in suction line of the pump also.
(57) Low Suction Pressure Alarm in the Pump Suction should be provided
(58) ROV has been provided in liquid line at the out let from the Bullet to LPG
Pump. So before start up of LPG pump it is should be ensured that the
connected ROV is kept open.
(59) ROV operation signal should be provided in Pump and Compressor panel.
Proper SOP should follow before start of Pump
(60) Alarm at high discharge pressure of LPG pumps may be provided at Pump
panel / Control room.
(61) Auto bypass valve should be provided in Manual Cylinder filling section also.
(62) Check adequate provision for isolation, depressurization & purging of pumps
before maintenance. Check provision of lifting & handling arrangement for
pumps & motors during maintenance of Pumps and Compressors.
(63) During any leakage of LPG liquid, the Operator should be trained to handle
emergency in the plant. They should be expertise in closing of ROV in the liquid
line manually during any failure of/leakage in LPG line, so that system may be
made safe.
(64) Proper SOP should be followed before starting of Pump. A pressure switch
actuating a low pressure alarm in control room and locally shall be provided,
taken from discharge end OISD 144 6.6 .V
(65) Pressure Switch has been provided in the local Panel provided in Pump
Building. Alarm due to high pressure in Liquid LPG Pump discharge is also
should be provided in Pump operating Panel and also should be available in
Pump Building.
------------------------------------x----------------------------------------------
6. List of Abbreviations
1. API American Petroleum Institute 30 NFPA National Fire Protection
Association
2 ASME American Society of Mechanical 31 NRV Non Return Valve
Engineers
3 BLEVE Boiling liquid expanding vapor 32 OHSMS Occupational Health & Safety
explosion Management System
4 DG Diesel Generating Set 33 OISD Oil India Safety Directorate
5 DCS Distributed Control System 34 PA Pressure Alarm- Low/ High
6 DMP Disaster Management System 35 PI Pressure Indicator
7 DPT Dye Penetration Test 36 PLC Programmed Logical
Controller
8 EMS- Environment Management 37 PHAST Process Hazard Analysis
System Software Tool
9 EQMS Environment Quality 38 PESO Petroleum and explosive safety
Management System Limited organization
10 E&P Exploration & Production 39 PNGRB Petroleum & Natural Gas
Regulatory Board
11 FIC Flow Indicator Controller 40 PSV Pressure Safety Valve
12 FC Flow Controller 41 PS Pressure Switch- Low-Low/
Low/ High
13 HAZOP Hazards and Operatibility Study 42 QMS Quality Management System
ANNEXURE – 1
Contents
Node No. Node Description Page No.
103 LPG Vapor from LPG Vapor Compressor discharge to LPG Road 19
Tanker
105 Liquid LPG from mounded Bullet to Suction of LPG Pump for 32
LPG Bottling Plant
106 Liquid LPG from LPG Pump Discharge to LPG Bottling Plant 37
Page 2 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 101 Liquid LPG from Road Tanker to LPG Mounded Bullet DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent Unloading of Liquid LPG from LPG Road Tanker’s Bay (No-1 toNo-12)into Mounded Bullets (1,2,3,4&5)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
No/ Less Flow Low pressure in tanker due Low filling rate in LPG Monitoring of tanker
to Compressor C-1,C-2&C- Bullets level during unloading
3 malfunction/ running in (Roto Gauge provided)
low load Standby Compressor
Excess flow check valve Low filling rate in LPG provided
Provided in individual Bullet
tanker vapor inlet line Sight Flow Indicator
might have stuck close (SFI)/sight glass in
One Gate Valve Provided Liquid LPG tanker
after NRV with individual unloading line
tanker out let LPG liquid
line might have closed
(a)Manual Vent provided in Loss of LPG in vent. Gas leakage detector Before start of unloading of Check safe
the Tanker Liquid out let Fire hazard provided. LPG tanker, the position of the location of
line header just before Pop Action Vent valve should outlet from
individual unloading arm be checked. This should be vent valve in
might have opened. included in SOP.(R-01) LPG line.
ROV provided in Tanker Delay in tanker Sight Flow Indicator
Liquid LPG out let header unloading (SFI) in LPG tanker
(8.0” header) might have High level in Tanker at unloading line.
closed the end of unloading Level gauge provided
Page 3 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 101 Liquid LPG from Road Tanker to LPG Mounded Bullet DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent Unloading of Liquid LPG from LPG Road Tanker’s Bay (No-1 toNo-12)into Mounded Bullets (1,2,3,4&5)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
in tanker (Roto gauge).
More Flow Compressor discharge Possible accumulation Earthing of tanker, Earthing strips made of Copper Regular
pressure increased (More of electrostatic charge. bullet and piping. jumper strips are to be checking of
pressure difference between Ignition hazard Sight Flow Indicator provided across flanges to resistance of
tanker and bullet) (SFI) in LPG tanker avoid hazard from static charge earthing
unloading line to accumulation in piping and connections
Two Compressor might be monitor liquid flow. LPG storage tank ( OISD-144- and earth pits
running Excess flow check 6.15-viii) (R-02) and a record
valve has been The design vapor pressure of is to be
provided on the Tanker the bullet should be 14.5 maintained.
discharge Unloading Kg/cm2g (1.42 Mpa) at the
arm after Site Glass. top of the vessel (as per IS :
Compressor discharge 4576 or IS :14861 ) at 55 0C.-
pressure is set at 11.0 OISD-150 -5.1(iii) (R-03)
Kg/cm2g but high
discharge pressure
Trip has been set at
12.0 kg/cm2g.
Reverse Flow Low pressure in tanker and Over filling of tanker by Roto gauge has been Continuous monitoring of Roto
high pressure in bullet. reverse flow of LPG provided in the Road gauge Level indicator should be
from bullet. Tanker done during unloading of LPG
Page 4 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 101 Liquid LPG from Road Tanker to LPG Mounded Bullet DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent Unloading of Liquid LPG from LPG Road Tanker’s Bay (No-1 toNo-12)into Mounded Bullets (1,2,3,4&5)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
Fire/ explosion hazard NRV provided in the from LPG Road Tanker.(R-04)
due to leakage from Liquid LPG out let
tanker 3.0” line.
Higher Excess pressurization by Potential damage of Two Safety Valves Pressure Safety valve/ PSV is
Pressure in compressor tanker due to provided on the tanker to be provided at compressor
Tanker overpressure. Compressor will trip at discharge suitably(R-05)
The leakage in 12.0 kg/cm2g. The testing of each Pressure
unloading arm due to . safety valve of compressor
high pressure discharge line should be done
Fire/ explosion hazard once in a year (R-06)
due to leakage from Design pressure of LPG tanker
tanker and set pressure of PSV at
compressor discharge is to be
checked (R-07)
It is to be ensured that the LPG
unloading arm fitted with
tanker shall be provided with
breakaway couplings. Only
approve type Loading arm
should be provided for
unloading of LPG from the
Road Tanker and should be
Page 5 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 101 Liquid LPG from Road Tanker to LPG Mounded Bullet DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent Unloading of Liquid LPG from LPG Road Tanker’s Bay (No-1 toNo-12)into Mounded Bullets (1,2,3,4&5)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
tested as per OEM
recommendations.
(OISD-144-6.3)
(R-08)
High Pressure Inlet gate valve provided Overpressure in piping Compressor will Trip Thermal Pressure relief valve .
in Liquid LPG for individual Bullet is due to thermal at 12.0 kg/cm2g. no.-1102 provided in long
discharge line closed expansion of trapped Pressure gauge & pipes line header should be
ROV in liquid outlet 8.0 liquid. safety relief valve checked regularly.(-OISD-144-
inches header line as well Fire hazard due to provided on tanker 9.5.5/e and also OISD-STD-
just before entry to bullet leakage from pipe Thermal Pressure relief 132 on "Inspection of Pressure
might have closed flange etc. valve N0-1102 has Relieving Devices)" (R-09)
Any of two Gate Valves been provided in long Set point of tripping of Comp.
provided in the Liquid pipes line header should be checked
discharge line after (OISD-144-6.9) (R-10)
Unloading Arm is closed.
LPG liquid blocked in pipe
between closed two
isolation valves
Lower Less pressure in tanker due Refer to No/ Less Flow
Pressure to malfunction in the
compressor.
Refer to No/ Less Flow
Page 6 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 101 Liquid LPG from Road Tanker to LPG Mounded Bullet DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent Unloading of Liquid LPG from LPG Road Tanker’s Bay (No-1 toNo-12)into Mounded Bullets (1,2,3,4&5)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
Higher High ambient temperature Higher pressure is The tanker design As per OISD 144, clause 6.2.1
Temperature in summer season will be created in tanker due to pressure as per OISD (iv) maximum vapor pressure
approx. Max. 480C. high environment temp. The ambient of LPG at 55C is 16.9
Possible leakage of temperature remains kg/cm2g. Tanker should be
LPG. quite below the designed accordingly(R-11)
Fire hazard. temperature 550C as One Study is to be carried out
specified by OISD-144 by a reputed Electrical
clause 6.2.1(iv). Consultant for the
So vapor pressure in improvement in effectiveness
the tanker remains of Lighting Arrestor provided
within design limit. in Plant area (R-12)
Less Flow due to Delayed emptying of In summer season,
equalization of pressure the tanker compressor will trip at
developed in bullet as well LPG vapor temperature
tanker during summer of 90 degree Celsius.
season
External fire High pressure in tanker. PSV provided on the Water sprinkler system
Potential BLEVE Tanker. (automatic) should be in
hazard. Two PSV in each working condition at the tanker
High pressure in bullet Bullet are provided on loading area and also in Bullet
due to entry of warm the top of the each area. A regular periodic check
LPG from the road bullet. should be carried out. (OISD-
Page 7 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 101 Liquid LPG from Road Tanker to LPG Mounded Bullet DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent Unloading of Liquid LPG from LPG Road Tanker’s Bay (No-1 toNo-12)into Mounded Bullets (1,2,3,4&5)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
tanker. Gas detector provided. 150-8.1) (R-13)
Automatic sprinklers
for domes of LPG
bullets as well as for
Tanker area will be
activated by quartz
bulbs
Lower Depressurization of Cooling of equipment/ Equipment and piping Data sheets for design
Temperature equipment/ piping piping to temperature designed for (-) 27C. temperature of (-) 27C is to be
containing liquid LPG below (-) 20C by verified for new Bullet. (R-14)
through vent line. flashing of LPG liquid.
Possible brittle fracture.
Lower Level Less quantity of LPG Fire hazard due to LPG Weighment of tanker.
(LPG Tanker) received in tanker. Possible leak in tanker.
leakage in tanker.
Impurity Water in LPG tanker Corrosion in LPG Provision for draining Procedure for taking sample
(contamination in product) piping and storage tanks water from LPG from tanker to be checked with
due to water. storage tanks. proper PPE.(R-15)
Procedure for checking
quality of LPG
received is done
regularly & followed.
Page 8 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 101 Liquid LPG from Road Tanker to LPG Mounded Bullet DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent Unloading of Liquid LPG from LPG Road Tanker’s Bay (No-1 toNo-12)into Mounded Bullets (1,2,3,4&5)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
Utility Failure Power failure Compressor C-1/C-2/ DG sets of 380 KVA, Provision is to be made to start
C-3 will stop. No 400KVA & 125 KVA the Air Compressor
transfer of Liquid LPG has been provided and immediately after starting the
from tanker to bullet. further 500 KVA DG set on power failure. This is
All ROVs will close due capacity one new DG to provide air to operate
to stoppage of Air set will be provided in ROVs.(R-16)
Compressor the plant.
Start-up/ Shut- Improper connection of Delay in LPG tanker Operating manual is Proper SOP is to be made for
down LPG unloading arms with unloading. available. startup & shutdown of LPG
tanker valves Possible leakage of system (R-17)
LPG. Valves /PSVs ROVs are to be
numbered in P&ID for
reference in SOP (TSV
provided in the system has been
numbered.)(R-18)
Maintenance Incomplete isolation and Injury to personnel During attending any The
incomplete purging of LPG (cold burn). maintenance job at Road tanker requirement
from equipment/ piping LPG leakage. liquid and vapor line, Proper for providing
Fire/ explosion hazard. isolation, purging & permit blinds to
system should be incorporated ensure
in SOP (R-19) positive
Page 9 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 101 Liquid LPG from Road Tanker to LPG Mounded Bullet DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent Unloading of Liquid LPG from LPG Road Tanker’s Bay (No-1 toNo-12)into Mounded Bullets (1,2,3,4&5)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
Regular external inspection isolation for
and compressive inspection of safe
LPG Pipe line should be made maintenance
as per guide line given in is to be
OISD-144--9.5.3 (ii)&(iii) assed..
(R-20)
Leakage Leakage in LPG Unloading LPG release during Immediately To avoid leakage in Unloading .
Arm tanker unloading compressor will be arm, Periodic inspection/ leak
Fire/ explosion hazard stopped manually. testing and maintenance of
Gas detector is there Unloading Arm should be
which will send Signal carried out Periodically.
to Gas detector panel. (R-21)
During excess flow of
LPG from Tanker,
Excess flow check
valve in liquid outlet of
tanker will stop the
flow.
Movement of vehicle Fire/ explosion hazard SOP for LPG tanker To take immediate action
during LPG unloading. due to LPG release unloading during any leakage in Road
Tanker’s liquid outlet line,
Provision of manual emergency
Page 10 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 101 Liquid LPG from Road Tanker to LPG Mounded Bullet DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent Unloading of Liquid LPG from LPG Road Tanker’s Bay (No-1 toNo-12)into Mounded Bullets (1,2,3,4&5)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
isolation valve at tanker outlet
should be considered.
(R-22)
During unloading time of LPG
from LPG Tanker, a temporary
Barriers should be placed on
both sides of LPG tanker to
prevent vehicle movement
during unloading
(R-23)
Corrosion in tanker/ piping LPG leakage from the LPG gas sensor system Periodical checking of Push The
LPG tanker or piping provided in Tanker - Bottom working should be checking of
Fire/ explosion hazard unloading area near made for observing working of valid
liquid line connection. Emergency Shutdown inspection
One Push button has Interlocks (R-24) certificate
been provided in for tanker
Tanker area for should be
emergency shutdown included in
Periodic testing & SOP
inspection of tanker.
Corrosion in Pipe line. LPG leakage from the - One Push Bottom as provided
pipe line in-between in No-1Tanker unloading area
Page 11 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 101 Liquid LPG from Road Tanker to LPG Mounded Bullet DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent Unloading of Liquid LPG from LPG Road Tanker’s Bay (No-1 toNo-12)into Mounded Bullets (1,2,3,4&5)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
Tanker and Bullet should be provided in No-4 as
(approximately well Tanker outlet area also, so
200meter that during any leakage from
Fire/ explosion hazard the flange connection can be
taken care immediately.
(R-25)
Failure of gasket in flange The flange joints of the valves
joint used in LPG system shall either
have spiral wound metallic
gaskets or ring joints (OISD-
144-6.2.2)
(R-26)
Breakage of sight glass in There is every possibility of
LPG unloading line breakage of side glass and LPG
liquid may spill at nearby area
which may create fire and
explosion. Here in the P&ID
the Side glass has not been
shown.
Generally this side glass is used
to see the flow of LPG from
Tanker. But if it breaks then
Page 12 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 101 Liquid LPG from Road Tanker to LPG Mounded Bullet DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent Unloading of Liquid LPG from LPG Road Tanker’s Bay (No-1 toNo-12)into Mounded Bullets (1,2,3,4&5)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
somebody has to close the
Tanker outlet valve. So this
Side glass should be used and
should be removed from the
line. The Mgt. should review
it.(R-27)
Node: 102 LPG Vapor from LPG Bullet to Suction of LPG Vapor Compressor DRG NO : -P1-PC105-9512-0020-
C-1/C-2/C-3. Sheet 1/1 -Revesion-04
Design Intent To pressurize tanker with LPG vapor from bullet through Vapor Compressor (Suction of Compressor)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
No/ Less Flow Less flow of the vapor from Possible negative Compressor will Trip Pressure Indication at
of Vapor from the Bullet. pressure in bullet if in low suction pressure Compressor suction and
Bullet top to Liquid level in Knock out compressor continues to (1.0 kg/cm2) discharge does not shown in the
LPG drum may be high and operate with low suction Pressure indicator P1- P&ID. Pressure indicator is to
Compressor obstructing gas to come out pressure. 1101 provided at the be provided at the suction and
top of the Knock out discharge side of each
drum.. Compressor.
Pressure switch in the (R-28)
Compressor Suction.
Page 13 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 102 LPG Vapor from LPG Bullet to Suction of LPG Vapor Compressor DRG NO : -P1-PC105-9512-0020-
C-1/C-2/C-3. Sheet 1/1 -Revesion-04
Design Intent To pressurize tanker with LPG vapor from bullet through Vapor Compressor (Suction of Compressor)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
Level gauge has been
provided which will
indicate liquid level in
the knock-out drum
High level alarm has
been provided in Knock
Out Drum.
ROV-provided in suction Stoppage of LPG Vapor One Alarm has been An Alarm has been provided in
line (just in outlet of Bullet) flow to suction of the provided in Compressor House to actuate at
may have been closed. compressor and finally Compressor House the time of low suction/
stoppage of flow of which will be actuated discharge pressure of
vapor to tanker. at the time of low Compressor. The working of
Flow of liquid LPG to suction/ discharge Alarm should be checked
Bullet will stop. pressure of Compressor regularly
(R-29)
More Flow of Excess pressurization by Potential damage of Compressor will trip at Pressure safety valve testing Check the
Vapor from compressor tanker due to 12.5 kg/cm2g. should be incorporated in Design
the Bullet to overpressure. Leakage Pressure safety valve maintenance schedule.PSV pressure of
LPG Tanker. of LPG. Fire hazard. PSV-has been provided should be tested once in year LPG tanker
at compressor (OISD-144-9.5.5.e) and set
discharge. PSV will (R-30) pressure of
Page 14 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 102 LPG Vapor from LPG Bullet to Suction of LPG Vapor Compressor DRG NO : -P1-PC105-9512-0020-
C-1/C-2/C-3. Sheet 1/1 -Revesion-04
Design Intent To pressurize tanker with LPG vapor from bullet through Vapor Compressor (Suction of Compressor)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
work on 13.0 kg/cm2g PSV at an
interval of
one year.
Low Suction Any of the gate Valve Stoppage of LPG Vapor Compressor will Trip
Pressure provided after Bullet outlet flow to suction of the in low suction pressure
in Compressor up to suction valve of the compressor and finally (1.5 kg/cm2)
Compressor may have been stoppage of flow of Pressure indicator in at
be closed vapor to tanker due to the top of the Knock
low suction pressure of out drum..
Knock out Drum vent might Compressor. Pressure indicator and
Have opened. Flow of liquid LPG to pressure switch
Bullet will stop. provided in the
Compressor suction.
Node: 102 LPG Vapor from LPG Bullet to Suction of LPG Vapor Compressor DRG NO : -P1-PC105-9512-0020-
C-1/C-2/C-3. Sheet 1/1 -Revesion-04
Design Intent To pressurize tanker with LPG vapor from bullet through Vapor Compressor (Suction of Compressor)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
water line Regular checking at a definite
interval should be made, for
activation of Sprinklers ( in
case of Fire) with the help
Quartz bulb and Deluge Valve
for LPG compressor area and
road tanker area (R-32)
Low No issue
Temperature
Composition/ Refer to Node 101
Impurity
Maintenance Incomplete isolation and Fire hazard/ injury due One isolation valves, Specify procedure is to be made Proper SOP
purging of system before to release of LPG from ROV and NRV in for keeping valve at before the is to be
starting maintenance work bullet vapor outlet and vapor line /from top of PSV always open & Locked, made.
in Compressor. suction of LPG each bullet except when the PSV is
Flange leakage Compressor One isolation valves for removed for maintenance
each PSV on the top of (R-33)
Knock out drum in the The flange joints of the valves
suction of the used in LPG vapor system shall
compressor either have spiral wound
Two PSV (Pressure metallic gaskets or ring Joints
safety Vent) along with (OISD-144-6.2.2) (Same as -R-
Page 16 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 102 LPG Vapor from LPG Bullet to Suction of LPG Vapor Compressor DRG NO : -P1-PC105-9512-0020-
C-1/C-2/C-3. Sheet 1/1 -Revesion-04
Design Intent To pressurize tanker with LPG vapor from bullet through Vapor Compressor (Suction of Compressor)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
one isolation valve in 26)
each PSV provided on During any maintenance job in
the top of each Bullet any flange of liquid /vapor line,
Double Isolation Valve the area should not have
for each Bullet drains ignition source near the flange.
line. The line is to be purged
properly with the help of
Nitrogen. Spark proof tools
should be used during opening
of the flange. The safe opening
procedure and procedure for
attending maintenance job
should be specified in SOP.
(R-34)
Start-up Incomplete removal of air Forming Explosive During commissioning, Presently no Nitrogen
from LPG vapor line during Mixture inside the the new vessel after all Connection is available at Patna
start-up of newly Bullet. testing is completed; Plant. Generally Nitrogen
commissioned vessel the Bullet is filled with Cylinders are used to purge the
water. Then gradually vapor line in LPG plant. One
LPG is introduced & nozzle with valve for Nitrogen
water is removed from connection in the Bullet should
the drain line of the be made permanently, so that
Page 17 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 102 LPG Vapor from LPG Bullet to Suction of LPG Vapor Compressor DRG NO : -P1-PC105-9512-0020-
C-1/C-2/C-3. Sheet 1/1 -Revesion-04
Design Intent To pressurize tanker with LPG vapor from bullet through Vapor Compressor (Suction of Compressor)
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
vessel. This way the Nitrogen hose can be connected
complete vessel is from the Nitrogen Cylinder to
being purged with LPG purge the Bullet. The Nozzle
should have double isolation
valves, NRV and spectacle
blind. So Nitrogen Cylinders are
to be arranged.(R-35)
PSSR system should be
followed for first start up pipe
Hydro-test is carried lines of new Mounded
out for testing vessel. Bullets(R-36)
Then LPG vapor is
taken in the vessel &
connected in the
pipeline for purging the
vessel.
Leakage Flange leak in LPG vapor Fire/ explosion hazard LPG Gas Sensor The flange joints of the valves
pipe due to LPG release. Excess flow check used in LPG system shall either
valve in each have spiral wound metallic
connection to bullet. gaskets or ring Joints (OISD-
144-6.2.2)(Same as R-26)
Page 18 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 103 LPG Vapor from LPG Vapor Compressor discharge to DRG NO : -P1-PC105-9512-0020- Sheet 1/1
LPG Road Tanker Revesion-04
Design Intent To pressurize tanker with LPG vapor from bullet through Vapor Compressor discharge for LPG unloading
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
No/ Less Flow Less flow of the vapor from Possible negative Compressor will Trip
of Vapor to the Bullet. pressure in bullet if in low suction pressure
LPG Tanker Liquid level in Knock out compressor continues to (1.5 kg/cm2)
after drum may be high and operate with low suction Pressure indicator in
compressor obstructing gas to come out pressure. Vapor line entering the
discharge Tanker.
Pressure indicator in
the Compressor
discharge.
Level gauge has been
provided which will
indicate liquid level in
the knock-out drum
High level alarm has
been provided in Knock
Out Drum.
ROV-provided in suction Stoppage of LPG Vapor . One Alarm May be provided in It is
line may have been closed. flow to suction of the Compressor House to actuate recommende
compressor and finally at the time of low discharge d to provide
stoppage of flow of pressure of Compressor a process
vapor to tanker. (Same as R-29) control room
Flow of liquid LPG to attached to
Page 19 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 103 LPG Vapor from LPG Vapor Compressor discharge to DRG NO : -P1-PC105-9512-0020- Sheet 1/1
LPG Road Tanker Revesion-04
Design Intent To pressurize tanker with LPG vapor from bullet through Vapor Compressor discharge for LPG unloading
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
Bullet will stop. security
where
process
safety in
charge can
sit operate
and monitor
all the
process
parameter
More Flow of Excess pressurization by Potential damage of Compressor will trip at Check the
Vapor to LPG compressor tanker due to 12.0 kg/cm2g. Pressure safety valve testing Design
Tanker. overpressure. Leakage Pressure safety valve (once in a year) should be pressure of
of LPG. Fire hazard. PSV-has been incorporated in maintenance LPG tanker
provided at schedule and set
compressor discharge (Same as –R-30) pressure of
PSV at
compressor
discharge is
to be
checked
High Pressure Any of the gate Valve The compressor will be Compressor will trip at
Page 20 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 103 LPG Vapor from LPG Vapor Compressor discharge to DRG NO : -P1-PC105-9512-0020- Sheet 1/1
LPG Road Tanker Revesion-04
Design Intent To pressurize tanker with LPG vapor from bullet through Vapor Compressor discharge for LPG unloading
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
In LPG outlet provided in the discharge of pressurized and may get 12.0 kg/cm2g. Pressure safety valve testing
line from compressor to the LPG damaged. Pressure safety valve should be incorporated in
vapor Tanker may be closed PSV-has been maintenance schedule
compressor to provided at (Same as R-30)
Tanker compressor discharge
Node: 103 LPG Vapor from LPG Vapor Compressor discharge to DRG NO : -P1-PC105-9512-0020- Sheet 1/1
LPG Road Tanker Revesion-04
Design Intent To pressurize tanker with LPG vapor from bullet through Vapor Compressor discharge for LPG unloading
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
starting maintenance work bullet to/from top of each PSV always open & Locked, made.
in Bullet & Compressor. bullet except when the PSV is
Flange leakage One isolation valves for removed for maintenance
each PSV on the top of (Same as -R-33)
Knock out drum in the The flange joints of the valves
suction of the used in LPG system shall either
compressor have spiral wound metallic
Two PSV (Pressure gaskets or ring Joints (OISD-
safety Vent) attached 144-6.2.2) (Same as R-26)
with one isolation valve During any maintenance job in
in each PSV on the top any flange of liquid /vapor line,
of each Bullet the area should not have
ignition source near the flange.
Double Isolation Valve The line is to be purged
for each Bullet drains properly with the help of
line. Nitrogen. Spark proof tools
should be used during opening
of the flange. The safe opening
procedure and procedure for
attending maintenance job
should be specified in SOP.
(Same as R-34)
Page 22 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 103 LPG Vapor from LPG Vapor Compressor discharge to DRG NO : -P1-PC105-9512-0020- Sheet 1/1
LPG Road Tanker Revesion-04
Design Intent To pressurize tanker with LPG vapor from bullet through Vapor Compressor discharge for LPG unloading
Remark/
Deviation Cause Consequence Safeguard Recommendation
Action
Start-up Incomplete removal of air Possible formation of Hydro-test is carried One nozzle with valve for
from LPG vapor line during explosive gas mixture in out for testing vessel. Nitrogen connection in the LPG
start-up LPG vapor line during Then LPG vapor is liquid pipe line to Bullet should
initial filling taken in the vessel & be made permanently, so that
connected Pipeline only Nitrogen hose can be connected
after purging the from the Nitrogen Cylinder to
system. LPG inlet pipe to purge the
Compressor discharge lines,
NRV and spectacle blind.(Same
as R-35)
PSSR system should be
followed for first start up pipe
lines of new Mounded Bullets.
(Same as R-36)
Leakage Flange leak in LPG vapor Fire/ explosion hazard LPG Gas Sensor The flange joints of the valves
pipe due to LPG release. Excess flow check used in LPG system shall either
valve provided in the have spiral wound metallic
pipeline before entry to gaskets or ring Joints (OISD-
tanker. 6.2.2)(Same as R-26)
Page 23 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 104 Mounded LPG Bullets (LPG Storage Vessel) DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent To store liquid LPG in mounded bullets at ambient temperature
Deviation Cause Consequence Safeguard Recommendation Remark/Action
No/ Less Flow Covered in Node 101
of liquid LPG to
Bullet
No/ Less Flow Covered in Node 102
of Vapor LPG
from Bullet
More Flow of Covered in Node 101
Liquid LPG to
Bullet
More flow of Covered in Node-102
Vapor from
Bullet
Reverse Flow of Covered in Node 101
liquid from
Bullet to Road
Tanker
Reverse flow of Covered in Node-102
Vapor to Bullet
Higher Pressure High vapor pressure Possible leakage due to Pressure indicator for (a) The pressure indicator
In Bullet of LPG in bullet overpressure in bullet. each bullet provided in the top of
Fire/ explosion hazard Two PSV in each Bullet the Bullet should be
provided on the top of based on Differential
the bullet. pressure transmitter
Page 24 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 104 Mounded LPG Bullets (LPG Storage Vessel) DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent To store liquid LPG in mounded bullets at ambient temperature
Deviation Cause Consequence Safeguard Recommendation Remark/Action
(b) The set pressure of
PSV should be 14.2
Kg/Cm2 g
(Compressor normal
discharge pressure is
11.0 Kg/Cm2 )
(R-37)
Exposure of LPG Increase in vapor Mounded construction As per OISD-150 -8.1
bullet to external fire. pressure of LPG in of LPG bullets not Automatic fire detection and
bullets. susceptible to BLEVE /or protection (Fixed) system
Weakening of vessel hazard. based on heat detection
shell at high Gas detector provided. through thermal fuses/ quartz
temperature (BLEVE Automatic sprinklers for bulbs/ EP detectors shall be
hazard) domes of LPG bullets provided above the each
activated by quartz Mounded Bullet. Sensors
bulbs shall be installed at all critical
System design as per places as mentioned in OISD-
OISD-144/ 150 150-8.1.(R-38)
standards. As mentioned in OISD-150-
4.1a.The area at the which,
the location of Mounded
Bullet is made, should be
cleaned completely from tree,
Page 25 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 104 Mounded LPG Bullets (LPG Storage Vessel) DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent To store liquid LPG in mounded bullets at ambient temperature
Deviation Cause Consequence Safeguard Recommendation Remark/Action
stump, root, bush,
combustible material and
other objectionable matter(R-
39)
Lower Pressure Depressurization of Possible failure of Design temperature (-) We may Consider low
bullet due to opening bullet shell/ piping by 27C to (+) 550C Pressure alarm in each Bullet
of PSV by cracking at low considering normal to control low temperature in
malfunction or temperature. boiling point of LPG. Bullet as well as in connected
leakage in vapor lines Standby PSV in each piping.(R-40)
Bullet
Higher Exposure of LPG Increase in vapor Mounded construction Regular checking of
Temperature bullet to external fire. pressure of LPG in of LPG bullets not Sprinklers is to be done for
bullets. susceptible to BLEVE their working on auto mode
Weakening of vessel hazard. (R-41).
shell at high Gas detector provided. Gas detectors are also to be
temperature (BLEVE Automatic sprinklers for checked regularly. A schedule
hazard) domes of LPG bullets is to be made in this respect
activated by quartz (R-42)
bulbs
System design as per
OISD-144/ 150
standards.
Lower Covered under Low
Page 26 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 104 Mounded LPG Bullets (LPG Storage Vessel) DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent To store liquid LPG in mounded bullets at ambient temperature
Deviation Cause Consequence Safeguard Recommendation Remark/Action
Temperature Pressure
Higher Level Excess filling of LPG Overfilling of bullet. Two level indicators for As per OISD-144, 6.2.3 The
in bullet due to LPG spillage. each bullet. storage vessel shall have
malfunction of level Fire/ explosion hazard. High level alarm from minimum two independent
indicator (incorrect separate level level indicators and one
level indication) transmitter for interlock independent high level switch.
to close ROV in LPG High level alarms shall be set
inlet line of each bullet. at not more than 85% level of
the volumetric capacity of the
vessel (R-43)
High level switch shall be
interlocked with closure of
ROV and compressor
shutdown.(R-44)
Lower Level LPG bullet empty No LPG supply to Other individual LPG
cylinder filling station Mounded bullets will
be available.
Composition/ Accumulation of Lower vapor pressure In a different interval the LPG
Impurity high-boiling in bullets. product should be tested
component (butane) in Possible cavitation in (mainly presence of Butane &
LPG. LPG pump due to low Condensate)
NPSH (R-45)
Accumulation of low- Higher vapor pressure In a different interval the LPG
Page 27 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 104 Mounded LPG Bullets (LPG Storage Vessel) DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent To store liquid LPG in mounded bullets at ambient temperature
Deviation Cause Consequence Safeguard Recommendation Remark/Action
boiling component in LPG bullets & less product should be tested
(propane) in LPG. heating value of LPG (mainly presence of propane
& Condensate) (R-46)
Accumulation of Adverse effect on Provision with double Written procedure for The arrangement
water in bullet quality of product (LPG valves for draining draining water from LPG provided for
filled in cylinders) water from bottom of bullet should be available, as draining water from
each bullet. serious accidents may occur bullet for safety is
due to mal-operation for water to be checked.
draining from LPG bullet. Water freezing in
the drain pipe may
Antifreeze gate valve to be prevent the valve
provided in drain line to from closing and
avoid accident caused when LPG will be
Water freeze and block the released after the
line and valve ice melts.
(R-47)
Maintenance Incomplete isolation Fire hazard/ injury due Double isolation valves Specify procedure for keeping Proper SOP is to be
and purging of system to release of LPG from with blind in LPG inlet valve at the outlet of PSV made.
before starting bullet line to top of each always open, except when the
maintenance work in bullet. PSV is removed for
Bullet Double isolation valves maintenance (R-48)
and NRV in vapor line
Page 28 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 104 Mounded LPG Bullets (LPG Storage Vessel) DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent To store liquid LPG in mounded bullets at ambient temperature
Deviation Cause Consequence Safeguard Recommendation Remark/Action
to/from top of each Nitrogen connection (Nozzle
bullet for Connection) in liquid inlet
Double isolation valves line of each bullet with double
with spectacle blind in isolation valves, NRV and
liquid outlet from spectacle blind should be
bottom of each bullet provided for purging the
Double isolation system. Nitrogen Cylinders
valves) for each PSV are to be arranged for safe
on LPG bullets purging of Bullets
Double Isolation Valve (R-49)
for each Bullet drains
line.
Leakage Corrosion inside Leak from pitting or Anti-corrosion painting
bullet due to crack in LPG bullet for bottom of LPG
contamination in LPG shell caused by internal bullet (internal).
from Tanker corrosion Periodic inspection of
bullet.
External corrosion in Leak from pitting in Protection against To avoid external corrosion of
bullet and piping. LPG bullet or piping external corrosion Mounded Bullet, provision of
caused by external (special cathode protection system for
corrosion coating).cathodic mounded bullets is to be
Protection provided. made.(OISDstandard-150
Annexure-I) (R-50)
Page 29 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 104 Mounded LPG Bullets (LPG Storage Vessel) DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent To store liquid LPG in mounded bullets at ambient temperature
Deviation Cause Consequence Safeguard Recommendation Remark/Action
Utility Failure Power failure No Supply of LPG to DG set provided for
Bottling Section. alternate power supply.
Instrument Air Failure All ROVs will close. Fail-safe position for Provision of instrument air
ROVs and control receiver/ emergency power
valves (fail-to-close) back up connection to
DG sets run on Auto Instrument Air Compressor
start mode.. during power failure.
Instrument Air Compressor
should take start immediately
through DG set. (R-51)
Problem in Incomplete removal Possible formation of Nitrogen connection is to be
Start-up LPG of air from LPG bullet explosive gas mixture made at LPG inlet Pipe to
Bullet during start-up in LPG bullet during each bullet.
initial filling Proper SOP is to be made for
attending start up & shut
down of LPG Bullet system
(R-52)
Incomplete Low temperature in All LPG bullets
pressurization of bullet due to flashing of connected to
bullet with LPG vapor LPG at low pressure Vapor balancing line.
before starting LPG
filling
Leakage Corrosion outside & Fire/ explosion hazard Corrosion protection To avoid external corrosion of
Page 30 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 104 Mounded LPG Bullets (LPG Storage Vessel) DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent To store liquid LPG in mounded bullets at ambient temperature
Deviation Cause Consequence Safeguard Recommendation Remark/Action
inside of LPG Bullet. due to LPG release coating inside bottom Mounded Bullet, provision of
LPG loss part of bullet. cathode protection system for
Special coating outside mounded bullets is to be
LPG bullet. made.(OISDstandard-150
Annexure-I) (Same as R-50)
Flange leak in bullet/ Fire/ explosion hazard ROV in each liquid and Only spiral wound metallic
LPG lines due to LPG release vapor line connected to gaskets or ring joints should
bullets. be used in all the flanges.(
Mounded bullet not OISD-150-6.4) (Same as R-
susceptible to BLEVE 26)
hazard.
HSE/ Safety (HSE) is prime
Regulatory concern during handling of
issues LPG. So for running LPG
handling system safely ,
always we have to check the
following with respect to
OISD standards
Fire protection system
Spacing of equipment/
buildings
Access/ approach roads
Page 31 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 104 Mounded LPG Bullets (LPG Storage Vessel) DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Revesion-04
Design Intent To store liquid LPG in mounded bullets at ambient temperature
Deviation Cause Consequence Safeguard Recommendation Remark/Action
Emergency response
system (R-53)
Fire Protection Fire Protection System should
System always be in healthy
condition. Particularly,
Fire water storage level
DG operated Fire Pumps
on auto mode
Fire Hydrant net work
Fire sprinkler system on
auto mode
All ROV in Auto mode.
Fire Extinguisher at
proper place to
extinguish small Fire (R-
54)
Node: 105 Liquid LPG from mounded Bullet to Suction of LPG DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Pump for LPG Bottling Plant Revesion-04
Design Intent To supply liquid LPG from bullets to Suction of LPG Pump for transferring LPG to LPG Bottling Plant.
Deviation Cause Consequence Safeguard Recommendation Remark/Action
No/ Less Flow Some obstruction in the Possible damage of LPG Pump will be Minimum circulation line
Page 32 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 105 Liquid LPG from mounded Bullet to Suction of LPG DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Pump for LPG Bottling Plant Revesion-04
Design Intent To supply liquid LPG from bullets to Suction of LPG Pump for transferring LPG to LPG Bottling Plant.
Deviation Cause Consequence Safeguard Recommendation Remark/Action
Suction of LPG Pump pump/ seal due to stopped due to should be provided in all
cavitation Low flow rate Liquid LPG centrifugal
04Kg/Cm2g Pumps.(R-55)
pressure Pump
will stop.
Stoppage of LPG pump. No LPG supply to Pressure gauge One Pressure Gauge should Review the functioning
cylinder filling station provided in be provided in suction line of cylinder filling
discharge line of the pump also. (R-56)
of the Liquid provided.
Pump.
Any of the gate valve No Flow of LPG Pressure gauge One Pressure Gauge should
provided in Suction and provided in be provided in suction line
Discharge line is closed discharge line of the pump also.(Same as
03 Way Valve provided in of the Liquid R-56)
the Suction line (250/150 Pump Low Suction Pressure
NB line to (350/250 NB Alarm in the Pump Suction
line) might have wrongly should be provided. (R-57)
closed. One ROV has been provided
Closure of ROV in the in liquid suction line (at the
Bullet outlet line out let from the Bullet to LPG
Strainer provided in Pressure gauge Pump). So before start up of
LPG pump, it is should be
suction of LPG Pump may provided in
ensured that the connected
be choked both the side of ROV is kept open. It should be
Page 33 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 105 Liquid LPG from mounded Bullet to Suction of LPG DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Pump for LPG Bottling Plant Revesion-04
Design Intent To supply liquid LPG from bullets to Suction of LPG Pump for transferring LPG to LPG Bottling Plant.
Deviation Cause Consequence Safeguard Recommendation Remark/Action
Strainer. included in SOP. (R-58
More Flow Both LPG pumps kept in High Discharge flow. Net Positive ROV operation signal
operation Suction Head should be provided in Pump
(E.g. during changeover Required and Compressor panel.
of pumps). (NPSHR) for a Proper SOP should follow
Excess flow of LPG in pump is before start of Pump.(R-59) Review safety
Carousel (Cylinder considered Alarm at high discharge provisions for over
filling area) due to during pump pressure of LPG pumps may pressure in the LPG line
malfunction of filling selection and be provided at Pump panel. before Cylinder filling.
scale layout. (R-60)
.. Auto bypass valve should
SRV / TRV will be provided in Manual
popp due to Cylinder filling section also.
high pressure (R-61)
Auto bypass
valve provided
in Cylinder
filling section at
Carousel.
Reverse Flow During Stoppage of pump Possible reverse flow NRV in pump .
Page 34 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 105 Liquid LPG from mounded Bullet to Suction of LPG DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Pump for LPG Bottling Plant Revesion-04
Design Intent To supply liquid LPG from bullets to Suction of LPG Pump for transferring LPG to LPG Bottling Plant.
Deviation Cause Consequence Safeguard Recommendation Remark/Action
from LPG filling system discharge line
into tank The minimum
circulation line
at pump
discharge taken
before NRV..
Lower Pressure Low level in bullet. Less quantity of Liquid Level indicators
Problem with LPG pump. LPG may go to in bullet.
Carousel. PG at pump
LPG filling will be discharge
affected. Other two
Bullets
available.
Higher Covered in Node 104
Temperature
Lower Covered in Node 104
Temperature
Lower Level Covered in Node 104
Impurity/ Covered in Node 104
Contaminant
Utility Failure Power failure Stoppage of LPG pump. DG set
No supply of LPG to available to take
carousel. loads for all
Page 35 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 105 Liquid LPG from mounded Bullet to Suction of LPG DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Pump for LPG Bottling Plant Revesion-04
Design Intent To supply liquid LPG from bullets to Suction of LPG Pump for transferring LPG to LPG Bottling Plant.
Deviation Cause Consequence Safeguard Recommendation Remark/Action
power
requirement.
Sampling
Maintenance Incomplete isolation of Injury to personnel (cold Adequate provision for Check provision of
LPG pumps for burn due to exposure to isolation, depressurization lifting & handling
maintenance. LPG). & purging of pumps before arrangement for pumps
Fire hazard due to LPG maintenance is to be & motors.
release. checked
(R-62)
Loss of Due to sudden failure of Fire & Explosion Gas sensor The Operator should be
containment/ Gasket or pipe line provided which trained to handle
Leakage will give alarm emergency in the plant.
at Security They should be expertise in
cabin and closing of ROV in the
Control room liquid line manually during
any failure of/leakage in
LPG line, so that system
may be made safe.(R-63)
Only spiral wound metallic
gaskets or ring joints
should be used in all the
Page 36 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 105 Liquid LPG from mounded Bullet to Suction of LPG DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Pump for LPG Bottling Plant Revesion-04
Design Intent To supply liquid LPG from bullets to Suction of LPG Pump for transferring LPG to LPG Bottling Plant.
Deviation Cause Consequence Safeguard Recommendation Remark/Action
flanges.( OISD-150-6.4)
(Same as R-26)
.
Start-up Start up after maintenance Leakage may persist due System of SOP for start Up should be
job. to poor maintenance Checking followed.
before start up
for any leakage.
Shut-down Proper Isolation
Proper Purging
Safety Work
permits.
Node: 106 Liquid LPG from LPG Pump Discharge to LPG Bottling DRG NO: -P1-PC105-9512-0020- Sheet 1/1.
Plant Revesion-04
Design Intent Transfer of LPG from LPG Pump to LPG Bottling Plant (Carousel).
Deviation Cause Consequence Safeguard Recommendation Remark/Action
No/ Less Flow Some obstruction in the Possible damage of Pump will be stopped .
Suction of LPG Pump LPG pump/ seal due to due to Low flow rate
cavitations Minimum circulation
Page 37 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 106 Liquid LPG from LPG Pump Discharge to LPG Bottling DRG NO: -P1-PC105-9512-0020- Sheet 1/1.
Plant Revesion-04
Design Intent Transfer of LPG from LPG Pump to LPG Bottling Plant (Carousel).
Deviation Cause Consequence Safeguard Recommendation Remark/Action
flow valve at pump
discharge
Stoppage of LPG pump. No supply of LPG to Pressure gauge
carousel. provided in the
discharge line of the
Liquid Pump.
NRV in the 80 NB Pressure gauge Proper SOP should follow
discharge line of the provided in discharge before start of Pump
Pump might have line of the Liquid One pressure gauge should be
choked( Common Pump provided
Discharge Header is in suction line of LPG Pump.(
100NB line) Same R-56)
Any of the Gate valve Pressure gauge Low Suction Pressure Alarm
provided in Suction and provided in both the is to be provided in the Pump
Discharge line might side of Strainer Suction
have closed One ROV has been provided in
Closure of ROV in the liquid suction line (at the out let
Bullet outlet line. Low Suction Pressure from the Bullet to LPG Pump).
Alarm in the Pump So before start up of LPG pump,
it is should be ensured that the
Strainer provided in discharge
connected ROV is kept open. It
suction of LPG Pump should be included in SOP
might have choked (same as R-58)
Page 38 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 106 Liquid LPG from LPG Pump Discharge to LPG Bottling DRG NO: -P1-PC105-9512-0020- Sheet 1/1.
Plant Revesion-04
Design Intent Transfer of LPG from LPG Pump to LPG Bottling Plant (Carousel).
Deviation Cause Consequence Safeguard Recommendation Remark/Action
More Flow Both LPG pumps kept High Discharge flow. Alarm at high Proper SOP should follow
in operation discharge pressure of before start of Pump.
(E.g. during changeover LPG pumps A pressure switch actuating a
of pumps). Net Positive Suction low pressure alarm in control
Due to high pressure in Fire\Explosion Head Required room and locally shall be
discharge line, the (NPSHR) for a pump provided, taken from
pipeline may fail and is considered during discharge end OISD 144 6.6
case high flow of LPG pump selection and .V . (R-64)
layout.
Pressure gauge is
available in discharge
line
Excess flow of LPG to SRV / TRV may
carousel due to Starting popped due to high Pop Action Valve is
of both the pumps pressure.. provided in the line
Reverse Flow Not Possible NRV provided in
Pump discharge line.
Higher Closing of ROV in the Discharge Pressure in Minimum flow Pressure Switch has been In future Alarm and
Pressure pump discharge line to the line before ROV circulation for LPG provided in the local Panel other operating
Carousel , will be high. pump. provided in Pump Building. parameter should be
Leakage in the Pump Alarm due to high pressure in shifted to a Control
Closing of any other discharge flange gasket Liquid LPG Pump discharge room.
valve available in the due to high pressure.. is also should be provided in
Page 39 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 106 Liquid LPG from LPG Pump Discharge to LPG Bottling DRG NO: -P1-PC105-9512-0020- Sheet 1/1.
Plant Revesion-04
Design Intent Transfer of LPG from LPG Pump to LPG Bottling Plant (Carousel).
Deviation Cause Consequence Safeguard Recommendation Remark/Action
pump discharge line Possible damage of Pump operating Panel also
upto Carousal may be pump seal. available in Pump
closed Fire hazard. Building.(R-65).
Lower Low level in bullet. Less quantity of Liquid Level indicators in .
Pressure Problem with LPG LPG may go to bullet.
pump. carousel.. PG at pump discharge
LPG filling will be Other two Bullets
affected. available.
Higher Exposure of LPG bullet Increase in vapor Mounded construction Regular checking of
Temperature to external fire causing pressure of LPG in of LPG bullets not Sprinklers for their working
of Liquid LPG high temperature of bullets. susceptible to BLEVE on auto mode.
liquid.. Weakening of vessel hazard. Gas detectors are also checked
shell at high Gas detector provided. regularly.
temperature (BLEVE Automatic sprinklers (same as R-32)
hazard) for domes of LPG
bullets activated by
quartz bulbs
System design as per
OISD-144/ 150
standards.
Lower Covered under Low
Temperature Pressure
Impurity/ Covered in Node 104
Page 40 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 106 Liquid LPG from LPG Pump Discharge to LPG Bottling DRG NO: -P1-PC105-9512-0020- Sheet 1/1.
Plant Revesion-04
Design Intent Transfer of LPG from LPG Pump to LPG Bottling Plant (Carousel).
Deviation Cause Consequence Safeguard Recommendation Remark/Action
Contaminant
Start Up May have malfunction LPG filling will not SOP should be followed.
during start up start tanker filling
Node: 107 Balance Vapor from empty Tanker to Bullet through the DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Compressor Revesion-04
Design Intent Transfer of LPG Vapor from Empty liquid Road Tanker to Bullet.
Deviation Cause Consequence Safeguard Recommendation Remark/Action
No/ Less Flow Some obstruction in the Possible damage of Compressor will Trip in One Alarm May be
Suction of LPG vapor LPG Compressor due low suction pressure (1.5 provided in Compressor
Compressor to obstruction in kg/cm2) House to actuate at the time
Suction line of low discharge pressure of
Pressure indicator in the Compressor
Compressor discharge. (Same as R-29)
Node: 107 Balance Vapor from empty Tanker to Bullet through the DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Compressor Revesion-04
Design Intent Transfer of LPG Vapor from Empty liquid Road Tanker to Bullet.
Deviation Cause Consequence Safeguard Recommendation Remark/Action
Any of the Gate valve Stoppage of LPG provided in Compressor where process safety
provided in Suction and Vapor flow to suction House to actuate at the time in charge can sit
Discharge line Vapor of the compressor and of low discharge pressure of operate and monitor
Compressor might finally stoppage of Compressor all the process
have closed removal Vapor from the (Same as R-29) parameter
Closure of ROV in the tanker.
Bullet inlet line. Loss of LPG vapor
which will remain in
the Tanker
More Flow Excess pressurization Potential damage of Compressor will trip at
by compressor. Two tanker due to 12.0 kg/cm2g. Pressure safety valve
Compressor may take overpressure. Leakage Pressure safety valve testing (once in a year)
start. of LPG vapor. Fire PSV-has been provided should be incorporated in
hazard. at compressor discharge maintenance schedule
(Same as –R-30)
Higher Any of the gate Valve The compressor will be Compressor will trip at Pressure safety valve testing
Pressure provided in the pressurized and may get 12.0 kg/cm2g. should be incorporated in
discharge of compressor damaged. Pressure safety valve maintenance schedule
to the LPG Bullet may PSV-has been provided (Same as R-30).
be closed at compressor discharge
.
Page 42 of 44
HAZOP WORKSHEET FOR EQMS, DELHI
HPCL PATNA PROPOSED MOUNDED LPG STORAGE DATED 27.08.2016
HPCL PATNA
Node: 107 Balance Vapor from empty Tanker to Bullet through the DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Compressor Revesion-04
Design Intent Transfer of LPG Vapor from Empty liquid Road Tanker to Bullet.
Deviation Cause Consequence Safeguard Recommendation Remark/Action
Pressure
Node: 107 Balance Vapor from empty Tanker to Bullet through the DRG NO : -P1-PC105-9512-0020- Sheet 1/1
Compressor Revesion-04
Design Intent Transfer of LPG Vapor from Empty liquid Road Tanker to Bullet.
Deviation Cause Consequence Safeguard Recommendation Remark/Action
damaged flange gasket. . shall either have spiral
wound metallic gaskets or
ring Joints (OISD-
6.2.2)(Same as R-26)
Page 44 of 44
HAZOP STUDY REPORT OF HPCL PATNA LPG
EQMS INDIA
BOTTLING PLANT FOR PROPOSED NEW LPG
DATED 04.10.2016
HPCL LPG MOUNDED BULLETS
BOTTLING PLANT
ANNEXURE – 2
ANNEXURE-3
Prepared by
October 2016
Page 1 of 36
Project: Quantitative Risk Analysis Report for
HPCL LPG Storage & Bottling Plant at Patna
TABLE OF CONTENT
1. INTRODUCTION......................................................................................................................... 1
1.1. ABOUT HPCL .......................................................................................................................... 1
1.2. HP GAS SAFETY, HEALTH & ENVIRONMENT POLICY ............................................................ 1
1.3. ABOUT THIS QRA PROJECT .................................................................................................... 2
1.4. ABOUT EQMS ......................................................................................................................... 2
2. SCOPE, OBJECTIVE & METHODOLOGY ............................................................................ 3
2.1. SCOPE OF WORK ...................................................................................................................... 3
2.2. OBJECTIVE OF THE STUDY ...................................................................................................... 3
2.3. METHODOLOGY ...................................................................................................................... 3
2.3.2. Consequence Analysis .................................................................................................... 4
2.3.3. Quantitative Risk Analysis (QRA) ................................................................................. 4
2.3.4. Risk tolerability criteria .................................................................................................. 6
2.3.5. Societal Risk (or Group Risk) Criteria ............................................................................ 7
2.3.6. Risk Assessment ............................................................................................................. 8
3. FACILITIES DESCRIPTION ..................................................................................................... 9
3.1. HPCL LPG STORAGE & BOTTLING PLANT AT PATNA ........................................................... 9
4. QUANTITATIVE RISK ANALYSIS ....................................................................................... 13
4.1. INPUT DATA FOR QRA .......................................................................................................... 13
4.2. POPULATION DATA ............................................................................................................... 13
4.3. IGNITION SOURCES ................................................................................................................ 14
4.4. WEATHER PARAMETERS ....................................................................................................... 14
4.5. IGNITION SOURCES ................................................................................................................ 16
4.6. HAZARDOUS PROPERTIES OF LPG ........................................................................................ 16
4.7. CONSEQUENCE ANALYSIS ..................................................................................................... 17
4.7.1. Jet/ Pool Fire Radiation ................................................................................................. 17
4.7.2. Vapour cloud explosion (VCE)..................................................................................... 17
4.7.3. Consequence Analysis Results for LPG Bottling Plant ................................................ 18
4.7.4. Review of Consequence Analysis Results .................................................................... 24
4.8. QRA RESULTS FOR LPG STORAGE & BOTTLING PLANT...................................................... 24
4.8.1. Individual risk ............................................................................................................... 24
4.8.2. Societal Risk ................................................................................................................. 26
5. CONCLUSIONS & RECOMMENDATIONS ......................................................................... 28
5.1. CONCLUSIONS ....................................................................................................................... 28
5.2. RECOMMENDATIONS ............................................................................................................. 29
Page | iii
QRA for LPG Storage & Bottling Plant of HPCL at Patna
LIST OF TABLES
Table 2.1 : Generic Failure Rate Data for Equipment Items ................................................................... 5
Table 3.1 : LPG Storage Capacity ........................................................................................................ 10
Table 4.1 : Failure scenarios and the relevant input data ...................................................................... 13
Table 4.2 : Distribution of People in LPG Bottling Plant, Patna .......................................................... 13
Table 4.3 : Pasquill parameters ............................................................................................................. 14
Table 4.4 : Relationship between wind speed and atmospheric stability .............................................. 15
Table 4.5 : Monthly average weather data ............................................................................................ 15
Table 4.6 : Weather Parameters for Risk Analysis ............................................................................... 16
Table 4.7 : Damage Effects due to Jet/ Pool Fire Radiation ................................................................. 17
Table 4.8 : VCE over pressure limit and Observed Effect .................................................................... 17
Table 4.9 : Results of Consequence Analysis for LPG Bottling Plant .................................................. 19
LIST OF FIGURES
Figure 2.1 : Flow diagram of quantitative risk assessment (QRA) ......................................................... 4
Figure 2.2 : Iso-Risk Contours on Site Plan (Typical) ............................................................................ 6
Figure 2.3 : Individual Risk Criteria ....................................................................................................... 7
Figure 2.4 : Societal Risk Criteria........................................................................................................... 8
Figure 3.1 : Layout of HPCL LPG Storage & Bottling Plant, Patna ...................................................... 9
Figure 4.1 : Wind Rose Diagram for Patna ........................................................................................... 16
Figure 4.2 : Mounded LPG Bullet Liquid Line Leak - Pool Fire Radiation Intensity .......................... 20
Figure 4.3 : Mounded LPG Bullet Liquid Line Leak – VCE Overpressure ......................................... 20
Figure 4.4 : LPG Pump Discharge Line Leak - Pool Fire Radiation Intensity ..................................... 21
Figure 4.5 : LPG Pump Discharge Line Leak – VCE Overpressure .................................................... 21
Figure 4.6 : LPG Compressor Discharge Line Leak - Jet Fire Radiation Intensity .............................. 22
Figure 4.7 : LPG Road Tanker Unloading Arm Leak - Pool Fire Radiation Intensity ......................... 22
Figure 4.8 : LPG Road Tanker Unloading Arm Leak – VCE Overpressure ........................................ 23
Figure 4.9 : LPG Road Tanker Failure – VCE Overpressure ............................................................... 23
Figure 4.10 : LPG Road Tanker Failure – Fire ball Radiation Intensity............................................... 24
Figure 4.11 : Iso-Risk Contours on Plot Plan ....................................................................................... 25
Figure 4.12 : Iso-Risk Contours on Plot Plan (Enlarged) ..................................................................... 25
Figure 4.13 : Maximum Individual Risk at HPCL LPG Bottling Plant, Patna ..................................... 26
Figure 4.14 : Societal Risk due to HPCL Storage & Bottling Plant, Patna .......................................... 27
Page | iv
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Caution Note & Liability: The consulting services conducted by EQMS India Private Ltd (the
“Company”) were performed in good faith using generally accepted guidelines, standards, and/or
practices, which the Company considers reliable. Although the Company performed its consulting
services pursuant to reliable and generally accepted practices in the industry, the Company does not
guarantee or provide any representations or warranties with respect to HPCL Patna LPG Bottling
Plant (the Client)’s use, interpretation or application of the findings, conclusions, and/or suggestions
of the consulting services provided by the Company. Moreover, the findings, conclusions, and the
suggestions resulting from the consulting service are based upon information provided by the Client.
EQMS does not hold any liability with respect to interpretation or application of the consulting
services provided by the Company for this assignment / report. No responsibility, whatsoever it may
be is assumed by company for any injury and /or damage to persons or property as a matter of
products liability, negligence, or otherwise, or from any use or operation of any methods, products
instructions or ideas contained in the material of the report. Client is advised to review the actual text
of applicable legislation for analysis & ensuring compliance.
Page | v
QRA for LPG Storage & Bottling Plant of HPCL at Patna
ABBREVIATIONS
Page | vi
QRA for LPG Storage & Bottling Plant of HPCL at Patna
1. INTRODUCTION
1.1. About HPCL
Hindustan Petroleum Corporation Limited (HPCL) is a Public Sector company under the
administrative control of Ministry of Petroleum & Natural Gas (MoP&NG), Govt. of India,
and operates in the Indian Oil & Gas Industry through different verticals. The company’s
infrastructure includes refineries, cross-country pipelines, liquefied petroleum gas (LPG)
bottling plants and storage facilities (Depot/Terminal), lube-blending plants, and aviation
service facilities. It is engaged in the business of Refining, Storing, Marketing and
Distribution of petroleum products. It has two refineries located at Mumbai and
Vishakhapatnam. It produces a host of petroleum products, such as motor spirit, High Speed
Diesel, Kerosene, liquefied petroleum gas, automotive and industrial lubricants, fuel oils and
aviation fuels and distributes the same through its widespread retail network. Further, the
company operates through three reportable segments namely refining, marketing and
Exploration & Production (E&P).
HPCL is headquartered in Mumbai, India. Hindustan Petroleum Corporation Limited
(HPCL) is one of India's largest PSU companies. HPCL, along with a Public Sector
Undertaking (PSU) is also a Navaratana Company; together with Indian Oil
Corporation Limited and Bharat Petroleum Corporation Limited dominate the
downstream petroleum sector in India. The Company is among the few Indian
representatives in the Fortune 500.
HPCL also owns and operates the country’s largest Lube Refinery, producing Lube
Base Oils of international standards with a capacity of 335,000 MT. This refinery
accounts for over 40% of the country’s total Lube Base Oil production.
HPCL is one of the Top 10 Public Sector Enterprises who fall under the ‘Excellent’
category.
1.2. HP GAS Safety, Health & Environment Policy
HPCL markets LPG under its brand name HP Gas. HPCL has a well-established
Safety, Health & Environment Policy. HP Gas has over 33 million domestic LPG
consumers catered through a network of over 2630 distributors. HPCL as a
responsible Corporate Citizen has always strived to strike a right balance between
operating its business and maintaining a sense of harmony with its surroundings.
HP Gas committed to conduct its business in the way that protects the safety of
personnel involved in the business including the customers and the public. It is the
Company’s goal to have our business 100% free from accidents, injuries and
occupational illness through the active participation of everyone involved in its
business.
To meet goal of 100% accident free operation HP Gas commits to carry out
following:
Design, Install, implement and maintain facilities which control safety risks.
Comply with statutory regulations and standards for controlling the risks.
Adheres to Standard Operating Procedures.
Page 1 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Train the personnel working at work place for safety aspects, safe behaviour and
effective use of equipment's to avoid any incident/accident.
Undertake reviews, analyze, evaluate and install optimum value available
safety/operational equipment's for achieving the accident free operations
economically.
Comply with statutory regulations & regulation of Oil Industry Safety Directorate
(OISD), Ministry of Petroleum and Natural Gas, New Delhi for safe operation of
plants.
HP Gas ensures that Risk Analysis studies are conducted as and when required at
Plants/Import facilities to analyze the risk involved and how to manage the risk.
Necessary measures are taken to minimize the risk at work places.
1.3. About this QRA Project
HP Gas has LPG storage and bottling facility at Patna in the state of Bihar. In order to
augment the storage capacity from 1,000 MT to 2,500 MT it is proposed to install three
mounded type LPG bullets (each 500 MT capacity) conforming to the current best safety
norms.
In compliance to its SH&E policy HP Gas wishes to ensure that the risks associated with the
LPG bottling plant at Patna with the proposed additional storage capacity are as low as
reasonably practicable and all necessary measures to control and mitigate emergencies are in
place.
For this purpose, HPCL decided to carry out the Quantitative Risk Assessment (QRA) study
for the LPG Bottling Plant at Patna.
1.4. About EQMS
EQMS is a leading ISO 9001:2008 certified consulting company dedicated to providing
strategic services in the areas of environmental impact assessment (EIA)/ environmental
management plan (EMP), risk assessment, environmental audits, due diligence assessments,
quality/ occupational health & safety/ social accountability management systems, enterprise
level behaviour based safety (BBS) management; EHS performance benchmarking & post-
project management.
EQMS has conducted EIA, hazard identification and risk assessment studies for many clients
including refineries, oil & gas installations, power plants etc.
EQMS is pleased to submit this report on QRA for the HPCL LPG storage & bottling plant at
Patna with the trust that it will help HPCL in achieving high standards of SH&E
management.
Page 2 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Page 3 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Page 5 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
The results of quantitative risk analysis are commonly represented by the following
parameters:
Individual Risk
Societal Risk
Individual risk is the risk that an individual remaining at a particular spot would face from the
plant facility. The calculation of individual risk at a geographical location in and around a
plant assumes that the contributions of all incident outcome cases are additive. Thus, the total
individual risk at each point is equal to the sum of the individual risks, at that point, of all
incident outcome cases associated with the plant.
The individual risk value is a frequency of fatality, usually chances per million per year, and
it is displayed as a two-dimensional plot over a locality plan as contours of equal risk in the
form of iso-risk contours as shown in Figure 2.2.
Page 6 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
should be used as a guideline for the boundary between the risk acceptable
and ALARP regions.
An individual risk of death of one in a thousand (1 x 10-3) per annum
should on its own represent the dividing line between what could be just
tolerable for any substantial category of workers for any large part of a
working life, and what is unacceptable.
For members of the public who have a risk imposed on them ‘in the wider
interest of society’ this limit is judged to be an order of magnitude lower, at
1 in 10,000 (1 x 10-4) per annum.
The upper limit of tolerable risk to public, 1 x 10-4 per year is in the range of risk due to
transport accidents. The upper limit of acceptable risk, 1 x 10-6 per year, is in the range of risk
due to natural hazard such as lightning.
The tolerability criteria for individual risk are shown in Figure 2.3.
Page 7 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Page 8 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
3. FACILITIES DESCRIPTION
The site map of the plant and surrounding area is shown in Figure 3.1.
Figure 3.1 : Layout of HPCL LPG Storage & Bottling Plant, Patna
The total capacity of the LPG storage after installation of the three mounded bullets
will be 2,500 MT.
HPCL LPG plant at Patna receives LPG from HMEL Bathinda refinery, HPCL
Visakhapatnam, GAIL petrochemical plant in Pata (UP) and HPCL Haldia through
road Tankers of 17 or 18 MT capacity. Eight unloading bays are provided for transfer
of LPG from the road tankers to storage bullets.
LPG Storage
The details of existing and proposed LPG storage are provided in Table 3.1.
Page 9 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
The present storage capacity is equivalent to 3 days cover for LPG filling on the
basis of double shift bottling operation. The capacity augmentation would increase
the number of days cover to about 5 days on the basis of double shift bottling
operation.
LPG Pumps
LPG
Motor Purpose Size of Size of
Pump Pump Year in
Capacity (Bottling/ TT Suction Pipe Discharge Pipe
Capacity Type Service
(KW) Loading) (mm) (mm)
(M3/Hr)
200 NB 150 NB
50 Vertical 22 2009 Cylinder Filling
(6 inches) (6 inches)
200 NB 150 NB
50 Vertical 22 2009 Cylinder Filling
(6 inches) (6 inches))
200 NB 150 NB
150 Vertical 75 New Cylinder Filling
(6 inches) (6 inches)
200 NB 150 NB
150 Vertical 75 New Cylinder Filling
(6 inches) (6 inches))
LPG Compressors
LPG
Motor Size of Size of
Compressor Compressor Year in
Capacity Purpose Suction Pipe Discharge Pipe
Capacity Type Service
(KW) (mm) (mm)
(CFM)
Reciprocating
Tanker
156 Horizontal 55 2012 100 NB 80NB
Unloading
type
Reciprocating
Tanker
156 Horizontal 55 100 NB 80NB
2007 Unloading
type
Reciprocating
Tanker
192 Horizontal 75 New 100 NB 80NB
Unloading
type
LPG is received from Road Tankers and transferred to a storage vessel (LPG Bullet).
The LPG vapour pressure in the storage vessel is about 7 kg/sq.cm. The LPG pressure
is boosted to about 12-13.5 kg/sq.cm. by pump and sent to integrated carousel
machine (LPG filling area) through pipe lines.
The LPG cylinders are washed with multiple forced jet of water to remove mud, dirt,
stains, etc., from the outer surfaces. Subsequently the cylinders coming out of
Page 10 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
washing unit are dried by blowing the air on the sides and top surfaces of the
cylinders as they move.
Measured quantity of LPG is filled into cylinders at the filling shed under pneumatic
control.
The Purging Unit which is on-line equipment creates a vacuum in the first stage and
fills LPG vapor in the second stage in new / hot repaired empty cylinders. Aluminium
seal crimping unit/Hot air sealing unit crimps the aluminium cap and seal around the
cylinder valve as a final operation on the filled LPG cylinder. Auto cap fixer fixes
safety caps on to the valve of LPG cylinders.
Filled cylinders are subjected to 100 % weight check, presence and effectiveness of
‘O’ ring inside cylinder valve and checks for leak and bung leak. Tamper proof seals
are fixed on the valves of sound cylinders. These cylinders are loaded to stake trucks
and dispatched to various markets. Cylinder movement inside the Plant is achieved
using chain conveyors driven by electrical motors through worm gear
reducers/planetary gear reducers.
LPG is filled in the cylinders from 14.2 kg weight to 19.0 Kg Weight (as per
requirement) in the integrated carousel machine and filled cylinders after leak testing,
weight testing and fixing safety caps are stacked in the filled cylinder shed near the
delivery end as per rules laid down by OISD/Gas Cylinder Rules, 1981.
LPG Cylinders of 35.0 kg & 47.5 kg capacity used for industrial purpose are also
filled in HPCL Patna plant by stationary filling scales system.
Filled cylinders are delivered only to the authorized LPG distributors. Drivers of the
trucks carrying LPG are having valid license and are having training in safety & fire
fighting procedures.
Safety measures are provided as follows to prevent leaks and control ignition sources
Use of flame‐proof electrical equipment & fittings
Page 11 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
All Hot jobs are carried out by Safety Work Permit System
Strict implementation of ‘No Smoking’ rule
The flange joints of the valves used in LPG system are used either have spiral
wound metallic gaskets or ring Joints (OISD-6.2.2)
Safe procedures for maintenance including nitrogen purging and use of non-
sparking tools.
The total storage facility will be covered properly by the following Fire Protection
System as per OISD 144 standard.
Entire fire protection/ hazard control and detection system has been made to
meet OISD 144 standard.
Two fire water tanks of total capacity of 5085 KL have been installed. This
storage Capacity will also take care of requirement for the three additional
mounded bullets.
Hydrant ring main system around the new Bullets will be provided with fire
hydrant points and monitors as per requirements of OISD. The proposed
Mounded Bullets will also be provided with a fire hydrant system all around
and water sprinkler system as required In addition, adequate numbers of
portable fire extinguishers of dry chemical type will also be provided.
Supplementary protection of bullets by medium facility of water spray system
hooked up with fire detection system.
Provision of Fire Extinguishers as per requirement of OISD and TAC.
Existing water storage capacity and fire pumps will be augmented as per OISD
to meet the requirement of the plant post-augmentation.
Safety distances between facilities and new proposed LPG Bullets will be
provided as per PESO/ OISD norms.
Mock fire drills are conducted at regular intervals and the observations are
recorded. Personnel intended to operate the plant are well qualified and well
trained. Plant operations are supervised by a responsible Officer. The working
personnel are well informed and well trained for fire hazards and firefighting
systems. Bottling Plant security system has been so envisaged to ensure strict
compliance of safety requirements and to take up prompt and proper action in
case of any emergency.
Page 12 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
No vehicle is allowed inside the premises without approved spark arrestor in the
engine exhaust.
Category D (neutral) is the most probable at sites in moderate climates and may occur for up
to 80 % of the time at relevant sites. Stability F (very stable) represents the most adverse
condition in which dispersion extends over longer distances horizontally. Normally, stability
F occurs for short periods in the year, mainly during winter nights.
Weather data (monthly average maximum & minimum temperature and rain fall) for Patna
are indicated in Table 4.5.
Table 4.5 : Monthly average weather data
Month Max. Temperature Min. Temperature Precipitation
(°C) (°C) (mm)
January 23 11 15
February 25 13 19
March 32 19 11
April 37 23 7
May 38 26 36
June 36 27 181
July 33 27 294
August 32 26 332
September 32 26 218
October 31 23 58
November 28 16 9
December 24 11 6
Wind rose diagram for distribution of direction from which wind is blowing and wind
speed is shown in Figure 4.1.
Page 15 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
LPG is stored as liquid under pressure. LPG vapours are heavier than air and
disperse close to ground level. LPG odorized with ethyl mercaptan is received in
the plant so as to provide warning in case of leakage.
4.7. Consequence Analysis
4.7.1. Jet/ Pool Fire Radiation
The effect from jet fire and pool fire is thermal radiation intensity on the receptor surface as
shown in Table 4.7.
Table 4.7 : Damage Effects due to Jet/ Pool Fire Radiation
Heat Radiation Intensity Observed Effect
(kW/m2)
4 Sufficient to cause pain to personnel if unable to
reach cover within 20 seconds; 0% lethality.
12.5 Minimum energy required for piloted ignition of
wood, melting of plastic tubing.
37.5 Sufficient to cause damage to process equipment.
Thermal radiation intensity exceeding 37.5 kW/m² may cause escalation due to damage of
other equipment.
Thermal radiation intensity exceeding 12.5 kW/m² may cause ignition of combustibles on
buildings and impairment of escape route.
Thermal radiation intensity exceeding 4 kW/m² may cause burn injury on personnel injury.
4.7.2. Vapour cloud explosion (VCE)
When a large quantity of flammable vapour or gas is released, mixes with air to produce
sufficient mass in the flammable range and is then ignited, the result is a vapour cloud
explosion (VCE). In the LPG installation large release of LPG from equipment or piping has
potential for vapour cloud explosion. The damage effect of vapour cloud explosion is due to
overpressure as shown in Table 4.8.
Table 4.8 : VCE over pressure limit and Observed Effect
Over-pressure Effect Observed Damage
bar(g) psig
0.021 0.3 “Safe distance” (probability 0.95 of no serious damage
below this value); projectile limit; some damage to
house ceilings; 10% of window glass broken.
0.069 1 Repairable damage; partial demolition of houses; steel
frame of clad building slightly distorted.
Page 17 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Page 18 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
which is not susceptible to such failure. Therefore, catastrophic failure of LPG road
tanker is considered for worst case scenario.
Results of consequence analysis by Phast software for significant leak scenarios relevant to
the LPG bottling plant are shown in the Table 4.9.
Graphical results plotted on the site map drawings are shown in Figure 4.2 to 4.8.
Table 4.9 : Results of Consequence Analysis for LPG Bottling Plant
Downwind Distance (metres)
S.
Description Parameter Weather (Wind speed & Stability)
No.
2 m/s; F 3 m/s; D 5 m/s; D
Maximum Credible Scenario
1. LPG Mounded Bullet Liquid Line Leak
Pool Fire Radiation Intensity 4 kW/m2 55 54 53
12.5 kW/m2 34 34 35
37.5 kW/m2 16 17 19
VCE Overpressure 0.02 bar 46 41 38
0.07 bar 25 23 22
0.2 bar 18 17 16
2. LPG Pump Discharge Line Leak
Pool Fire Radiation Intensity 4 kW/m2 56 56 55
12.5 kW/m2 35 35 36
37.5 kW/m2 17 18 20
VCE Overpressure 0.02 bar 46 41 39
0.07 bar 25 23 22
0.2 bar 18 17 16
3. LPG Tanker Unloading Arm Leak
Pool Fire Radiation Intensity 4 kW/m2 53 50 50
12.5 kW/m2 32 32 33
37.5 kW/m2 15 16 17
VCE Overpressure 0.02 bar 46 40 38
0.07 bar 25 22 22
0.2 bar 17 17 16
4. LPG Vapour Compressor Discharge Line Leak
Jet Fire Radiation Intensity 4 kW/m2 20 20 20
12.5 kW/m2 16 16 17
37.5 kW/m2 12 9 11
Worst Case Scenario
5. LPG Road Tanker Failure
VCE Overpressure 0.02 bar 225 227 222
0.07 bar 99 99 97
0.2 bar 54 54 53
BLEVE/ Fire Ball Radiation 4 kW/m2 264 254 249
12.5 kW/m2 133 128 124
37.5 kW/m2 Not Not Not
reached reached reached
Page 19 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Figure 4.2 : Mounded LPG Bullet Liquid Line Leak - Pool Fire Radiation Intensity
Figure 4.3 : Mounded LPG Bullet Liquid Line Leak – VCE Overpressure
Page 20 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Figure 4.4 : LPG Pump Discharge Line Leak - Pool Fire Radiation Intensity
Page 21 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Figure 4.6 : LPG Compressor Discharge Line Leak - Jet Fire Radiation Intensity
Figure 4.7 : LPG Road Tanker Unloading Arm Leak - Pool Fire Radiation Intensity
Page 22 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Figure 4.8 : LPG Road Tanker Unloading Arm Leak – VCE Overpressure
Page 23 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Figure 4.10 : LPG Road Tanker Failure – Fire ball Radiation Intensity
Page 24 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Risk to Risk to
Personnel Public
Intolerable
Risk
-3
10 per year
-4
10 per year
Figure 4.13 : Maximum Individual Risk at HPCL LPG Bottling Plant, Patna
Page 26 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
Figure 4.14 : Societal Risk due to HPCL Storage & Bottling Plant, Patna
It is seen that the societal risks due to HPCL Patna LPG storage & bottling plant at Patna is
close to the Acceptable Risk region.
Page 27 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
5.1. Conclusions
The scope of this QRA study covers the existing LPG storage and bottling plant of HPCL at
Patna including the proposed three mounded bullets each with 500 MT capacity and related
facilities.
The conclusions of QRA study are as follows.
Maximum individual risk to the public is 1.0E-06 per year which is in the
Acceptable Risk level.
Page 28 of 36
QRA for LPG Storage & Bottling Plant of HPCL at Patna
5.2. Recommendations
The following recommendations are made to ensure that the risks at HPCL Patna LPG
storage and bottling plant are maintained at low level.
1. Emergency push buttons for closing the remote-operated shut-off valves
(ROSOVs) and stop LPG pumps/ compressors are to be provided in control
room and other safe locations.
2. Flange joints are potential source of leakage. Raised face flanges with metallic
spiral wound gaskets or tongue & groove type flanges should be used in LPG
service as specified by OISD.
3. Prevention of ignition
The flame-proof electrical equipment should be properly maintained by
competent and trained personnel to ensure their integrity.
The spark arrestors used for vehicles should be maintained by regular
checking.
Use of cell phones should not be allowed in the LPG installation.
4. Control room: There is provision of control room for housing the instrument
panels, alarms from fire & gas detection system, emergency push button and
communication equipment.
***************
Page 29 of 30
QRA for LPG Storage & Bottling Plant of HPCL at Patna
ANNEXURE – I
Page 30 of 30
Annexure XI
:
Emergency Response Disaster Management Plans
(ERDMP)
HPCL LPG BOTTLING PLANT
AT PATNA
10THOCTOBER, 2016
TABLE OF CONTENTS
1.0 NAME AND ADDRESS OF THE PERSON FURNISHING THE INFORMATION .........................................1
2.0 INTRODUCTION (ERDMP CLAUSE NO- 1.0) .........................................................................................3
3.0 DEFINITIONS OF TERMS (ERDMP CLAUSE NO- 2.0) ............................................................................7
4.0 APPLICABILITY (PNGRB CLAUSE NO- 3.0), SCOPE & INTENT (PNGRB CLAUSE NO 4.0)
ANDASSIGNMENT ...................................................................................................................................12
5.0 CONTENTS (PNGRB -CLAUSE NO-5.0) ...............................................................................................15
6.0 CLASSIFICATION OF EMERGENCIES (ERDMP-CLAUSE NO 6.0) AND SCHEDULE OF
IMPLEMENTATION OF CODE OF PRACTICE FOR ERDMP (ERDMP-CLAUSE NO-7)..................................16
7.0 CONSEQUENCES OF DEFAULT OR NON COMPLIANCE (ERDMP CLAUSE NO 8.0).............................20
8.0 REQUIREMENTS UNDER OTHER STATUTES (ERDMP CLAUSE NO 9.0) .............................................22
9.0 PRE-EMERGENCY PLANNING (ERDMP CLAUSE NO-10) ....................................................................24
CHECK LIST-1 ...........................................................................................................................................47
10.0 EMERGENCY MITIGATION MEASURES (ERDMP CLAUSE NO- 11.0)................................................49
CHECK LIST-2 ...........................................................................................................................................52
11.0 EMERGENCY PREPAREDNESS MEASURES. (ERDMP CLAUSE NO-12)..............................................53
CHECK LIST-3 ...........................................................................................................................................58
12.0 RESPONSE PROCEDURES AND MEASURES (CLAUSE NO 13.0)........................................................59
CHECK LIST-4 ...........................................................................................................................................61
13.0 EMERGENCY ORGANIZATION AND RESPONSIBILITIES (ERDMP CLAUSE NO-14). ..........................62
CHECK LIST-5 ...........................................................................................................................................70
14.0 EMERGENCY INFRASTRUCTURE (ERDMP CLAUSE NO 15.0) ...........................................................70
15.0 DECLARRAHTION OF ON-SITE & OFF-SITE EMERGENCIES (ERDMP-CLAUSE NO 16.0) ...................73
16. RESOURCES FOR CONTROLLING EMERGENCY (ERDMP-CLAUSE NO.17) .........................................76
CHECK LIST-6 ...........................................................................................................................................81
17.0 DEMOGRAPHIC INFORMATION (ERDMP-CLAUSE 18.0) .................................................................82
18.0 MEDICAL FACILITIES (ERDMP- CLAUSE NO 19.0) ............................................................................84
19. SAFE- EVACUATION (ERDMP CLAUSE NO-20)...................................................................................86
20. ROLES AND RESPONSIBILITIES OF STAKEHOLDERS INCLUDING EXTERNAL AGENCIES.( ERDMP
CLAUSE NO-22)........................................................................................................................................89
21. REPORTING OF THE INCIDENT (ERDMP CLAUSE NO-23) ..................................................................91
Page | i
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
22.0 ACTION AFTER REPORTING OF THE INCIDENT (ERDMP CLAUSE NO-24), TERMINATION OF
EMERGENCY (ERDMP CLAUSE NO-25) AND EMERGENCY RECOVERY PROCEDURES (ERDMP CLAUSE
NO-26) .....................................................................................................................................................92
CHECK LIST-7 ...........................................................................................................................................93
23.0 ERDMP FOR PIPELINE CARRYING PETROLEUM PRODUCTS ............................................................95
24. ERDMP FOR ROAD TRANSPORTATION (ERDMP CLAUSE NO-28). ....................................................96
24.0 INTEGRATION OF THE ERDMP WITH THE NATIONAL DISASTER MANAGEMENT PLAN (ERDMP
CLAUSE NO-28)......................................................................................................................................106
25.0 INTEGRATION OF THE ERDMP WITH THE NATIONAL DISASTER MANAGEMENT PLAN ...............108
26.0 Miscellaneous (ERDMP Clause No- 30.0)......................................................................................108
Page | ii
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 1
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 2
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
The total population around 2 km radius is aprox 40000. The large settlements are Kayamnagar and
Sakkadih.
Page | 3
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 4
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Description of Facilities
HPCL LPG Bottling Plant at Patna consists of the following systems:
Receipt of LPG through Road Tankers
Storage of LPG in MSV bullets.
Receiving of empty LPG cylinders
Filling of LPG into cylinders
Dispatch of filled cylinders
Pressure Testing of Cylinder
LPG Storage
The existing facility contains two Mounded bullets of 500 MT capacity each. The Storage
vessels have been provided with all necessary fittings, for filling, emptying, vapor
pressurization, draining facilities and measuring devices like pressure gauges temperature
gauges, level indicators, High level alarm, safety relief valves etc. It is proposed to install three
mounded bullets of 500 MT capacities with total expansion capacity of 2500 MT Capacity.
S. No. Product Vessel Capacity (MT)
1 LPG Mounded Bullets 2x500MT=1000MT
The capacity of Proposed additional Mounded Bullet Bullets.
2 LPG Mounded bullets 3x500 MT= 1500 MT
Total Capacity after Expansion 2500 MT
Page | 5
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Receipt Bulk LPG through ` HMEL Bhatinda, HPCL Vizag, GAIL- Auriya,
HPCL-Haldia
Page | 6
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 7
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
thereof
Incident Incident means an unplanned or unintended or intended event having
potential to cause damage to life, property and environment
Incident Record Register Incident Record Register means a register containing complete information
pertaining to all incidents covering near miss, and all other incidents leading
to Level-I, Level-II and Level-III emergencies
Installation Installation means facilities, namely, gaseous product pipeline, liquid Product
pipeline, hydrocarbons processing installation, oil and natural gas ASFs and
commercial storage and transportation, hydrocarbons gas bottling
Installations including CNG, city gas distribution facilities and retail outlets
Key Personnel The essential actions during a Disaster depend upon the prevailing
circumstances. Nevertheless, it is imperative that the required actions are
promptly and effectively organized by nominated people, each having
specified responsibilities as part of coordinated plan. Such nominated
personnel are known as KEY PERSONNEL.
Leak Leak means release or discharge of a dangerous chemicals or substances or
material into the environment.
Level-I, Level-II & Level-III Level-I, Level-II & Level-III emergency means an emergency as defined under
emergency sub regulation 6 (a), 6(b) &6(c)
Mutual aid association Mutual aid association means an industrial mutual aid association in which
participating industries as a community shall assist each other in case of
emergency. Mutual aid associations supplement a site’s emergency control
plan. Services of member industries shall be requested only when the
emergency threatens to exceed the capability of otherwise available
resources.
Non-Key Personnel Non-Key Personnel are those to whom specific responsibility is not assigned
in the management of emergency.
Occupier Occupier of an installation means the person who has ultimate control over
the affairs of the installation.
Off site emergency plan Off site emergency plan means a response plan to control and mitigate the
effects of catastrophic incidents in above ground installation (AGI) or
underground installations (UGI) or road transportation. This plan shall be
prepared by the district administration based on the data provided by the
installation(s), to make the most effective use of combined resources, i.e.
internal as well as external to minimize loss of life, property, and environment
to restore facilities at the earliest.
On site emergency On site emergency means an emergency that takes place in an installation
and the effects are confined to the Installation premise’s involving only the
people working inside the ASFs and to deal with such eventualities is the
responsibility of the occupier and is mandatory. It may also require help of
outside resources
On site emergency plan On site emergency plan means a response plan to contain and minimize the
effects due to emergencies within the installations which have a potential to
cause damage to people and facilities within the installation premises.
Recovery It means that all those short term and long term activities undertaken by the
management to normalize the operations after an emergency./ Disaster.
Risk Risk means the chance of a specific undesired event occurring within a
specified period or in specified circumstances and it may be either a
frequency or a probability of a specific undesired event taking place.
Page | 8
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Risk analysis Risk analysis means the identification of undesired events that lead to the
materialization of a hazard, the analysis of the mechanisms by which these
undesired events could occur and, usually, the estimation of the extent,
magnitude, and likelihood of any harmful effects.
Risk Assessment Risk Assessment means the quantitative evaluation of the likelihood of
undesired events and the likelihood of harm or damage being caused by
them, together with the value judgments made concerning the significance of
the result.
Risk Management Risk Management means the program that embraces all administrative and
operational programs that are designed to reduce the risk of emergencies
involving acutely hazardous materials. Such programs include, but are not
limited to, ensuring the design safety of new and existing equipment,
standard operating procedures, preventive maintenance, operator training,
incident investigation procedures, risk assessment for unit operations,
emergency planning, and internal and external procedures to ensure that
these programs are being executed as planned.
Site incident controller Site incident controller means the person who goes to the scene of the
emergency and supervises the actions necessary to overcome the emergency
at the site of the incident
Spill Spill” means an unintended release or discharge of hydrocarbon or any other
dangerous liquid into the environment.
Site Incident Controller/ Site incident Controller is the first person who goes to the scene of
Coordinator emergency and directs the actions at the location of incident to overcome the
Disaster.
Teams A number of special actions may have to be carried out by specified works
personnel to control as well as minimize the damage and loss. For this
purpose, designated teams should be available. Each Team will be headed by
a Leader
Transport Emergency Transport Emergency (TREM) Card means a card containing details about the
(TREM) Card nature of hazards, protective devices, telephone numbers and actions related
to spillage, fire, first aid and other details of national and international (UN)
numbers or signage which is common in India and abroad
Unconfined Vapour Unconfined Vapour Cloud Explosion (UVCE) means the formation of vapour
Cloud Explosion (UVCE) cloud due to release of significant quantity of liquefied hydrocarbons into the
atmosphere and its explosion due to ignition which may cause high over
pressure and low pressure that cause very heavy damage
Words and expressions used and not defined in these regulations, but defined in the Act or rules or
regulations made there under, shall have the meanings respectively assigned to them in this Act or in the
rules or regulation, as the case may be.
Page | 9
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 10
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 11
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
4.0 APPLICABILITY (PNGRB CLAUSE NO- 3.0), SCOPE & INTENT (PNGRB CLAUSE NO
4.0) ANDASSIGNMENT
(A) APPLICABILITY
ERDMP is based upon PNGRB regulations G.S.R. 39(E) titled ‘Petroleum and Natural Gas
Regulatory Board (Codes of Practices for Emergency Response and Disaster Management Plan
(ERDMP) Regulations, 2010’.
Clause No. 3 (b) of PNGRB regulations GSR 39 (E) is applicable for ERDMP of HPCL Patna LPG Plant.
Emergency Response and Disaster Management Plan (ERDMP) describes the organizational
structure, facilities, equipment, services and infrastructure necessary to respond to the emergency
situation which could have on-site as well as off-site implications at Receipt, Storage & Delivery
points. Emergency Response Plan covers all emergencies relating to Operation & Maintenance,
personnel, properties including serious accidents, explosions, floods, fire and bomb threat etc.
This plan also applies to those Governmental Agencies that are responsible for emergency
response within the immediate area surrounding the facilities and those agencies, organizations,
contractors, and facilities providing assistance to plant in the event of an emergency. LPG Plant
shall maintain liaison with concerned governmental agencies to ensure proper understanding and
interfaces regarding aspects of notification, responsibilities of personnel and resources of state
and local agencies to be deployed in case of actual emergency situation.
Other important Regulations also have been considered during preparation of ERDMP for HPCL
Patna LPG Bottling Plant.
(a) Factories Act,1948
(b) Environment (Protection) Act, 1986
(c) the National Environment Tribunal Act, 1995
(d) the Petroleum Act, 1934,
(e) the Explosives Act, 1884 mentioned in Schedule–II.
(f) provisions and guidelines of the Disaster Management Act, 2005 and National Disaster
Management Guidelines Chemical Disasters (Industrial), April, 2007
(g) OISD-141(schedule –VIII)
(B) SCOPE & INTENT
SCOPE.
The Scope covers-
(i) The identification of emergencies;
(ii) The mitigation measures to reduce and eliminate the risk or disaster;
(iii) The preparedness plans and actions when disaster or emergencies occur;
(iv) The responses that mobilize the necessary emergency services including responders like fire
service, police service, medical service, ambulance, Government as well as Non-
Governmental agencies;
(v) The post disaster recovery with aim to restore the affected area to its original conditions;
Page | 12
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Intent.
(a) Intent of this Emergency Response and Disaster Management Plan (ERDMP) document is to
formulate action plan for all necessary functions that are required to be carried out towards
preparedness, response & management of emergencies. It describes the emergency
response organization, the resources available (internal as well as external) and specific
response actions required for various types of emergencies that could occur in HPCL Patna
LPG Plant.
(b) ERDMP is not just to use as reference material for training.
Objectives of Emergency Response and Disaster Management Plan (ERDMP) are:
(i) to prevent causalities-both on-site and off-site;
(ii) to reduce damage to property, machinery, public and environment;
(iii) to develop a state of readiness for a prompt and orderly response to an emergency and
to establish a high order of preparedness (equipment, personnel) commensurate with
the risk;
(iv) to provide an incident management organogram with clear missions and lines of
authority;
(v) to ensure an orderly and timely decision-making and response process (notification,
standard operating procedures);
(vi) to maintain good public relations;
In order to achieve the objectives of emergency planning, the critical elements that form the
backbone of the Emergency Response and Disaster Management Plan (ERDMP) are:
i) Reliable and early detection of an emergency and careful planning.
ii) The command, co-ordination and response organization structure along with efficient
trained personnel.
iii) Availability of resources for handling emergencies.
iv) Appropriate emergency response actions.
v) Effective notification and communication facilities.
vi) Regular review and updating of the Disaster Management Plan.
vii) Proper training of the concerned personnel.
viii) Liaison with civil Administration.
Imperatives of such a plan are to minimize the adverse effects of an accident and restoration of
normalcy at the earliest by providing measures to contain the incident and limit the
consequences.
Above objectives are sought to be achieved through following measures:
I) Providing information to all concerned regarding consequences of likely
emergencies
II) Warning and advising LPG personnel & people likely to be affected
III) Mobilizing on-site and off-site resources
Page | 13
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 14
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 15
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 16
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
The damage potential of the above sections has been discussed in detail in the chapter on Risk
Analysis. The credible hazard scenarios are found to be gasket failure, mechanical seal failure of
pumps, road tanker unloading arm failure and small bore pipe line failure etc.
Apart from the above, fire cannot be ruled out in substation & MCC as well as in other places from
short circuiting and also secondary fire from nearby industries.
However, major accident may occur in the plant and call for emergency/disaster
Page | 17
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Level- 3 Emergency: This is an emergency or an incident which could be catastrophic and is likely to
affect the population, property and environment inside and outside the installation, and
management and control is done by District Administration
Following events are considered as of Level - 3 Emergencies in the organisation
1. Bursting of Storage bullets resulting in heavy leakage leading to BLEVE.
2. Agitation / forced entry by external group of people.
3. Natural Perils - Earthquake
4. Sabotage, Bomb explosion / Threat
Tabular Data of Emergencies
Applicable
Type of
Sl. No Emergency Description of Emergency
Emergency
Action Plan
1 Level-1 On site 1. LPG Unloading Arm leakage in Filling Shed.
2. Cylinder Body Leak
3. TRV/PAV pop up
4. Filling gun or Gas Stop valve failure
5. LPG Pump Mechanical seal failure
6. Leakage of product line valves
7. Hose leakage or failure during cold flaring in CR Shed
2 Level-2 On site 1. Storage vessel SRV pop up
2. Failure of product pipeline leading to leakage
3. Bush/dry grass fires during peak summers.
4. Leakage during draining operation.
3 Level-3 Off Site 1. Bursting of Storage bullets resulting in heavy leakage
leading to BLEVE
2. Agitation / forced entry by external group of people.
3. Natural Perils - Earthquake
4. Sabotage, Bomb explosion / Threat
Important Note: - The earlier emergency classification at plant as per OISD-117 has been renamed
as per PNGRB Regulation- 2010 as follows.
OISD-117 classification ERDMP Regulation-2010 classification
Henceforth in the whole manual, terminology used for emergency is Level 1, Level 2 & Level 3 and
words like Small fire; Major fire and Disaster as per OISD-117 have been dropped
On-site and Off-site Planning
An on-site emergency is one, which is having negligible effects outside the factory premises and can
primarily be controlled by internal facilities and resources available. Some help may be required from
external agencies or local authorities.
Page | 18
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
An off-site emergency will affect the neighbouring areas and population outside the factory
premises and would require substantial contribution from local authorities and institutions like
police, civil defence, state hospital and civil administration in addition to state fire services.
With reference to the HPCL Incident reporting matrix emergencies are classified and probable
scenarios in accordance with QRA area of exposure due to heat radiation as detailed in table: 6.1
Here we will consider the control of emergencies generated from Level-II and Level-III will be taken as
part of Onsite Disaster Management Plan
Table-6.1
HPCL LPG LEAKGE
Level-1 Minor leak size (5 mm dia.) / Fire
Page | 19
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
(a) There shall be a system for ensuring compliance to the provision of these regulations through
developing a well defining ERDMP plan and conduction of mock drill and safety audit during the
construction, commissioning and operation phase, as well as an on-going basis. There shall also
be system of do’s & don’ts regarding safety, mock drill or real emergencies for visitors before
entering and establishment. This should be supported by written instruction sheet for visitor
and ensured the visitor is accompanied by the plant representative on forward visit and return
gate.
DO'S AND DON'TS
DO'S DON'TS
Any One Noticing If any person inside the plant will see the DO NOT panic and avoid running
An Emergency leakage or fire incidence will inform to officer all over the place, prevent other
Situation /Operation Control Room/ Security control from doing so.
room, Fire Control Room. The Control Room
officer /security person on duty will inform to DO NOT enter the site unless
Plant Head or Manager (Operation) or Safety instructed or all clear
Officer. siren/message is heard.
Plant Manager-9431821217,
Manager Operations- 9430457040,
Safety Officer- 9473192464,
All other Employees After getting information of Fire, the fire DO NOT panic
On Site ( Fire & Safety fighter available at site to activate siren and DO NOT enter the site unless
Personal) start fire fighting. Fire detectors also will instructed or all clear
activate spray of water on the affected vessel/ siren/message is heard.
Equipment’s. If situation is serious, inform fire
brigade available in Arrah. Inform local police
control room –telephone no-100 and fire
control room –at Arrah) through Plant
Head/Safety officer.
.
Contractor Personnel Stop work on hearing alarm. Assemble at the DO NOT enter the site, till it is
nearest / designated ASSEMBLY POINT and be cleared for the normal work by
ready to evacuate. site incident controller.
Security Keep the gate manned; Keep the road clear for DO NOT allow unauthorized
movement of Emergency Vehicles/ Fire visitors free to enter.
Tenders/Ambulance. Control traffic at gates.
Take the position as per standing Order.
Visitors Leave the place and assemble at Assembly DO NOT enter the site if
point. emergency alarm is heard.
Drivers/Helpers of Bulk Stop the operation; disconnect the hoses/arms Do not panic or leave the vehicle
Trucks safely. and wait for the instructions of unless given directions.
operator for evacuation
Drivers/Helpers of Stack Stop the operation, tie the gates properly and Do not panic or leave the vehicle
Trucks wait for the instructions of operator for unless given directions.
evacuation
Page | 20
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
(b) A meeting is to be arranged by Disaster Management Committee of the plant and will scrutinize
all the action taken by the concerned authority of ERDMP group .The failure of action made by
Plant operating personal/ Fire Personal are also discussed thoroughly. A report is to be made by
the Plant authority on the emergency handled as per ERDMP and action taken to overcome the
situation in future safely. The report if required may be submitted to the Board of ERDMP in
this context as per regulation 8.2. The Board may asses the compliance of ERDMP, Technical
Standards and Specifications including Safety Standards either directly or indirectly.
(c) In case of any deviation or shortfall ,in achieving the recommended standard ,the company may
be liable to have penal provision under the act PNGRB 8.0
(d) If the Mutual Aid Association available near HPCL Patna LPG Bottling Plant have not
responded as per Memorandum of Understanding (MOU) or written agreement on the
request of assistance shall attract penalty under these regulations as under:
(i) for first default in response, the defaulting entity with the application and its
management shall have to submit written explanation to affected mutual aid
members.
(ii) For the second and successive ,the defaulting entity shall have to pay the doubled
amount of expenses incurred by affected by mutual aid members in case of any
eventuality occur in the premises of a affected mutual aid members
Page | 21
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
It shall also be necessary to comply with the relevant statutes, provisions and guidelines of
the Disaster Management Act, 2005 and National Disaster Management Guidelines Chemical
Disasters (Industrial), April, 2007
Current compliance status with above rules / permissions is stated in TABLE. 8.1
below
SL.N DESCRIPTION APPROVAL NO. RENEWAL VALID TO REMARKS
O. LICENCE NO. APPLIED ON
FACTORY LIECENCE (DIRECTOR OF FACTORIES, BIHAR)
DECEMBER-
1 Factory License 00001/BR/BPR
2020
Certificate Of One time
2 R-7/99-AIC-I(R)
registration for issued on-
Page | 22
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
laborlicense 19-8-99
EXPLOSIVE LICENSES ( Chief Controller Of Explosive, Nagpur)
3 Bulk Storage S/HO/BI/03/41(S21702)
31/03/2017
(Mounded Bullet )
4 Bulk Storage
(Mounded Bullet)
5 Filling of Cylinder G/HO/BI/05/10G/HO/BI 30/09/2016
/06/10(G1802)
6 Filled Cylinder Storage G/HO/BI/05/10&G/HO/ 30/09/2016
BI/06/10(G1802)
7 Grant of recognition DPT-GC(EC)F-90/BI permanent
(Permission) of
Periodical Testing &
Examination of LPG
Cylinders at Plant as
per Gas Cylinder Rules
Environmental Consents (PSB)
8 Air Consent P/T-3-1012/01-T858 12/01/2016 30/11/2018
9 Water Consent 2-105/01-T859 12/01/2016 30/11/2018
10 Authorisation for P/T-4-06/08 08/01/2016 08/01/2021
Handling of Hazardous
waste
11 VHF License FL-1157/1-8 05/10/2015 30/11/2016
Other Approvals
12 Prohibited area yes
Permanent
notification
13 Public Liability yes
Insurance
14 BIHAR Fire Service YES
, NOC
Page | 23
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
RISK
UNDERSTANDING
What can
go wrong?
How likely What are the
is it? impacts?
Frequency Hazard Consequence
Analysis Identification Analysis
Page | 24
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Safety review
Checklist analysis
Relative ranking
What-if analysis
Preliminary hazard analysis
Failure mode and effect analysis
Hazop study
Fault tree analysis
Event tree analysis
Bow tie analysis
Each method of hazard analysis finds application for specific purpose. They can be considered as different
weapons in the war against accidents.
Page | 25
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Explosion due to delayed ignition of vapour cloud in flammable range formed by large
quantity of LPG mixed with air
Cold burn due to contact with flashing liquid LPG at very low temperature
LPG received in road tankers or GAIL pipeline is odorized with ethyl mercaptan to alert the people in
the area in case of any leaks.
Gas detectors are provided in areas around bullets, pumps & tanker loading stations.
Ignition sources are strictly controlled by the following measures:
Use of flame-proof electrical equipment & fittings
Strict implementation of ‘No Smoking’ rule
HPCL LPG Bottling Plant have elaborate Fire Protection System and measure taken by the plant
conform relevant OISD Standard
HAZOP STUDY METHODOLOGY
HAZOP study is a technique widely used in process plants for hazard identification. It follows a
structured approach of creative brainstorming by a team of specialists using a set of guidewords. The
documents consisting mainly of process flow diagrams, piping & instrumentation diagrams (P&ID),
plant layout diagram, safety instrument interlock logic diagrams, operating instructions, MSDS for the
chemicals used etc. Form the basis for HAZOP study.
The plant under the scope of HAZOP study is divided into a number of Nodes, which may be
specifically defined equipment and connected lines. Each node of the plant is studied in detail to
understand its function and the associated parameters such as physical and chemical conditions
(pressure, temperature, flow, composition, etc.) as well as activities such as maintenance.
Next all meaningful deviations are identified by applying certain guide words to the pArrahmeters.
Commonly used guide words are: No, Less, More, Reverse, Part of, Other than
Guide words combined with Parameters provide the Deviations which are considered in HAZOP
study.
No/ Less flow More flow Reverse flow
Lower pressure Higher pressure
Lower temperature Higher temperature
Lower level Higher level
Lower concentration Higher concentration Contaminant
Utility failure Start-up/ shutdown
Leak
The first node is selected and applicable deviations from design intent are taken up one by one. For
each deviation first all possible causes are identified by brainstorming among the HAZOP study team
members. For equipment in batch operation, deviations for each stage of the batch are to be studied
separately.
It is important to ensure that the causes are identified within the node under Study, whereas the
consequences may occur anywhere in the plant. This procedure helps to minimize confusing
repetition and maintain focus
The safeguards provided in the system are reviewed to ensure their adequacy. If found necessary the
HAZOP study team then formulates necessary recommendations, which may consist of improvement
Page | 26
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
in procedures, changes in the hardware or additional safety devices depending on the level of risk
involved.
All the lines and equipment in the sections are covered in HAZOP Nodes. The Nodes considered in the
HAZOP study along with the list of P & Ids are listed in the following Table.
List of HAZOP Study Nodes
Node Node Description P&I Diagrams
No.
101 Liquid LPG from Road Tanker to LPG Bullet
102 LPG Vapour from LPG Bullet to Suction of LPG Vapour
Compressor
103 LPG Vapour from LPG Vapour Compressor discharge to LPG DRG NO : -P1-PC105-9512-
Road Tanker 0020- Sheet 1/1
104 Mounded LPG Bullets Revesion-04
105 Liquid LPG from mounded Bullet to Suction of LPG Pump for
LPG Bottling Plant
106 Liquid LPG from discharge of LPG Pump for LPG Bottling
Plant
107 Balance Vapour from empty Tanker to Bullet through the
Compressor.
Page | 27
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
(7) Design pressure of LPG tanker and set pressure of SRV at compressor discharge is to be
checked
(8) It is to be ensured that LPG unloading arm fitted with tanker shall be provided with breakaway
couplings. Only approved type Loading arm shall be of provided and be tested as per OEM
recommendations (OISD-144-6.3)
(9) Thermal Pressure relief valve provided in long pipes 80-LPG-l-131-A should be checked
regularly.(-OISD-144-9.5.5/e and also OISD-STD-132 on "Inspection of Pressure Relieving
Devices)" valve is to be provided in long pipes having isolation valves at both ends (OISD-144-
6.9)
(10) Set point of tripping of Comp. should be checked regularly
(11) As per OISD 144, clause 6.2.1 (iv) maximum vapour pressure of LPG at 55C is 14.5 kg/cm2g.
Tanker is to be designed accordingly
(12) One Study is to be carried out by a reputed Electrical Consultant for the improvement of
effectiveness of Lighting Arrestor provided in Plant area.
(13) Water sprinkler system (automatic) should be in working condition at the tanker loading area
and also in Bullet area. A regular periodic check should be carried out. (OISD-150-8.1)
(14) Data sheets for design temperature of (-) 27C is to be verified for new Bullet
(15) Procedure for taking sample from tanker to be checked with proper PPE
(16) Provision is to be made to start the Air Compressor immediately after starting the DG set on
power failure. This is to provide air to operate ROVs Proper SOP is to be made for startup &
shutdown of LPG system
(17) Proper SOP is to be made for start up & shutdowns of LPG system are to be numbered in P&ID
for reference in SOP.
(18) Valves /PSVs ROVs are to be numbered in P&ID for reference in SOP
(19) During attending any maintenance job at Road tanker liquid and vapour line Proper isolation,
purging & permit system should be incorporated in SOP. The requirement for providing blinds
to ensure positive isolation for safe maintenance is to be assessed.
(20) Regular external inspection and compressive inspection of LPG Pipe line should be made as per
guide line given in OISD-144--9.5.3 (ii)&(iii)
(21) To avoid leakage in Unloading arm, Periodic inspection/ leak testing and maintenance of
Unloading Arm should be carried out periodically.
(22) To take immediate action during any leakage in Road Tanker’s liquid outlet line, Provision of
manual emergency isolation valve at tanker outlet should be considered.
(23) It has been observed at most of the time, 04 LPG Road tanker- Trucks are connected for
unloading job. At that time, unloading arm, vapour line are connected individual unloading
system. If that time any vehicle in a speed move in that area, (and break fail) the same may heat
the tanker truck causing leakage from the Loading Arms or Vapour inlet line. Therefore, during
unloading time of LPG from LPG Tanker, a temporary Barriers should be placed on both sides
of LPG tanker Truck to prevent vehicle movement during unloading time
Page | 28
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
(24) Periodical checking of Push Bottom working should be made for observing working of
Emergency Shutdown Interlocks. The checking of valid inspection certificate for tanker is to be
included in SOP
(25) One Push Bottom as provided in Tanker unloading area should be provided in Bullet area also,
so that any leakage from the flange connection can be taken care immediately
(26) The flange joints of the valves used in LPG system shall either have spiral wound metallic
gaskets or ring joints (OISD-144-6.2.2 )
(27) Sight Glass has been provided in the LPG unloading line to see flow of LPG to Bullet. There is
every possibility of breakage of side glass and LPG liquid may spill at nearby area which may
create fire and explosion. Generally this side glasses are used to see the flow. Though In P&D
Side Glass has not shown .But if the sight glass have been kept and it breaks then somebody
with all safety measure has to go to the top of the Tanker to close the Tanker outlet Valve which
may be unsafe for the operator who will attend the leakage. Management may review the
provision of Side glass in pipelines.
Node: 102 -LPG Vapor from LPG Bullet to Suction of LPG Vapour Compressor
(28) Pressure Indication at Compressor suction and discharge does not shown in the P&ID. Pressure
indicator is to be provided at the suction and discharge side of each Compressor
(29) One Alarm May be provided in Compressor House to actuate at the time of low suction/
discharge pressure of Compressor. The working of Alarm should be checked regularly.
(30) Pressure safety valve testing should be incorporated in maintenance schedule.PSV should be
tested once in year (OISD-144-9.5.5.e)
(31) Temperature indicator in Cooling water line should be provided
(32) Regular checking at a definite interval should be made, for activation of Sprinklers with the help
Quartz bulb and Deluge Valve for LPG compressor area and road tanker area
(33) Specify procedure is to be made for keeping valve at before the PSV always open & Locked,
except when the PSV is removed for maintenance
(34) During any maintenance job in any flange of liquid /vapour line, the area should not have
ignition source near the flange. The line is to be purged properly with the help of Nitrogen.
Spark proof tools should be used during opening of the flange. The safe opening procedure and
procedure for attending maintenance job should be specified in SOP.
(35) Presently no Nitrogen Connection is available at PATNA Plant. Generally Nitrogen Cylinders are
used to purge the vapour line in LPG plant. One nozzle with valve for Nitrogen connection in the
Bullet should be made permanently, so that Nitrogen hose can be connected from the Nitrogen
Cylinder to purge the Bullet. The Nozzle should have double isolation valves, NRV and spectacle
blind. So Nitrogen Cylinders are to be arranged
(36) PSSR system should be followed for first start up of new Mounded Bullets and piping
connection.
Node-104- Mounded LPG Bullets (LPG Storage Vessel)
Page | 29
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
(37) (a) The pressure indicator provided in the top of the Bullet should be based on Differential
pressure transmitter. (b) The set pressure of PSV should be 12.5 Kg/Cm2 g (Compressor normal
discharge pressure is 11.0 Kg/Cm2)
(38) As per OISD-150 -8.1 Automatic fire detection and /or protection (Fixed) system based on heat
detection through thermal fuses/ quartz bulbs/ EP detectors shall be provided above the each
Bullet. Sensors shall be installed at all critical places as mentioned in OISD-150-8.1
(39) As mentioned in OISD-150-4.1a.The area at the which, the location of Mounded Bullet is made,
should be cleaned completely from tree, stump, root, bush, combustible material and other
objectionable matter
(40) We may consider low pressure alarm in each Bullet to control low temperature in Bullet as well
as in connected piping.
(41) Regular checking of Sprinklers is to be done for their working on auto mode.
(42) Gas detectors are also to be checked regularly. A schedule is to be made in this respect.
(43) As per OISD-144, 6.2.3, the storage vessel shall have minimum two independent level indicators
and one independent high level switch. High level alarms shall be set at not more than 85%
level of the volumetric capacity of the vessel.
(44) High level switch shall be interlocked with closure of ROV and compressor shutdown.
(45) In a different interval the LPG product should be tested (mainly presence of Butane &
Condensate)
(46) In a different interval the LPG product should be tested (mainly presence of propane &
Condensate)
(47) Written procedure for draining water from LPG bullet should be available, as serious accidents
may occur due to mal-operation for water draining from LPG bullet. Water may freeze and
block the line and valve. The arrangement provided for draining water from bullet for safety is
to be checked. Water freezing in the drain pipe may prevent the valve from closing and LPG will
be released after the ice melts
(48) Specify procedure for keeping the valve at the outlet of PSV always open, except when the PSV
is removed for maintenance.
(49) Nitrogen connection (Nozzle for Connection) in liquid inlet line of each bullet with double
isolation valves, NRV and spectacle blind should be provided for purging the system. Nitrogen
Cylinders are to be arranged for safe purging of Bullets
(50) To avoid external corrosion of Mounded Bullet, provision of cathode protection system for
mounded bullets is to be made.(OISDstandard-150 Annexure-I)
(51) Provision of instrument air receiver/ emergency power back up connection during power
failure. Instrument Air Compressor should take start immediately through DG set.
(52) Nitrogen connection is to be made at LPG inlet Pipe to each bullet. Proper SOP is to be made for
attending start up & shut down of LPG Bullet system.
(53) Safety (HSE) is prime concern during handling of LPG. So for running LPG handling system safely
, always we have to check the following with respect to OISD standards
Fire protection system
Page | 30
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 31
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Scope of work
The scope of work of this study covers the Quantitative Risk Assessment (QRA) for the proposed
mounded LPG storage installation of HPCL Patna LPG Plant at Patnain Bihar State.
Objective of the Study
The objectives of this study are as follows:
Identifying the potential failure scenarios for release of flammable/ toxic material in
the LPG storage installation.
Carrying out consequence analysis for significant accident scenarios.
Carrying out for Quantitative Risk Analysis
Estimating the individual risk and societal risk due to the installation.
Assessing the risk with respect to the risk tolerance criteria
Identifying risk reduction measures wherever warranted to ensure that the risk is as
low as reasonably practicable.
Methodology
Risk arises from hazards. Risk is defined as the product of severity of consequence and likelihood of
occurrence. Risk may be to people, environment, assets or business reputation. This study is
specifically concerned with risk of serious injury or fatality to people. The flow diagram of QRA is
shown in Figure 2.1.
The following steps are involved in quantitative risk assessment (QRA):
Study of the plant facilities and systems.
Identification of the hazards.
Enumeration of the failure scenarios.
Estimation of the consequences for the selected failure incidents.
Risk analysis taking into account the failure frequency, extent of consequences and
exposure of people to the hazards.
Risk assessment to compare the calculated risk with risk tolerability criteria and
review the risk management system to ensure that the risk is “As Low As Reasonably
Practicable” (ALARP)
Page | 32
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 33
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
The results of quantitative risk analysis are commonly represented by the following parameters:
Individual Risk
Societal Risk
Page | 34
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Individual risk is the risk that an individual remaining at a particular spot would face from the plant
facility. The calculation of individual risk at a geographical location in and around a plant assumes
that the contributions of all incident outcome cases are additive. Thus, the total individual risk at
each point is equal to the sum of the individual risks, at that point, of all incident outcome cases
associated with the plant.
The individual risk value is a frequency of fatality, usually chances per million per year, and it is
displayed as a two-dimensional plot over a locality plan as contours of equal risk in the form of iso-
risk contours.
Risk tolerability criteria
For the purpose of effective risk assessment, it is necessary to have established criteria for tolerable
risk. The risk tolerability criteria defined by UK Health & Safety Executive (UK-HSE) are normally used
for risk assessment in the absence of specific guidelines by Indian authorities.
UK-HSE has, in the publications “Reducing Risk and Protecting People” and “Guidance on ALARP
decisions in control of major accident hazards (COMAH)” enunciated the tolerability criteria for
individual risk.
The guidance on QRA also can be taken from MoE&F, Gov. of India from their publication “Technical
EIA Guidance Manual for Offshore and Onshore Oil and Gas Exploration Development and
Production, September 2009.” and Bureau of Indian Standards Hazard Identification and Risk Analysis
(IS 15656:2006).
An individual risk of death of one in a million (1 x 10-6) per annum for both workers
and the public corresponds to a very low level of risk and should be used as a
guideline for the boundary between the risk acceptable and ALARP regions.
An individual risk of death of one in a thousand (1 x 10-3) per annum should on its
own represent the dividing line between what could be just tolerable for any
substantial category of workers for any large part of a working life, and what is
unacceptable. For members of the public who have a risk imposed on them ‘in the
wider interest of society’ this limit is judged to be an order of magnitude lower, at 1
in 10,000 (1 x 10-4) per annum.
The upper limit of tolerable risk to public, 1 x 10-4 per year is in the range of risk due to transport
accidents. The upper limit of acceptable risk, 1 x 10 -6 per year, is in the range of risk due to natural
hazard such as lightning
Societal Risk (or Group Risk) Criteria
Societal Risk parameters consider the number of people who might be affected by hazardous
incidents. Societal risk is represented as an F-N (frequency-number) curve, which is a logarithmic plot
of cumulative frequency (F) at which events with N or more fatalities may occur, against N.
Risk Assessment
Based on the results of QRA, necessary measures to reduce the risk to ALARP are to be formulated.
For this purpose PHAST Risk software provides the information regarding risk contribution from each
leak scenario modelled.
The Liquefied Petroleum Gas (LPG) bottling facility is located at GIDHA (Gidha Industrial Growth
Centre) Arrah, Dist-Bhojpur which is notified as industrial area by Bihar Industrial Development
Authority (BIADA). The plant is principally engaged in bottling of LPG Cylinders. This industrial area is
Page | 35
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
located on Varanasi-Patna National Highway. Plant has direct accessibility by road. The plant is 11 km
away from the Arrah, District Head Quarter of Bhojpur District. The Plant is surrounded by other
industrial installations such as
East Side - Road
West Side - Agricultural Plot
North Side - Flour Mill
South Side - Retail Outlet and Go-down
Page | 36
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 37
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Population Data
Plant operations are carried out double shift operation (A+B). The distribution of personnel in the
HPCL Patna LPG bottling plant is shown in Table 9.3.
Table 9.3: Distribution of People in LPG Bottling Plant, Patna
S.No
1 Officers 2 1 3 6
2 Employees 4 4 0 8
3 Contract workers 38 38 1 25 102
PMCC contract
4 1 1 1 3
workers
5 Loading unloading 16 15 31
Page | 38
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
contract workers
6 Security 4 4 4 7 19
Total Manpower shift wise 65 63 5 36 169
Ignition sources are strictly controlled in the LPG bottling plant area. All electrical equipment and
fittings are flame-proof type.
No vehicle is allowed inside the premises without approved spark arrestor in the engine exhaust.
The following sources of ignition are considered in the risk analysis.
Transformer
MCC/ Electrical Room
Canteen
Weather parameters
Weather parameters play a significant role in dispersion analysis. The notable parameters for
assessing the atmosphere are wind speed, atmospheric stability, ambient temperature, humidity and
topographic parameters.
Atmospheric stability represents the vertical turbulence in the air due to temperature differentials
caused by heating of the earth by solar radiation. Atmospheric stability effects are represented
through Pasquill parameters as follows shown in Table 9.3.
Page | 39
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
The relationship between wind speed and atmospheric stability is shown in Table 9.4.
Table 9.4: Relationship between wind speed and atmospheric stability
Wind speed Day-Time: Night-Time
Solar Radiation Cloud Cover
(m/s) Strong Medium Slight Thin Medium Overcast
<3/8 >3/8 >4/5
<2 A A-B B - - D
2-3 A-B B C E F D
3-5 B B-C C D E D
5-6 C C-D D D D D
>6 C D D D D D
Category D (neutral) is the most probable at sites in moderate climates and may occur for up to 80 %
of the time at relevant sites. Stability F (very stable) represents the most adverse condition in which
dispersion extends over longer distances horizontally. Normally, stability F occurs for short periods in
the year, mainly during winter nights.
Weather data (monthly average maximum & minimum temperature and rain fall) for Patna are
indicated in Figure 9.5
Table 9.5: Weather Data for Gidha (Arrah)
Max. Min.
Month Temperature Temperature
(°C) (°C)
January 23.0 110
February 25.0 13.0
March 32.5 19.0
April 37.0 23.0
May 38.0 26.0
June 36.3 27.0
July 33.0 27.0
August 32.0 26.0
September 32.0 26.0
October 31.0 23.0
November 28.0 16.0
December 24.0 11.0
Wind rose diagram for distribution of wind direction and wind speed is shown in Figure 9.2.
Page | 40
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Weather parameters
Weather parameters play a significant role in dispersion analysis. The notable parameters for
assessing the atmosphere are wind speed, atmospheric stability, ambient temperature, humidity and
topographic parameters Atmospheric stability represents the vertical turbulence in the air due to
temperature differentials caused by heating of the earth by solar radiation. Atmospheric stability
effects are represented through Pasquill parameters as follows shown in Table 9.6.
Table-9.6: Pasquill parameters
Stability Class Atmospheric Condition
A Very Unstable
B Unstable
C Slightly Unstable
D Neutral
E Stable
F Very Stable
The relationship between wind speed and atmospheric stability is shown in Table 9.7
Table-9.7: Relationship between wind speed and atmospheric stability
Wind speed Day-Time: Night-Time
Solar Radiation Cloud Cover
(m/s) Strong Medium Slight Thin Medium Overcast
<3/8 >3/8 >4/5
<2 A A-B B - - D
2-3 A-B B C E F D
3-5 B B-C C D E D
5-6 C C-D D D D D
>6 C D D D D D
Category D (neutral) is the most probable at sites in moderate climates and may occur for up to 80 %
of the time at relevant sites. Stability F (very stable) represents the most adverse condition in which
Page | 41
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
dispersion extends over longer distances horizontally. Normally, stability F occurs for short periods in
the year, mainly during winter nights.
Weather data (monthly average maximum & minimum temperature and rain fall) for Patna are
indicated in Figure 9.3
Table 9.5: Weather Data for Gidha (Arrah)
Max. Min.
Month Temperature Temperature
(°C) (°C)
January 23.0 110
February 25.0 13.0
March 32.5 19.0
April 37.0 23.0
May 38.0 26.0
June 36.3 27.0
July 33.0 27.0
August 32.0 26.0
September 32.0 26.0
October 31.0 23.0
November 28.0 16.0
December 24.0 11.0
The following representative combinations of weather parameters for the site are considered in this
study.
Table-9.8: Weather Parameters for Risk Analysis
Description #1 #2 #3
Temperature (C) 35 30 15
Wind speed (m/s) 3 5 2
Atmospheric Stability D D F
Ignition Sources
In case of gas leakage, ignition of the gas will result in damage due to fire or explosion. Therefore,
identification of ignition sources is important in risk analysis.
The electrical and instrument items in the installation conform to the electrical hazardous area
classification. Flame-proof electrical items will be installed in the classified areas, and these will not
be ignition sources. Vehicles inside the plant are provided with spark arrestors in the exhaust.
There is no overhead HT electrical line in the plant area which may act as ignition source.
The following ignition sources are identified for input to PHAST Risk software.
Vehicles moving in the road
Electrical switchgear room and transformer area
Diesel generator.
Hazardous Properties of LPG
The flammable consequences of LPG release from equipment are mainly the following:
Page | 42
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
LPG is stored as liquid under pressure. LPG vapors are heavier than air and disperse close to ground
level. LPG odorized with Ethyl Mercaptan is received in the plant so as to provide warning in case
of leakage.
Consequence Analysis
Jet/ Pool Fire Radiation
The effect from jet fire and pool fire is thermal radiation intensity on the receptor surface as shown in
Table 9.9.
Table-9.9 Damage Effects due to Jet/ Pool Fire Radiation
Heat Radiation Observed Effect
Intensity
(kW/m2)
4 Sufficient to cause pain to personnel if unable to reach cover
within 20 seconds; however blistering of the skin (second-degree
burn) is likely; 0% lethality.
12.5 Minimum energy required for piloted ignition of wood, melting of
plastic tubing.
37.5 Sufficient to cause damage to process equipment.
Thermal radiation intensity exceeding 37.5 kW/m² may cause escalation due to damage of other
equipment.
Thermal radiation intensity exceeding 12.5 kW/m² may cause ignition of combustibles on buildings
and impairment of escape route.
Thermal radiation intensity exceeding 4 kW/m² may cause burn injury on personnel injury.
Vapour cloud explosion (VCE)
When a large quantity of flammable vapour or gas is released, mixes with air to produce sufficient
mass in the flammable range and is then ignited, the result is a vapour cloud explosion (VCE). In the
LPG installation large release of LPG from equipment or piping has potential for vapour cloud
explosion. The damage effect of vapour cloud explosion is due to overpressure as shown in Table
9.10.
Table-9.9: VCE over pressure limit and Observed Effect
Over-pressure Effect Observed Damage
Page | 43
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
bar(g) psig
0.021 0.3 “Safe distance” (probability 0.95 of no serious damage below this
value); projectile limit; some damage to house ceilings; 10% of
window glass broken.
0.069 1 Repairable damage; partial demolition of houses; steel frame of clad
building slightly distorted.
0.138 2 Partial collapse of walls of houses.
0.207 3 Heavy machines in industrial buildings suffered little damage; steel
frame building distorted and pulled away from foundations.
(c) Consequence Analysis Results for LPG Storage & Handling System
Results of consequence analysis by PHAST software for significant leak scenarios relevant to the LPG
bottling plant are shown in the Table 9.10:
Table-9.10 Results of Consequence Analysis for LPG Bottling Plant
Downwind Distance (meters)
S.No. Description Parameters Weather (Wind speed & Stability)
2 m/s; E 3 m/s; D 5 m/s; D
1. LPG Bullet Liquid Line Leak
Pool Fire Radiation Intensity 4 kW/m2 55 54 53
12.5 kW/m2 34 34 35
37.5 kW/m2 16 17 19
VCE Overpressure 0.02 bar 46 41 38
0.07 bar 25 23 22
0.2 bar 18 17 16
2. LPG Pump Discharge Line Leak
Pool Fire Radiation Intensity4 kW/m2 56 56 55
12.5 kW/m2 35 35 36
37.5 kW/m2 17 18 20
VCE Overpressure 0.02 bar 46 41 39
0.07 bar 25 23 22
0.2 bar 18 17 16
3. LPG Vapour Compressor Discharge Line Leak
Jet Fire Radiation Intensity 4 kW/m2 20 20 20
12.5 kW/m2 16 16 17
37.5 kW/m2 12 9 11
Worst Case Scenario
4. LPG Road Tanker Failure
VCE Overpressure 0.02 bar 225 227 222
0.07 bar 99 99 97
0.2 bar 54 54 53
BLEVE/ Fire Ball Radiation 4 kW/m2 264 254 249
12.5 kW/m2 133 128 124
37.5 kW/m2 Not Not Not
reached reached reached
Page | 44
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
(C) Evacuation due to effect of Fire and explosion inside the plant and at outside the
plant
Based on Consequence Analysis (as per DNV soft ware PHAST-6.6), it has been found that the highest
effect distances and areas of fire and explosion are given below which are to be deal with seriously in
Onsite ERDMP.
Sl.No. Scenario Consequences Highest effected
Distances in Meter
1 LPG Bullet Liquid Line Leak VCE Overpressure 46 Meter
(0.02 bar)
2 LPG Pump Discharge Line Leak VCE Overpressure 46 Meter
(0.02 bar))
3 LPG Vapour Compressor Discharge Line Jet Fire Radiation 20 Meter
Leak Intensity(4 kW/m2)
4 LPG Road Tanker Failure Overpressure (0.02 227Meter
bar)
BLEVE/ Fire Ball 264Meter
Radiation( 4 kW/m2)
We may reveal that use of Mounded Bullet have less risk than an above ground Bullet.
Due to catastrophic failure made by any Bombing on LPG Road tanker, BLEVE will takes place and the
heat wave of 04KW/M2 area will reach the distance of 264Meter. It means during that condition, all
the employee is to be evacuated through Security Gate and taken to 270Meter distance away from
the plant. Before complete evacuation, the push bottom provided near Road Tanker unloading area is
to be operated and all ROVs are to be closed safely. All Pumps and Compressor are to be stopped.
Chief Incident Controller will inform to SHO, Police Station –Koelwar (Telephone no-9431822298)to
vacate all the employees of the factories installed at the west side of HPCL LPG plant. Though there
will be very rare chance of Bombing on above ground Bullet.
Due to catastrophic failure of Road Tanker at LPG unloading area due to over pressure with the help of
entry of high pressure Vapour, the heat wave at 0.2 Bar pressure will reach the distance of 227Meter.
It means the entire employee is to be evacuated and taken to outside of 230 Meter distance. Before
complete evacuation, the push bottom provided near Road Tanker unloading area is to be operated
and all ROVs are to be closed safely. All Pumps and Compressor are to be stopped. In this case also
Chief Incident Controller will inform to SHO, Police Station – Koelwar (Telephone no-9431822298) to
vacate all the employees of the factories installed at the west side of HPCL LPG plant
In other cases as mentioned above, the plant authority has to take care to evacuate people from 100
meter and below.
HPCL Patna LPG plant has only 02 sets of Self Contain Breathing apparatus with only one spare
cylinder of 30 minutes capacity. The management of HPCL Patna LPG plant should purchase 03
more Self Contain breathing apparatus (SCBA set) and should give vigorous training to their
employee to take action in emergency i.e. say operating Push Bottom, Stopping all LPG Pump and
Compressors and ROV quickly.
Regular Mock Drill is to be organised minimum at least once in six months to take action on evacuation
of working personal with all vehicles from the plant.
Page | 45
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
During Mock drill, the entire staff, after closing all the operation & maintenance jobs should assemble
at Assembly Places with proper head counting. The Emergency Control Centre operated inside the
plant should be activated.
Vigorous training to be given to all employees for carrying out fire fighting in emergency inside the
Plant against above fire & explosion.
(D) The common causes of disasters
The common causes of disasters are envisages are tabulated below for reference, and the ERDMP
should be prepared by the installation to deal with the following emergencies.
Man made Natural Calamities Extraneous
Heavy LPG Leakage from the Flood Riots/Civil Disorder/
LPG Tanker/ Bullets. Earth Quake Mob Attack
Fire Cyclone Terrorism
Explosion Excessive Rains Sabotage
Failure of Critical Control Tsunami Bomb Threat
system of the Road Tanker ,
LPG Bullet, Pump and
Compressor.
Page | 46
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
CHECK LIST-1
(Refer ERDMP-Clause- 10.1Hazard Identification)
Page | 47
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 48
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 49
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 50
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 51
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
IV. Internal safety audits and inspections are carried out quarterly as per OISD-145 checklists.
Inter unit safety audits are conducted by experts from other facilities.
V. Work permits in line with OISD – 105 are issued and monitored. List of Authorized issuers
and receives is approved by HPCL
VI. In-built safety interlocks system such as, Remote Operated Valve (ROV), Pressure Safety
Valves (PSVs); non-returning valves (NRVs), Shutdown Valves (SDVs) and emergency trip
systems are incorporated in design of installation.
VII. Written safety instructions are given to visitors including assembly procedure and escape
route, dos and don’ts before entry.
VIII. Safety MIS system is established. Unit sends monthly safety reports including Exception
reports to Corporate HSE department who issues monthly HSE report for whole
organization.
IX. All standby equipment’s are operated periodically and checked as per specified schedule.
Warning system, first aid & definitive treatment methods, evacuation procedures are tested
periodically.
X. Setting up of safety MIS system and sending Exception reports to the head of
organisations or CEO; all standby equipment’s should be tried and operated periodically and
recorded. similarly back up power for safety equipment and instrument should be checked
periodically and observations be recorded;
XI. check points for incident prevention measures are given at Check list -2.
CHECK LIST-2
(Refer ERDMP Clause No- 11.(c) (Xii))
Page | 52
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 53
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Mock Drill rehearsal of On Site Emergency action plan is carried out once in a month. On completion
of the mock drill rehearsal, the debriefing meeting chaired by Location-In-charge of the unit is
conducted to ensure the efficacy of the rehearsal and to discuss the observations.
Recommendations/observations received from the observers in this regards are complied with time
bound schedule.
Moreover the rehearsal on “Off-site emergency action” has been conducted with the consent of and
under the guidelines of District Collector for surrounding MAH industries.
Last on site emergency mock drill rehearsal was conducted on 14.03.16
Location of Emergency was 14.2 Kg Filled Cylinder Storage Shed
Mock Fire Drill Report with other agencies conducted on 14.03.2016
Mock Drill was conducted by Mr Amar Kumar - Location In-charge , HPCL, Patna LPG Bottling
Plant
Mock Drill was attended by Fire Incharge, Fire Station-Arrah,
Dated -14/03/2016
Name of Emergency LPG leakage & fire in 14.2kg filled cylinder in
Cylinder Storage shed
Date of Drill 14.03.2016
Details of Drill – As the part of Emergency Mock Response Drill, Plant Manager Conducted The
Mock Drill to assess the preparedness and awareness level of the employees and the Officers
along with the functioning of Safety Equipment in the presence of Bihar Fire Service, Bhojpur and
Mutual Aid members
Details of Response Time.-
SR. NO EMERGENCY SCENERIO REMARKS
1 LOCATION OF EMERGENCY Filled Cylinder storage Shed
2 NATURE OF EMERGENCYV LPG leakage & fire in 14.2kg filled cylinder in
Cylinder Storage shed
3 DATE OF FIRE DRILL 14.03.2016
4 DETAILS OF RESPONSE TIME TIME (Hrs)
ACTIVITY
4.1 EMERGENCY SPOTTED 12:01:00
4.2 ALARM RAISED(VOCAL/ HAND SIREN) 12:01:02 Through walkie-talkie,
PA Paging system
4.3 ELECTRICAL SIREN SOUNDED(Wailing) 12:01:24
4.4 Sprinkler started 12:01:24
4.5 Monitor started 12:01:24
4.6 1ST Fire Extinguisher Discharged 12:01:04
22.5 KG FIRE EXTINGUISHER
4.7 Rescue Team onsite 12:01:25
4.8 ALL BULK TTs EVACUATED 12:05:46
4.9 ALL PACKED TTs EVACUATED 12:05:46
4.10 MUTUAL AID MEMBERS ON SITE 12:01:30
4.11 KEEP ADDING RELEVANT ACTIVITIES
4.12 ALL CLEAR GIVEN ON SITE 12:11:05
4.13 ELECTRICAL SIREN SOUNDED FOR ALL 12:16:30
CLEAR
Page | 54
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
5.0 FEATURES OF THEDRILL: One outsider somehow managed to come inside the
Plant, planted a bomb near the Security Cabin No.2 and then went to Filled
Cylinder Storage Shed for making Fire. The person working in the Filling Shed
recognized the Fire and immediately gave FIRE SHOUT followed by discharge of
DCP Fire Extinguisher. Shift Officer informed others over Walkie-Talkie and PA
paging for Fire and operated Manual Call Point. On activation of MCP, Siren
Automatically got started followed by tripping of Plant Equipments and actuation
of Deluge Valves. On actuation of Deluge valves, sprinklers got started. Meanwhile,
Team members of Fire Fighting and Auxiliary Team reached the site and acted as
advised by the Site Controller. Mutual Aid Members of Fire Brigade, nearby IOC
LPG Plant Officials and Police also reached the Emergency Location and assisted in
Fire Fighting. Once fire fighting got over, traces of LPG were checked with
explosive-meter and All-Clear signal was given by the Site Controller.
V OVERALL ASSESSMENT OF PREPAREDNESS FOR EMERGENCIES:
Excellent mock drill. Communication is very effective. Response of individual team
members is very good. Position and working of fire fighting Equipment’s and
systems is good. Fire communications & methodology of extinguishment was very
good.
7.0 AREAS OF IMPROVMENTS/RECOMMENDATIONS:
Page | 55
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 56
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
(v) Familiarization of topography and drills for access and exit details carried out by mutual aid
members.
(vi) A LIST OF MUTUAL AID MEMBERS AND THEIR DETAILS ARE FURNISHED BELOW
COMPANY NAME CONTACT NUMBER
HPCL Patna New IRD at Bihta 9603964242
IOCL LPG Bottling Plant at Gidha 9473192690, 06182-277550, 277320, 277669
Page | 57
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
CHECK LIST-3
[Refer ERDMP-Clause No-12.1(i)]
Page | 58
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 59
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 60
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
CHECK LIST-4
(Refer to ERDMP Regulation 13.0)
ERDMP Response Measures/Infrastructure
SL. CHECK POINT REMARKS
NO YES NO
Zones, maps and layouts
1 Does the Location have Emergency Zones clearly identified for
Incident prone areas
2 Do the Maps indicate location of Emergency Assembly Points and
Emergency Control Room
3 Is the process Lay-out prominently displayed
4 Does the Piping and instrument Diagram include emergency control
valves, shutdown system, isolation valves, important control valves etc
5 Does the Fire Hydrant Layout conspicuously displayed.
Manpower
1 Is the ERDMP Organogram clearly displayed.
2 Does the Organogram include all duties to be attended in
connection with an emergency
3 Is the organogram include key personnel by their names or, work
position
4 Does it have the alternate coverage to take care of the absence of a
particular person [ in cases where organogram is developed basis
names]
5 Does it include assignment of all key coordinators viz. the Incident
Controller, Administration and Communication Controller and Safety
Coordinator
Emergency Control Centre (ECC)
1 Is the ECC well defined and clearly marked on the displayed layout
2 Is it strategically positioned to be outside the periphery of
immediate affected area.
3 Is the centre have adequate communication channels including
internal and external telephone connections, PA, paging and VHF
systems
4 Is list of key personnel and essential telephone nos. are prominently
displayed.
5 The layout of fire fighting system, different hazardous zones, Assembly
Points is prominently displayed.
Emergency Assembly Points
1 Are the EAPs well defined and clearly marked on the displayed
layout
2 The EAPs have pre-defined in-charges during emergencies who keep
in touch with the Emergency Control Centre and
Administrative Controllers and updates on the roll call on people
reporting.
Page | 61
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 62
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 64
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
x. Inform Patna Fire Control room (Telephone no-100). Arrange proper Fire
Fighting in the affected areas by City Fire Fighting Squads. Take the help of
Mutual and External aid members on need basis.
xi. Ensure/maintain sufficient pressure in the Hydrant mains (minimum 7.0
Kg/Cm2 pressure).
xii. Assess water level in the storage tank/reservoir and plan replenishment.
xiii. Monitor the requirements of Fire equipment and coordinate for procurement
of spares.
xiv. Arrange for flood lighting of the affected areas and dewatering of the Fire
fighting area, if required.
xv. Arrange to remove and park the tank Lorries (Bulk & Packed) to a safer place
outside gate, as necessary.
(d) Auxiliary Team Coordinator
I. Operate the Emergency push button for auto shut down of all LPG
equipment’s
II. Immediately move to the site &take a stock of the situation
III. Use proper Gas Mask / Self Content breathing apparatus and advice to use
the same to all main operating staff to control emergency.
IV. If LPG Road tankers are being emptied. Stop the operation .Close the
isolation valve Road Tanker Arm.
V. Remove all LPG Road Tankers to outside the gate safely.
VI. Operate the Push bottom provided in the LPG Tanker area and close all the
MOV to stop the flow of Liquid/ Vapour LPG leakages.
VII. Stop all LPG Pumps and Vapour Compressors and closed their Suction and
Discharge Valve of running Pumps and Compressors.
VIII. Stop LPG Cylinder Filling operation safely.
IX. Isolate all the above ground Bullets and Proposed LPG Mounded Bullets.
X. If Fire takes place, help the Concerned Fire fighter to fight the fire with the
consultation of Plant Manager / Dy. Manager (Operation).
XI. Instruct all his staff to assemble as Assembly Places.
XII. Communicate with relatives of persons injured/involved in fire fighting
activities
XIII. Arrange evacuation of premises as directed by Main incident controller.
XIV. Use proper Gas Mask / Self Content breathing apparatus and advice to use
the same to all main operating staff to control emergency.
I. See the leakage / Fire Condition and mobilise the maintenance manpower
with Gas Mask to take corrective action of leakage with permission and
guidance of Plant Manager.
II. If any outside source is required mobile it.
Page | 65
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 66
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Following methods of communications are available with HPCL Patna, LPG Bottling Plant
Messenger
Telephone – Intercom and STD facility
FAX machine
Mobile
Email/ Internet
Local area networks(LAN)
Page | 67
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 68
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 69
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
CHECK LIST-5
[Refer ERDMP-Clause No-14.2.1 (a)]
Review & Updating of ERDMP
Sl.No CHECKPOINT YES NO REMARKS
1 Frequency of mock-drills for practice, refinement & √ Monthly basis
updation.
2 Does the records for periodic Mock drills maintained in a √ Records are
well-defined format. maintained in a
well-defined
format
3 After each drill, whether assembly meetings involving all √
staff and contract personnel are conducted to share
experience of the event as also to identify the
shortcomings and scopes for further improvement in
procedures. Whether the issues are discussed & the plan
modified suitably.
4 Does the review ensures efficiency of the plan √
particularly w.r.to. Response, communication &
coordination aspects.
5 Do the Mutual Aid members participate in the drills and √ YES
based on the actual response & difficulties experienced, During Half
corrective actions initiated for refinement of the plan. yearly Mock Drill
6 Does a procedure exist in incorporating the √
findings/learning of the actual disaster management
handling, if any so that the plan can be revised
accordingly.
Page | 70
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 71
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Assembly Places are the places where the plant personnel can assemble during any emergency. The
assembly Places are seems to be safest place in the scenario of Disaster and finally they are taken to
safer places from the Disaster area. Assemble place has been made just at following places
NUMBER OF ASSEMBLY POINTS ASSEMBLY PLACES
ASSEMBLY POINT-A Near Main Gate
Emergency Assembly near security main gate area is pre-designated areas in safe zone as per
quantitative risk assessment, where the personnel like workers, staff, contractor workers etc. not
involved in emergency operations (as per ERDMP) shall assemble in case of an emergency.
(1) Depending on the location of the emergency, the assembly point can vary. Accordingly
for each potential hazardous zone, a specific assembly point is identified and clearly
marked on the zones or maps as tabulated below.
Assembly point
SL.No Potential Hazard Zone
Designated
1 Office/Workers cabin/PMCC Assembly point-A
2 Filling Shed/Cylinder Repair Shed /DPT Assembly point-A
Shed/Bullet area/ Loading Shed/TT
Gantry/Pump House/Filled Shed/ TT
Parking
3 MCC Room/Fire engine Shed/Weigh Assembly point-A
Bridge/Store Room
(2) All Designated assembly points are clearly marked with directional display board along
the route. Routes are well lighted with florescent marking.
(3) During an emergency, pre-designated persons would take charge of this point and take
the roll call of the people reporting. Provisions are made for assembly points,
communication and headcount facilities at assembly points, and personnel to control
the movement of assembled employees.
(4) The assembly point coordinators should rush to their designated assembly point. The
name of coordinators and their assembly points are CIC/Security Representative at Main
Gate.
(5) The assembly point coordinators will
Keep in touch with Chief Incident Controller for further instruction.
Ensure the assembling of residents at their nearest Assembly point.
Request the assemble persons, not to get panic and be ready for evacuation (if
required).
Keep in touch with Welfare and Media Coordinator (i.e. Safety Officer) for
arrangement of transport facility for evacuation (if required)
Carryout the head count of the assembled persons at the respective assembly point
and report the same to the CIC.
Page | 72
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 73
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Communication, Welfare & Medical, and Material Coordinator in addition to his normal
duties till the arrival of the concerned coordinator.
2. The Security in-charge in consultation with the site incident controller shall act upon
depending on the situation till arrival of the concerned coordinators for effective handling
of emergency. They shall take care of the safety of personnel, ASF, property etc. Safe
operating procedures which are already in practice shall be followed.
3. All other non-essential personnel whose roll is not defined in the action plan shall assemble
at assembly points and wait for further instruction from CIC Control Room.
(v) Fire / Vapor Cloud Explosion / Emergency
1. irst responder is operator or maintenance worker who on discovering fire / explosion /
product leak shall inform to local CR.
2. Try to extinguish or contain fire with help of nearest available fire extinguisher, water
hydrant, Monitors without endangering himself.
3. The person has to operate the nearest ETB (Emergency trip button).
4. Upon operation of ETB, Control supply of all equipment will get tripped and siren will get
activated and ROVs of the concerned area gets closed.
5. Location In-charge shall take charge to deal with emergency.
6. Fire coordinator shall take immediate action to control emergency.
7. All the teams Combat/Rescue/Auxiliary will report to CIC and take charge as per their
responsibilities mentioned in Fire Organization Chart.
8. Security coordinator shall carry out rescue operations at site and control of personnel to
those required for emergency control.
9. SIC shall rush to site with members of Emergency Management team and take action to
mitigate / contain emergency. Time to time, he shall communicate to CIC regarding status
& action plan of emergency and execute his instructions.
10. All coordinators shall be at respective duty stations and obey instructions from CIC.
11. CIC will assume full responsibility of emergency action plan. He shall take decision
regarding level of emergency, start of Emergency Control Centre (ECC).
12. CIC shall take necessary emergency control measures till situation is brought under control.
He shall initiate actions & decisions regarding:
Operation & maintenance
Shut-down of equipment
Evacuation of personnel
Medical assistance to injured
Assistance from mutual aid members and external agencies.
Escalation of emergency & reporting incident to district authorities
Communication & assistance to affected public
Page | 74
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
SN AUTHORITY TELEPHONE
LOCATIONS TELEPHONE
Page | 75
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
1. When emergency becomes catastrophic and evacuation beyond the Plant premises is considered
necessary by the chief incident controller, the situation will be handed over to district authority
for implementing the off-site emergency plan.
2. The management of emergency henceforth has to be controlled by the district crisis management
group under the supervision of the District Collector/DDMA.
3. In addition to preparation of on-site emergency plan, furnishing relevant information to the
district authorities for the preparation of off-site emergency plan is a statutory responsibility of
the occupier of every industry handling hazardous substance.
16. RESOURCES FOR CONTROLLING EMERGENCY (ERDMP-CLAUSE NO.17)
In order to meet all possible emergencies, adequate number of resources and systems has been
provided as per identified Risk level and also in compliance with statutory requirements under
Factories Act, 1948 and other OISD regulations.
The available emergency control systems and facilities within the installation are provided as under: -
(a) Fire and gas detection system
(b) Fire protection system (Active and Passive)
(c) Fire fighting systems
(d) Ambulance facility in house, if not available then should be available on urgent call basis.
Page | 76
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 77
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
During any maintenance job in any flange of liquid /vapour line, the areas are so protected
that should not have ignition source near the flange. The pipe line is purged properly with the
help of Nitrogen. Spark proof tools are used during opening of the flange. The safe opening
procedure and procedure for attending maintenance job are specified in SOP.
The LPG installation and fire protection measures conform to relevant OISD standards.
(d) Fire Extinguishers available in the Plant
Number of Fire Extinguishers available in Plant
DCP Fire
DCP Fire Extinguishers Co2 Fire Extinguishers.
Extinguishers No. of Sand buckets
10 Kg Capacity. 4.5 Kg Capacity
75 Kg Capacity
5 91 15 12
Total spare DCP Powder available CO2 Cartridges
540 KG 145 NOS.
Classification of Fire:
Fire is classified basically on the basis of the combustible material involved in it as below:
Type of Fire Materials Involved
Class ‘A’ Fire Ordinary combustibles as Wood, Cloth, Rubbish, Plastic,
(Combustible Solid) Paper.
Class ‘B’ Fire Inflammable substances as Oil, Mob, Benzoyl, Solvent etc.
(Combustible Liquid) And also all the fires, which occur in fast and vapour.
Class ‘C’ Fire Fire involving gases i.e. LPG, CNG, Synthetic gas,
(Combustible Gases & Energized Hydrocarbon Gases etc. and energized electrical
Electrical Equipment ) equipment.
Class ‘D’ Fire All Combustible metallic fire, Potassium, Magnesium,
(Combustible Metal) Sodium etc.
Types of Extinguishers Class ‘A’ Class ‘B’ Class ‘C’ Class ‘D’
Water Type
Suitable Unsuitable Unsuitable Unsuitable
Fire Extinguishers
Foam Type Unsuitable but will
Suitable Unsuitable Unsuitable
Fire Extinguishers control small fires
CO2 Unsuitable but will
Suitable Suitable Unsuitable
Fire Extinguishers control small fires
Dry Powder Unsuitable but will
Suitable Suitable Suitable*
Fire Extinguishers control small fires
*Special type of DCP
Page | 78
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Telephones:
Following communication equipment’s are used for internal and external communication:
BSNL Telephone (Landline)– 2 nos.
VHF handsets- 08 No’s
PA System - 1
Page | 79
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Telephone is provided at administrative cabin for external communication with other outside working
agencies and in the planning office. Mobile phone facility is also available for officers for usage inside
administrative cabin and also at the residence of all employees.
VHF hand Sets:
VHF hand sets are provided to all officers & Security Main gate for internal communication during
emergency. Operating personnel/contractors are provided mobile type hand set walkie-talkies are
provided.
Transport Facilities:
Adequate transport vehicles are provided for medical treatment, evacuation and the movement of
key persons. One office car is stationed inside premise for taking care of emergency situations.
Contract personnel shall take help from outside transport agencies for mass evacuation, if required.
Check list - 6 as per regulation 17 (5) is attached in Appendix.
Page | 80
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
CHECK LIST-6
[Refer ERDMP Clause17.0 (5)]
Page | 81
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 82
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
TOPOGRAPHY:
Bhojpur district represents flat topography with a slope towards the Ganga River covering an area of
2,37,526 hectare. The district is located in the Ganga basin in its central parts and the river Ganga
forms the northern boundary of the district. The river Sone is the other major drainage flowing at the
eastern boundary of the district. It originates from the Maikals range of Amarkantak high lands in the
elevated plateau of central India. After flowing northerly and easterly directions for about 592km in a
hilly terrain, it debouches onto the Gangetic alluvial plains. The river flows in north-east direction in a
NE-SW trend and confluences with Ganga in the north-east corner of the Bhojpur district at Babura.
Land Use:
The Gangetic plains provide fertile soil suitable for agriculture. There are many medium and small
scale industries in Giddha Industrial Growth Centre. Basic infrastructure facilities like
Telecommunication, Security, Water Supply, Pollution Control, Water Disposal etc. Provided in the
Master Plan of BIADA.
DEMOGRAPHY DETAILS
Demography:
The Plant is surrounded by other industrial installations such as
Page | 83
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 84
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
DESIGATION OF
SN NAME OF THE HOSPITAL TELEPHONE
THE DOCTOR
1 Sadar Hospital, ARRAH Medical Officer 06182-222609
2 Paras Hospital, PATNA Medical Officer 0612-7107700,7107777
3 RML MEMORIAL HOSPITAL, ARRAH Medical Officer 9334078009
4 Ruban Memorial Hospital, PATNA Medical Officer 0612-2270059
(d) TELEPHONE NUMBERS OF AMBULANCE SERVICES
SN AMBULANCE SERVICE TELEPHONE
1 General 101
2 Indian Red Cross Society, Arrah 9934041541
(e) TELEPHONE NUMBERS OF BLOOD BANKS
SL NO BLOOD BANK TELEPHONE
1 Indira Gandhi Institute of Medical Science, Patna 0612 -2287099, 287099, 287404,
283744, 287225
2 Kurji Holy Family Hospital, Patna 0612-2262540, 2262516
3 Life Line Blood Bank, G.M Road, Patna 0612-2303025, 9234990509
4 Indian Red Cross Blood Bank, Indian Red Cross 06182-222426
Society, South Ramna Road Arrah, Bhojpur
Page | 85
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 86
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
The Chief Incident controller will intimate regarding evacuation. Evacuation of the personnel shall be
carried out in a planned manner along the escape route to assembly points. People must be
evacuated at right angle to wind or opposite the wind direction.
All Team Heads/Security will provide the exact head count details during the emergency. Accounting
for site personnel, visitors and contractors, particularly those known to have been in the affected
area will be done.
Figures of contract labour may vary depending upon day and time, but the exact figure (inside Plant)
will be available at main gate (Security Department keeps record of contract person/ visitor etc. who
have entered inside Plant. Total number of persons available at site shall be calculated from above.
Rescue operation will be carried out by the Rescue/Incident Control personnel immediately attending
to the emergency. The above operations will be led by the Incident Controller at site. The list of
casualties etc. shall be reported to the Communication coordinators who in turn will be reporting to
the Chief Incident Controller at site. Casualties will be shifted to hospital, if required, by
communication coordinators in consultation with Chief Incident Controller/SPM.
Evacuation of those personnel who are not required to be present will be carried out in consultation
with site incident controller. When required, all personnel shall proceed to ASSEMBLY POINTS
through designated routes.
HPCL LPG Bottling plant vehicle are available round the clock for emergency and all the HPCL staff /
security personnel are trained and participate in fire fighting
We have seen in Risk analysis and risk assessment. Chapter -10.2 for HPCL Patna LPG Plant
Sl. Scenario Consequences Highest effected
No. Distances in Meter
1 LPG Bullet Liquid Line Leak VCE Overpressure 46 Meter
(0.02 bar)
2 LPG Pump Discharge Line Leak VCE Overpressure 46 Meter
(0.02 bar))
3 LPG Vapour Compressor Discharge Line Leak Jet Fire Radiation 20 Meter
Intensity(4 kW/m2)
4 LPG Road Tanker Failure Overpressure (0.02 227Meter
bar)
BLEVE/ Fire Ball 264Meter
Radiation( 4 kW/m2)
(a) Due to catastrophic failure made by Bombing on LPG Road tanker, BLEVE will takes place and
the heat wave of 04KW/M2 area will reach the distance of 264 Meter. It means all the
employee is to be evacuated through Security Gate and taken to 280 Meter distance. Before
complete evacuation, the push bottom provided near Road Tanker unloading area is to be
operated and all ROVs are to be closed safely. All Pumps and Compressor are to be stopped.
Chief Incident Controller will inform to SHO, Koelwar Police Station –Arrah (Telephone no-
9431822298) for help to evacuate all the employees of the factories i.e. HPCL LPG plant.
Though there will be very rare chance of Bombing on above ground Bullet.
(b) Due to catastrophic failure of Road Tanker at LPG unloading area due to over pressure with
the help of entry of high pressure Vapour, the heat wave at 0.2 bar pressure will reach the
distance of 227 Meter. It means the entire employee is to be evacuated and taken to outside
of 230 Meter distance. Before complete evacuation, the push bottom provided near Road
Page | 87
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Tanker unloading area is to be operated and all ROVs are to be closed safely. All Pumps and
Compressor are to be stopped. In this case also Chief Incident Controller will inform to SHO
Koelwar Police Station –Arrah (Telephone no-9431822298) to evacuate all the employees of
the factories ,HPCL LPG plant
(B) LIST OF VEHICLES TO BE USED IN AN EMERGENCY
Keep streets and walkways next to exits clear for emergency vehicles and personnel. Keep
the street side of buildings clear so that emergency equipment can reach buildings.
Do not return to an evacuated building until & unless directed to do so by the Safety& Fire
Department personnel.
(C) EVACUATION & REHABILITATION
If a major industrial accident does occur, the general public in surrounding areas will have
very little time to react and save themselves. The local population will have to be warned in a
very short period. Time available to population for a safe escape and threatened by the
accident will depend on the nature of accident. A fire will give more time to escape and
generally area affected will be small. Effects of a fire on population will be injuries due to
thermal radiation. An explosion will give little time to warn population and area affected may
be much larger than that in case of a fire. Effects of an explosion on the population will be
injuries caused by shock wave, flying debris collapsing structures as well as exposure to
thermal radiation.
FOR INSIDE BATTERY AREA:
The entry of contract personnel working inside the battery area is through Main Gate only. In
case of emergency / major accident / disaster, assembly points have been identified and
marked in the safe area for assembling of people for head counting / transportation to a safe
place.
FOR OUTSIDE BATTERY AREA:
Evacuation of the population effected villages / other places outside the battery area
depending on the emergency and provision of temporary shelter and supplies (in the relief
camp) will be under the overall control of the District Administration.
PERIODIC ASSESSMENT:
Chief Incident Controller will carry out periodic assessment of the actual disaster zone and
resources deployment and status report of the same will be given to HPCL HQ.
Page | 88
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
If evacuation takes place after initial head counts are reported, then recounting will be
necessary. In this condition areas being evacuated will be thoroughly searched to ensure
everyone has departed safely. Portable mobile vehicle for announcement should be
available in the emergency.
(D) INFORMATION TO PUBLIC (ERDMP- CLAUSE NO-21.0)
i. General public who are likely to be affected shall be informed about safety measures to be
taken in the event of an emergency.
ii. Display boards carrying Do’s and Don’ts shall be located outside the gate as well as in the
neighbouring areas and other habitat areas in the immediate vicinity. Use of Dos' and Don’ts
shall be prepared and furnished to the District Crisis Management Group.
iii. Safety leaflets are printed having the information on Hazards of Petroleum products (LPG) &
action in case of emergency is distributed among villages near by the area as per Chapter-18.
iv. Safety Awareness camps are conducted in and around the Giddha -village and schools with
the help of Industrial Association and local public representative. They were told about the
hazards of LPG and steps to be taken during emergencies.
v. Safety Leaflet in local language Hindi for Villagers Awareness has been made.
20. ROLES AND RESPONSIBILITIES OF STAKEHOLDERS INCLUDING EXTERNAL
AGENCIES.( ERDMP CLAUSE NO-22)
(A) Roles and responsibilities of stakeholders including external agencies:
(1) Role and responsibilities of stakeholders including external agencies such as District
Authority, police, fire service, revenue department, health department, pollution control
board, National Disaster Response Force (NDRF) and State Disaster Response Force (SDRF).
(2) For roles and responsibilities of above stakeholders and responders, primarily district
collector as Head of emergency operation and other authorities under his charge including
external agencies, has been defined in Schedule–V. These roles and responsibilities are
generally in line with National Disaster Management Guidelines on Chemical Disasters,
April, 2007, brought out by National Disaster Management Authority.
Schedule–V
(B) The important Roles and Responsibilities of Various Stakeholders
a) HPCL Patna LPG Bottling plant, is LPG storage and cylinder refilling plant (Mentioned in
Regulation 3).The above mentioned Installation in Regulation 3 should provide necessary
information to Mutual Aid Association, District Authority, Police and Fire Services .
i) List of Hazardous Chemical and Systems which have potential to cause danger to
Human, Environment and Property.
ii) On-Site Emergency Plan and Periodic Mock Drill.
The above entities should support authorities in mitigation, rescue and rehabilitation, with
resources identified and agreed with the authorities in advance. Such areas shall be included
in Off-Site Emergency Plans.
Page | 89
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
b) The District Authority is responsible for the Off-Site emergency plan and it shall be equipped
with up-to-date Major Accident Hazard units, website, control room etc., with provisions for
monitoring the level of preparedness at all times. Regular meetings of various stakeholders of
Chemical Disaster Management will be conducted by district administration/District Disaster
Management Authority to review the preparedness of Chemical Disaster Management.
c) The Police will be an important component of all disaster management plans as they will be
associated with investigation of incident s/disasters. Police take overall charge of the Off-Site
situation until the arrival of the district collector or its representative at the scene.
d) The Fire Services are one of the first responders and shall be adequately trained and equipped
to handle chemical emergencies. Fire services are to acquire a thorough knowledge of likely
hazards at the incident site and the emergency control measures required to contain it.
e) In a chemical emergency, the Revenue Department shall coordinate with other agencies for
evacuation, establishment of shelters and provision of food, etc.
f) When required for evacuation purposes in a chemical emergency, the department of
transport should made transport promptly available.
g) The role of civil society and private sector in the Off-Site plan shall be defined.
h) The Health Department needs to assure that all victims get immediate medical attention on
the site as well as at the hospitals/health-care facility where they are shifted. In addition, the
department needs to network all the health-care facilities available in the vicinity for effective
management and also take effective measures to prevent the occurrence of any epidemic.
i) Pollution control boards need to ascertain the developing severity of the emergency in
accordance with responsive measures by constant monitoring of the environment. If and
when an area is fit for entry will depend upon the results of the monitoring. A
decontamination operation would be required to be carried out with the help of other
agencies and industries.
j) The NDRF and SDRF are the specialised forces to manage these disasters in a longer run
according to the severity and nature of the disaster. Their specialised training is an effective
measure that needs to be built up and maintained with time for achieving a higher standard of
preparedness. They need to coordinate with other local agencies such as the Central Industrial
Security Force that may be responsible for security at the industrial site.
* Role of above External Agencies have been defined in Annexure – E of National
Disaster Management Guidelines Chemical Disasters, April, 2007
NDRF: National Disaster Response Force and SDRF: State Disaster Response Force
(C) Assistance from various outsider Agencies
1) ASSISTANCE FROM OUTSIDE AGENCIES
Assistance may be required from outside agencies during the course of an emergency & SICs
will be responsible for establishing liaison with these agencies for effective assistance.
2) DISTRICT MAGISTRATE, POLICE & FIRE BRIGADE:
In case of LPG leakage, to ensure security at site to cordon off the areas and post guards for
preventing the villagers going near the site of the leakage.
In case of fire, mobilization of Foam Tenders and Crew from local Fire Stations.
Page | 90
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 91
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 92
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
CHECK LIST-7
(Refer ERDMP-Clause-No- 26.0 (2))
Page | 93
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 94
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 95
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 96
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
(a) In order to handle Emergencies, which may arise due to incident involving Petroleum Product
Transportation, it is required that a comprehensive Emergency Management Plan is readily
available with the industry as well as with other related authorities along the routes.
The ERDMP should be clearly understood by its users so that the emergencies can be
handled in a systematic manner with minimum response time in accordance with the
prescribed procedure.
(b) Copies of the ERDMP shall be made available by the Industry to all the field locations i.e.
Plants, Installations, POL Depots, Terminals / Installations, Refineries, Gas Processing
Plants, Dispatch units of etc., the concerned District Administration, Police Stations and
Fire Brigades en-route and within vicinity of specified tank truck routes, oil industry sales
personnel of concerned area as may be required.
(B) Role of External Agencies for road transportation emergency
The Objectives of an emergency control organization are:
To Control problems as they develop at the scene.
To Prevent or limit the impact on other areas and off-site.
To provide emergency personnel, selecting them for duties compatible with their
normal work functions wherever feasible. The duties and functions assigned to
various people includes making full use of existing organizations and service
groups such as fire, safety, occupational health, medical, transportation,
personnel, maintenance, and security.
Employees must assume additional responsibilities during an emergency
whenever an emergency alarm sounds
In setting up the organization, round-the-clock coverage is considered.
(C) Source of big LPG Tankers for HPCL Patna LPG Bottling Plant
The LPG big Tanker Trucks travelling from following two sources of LPG suppliers and reached at
HPCL Patna LPG Bottling Plant
SL.NO ADDRESS OF LPG SUPPLIERS
1 Hindustan Mittal Energy Limited(HMEL)
Phulokhari Village, Talwandi Sabo, Bhatinda-
151301,Punjab.
Phone- 9257202461, 855783715
2 GAIL (India) Ltd,
UP Petrochemical Complex, Pata,
Distict- Auraiya
Phone-05683-282356/282049
3 VISHAKH –NEW LPG-TERMINAL
Petro Park, Vishakhapatnam, Andhra Pradesh.
Phone: 0891-282691
4 IPPL Haldia Installation LPG BP, Kasberia Terminal, PO-
Haldia Oil Refinery, Midnapore 721606
Phone: 03224-276744 (HPCL Bulk Despatch)
Page | 97
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
A loaded LPG Bulk TT, on its way from above place to the unloading destination (HPCL Patna LPG
Plant), was travelling on National Highway when it may involve in an accident at a major
intersection. Consequently, there may be LPG leakage, vapour cloud formation, fire and, finally,
BLEVE causing devastation – loss of more lives and extensive damage to property of the
population
Salient details of any accident of LPG Road tanker which met collision with another truck/ vehicle: ‐
All the LPG Bulk Tank Truck is loaded with 17/18 MT of bulk LPG and come out from HMEL / Vizag
Refinery/ Gail installation to go to destination say HPCL Patna. The time is noted down while the
tanker after loading LPG liquid, from a refinery or other installation. The LPG tankers are generally
allowed to ply at night time from 06PM to 6AM in between all inter-state borders. The tankers are
accompanied with One Driver and one Helper.
Lot of accidents are taking place in the National/ state highway in the intersections after 08 PM
where there may be steep downward slope with divider and blind curve on the high way.
Due to the above terrain, blind curve, steep downward slope, cross-roads and absence of speed
barrier/s to the descending vehicles, the said intersection is itself an accident prone zone. On this
position on the high way, several accidents have been reported at the same type of place.
As per last case studies, the LPG Bulk TT some time lost control while coming downward in a blind
curve and the prime mover of the vehicle crossed the divider and got struck in between. Due to
impact on the vehicle, the free‐wheel Hinge Pin got broken off and the prime mover got disengaged
from the LPG tanker Bullet. In the process the LPG valve manifold also got damaged. Thereafter LPG
started leaking from the damaged LPG manifold
(D) LPG Tanker leakage -Consequence Analysis Results
The consequence Analysis Result of LPG Tanker leakage has been shown in the Table no24.1
Table no-24.1
Sl. No. Description Parameter Downwind Distance (meters)
Weather (Wind speed & Stability)
2 m/s; E 2 m/s; E 2 m/s; E
LPG Road Tanker Failure
Vapour Cloud Explosion 0.02 bar 225 227 222
0.07 bar 99 99 97
0.2 bar 54 54 53
BLEVE/ Fire Ball Radiation 4 kW/m2 264 255 255
12.5 kW/m2 133 128 128
37.5 kW/m2 Not reached Not reached Not reached
Page | 98
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
In case of Overpressure of LPG Tanker (0.2 bar), the leakage shows maximum non-
credible failure scenarios, the significant effect distances for LPG leakage are within
230 Meters from the leaky LPG Tanker.
In case of BLEVE/Fire ball Explosion , the significant effect distances for LPG
leakage( 4KW/m2 are within 280Meters from the leaky LPG Tanker
All along the route for Road transport, the truck contain LPG tanker, there may be
population of permanent locality at the both side of the road within the above
distances may be affected.
EVACUATION
A Planning and training on evacuation techniques are important in preventing burn injuries.
Evacuation of local communities or people near the Village site/ or city site (near the road where LPG
Tanker leakage occurred) may be prudent depending on the situation and down-wind dispersion
information etc. Although this action will normally be initiated and handled by Bhojpur District Crisis
Group with the help from HPCL Patna LPG Bottling Plant to implement such evacuation.
In that case, area in the radius of total 260 meter is to be evacuated with the help of District authority
and Police in Bhojpur District.
ACTIVATION OF OFFSITE DISATER MANAGEMENT PLAN
Here we will consider the responsibility for the control of Off-Site Disaster created due to accident of
LPG Road Tanker- Truck at Patna -Bhojpur region only.
24.1- Handling of LPG leakage emergency, created by LPG Tanker due to accident at Patna-Arrah
road area.
Sl. Responsibility Action Telephone Remarks
No. Number
1 Any person on After noticing the incident, (any leakage / fire at LPG Tanker on road
road to HPCL, Arrah (Patna) LPG Bottling Plant.).
The person will inform-
The person will Police station /Police 100
inform Control Room at Arrah
Police Station (Koelwar), 9431822298
Bhojpur
Page | 99
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 100
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
& Sr. Plant Will inform the suppliers of LPG Tankers at Gail Pata , HMEL-Bhatinda,
Manager, HPCL IPPL Haldia & HPC Viskha New LG Terminal for extending support for
Patna LPG Plant- attending leakage at their LPG Road Tankers.
Will inform SRM (LPG RO),HPCL, Patna
Mobile no- 8809329926, 0612-2220559 regarding offsite incidence
Page | 101
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
21.2 Flow Diagram for action plan for handling LPG Leakage Emergency
Page | 102
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Extend help in removal of injured personnel to the nearest first-aid centre /hospital,
contacting highway patrol, completing legal formalities in case of any casualty.
In addition to the above, Police is an important component of all disaster management plans as they
will be associated with investigation of accidents/disasters. Police take overall charge of the Off-Site
situation for mob control and law & order issues until the arrival of the district collector or its
representative at the scene.
(b) Fire Service–Arrah
On receipt of information from any source on incident of LPG Tanker Leakage area, fire brigade may
contact nearest police station. After assessing the situation, Fire service will come to action
Page | 103
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Send the Fire Tender to the incident site with all necessary SCBA set and supervise
Rescue operation
Use Self Contained breathing apparatus to handle the LPG leakage emergency. Take
help from the Official of HPCL Patna LPG Bottling Plant , for proper handling of LPG
leakage emergency AS EARLY AS POSSIBLE
A contingency plan is to be prepared for removal of leaky LPG Tanker, or stopping the
LPG leakage in consultation with official of HPCLLPG Bottling Plant, PatnaThe leakage
may create from any of the Nozzle of the LPG Tanker.
Remove general public from the scenario to a safe place
Take help from the Fire brigades from nearby District for additional help, if necessary.
In addition to the above, the Schedule-V of NDMA shall be followed.
The fire services are one of the first responders and are adequately trained and equipped to handle
fire emergencies and search and rescue activities. Fire services are to acquire a thorough knowledge
of likely hazards at the incident site and the emergency control measures required to contain it.
(c) District Authority / District Magistrate Patna)
On receipt of information, District Administration may take the following actions as per
Schedule-V derived from the National Disaster Management Guidelines Chemical
Disasters (Industrial), April, 2007. However, on receipt of information, following actions
should be taken care:-
Inform District Crisis Group immediately.
To keep watch on the overall situation.
Send ambulance to the incident site (LPG Tanker leakage area), if casualties are
reported.
Arrange cranes or any other such equipment to carry out lifting of Tanker and rescue
operations at site.
Issue warning messages to people through public address system, if any evacuation is
required.
Arrange emergency vehicles for evacuation purposes.
Give direction to hospitals having sufficient bed in the surgical ward for readiness to
receive patient in case of incident involving burn injury.
Provide basic amenities, e.g., water, electricity, food and shelter to the affected people
as required.
In addition to the above, the Schedule-V of NDMA shall be followed.
In nut-shell District Magistrate is responsible for the Off-Site emergency plan for
mass evacuation,
communication,
resource mobilization,
Page | 104
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Food, water, shelter arrangement and transport facilities. Regular meetings of various
stakeholders of Chemical Disaster Management are conducted by district
administration/District Disaster Management Authority to review the preparedness of
Chemical Disaster Management.
(D) District Crisis Group( Patna)
In a LPG leakage emergency if situation is critical, then District Crisis Group shall
coordinate with other agencies for evacuation, establishment of shelters and provision
of food, etc.
When required for evacuation purposes in a LPG leakage emergency, the department
of transport should made transport promptly available.
The role of civil society and private sector in the Off-Site plan shall be defined.
The health department needs to assure that all victims get immediate medical
attention on the site as well as at the hospitals/health-care facility where they are
shifted. In addition, the department needs to network all the health-care facilities
available in the vicinity for effective management and also take effective measures to
prevent the occurrence of any epidemic.
Pollution control boards need to ascertain the developing severity of the emergency in
accordance with responsive measures by constant monitoring of the LPG vapor
environment. If and when an area is fit for entry will depend upon the results of the
monitoring.
(a) Guidelines for Media and other agencies Communication:
Purpose: The purpose is to provide exact and correct information about the emergency
situation and guidance to statutory bodies and Public at large.
Chief Incident Controller in coordination with site incident coordinator (District Crisis
group), Technical Coordinator will release the information to Media coordinator.
Media coordinator will form a sub- team consisting of Sr. Plant Manager, Patna HPCL
LPG Plant/other Mutual industry member of Industrial Development Authority ,Patna
The information is processed looking at the authenticity and correctness and reply
shall be framed and forwarded to media and other agencies as required.
Media Coordinator (District Crisis group) will ensure that at site of incident proper
information is gathered and processed and quick approval; for release at site by the
site incident coordinator is ensured.
Apart from Media coordinator of District Crisis Group or Sr. Plant Manager, Patna HPCL
LPG Plant’s approval, no body shall speak to media in any circumstances. A one line
message of Sr. Plant Manager, Patna HPCL LPG Plant’s representative shall forward all
information to Media once the facts are ascertained / needs to be the answer to be
given to media.
(a) List of Basic Equipment’s required for attending LPG Leakage
Sl. No Equipment’s Quantities (Numbers)
1 Truck - 01 no. 01
2 Tractor 01
Page | 105
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
3 Welding generator 02
Page | 106
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
May 6, 1999 - Five killed in a flash fire at the hydro cracker unit of Indian Oil Corp's Panipat
refinery.
Oct 16, 1999 - Three people killed after inhaling hydrogen sulphide gas from a storage tank at
Kalyan near Mumbai.
Oct 28, 2000 - A worker dies after inhaling toxic emissions at a meat processing factory in
Howrah (West Bengal).
May 31, 2001 - Twenty-two labourers die after a gas cylinder explodes at a gold
processing unit in Mumbai.
Aug 17, 2001 - Twenty-two killed in an explosion in an industrial unit at Katpadi, Tamil Nadu.
July 30, 2002 - One killed after a gas leak at Pimpri, Maharashtra
Sep 22, 2002 - Six women die and 54 suffer burns when a fire breaks out at a match factory
near Kovilpatti in Tamil Nadu.
Nov 8, 2002 - Three killed after an explosion at a factory near Daund in Maharashtra
So, the Disaster Management Act enacted on December 23, 2005 empowers the setting up of
an effective disaster management system that extends across the whole of India. The
Disaster Management Policy of India was framed in 2009 on the basis of this Act. The
Government of India claimed to have established institutional and policy mechanisms for
response, relief, and rehabilitation. The orientation for handling disaster situations was also
changed from relief –centre to a holistic, multi-dimensional, and multi-disciplinary approach
involving diverse scientific, engineering, social, and financial processes.
It encompasses the entire scope of disaster management activities, i.e., prevention, mitigation,
preparedness, response, relief, and rehabilitation. Further, the Disaster Management Act of 2005
provides for the constitution of the following institutions at national, state and district levels:
The National Disaster Management Authority (NDMA) at the centre (NDMA Bhawan, A-1,
Safdarjang Enclave, New Delhi, - 110029) chaired by the Prime Minister is responsible
for laying down the national policies, plans and guidelines for disaster management.
The State Disaster Management Authorities (SDMA) for formulating policies and plans for
disaster management in the states. Chief Minister of the state control Disaster through
Director of Factories and Chairman, State pollution Control Board.
District Disaster Management Authorities (DDMA) for planning, coordinating, and
establishing systems for disaster management at the district level in accordance with
the guidelines laid down by the national and state authorities District Disaster
Management Authorities (DDMA) for planning, coordinating, and establishing systems for
disaster management at the district level in accordance with the guidelines laid down by the
national and state authorities [District Magistrate – Patna-Telephone - No-9454418351,515-
2820207(O)]
HPCL is a bigger national level organisation. They are maintaining all required initiation for
the control of emergency.
HPCL,PATNA, LPG Bottling Plant has maintained a good relation to District Magistrate, Patna
and will communicate the entire required emergency situation to DM for further help to
control emergency.
Page | 107
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
25.0 INTEGRATION OF THE ERDMP WITH THE NATIONAL DISASTER MANAGEMENT PLAN
Chief Incident Chief Incident Controller,
Controller, HPCL Patna HPCL Patna LPG Plantwill try DISTRICT DISASTER
LPG Plant, in serious to control the leakage in MANAGEMENT AUTHORITY
disaster (Such as their plant as well as pass on (DDMA)
Catastrophic failure of information to DDMA & If condition of emergency in
LPG Bullet) will pass on SDMA for extending the plant for LPG leakage is
toSRM (LPG), immediate help and very serious, then DDMA will
HPCLPATNA and DDMA Assistance immediately extend all help
for extending immediate and services to Local
help and Assistance Authority .They will also send
the information to SDMA for
further help and information,
if required
Page | 108
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 109
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
SCHEDULE – I
(Refer to ERDMP-Regulation 7)
Schedule of implementation of Code of Practice for ERDMP
S. No. Activity Implementation Time (from
the notification date of Codes of
Practices for ERDMP)
1 On-site Emergency Plan 3 months
2 Off-site Emergency Plan(submission 3 months
of information to District Authority)
3 Resources in position 6 months *
4 Accredited Third Party Certification 12 months
of ERDMP
5 Testing and Mock Drills (On-site) 3months
6 Testing and Mock Drills (Off-site) **12 months
Note: A copy of ERDMP, duly approved by the Board of Directors of the organisations shall be
submitted to the PNGRB.
* Long Delivery Items should be tied up with mutual aid organizations up to 12 months.
** To be coordinated with District Authority.
Page | 110
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Schedule – II
(Refer to ERDMP-Regulation 9(1))
List of Relevant Statutes on Management of Hazardous Substances
(A) The Environment (Protection) Act, 1986 (amended 1991) and following Rules
There under:
• The Environment (Protection) Rules, 1986 (amended 2004).
• The Manufacture, Storage and Import of Hazardous Chemicals Rules, 1989 (amended, 1994
and 2004).
• The Hazardous Wastes (Management and Handling) Rules, 1989 (amended 2000 and 2003).
• The Environment Prior clearance Notification, 2006.
• The Chemical Accidents (Emergency Planning, Preparedness and Response) Rules, 1996.
• Bio-medical Wastes (Management and Handling) Rules.1989.
(B) The Factories Act, 1948 (amended 1987).
• State Factory Rules.
(C) The Inflammable Substances Act, 1952.
(D) The Motor Vehicles Act, 1988 (amended 2001).
• The Central Motor Vehicles Rules, 1989 (amended 2005).
• The Public Liability Insurance Rules, 1991 (amended1992).
• The Public Liability Insurance Rules, 1991 (amended1993).
(E) The Petroleum Act, 1934.
• The Petroleum Rules, 2002.
(F) The Insecticide Rules, 1968 (amended 2000).
• The Insecticide Rules, 1971 (amended 1999).
(G) The National Environment Tribunal Act, 1995.
(H) The Explosives Act, 1884 (amended till 1983).
• The Gas Cylinder Rules, 2004,
• The Static and Mobile Pressure Vessels (Unfired) Rules, 1981 (amended
2002).
• The Explosives Rules, 1983 (amended 2002
Page | 111
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
SCHEDULE – III
(Refer to ERDMP-Regulation 11.1)
Basic Requirements of ERDMP
1. Location Plan of the Installation indicating siting of the installation at neighbouring details up to
a distance of 2 KM from the installation in each direction.
2. Site plan of the installation showing a complete layout of the installation indicating
boundary walls, exit and entry gates and location of various facilities.
3. Layout of Fire Water Systems and Fire Fighting Equipment details.
4. Line block diagram of manufacturing process and Process Flow Diagram (PFD) of each unit.
5. Material Safety Data Sheet (MSDS) for all hazardous chemicals stored, handled, produced and
transported in the installation. (Sample MSDS at Annexure-1)
6. Internal and External Emergency contact numbers and addresses of police, fire-station, hospitals,
mutual aid industry, factory inspectors, Board, State Pollution Control Board, Petroleum and
Explosive Safety Organization (PESO), etc.
7. Pipeline route map and details of various facilities such as sectionalising Valve (SV), intermediate
Pigging (IP) stations, intermediate pumping stations (IPS) across pipeline route
8. Addresses and Telephone Directory of Technical Support Services such as Environmental
Laboratories, fire fighting chemical supply
9. Security threat plan.
Page | 112
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
SCHEDULE – IV
(Refer to ERDMP-Regulation 11.2)
Resource Mobilisation (Men and Equipment)
Sl. Total Requirement Available Neighbouring Civil
No. with Units Authorities
Installation
1 MANPOWER
Regular employees
Security staff
Personnel Trained in first aid
Others ( Technicians / Helpers )
2 FIRE FIGHTING APPLIANCES/
EQUIPMENT/ CHEMICALS
Fire Tenders/ Fire fighting engines
Water storage capacity
Fire Hoses
Jet/Fog/Spray Nozzles
Foam Branch
Jumbo Jet Nozzles
Foam Compound ( KL )
3 SAFETY EQUIPMENT’S
PVC Suit
Compressed air B.A. Set
Refill Cylinders for B.A. Set
Cascade B.A Set
Fire Proximity Suit
4 COMMUNICATION
Walkie-Talkie
Public Address System
Megaphone
5 TRANSPORT
Jeep
Cars
Ambulance
Trucks
Buses
Tractors
Boats
Mobile crane
6 MISCELLANEOUS
Ropes ( Metres )
Empty Drums
Buckets
Sand Bags
Page | 113
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Dewatering Bags
Pneumatic pump
Photo Camera
Video Camera
7 EQUIPMENT’S FOR CORPS
DISPOSAL
Light Metal Stretchers
Tarpaulin 12’ X 12”
Rope fibre 3/8”
Buckets
Rubber Gloves
8 LIST OF EMERGENCY DRUGS
and APPLIANCES
Canvas Stretcher
Oxygen Cylinder
Sterilise Bandages
Cotton Sterilised
Antibiotics
Analgesties
Sedatives
Tetanus Toxoid
Dressing Instruments
Sterilisers
Autoclave for sterilising
Instruments, dressing
B.P. Apparatus
Suction Apparatus
I. V. Test
Anti-shock drugs
Glucose Saline Set
Glucose Saline Bottle
Page | 114
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Schedule – V
(Refer to ERDMP-Regulation 22.0)
The important Roles and Responsibilities of VariousStakeholders
a) Oil and Gas Installations and Areas (Mentioned in Regulation 3).
The above mentioned Installation in Regulation 3 should provide necessary information to
Mutual Aid Association, District Authority, Police and Fire Services.
i) List of Hazardous Chemical and Systems which have potential to cause danger to Human,
Environment and Property.
ii) On-Site Emergency Plan and Periodic Mock Drill.
The above entities should support authorities in mitigation, rescue and rehabilitation, with
resources identified and agreed with the authorities in advance. Such areas shall be included in
Off-Site Emergency Plans.
b) The district authority is responsible for the Off-Site emergency plan and it shall be equipped
with up-to-date Major Accident Hazard units, website, control room etc., with provisions for
monitoring the level of preparedness at all times. Regular meetings of various stakeholders of
Chemical Disaster Management will be conducted by district administration/District Disaster
Management Authority to review the preparedness of Chemical Disaster Management.
c) The police will be an important component of all disaster management plans as they will be
associated with investigation of incident s/disasters. Police take overall charge of the Off-Site
situation until the arrival of the district collector or its representative at the scene.
d) The Fire services are one of the first responders and shall be adequately trained and equipped to
handle chemical emergencies. Fire services are to acquire a thorough knowledge of likely hazards at
the incident site and the emergency control measures required to contain it.
e) In a chemical emergency, the Revenue department shall coordinate with other agencies for
evacuation, establishment of shelters and provision of food, etc.
f) When required for evacuation purposes in a chemical emergency, the Department of transport
should made transport promptly available.
g) The role of civil society and Private sector in the Off-Site plan shall be defined.
h) The health department needs to assure that all victims get immediate medical attention on the
site as well as at the hospitals/health-care facility where they are shifted. In addition, the
department needs to network all the health-care facilities available in the vicinity for effective
management and also take effective measures to prevent the occurrence of any epidemic.
i) Pollution control boards need to ascertain the developing severity of the emergency in
accordance with responsive measures by constant monitoring of the environment. If and when an
area is fit for entry will depend upon the results of the monitoring. A decontamination operation
would be required to be carried out with the help of other agencies and industries.
j) The NDRF and SDRF are the specialised forces to manage these disasters in a longer run according
to the severity and nature of the disaster. Their specialised training is an effective measure that
needs to be built up and maintained with time for achieving a higher standard of preparedness. They
need to coordinate with other local agencies such as the Central Industrial Security Force that may be
responsible for security at the industrial site.
Page | 115
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
* Role of above External Agencies have been defined in Annexure – E of National Disaster
Management Guidelines Chemical Disasters, April, 2007
NDRF: National Disaster Response Force
SDRF: State Disaster Response Force
Page | 116
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
SCHEDULE – VI
(Refer to ERDMP-Regulation 23.0)
INCIDENT REPORTING FORMAT
1. Organisation 2. Sector
3. Location 4. Incident Sr.No.
5. Date of Incident 5. Time of Incident
7. Major, Minor, Near- 8. Report -
Miss Preliminary / Final
9. Fire Incident 10. Duration of fire -
Hrs / Min
11. Type of Incident with loss of life / injury, Fire, Explosion, Blowout,
Electrocution, Fall from Height, Inhalation of Gas, Driving, Slip / Trip,
Others, NA
12.Location of Incident ( Name of Plant / Unit / Area / Facility / Tank
farm / Gantry / Road / Parking area etc )
13. Whether plant shutdown / caused outage of the facility? Yes / No
14. Fatality No. a) Employees = b) Contractor = c) Others =
15. Injury No. a) Employees = b) Contractor = c) Others =
16. Man Hours Lost a) Employees = b) Contractor = c) Others =
17. Direct Loss due to the incident ( Rs. In Lacs ). Loss to equipment /
Machinery as per Insurance claim etc.
18. Indirect Losses : Through put / Production Loss, etc.
19. Status of the Facility: Construction / Commissioning / Operation /
Shutting down / Turn around, Maintenance / Start-up / Any other.
20. Brief Description of the Incident including post
incident measures.
( Attach details in separate sheet )
21. Whether similar Incident has occurred in past at
the same location, If yes, give brief description of the
incident and attach details in separate sheet
22. Whether Internal Investigation has been
completed. If no, likely date by which it will be
completed.
23. Whether internal investigation report (Major
Incident ) has been submitted to PNGRB. If no, likely
date by which it will be submitted
24. Cause of the Incident ( Tick the most relevant cause preferably one, maximum two )
A) Deviation from Procedure I) Not using the PPE
B) Lack of Job Knowledge J) Equipment failure
C) Lack of supervision K) Poor design / Layout etc
D) Improper Inspection L) Inadequate facility
E) Improper Maintenance. ( Mech. / Elec. / Inst ) M) Poor House Keeping
F) Improper material handling N) Natural Calamity
G) Negligent Driving O) Pilferage / Sabotage
H) Careless walking / climbing etc. P) Any other (give details)
Page | 117
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Page | 118
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Signature
Name
Designation of the Occupier/Manager
Page | 119
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Schedule –VII
(Refer to ERDMP-Regulation 27.0)
ERDMP for pipelines carrying petroleum products
Pipelines are assuming importance as a means of transport of hazardous substances. Crude oil,
its derivatives and natural gas are among the main substances transported by pipelines.
The Guidelines, therefore, comprise:
i) Creation and maintaining an administrative framework to facilitate the development of a safe
and environmentally sound transportation infrastructure, including pipelines for hazardous
substances.
ii) The pipeline operator has the primary responsibility for the safety of the systems and for taking
measures to prevent incident s and to limit their consequences for human health and the
environment.
iii) Pipelines for the transport of hazardous substances will be designed and operated so as to
prevent any uncontrolled release into the environment.
iv)Risk assessment methods should be used in evaluating pipeline integrity and impact on human
health and the environment.
v) Land-use planning considerations will be taken into account both in the routing of new pipelines
(e.g. to limit proximity to populated areas and water catchment areas to the extent possible), and in
decisions concerning proposals for new developments/building in the vicinity of existing pipelines.
vi) Pipeline operators and the authorities responsible for pipelines shall review and, if necessary,
develop and implement systems to reduce third-party interference, which is a cause of incident
including their effects.
vii) National legislation shall be clear, enforceable and consistent to facilitate safe transport and
international cooperation.
viii) Competent authorities should ensure that pipeline operators:
(a) Draw up emergency plans.
(b) Provide the authorities designated for that purpose with the necessary information to enable
them to draw up Off-Site emergency plans.
(c) Emergency plans shall be coordinated between pipeline operators and competent
authorities, as well as with fire brigades and other disaster control units.
ix) Pipelines shall be designed, constructed and operated in accordance with recognised
national and international codes, standards and guidelines, notified by the Board.
x) Consideration will be given to the impact on the safety of a pipeline such as design and
stress factors, quality of material, wall thickness, and depth of burial, external impact protection,
markings, route selection and monitoring.
xi) The safety of the pipelines shall be demonstrated through a suitable risk assessment
procedure including the worst case scenario and including breakdowns and external additional
loads.
xii) The pipeline operator shall draw up a Pipeline Management System (PMS) to ensure that it is
properly implemented. The PMS shall be designed to guarantee a high level of protection of
Page | 120
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
human health and the environment. The following issues shall be addressed by the safety
management system.
(a) The pipeline will be inspected and maintained regularly. Only reliable trained staff or qualified
contractors may carry our maintenance work on a pipeline. Third party confirmatory assessment
bodies should inspect the pipeline at regular intervals as far as required by the Board. These
inspections are to cover in particular the proper condition of the pipeline and the functioning of the
equipment ensuring pipeline safety.
(b) Organization ability, roles and responsibilities, identification and evaluation of hazards,
operational control, and management of change, planning for emergencies, monitoring performance,
audit and review shall be duly addressed in the Pipeline Management System.
Page | 121
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
SCHEDULE –VIII
(Refer to ERDMP-Regulation 28.1)
Resource Mobilisation for Road Transportation Emergencies
A. In-Plant Resources
Following items should be available at the Plant inadequate quantity / nos. Mechanical Equipment:
1. Gaskets (Carbon Asbestos Filled)
2. Studs and bolts.
3. Teflon tapes.
4. ½” / ¾” crowbar (1 m long)
5. Spade / blind flange
6. Rope (Manila / Jute)
7. Spark arrestors.
8. 1” tapered wooden pegs.
9. Chopper
10. Spare fan belt for tank lorry with P.T.O. unit
11. Wind sock
12. M-Seal / epoxy-base cold-welding compound.
13. Wooden slippers
14. Teflon-taped spanners, wrenches
15. Spark-proof wrenches hammer and tools.
16. Barricading masts and ropes / tapes
17. hoses
18. Chain pulley blocks and stay pipes
19. Small valve keys for operating valves in the tank truck
Electrical Equipment :
1. Gas Explosimeter
2. Flame-proof torches
3. Earthing wires (10 m long) with crocodile clips
Personnel Protective Equipment :
1. Gloves:
i) Rubber gloves
ii) Low Temperature Gloves
iii) Industrial gloves (with leather lining)
iv) Canvas gloves
Page | 122
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
2. Face shields
3. Ear muff / ear plugs
Other Safety Items:
1. 1 rolls of gunny / hessian cloth (about 10 meters long)
2. First aid box (containing water gel compounds)
3. Soap
4. Blanket.
5. Water Gel Blanket
6. Breathing Apparatus (With spare filled cylinder and Canister gas masks)
7. Fire proximity suit
Fire Fighting Equipment:
1. Portable Dry Chemical Powder Fire Extinguishers
2. Fire-water Hoses
3. Triple Purpose diffuser nozzle for use with fire hoses.
Communication Equipment:
1. Hand operated sirens
2. Whistles
3. Megaphone, Mobile Phones, VHF sets.
Traffic Control Equipment:
1. Red lights (Battery operated) - for traffic diversion
2. Area maps
3. Diversion Boards
B. External Resources:
Particulars Name Address Phone No. Any
Information
1. Fire Station
2. Ambulance
3. Hospitals
4. Police Station
6.District
Administration /
Collector
7. Availability of
Cranes
8. Local PWD / CPWD
water supplies, sand,
morum, vehicles etc.
9. Local Army, Navy, Air
Page | 123
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
Force authorities
10. Any major industry
nearby
C. Identification of Communication Resources:
1. Public Address
System
2. Retail Outlets
3. Railway Station
4. Power Houses
5. Civil Authorities
6. Voluntary Agencies
7. Local All India Radio
/Doordarshan/
other channels
Page | 124
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
SCHEDULE – IX
(Refer to ERDMP-Regulation 28.2)
Transport Emergency Card Format (TREM CARD)
1. Nature of Hazard:
2. Protective Devices:
3. Emergency Action
4. Spillage
5. Fire
6. First Aid
7. Chemical Abstract Service (CAS). No
(for universal acceptance of material, both number should be mentioned on TREM Card)
Emergency Telephone Numbers/mobile numbers -
Name and contact numbers of the control room/contact person of the supplying
company-
Name and contact numbers of the control room/contact person of the receiving
company
Name and contact numbers of Transporter
Other important Name and contact numbers of civic authorities, fire and police
Note: The format shall be designed in English, Hindi and local language where crews are
operating.
Page | 125
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
First Aid - Pour water in case of cold or hot burn. Seek medical help, if necessary
Emergency Telephone Numbers/mobile numbers
HPCL _______________ HPCL_______________________
BPCL _____________________ IBPL________________________
FIRE- 101 _______________ POLICE- 100_________________
Page | 126
ERDMP-HPCL LPG BOTTLING PLANT, PATNA
ANNEXURES
ANNEXURES DETAILS
1 MSDS- LPG
2 OISD-STD-144 -LIQUEFIED PETROLEUM GAS (LPG)
3 OISD-STD-150-MOUNDED BULLET-Design and Safety Requirements
4 PNGRB-GUIDELINE ON ERDMP
Page | 127
Annexure XII
:
Land Use and Latest Satellite Image (10 & 5 Km)
Annexure XIII
:
License to Store Compressed Gas in Pressure Vessel or
Vessels
Annexure XIV
:
License from Petroleum & Explosive Safety Organization
(PESO)
Annexure XV
:
Copy of Work Order