August 3, 2021

Aranaz Construction Management Consultancy


No. 48, Unit 2, RCBS Bldg., Ermin Garcia St., Pinagkaisahan, 1008 Quezon City

Attention : ENGR. ROCK S. NACARIO


Project Manager – ACMC

Thru : ARCHT. ELLIANA MARIE M. CANONIGO


ACMC – Architect

Project : ARC TOWERS (PHASE 1)


N. Bacalso Corner V. Rama Ave., Cebu City

Subject : RESPONSE – SITE OBSERVATION REPORT NO. 228- MEFPS WORKABLE AREAS

Sir’s/Maam’s,

With regards to the letter re; Site Observation Report No. 228 MEFPS Workable Areas, it can
be observed that the we are already done in the preparation process and were waiting on the arrival
of the materials. In lieu to that, we would like to request for extension on its implementation until
the materials and consumables arrive.

Thank you very much.

Prepared by:

Site Engineer – NEBT

Noted by: Received by:

Engr. Jayare M. Dizon


Project Manager - NEBT Date:
Time:

153 Libya Extension, 1800 Marikina City, Metro Manila – Philippines