You are on page 1of 4

Name of the Project METHOD

STATEMENTS
Welspun one logistic Excavation
Park Bhiwandi Doc No:01
Rev-00
Date of Rev: 30/10/2020

METHOD STATEMENT FOR EXCAVATION .

Prepared by Approved by AIL Review by Approved by


AIL CBRE client/
consultant
NAME Sujeet Kumar Mr. Gajanan Joshi

DESIGANTION Sr. QA/QC Project


Engineer Coordinator
SIGN

Page 1 of 4
Name of the Project METHOD
STATEMENTS
Welspun one logistic Excavation
Park Bhiwandi Doc No:01
Rev-00
Date of Rev: 30/10/2020

TABLE OF CONTENT

 Purpose
 Scope
 Responsibility
 Controlling Specification
 Equipment
 Work Procedure
 Inspection & Documentation
 EHS
PURPOSE
The purpose of this procedure is to provide proper guideline for supervision of all excavation
work at site to established a system to control the earth work and to ensure the proper
quality control & safety.

SCOPE OF WORK
This procedure cover supervision and method or record keeping for all excavation work
(like initial and final (GL /slope benching etc.)For foundation, road work in UG project site.

RESPONSIBILITY

 Site engineer in charge for area will be responsible for the work implementation at
site as per Method statement (M.S.)
 Safety Engineer will assist Site engineer for the compliance of safe working
methods. . He will assess the hazards in the workplace and formulate remedial
actions to eliminate, contain or reduce them.
 QC Engineer is responsible for monitoring and surveillance of daily construction
activities to ensure that the execution of works are properly implemented in
compliance with latest revisions of the approved drawings and specification
requirements
 Supervisor will monitor housekeeping workers so that they keep the work area free
of unwanted materials and unattended tools. He will ensure housekeeping principles
are being implemented
Surveyor will be responsible for the benchmark and setting of points, including exact
elevations in accordance with the approved drawing reference documents.
Page 2 of 4
Name of the Project METHOD
STATEMENTS
Welspun one logistic Excavation
Park Bhiwandi Doc No:01
Rev-00
Date of Rev: 30/10/2020

CONTROLLING SPECIFICATION
4.1 GFC Drawings
4.2 Contract doc / BOQ

MACHINERY, EQUIPMENT -)

JCB, Poclain, Jack hammers, Dumpers, Dumpers, Surface compactor, Tandom roller, Dewatering
pumps of suitable capacity, Vibratory roller / 10T Power roller.

b) Surveying Equipment

1) Theodolite, Auto level, Measuring staff,

WORK METHODOLOGY:

Preparatory works-
Excavation:

1) It shall be ensured that all necessary equipment, tools, instruments, material and consumables
including temporary facilities like platform, walkways etc. as mentioned are available at site.

2) All skilled / unskilled manpower along with supervisory personnel for carrying out work shall have
sufficient experience on similar works.

3) Excavation drawings shall clearly indicate in plan (preferably by dotted line) the part of soil to be
excavated and also levels to which excavation needs to be carried out.

4) For the purpose of understanding terminology used for soil to be excavated, soil shall be classified
in accordance with IS-1200 part I. as under:

INSPECTION & DOCUMENTATION-

Inspection-All stage wise inspections shall be carried out as per approved FQP.

Documentation-Reports and other documentations shall be generated and maintained as per


approved FQP and in the approved formats only.

Page 3 of 4
Name of the Project METHOD
STATEMENTS
Welspun one logistic Excavation
Park Bhiwandi Doc No:01
Rev-00
Date of Rev: 30/10/2020

HSE -
 Soil/edge of excavation protection safety measures need to be done with safety net and
ensure clear and safe access to work location.
 Follow work permit systemVehicular movement will be strictly restricted to approved
logistic plan.
 Safety sign / Warning sign boards will be provided around the work area.
 PPE will be ensured for all site personnel.
 Scaffolding for working platform will be provided with hand rails at mid height to
prevent fall.
 Working platform area will be kept clear of loose pies, loose clamps or unwanted
material or tools.
 All diagonal and horizontal staging pipes will be connected to vertical staging pipes.
 Proper hand rail and hard barricades will be provided around the work area and in
the area of vehicular movement respectively.
 Staging shall be checked by the competent person & Tag should be display on
scaffolding.
 Entry to the basement level will be restricted to the access stairs as indicated in the
logistic plan.
 Plant and equipment to be fully licensed and regularly serviced and inspected prior
to use.
 Fire extinguishers will be provided, located in visible locations and maintained on a
regular basis.

Page 4 of 4