Professional Documents
Culture Documents
at the
MASSACHUSETTS INSTITUTE OF TECHNOLOGY
June 2019
Massachusetts Institute of Technology 2019. All rights reserved.
Signature redacted
Author ................................................ .......
Department of Mechanical Engineering
May 19, 2019
Signature redacted
C ertified by ............................
Ahmed Ghoniem
Professor
Thesis Supervisor
Signature redacted
Accepted by.
MASSACHUSETTS INSTITUTF Nicholas Iadjiconsantitou
OF TECHNOLOGY
Chairman, Department Committee on Graduate Theses
JUN 13 2019
LIBRARIES
ARCHIVES
2
The design of a bioenergy potential map and a GIS-enabled
optimization model for biofuel production in India
by
Yan Yan
Abstract
India has a remarkably large inventory of biomass, but the operation of biorefiner-
ies has been difficult due to the uncertainty in biomass availability and the lack of
biomass supply chain management in the industry. To help biorefinery operators make
strategic decisions, this study develops a model that optimizes and evaluates the eco-
nomic viability of bioenergy/biofuel production technologies in India. To enhance the
accuracy of the simulation, bioenergy potential is mapped out using geospatial infor-
mation system, and biomass transportation distances are calculated using geospatial
network analysis. The optimization model is built as a mixed integer linear program-
ming problem to solve for the optimal locations, number and scale of the biorefinery,
and biomass flows to it. Biosynthetic natural gas (bioSNG) production technology,
GoBiGas, is used to test the model. The levelized cost of bioSNG and the ensuing
cost sensitivity analysis concludes that this particular technology configuration is not
sustainably profitable in India, but a less capital intensive technology might be able
to demonstrate otherwise.
3
4
Acknowledgments
This work would have not been possible without the funding and support from MIT
Tata center for Technology and Design. I want to thank all Tata center staff, mentors
and students for adding so much to my MIT experience.
I want to thank Professor Ghoniem for always being patient and supportive, pro-
viding me insightful guidance and the flexibility of defining my own research topic.
I also want to extend my gratitude to every member of RGD lab. I could have not
asked for a better group of colleagues, friends and mentors.
I also want to thank all the staff at MIT GIS lab for providing me tremendous
help in collecting and processing my data.
Finally I want to thank my family for their unconditional love and support for
me.
5
6
1 Introduction 15
1.1 India bioenergy outlook and challenges . . . . . . . . . . . . . . . 15
.
1.2 Key steps of biorefinery supply chain . . . . . . . . . . . . . . . . 18
.
1.2.1 Harvesting and collection . . . . . . . . . . . . . . . . . . . 18
.
1.2.2 Preprocessing . . . . . . . . . . . . . . . . . . . . . . . . . 18
.
1.2.3 Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
.
1.2.4 Transportation . . . . . . . . . . . . . . . . . . . . . . . . 19
.
7
3.4.2 GIS origin-destination algorithm . . . . . . . . . . . . . . . . . 50
3.4.3 Optimization formulation . . . . . . . . . . . . . . . . . . . . 50
4 Results 55
4.1 Total cost breakdown . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
4.2 Environmental impact . . . . . . . . . . . . . . . . . . . . . . . . . . 57
4.3 Levelized cost of bioSNG . . . . . . . . . . . . . . . . . . . . . . . . . 59
4.3.1 Future Indian natural gas market price projection . . . . . . . 59
4.3.2 Levelized gas cost calculation . . . . . . . . . . . . . . . . . . 60
4.4 Sensitivity analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
A Tables 69
8
List of Figures
1-2 Annual emissions of different pollutants in India (left), and the contri-
butions of different activities toward annual emission levels(right) . . 17
1-3 Installed biomass power generation capacity in India from 2008 to 2017
[1] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
9
2-8 Type of biomass waste that has higher energy potential at each district.
Yellow regions have higher livestock manure ; blue regions have higher
municipal solid waste production, and green regions have higher burned
agricultural residues . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
3-1 Locations and the amount of burned crop residue in Punjab, 2018 . 34
3-2 Year-round PM2 .5 concentration in some major cities in India 14] 34
3-3 The cost of collection, processing and storing per ton of straw-based
agricultural residue . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
3-4 Gap between natural gas production and demand in India from 2000
to 2016 [5] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
3-5 Illustration of the flows in the gasification section of the GoBiGas plant
of the bed material (blue), product gas ash (green), and coarse flue gas
ash (orange) [6] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
3-6 Overall system layout of GoBiGas [7] . . . . . . . . . . . . . . . . . . 38
3-7 Linear piecewise breakdown of GoBiGas capital and operating costs . 40
3-8 Capital cost breakdown of GoBiGas in India and Sweden . . . . . . . 42
3-9 Annual operational cost breakdown of GoBiGas in India and Sweden 43
3-10 GIS-enabled optimization model building processes . . . . . . . . . . 43
3-11 Agricultural residue supply spots that are proximate to the road network 44
3-12 Different classes of roads included in OpenStreetMap data . . . . . . 45
3-13 Road network adopted for transporting biomass in Punjab . . . . . . 45
3-14 Suitability filtering maps for determining optimal biomass storage cen-
ters: a.regions with burned biomass, b. rice plantation area, c. prox-
imity to road network, d. proximity to biomass suppliers, e. land cover
m ap . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
3-15 Final suitability mapping products: a. compiled suitability map, b.
regions with suitability score greater than 39, c. suitable locations
that have area greater than 5000 m 2. . . . . . . . . . . . . . . . . . . 48
3-16 Potential bioSNG plant locations (highlighted in blue) in Punjab . . 49
10
3-17 Authorized city gas distribution regions in Punjab (highlighted in blue)
and their urban population density . . . . . . . . . . . . . . . . . . . 50
11
12
List of Tables
2.1 Predictor variables that have direct impact on livestock population [9] 27
2.2 The total annual energy potential derived from different types of biomass 32
A. 1 Investment costs and scale factors for all process sections of GoBiGas
plan t . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
A.2 Auxillary equipment, project costs and their corresponding scale fac-
tors of GoBiGas plant . . . . . . . . . . . . . . . . . . . . . . . . . . 70
13
14
Chapter 1
Introduction
The large population base of India makes its energy consumption grow rapidly. It is
estimated that the country will overtake China as the world's largest energy market
by mid 2020s 112]. Conventional or fossil fuel resources are limited, so the government
has started to focus more on the development of renewable energy. As for March 2018,
the total renewable energy installed power capacity in India was 69 GW, consisting
15
mostly of wind and solar power [13], as seen in figure 1-1. Such an energy landscape
indicates there is still great renewable energy potential awaiting to be explored in the
country.
Nuclear
Wind 50%
Solar 30%
Biomass
15%
L
Small Hydro 5%
Although biomass energy only accounts for 15% of the total installed renewable
power capacity, it plays an important role in India's energy market. Around 80% of
the energy consumed in rural communities for cooking and heating is from burning
biomass such as fuel wood, crop residues, and livestock manure [14]. However, this
traditional way of utilizing biomass is neither efficient nor environmental friendly.
As shown in figure 1-2, traditional biofuel burning is a major cause of emissions,
making India the third largest CO 2 emitter in the world [15] [16]. A better way to
utilize biomass is to convert it into heat, electricity,and biofuels using new thermal,
thermochemical or biochemical conversion technologies [17]. Carefully studied and
controlled biomass reactions in these systems ensure a much more efficient and cleaner
biomass conversion.
After realizing that converting biomass into clean biopower and biofuel can both
fulfill the growing energy demand, and reduce GHG emissions, the government started
to dedicate a significant amount of financial and political support to bioenergy and
biofuel development. In 2018, the Ministry of New and Renewable Energy (MNRE)
approved Rs.170 Crores (24 million USD) to assist biomass based cogeneration projects
[18], and set the target of reaching 20% blending of bioethanol in petrol and 5% blend-
16
S02
Pollutants Total emissions (Gg/yr)
CO
SO 2 4170
CO 62,000 C02
CO 2 1,860,000 PM2.5
PM 25 4290
OM
OM (organic matter) 2120 0
OC (organic carbon) 1150 0C
BC (black carbon) 400 BC
IOM (inorganic oxidized matter) 1765 1GM
Figure 1-2: Annual emissions of different pollutants in India (left), and the contribu-
tions of different activities toward annual emission levels(right)
ing of biodiesel in diesel by 2030 [191. With these incentives, the installed biomass
power generation capacity increased to 9.5 GW in 2017 [11, as shown in figure 1-
3. However, the sustainable operation of these installed biomass power/cogeneration
plants have been challenging. According to Natarajan and Pelkonen's report, more
than 20% (1200MW) of the total installed biomass power generating capacity in
India was either temporarily or permanently shut down in 2015 [20].
12000 - - - - - - - - - - --............................................................................
10000 - - - - - - - - 9.533-
--.......................................................................
9,024
4,01 . 4,280
2,453
Figure 1-3: Installed biomass power generation capacity in India from 2008 to 2017
[1]
Unsecured biomass supply and unorganized supply chains are two biggest chal-
lenges to the sustainability and profitability of biorefineries. Agricultural based
17
biomass is often only produced in certain time periods, but biomass plants have
to operate throughout the year. If reliable biomass supply is not secured at the
beginning of the new cropping season, the plant is likely to fail to operate at full
scale in the coming year. The locations of suppliers are also critical. The low energy
density and scattered distribution of biomass makes its transportation costly. If not
planned strategically, the cost of transportation alone can make the whole operation
unprofitable.
The supply chain of biomass involves various activities such as harvesting, handling,
baling, transport, preprocessing, storage, biofuel production and distribution to de-
mand zones. The subsections below detail some main steps of biomass supply chain.
The collection of agriwaste is more challenging than other types of biomass, because it
is strictly limited to a short window during which the crop seasons transition. During
that period of time, farmers are often occupied with crop harvesting and don't want to
participating in collecting the residues. Therefore it is important to recruit personnel
to perform this task and train them to use the right harvesting tool, e.g. baler for
rice straw and shredder for cotton stalks.
1.2.2 Preprocessing
18
refaction is a mild thermal treatment of biomass at a temperature around 200-300
Co. After torrefaction, biomass turns into a charcoal form [21]. The low moisture
content and high carbon density of torrefied biomass can greatly extends its shelf-life
and transportability.
1.2.3 Storage
Biomass is often stored at a collection storage center until it is needed at the plant. To
reduce mass loss and control the quality of stored biomass, it is favorable to establish
sheltered storage at locations that have humid climate. The size and location of the
storage center is determined by the scale of the plant and biomass distribution in the
region.
1.2.4 Transportation
19
40
-
35 .Or_
_
. 30
225
20
1
0 In
91
04
0 100 200 300 400 500
Distance Traveled (in km)
-.- Truck -- CSXT: Single Car
-a- CSXT: Unit Train 65 Cars
-++- CSXT: Unit Train 90 Cars -*- Barge
Figure 1-4: Biomass transportation costs using different transportation media [2]
The challenging economic viability of bioenergy systems has attracted a growing num-
ber of researchers to look into this field. Among different types of models created for
optimizing the biorefinery operation, the majority of models focus on minimizing the
production cost of bioenergy or biofuel, while the rest explore how to minimize the
system's social and environmental footprints, or how to fulfill different criteria si-
multaneously. [21]. Mathematical programming is the most common and effective
approach for building an optimizing model. Depending on the characteristics of opti-
mization variables, objectives and constraints, models can be categorized into linear
20
8
26
05
R4
C4 -4
.3
0)If611 I II IflIII I\
If)"""P1
1"
11\iili1
w US * Canada n Europe m India m Other
Figure 1-5: Publications on biomass supply chain optimization from 1997 to 2018 by
different regions
non-integer variables indicate the biomass flow. To further enhance the accuracy of
biomass transportation route and distance, the eographical information system (GIS)
is used to incorporate real-life geospatial information, such as the road and railroad
network, land cover and population into the model [221.
The development and adoption of biorefinery supply chain and operation opti-
mization models is lacking in India. As shown in figure 1-5, among 99 publications
on biomass supply chain design and optimization published between 1997 to 2018,
only 4% of them are based on Indian cases, while the majority of the rest are based
in Europe and North America. Therefore, the goal of this study is to fill this void in
the research and practice of optimizing biorefinery profitability in India.
21
22
Chapter 2
Being able to visualize the production and distribution of biomass is the first step
toward planning and optimizing bioenergy/biofuel production. Many countries with
large biomass inventory have dedicated national research resources on mapping out
biomass distribution in their national territories, such as the Biofuels Atlas devel-
oped by NREL and Biomass Inventory Mapping and Analysis Tool developed by
the Government of Canada. The user interface of NREL's Biofuel Atlas is shown in
figure 2-1.
T..OR AllL.06.
I U' -"1"-
Fedcks
somUUU A
*
sw AS
Neureal Go,
Figure 2-2 is a biomass power potential map from the Biomass Knowledge Portal
website created by the MNRE. Its resolution, however, is too coarse to be utilized for
23
intrastate or district-level biorefinery operation planning. Therefore, in this chapter,
a more refined and comprehensive visualization tool of bioenergy potential in India
is introduced.
LNOJ ASMIL
L A
RADESEH t
A ALAND
L P KER. AD NICOBAR I ON
M2 I1 to -A
~oiteoU
--tot
2
s
to 1
a1
toa 0
Figure 2-2: Biomass power generation potential map by MNRE Biomass Knowledge
Portal
24
efficiently. 64% of them were burned in the field according to the data collected in
2014 13], as shown in figure 2-3.
Figure 2-3: Percentages of utilized and burned bioniass surplus in India [3]
The distribution of these burned agricultural residues is mapped out using re-
motely sensed terrestrial observations from NASA's Moderate Resolution Imaging
Spectroradiometer (MODIS) instruments. NASA MODIS instruments have been used
extensively for generating a suite of global land, ocean and atmospheric dataset for
science community [24]. Among this suite, MCD45A1 and MCD64A1 burned area
products map out the spatial extent and the approximate date of biomass burning.
To improve the accuracy and reliability of the burning data, especially active fires
at a small scale, scientists reprocess the data into different collections using refined
algorithms. The most recent burned area product collection is generated using the
most updated burned area mapping algorithm by the Giglio et al , and it is used to
reprocess the raw burning area data in this study 124].
After generating the burning area map, the production of crops on per kilometer
of land and the ratio between crop grain and residue productions are used to convert
the burning area to the amount of agricultural residue produced [25]. Because the
majority of burned residues are rice and wheat, the residue production rates of these
two crops are adopted at all the points.
The final product is configured into an interactive website application using the
software ArcGIS online. The interface of final product is shown in figure 2-4. Each
dot on the map represents a burning spot. The size of the circle indicates the amount
25
of bioenergy that could be generated from the local residues. The time scale bar
on the bottom of the map allows users to scroll through the year and observe the
bioenergy production and distribution in each month.
Ghanbhd
-'t61r. :7 KISTAN F
- ISA CIF N-
According to the map, the highest burning rate occurs in May and October,
corresponding to the transition periods between Kharif and Rabi cropping seasons in
India, and most of the burning takes place in northern and middle regions of India.
Aside from having high production rate of crops, India also has a large livestock
population. According the 19th India Livestock Census, the total livestock population
in the country is more than 512 million, with its bovine and buffalo populations as the
highest in the world, and goat and sheep populations coming second and third (141.
26
Unlike crops, livestock population cannot be detected by remote satellite sensing, so
the raw data for animal manure mapping is from the Indian livestock census data.
The resolution of the available census data only goes up to district level, so a series
of reprocessing steps are conducted.
Table 2.1: Predictor variables that have direct impact on livestock population [91
Anthropogenic Human population density (consensus model between Worldpop, Landscan and GPW4)
Travel time to cities of 50,000 people
Topography Elevation(GTOPO30)
Slope(GTOPO30)
Vegetation 10 Fourier-derived variables from Normalized Difference Vegetation Index from MODIS
Length of growing period
Green-up and senescence (annual cycle 1 and 2)
Cropping intensity
Forest cover
Climate 14 Fourier-derived variables from Day Land Surface Temperature (MODIS)
Precipitation
iii Choose sampling points with a balance of data coverage and quality
The correlation between existing livestock density and predictor variables can be
learned by a machine learning model to predict the population density at a smaller
scale. To achieve this, a group of sampling points are selected from the available
dataset with a balance between high coverage and preference for points with more
27
detailed census data. The same selection approach is adopted by Nicolas et. al
[26]. The predictor variable values of all the sampling points are recorded, then
70% of the sampling points are categorized as the training data, while the rest
30% as testing data.
28
a. b.
Legsd Legend
bea,_Nvestvck_cowMbed
.ss.NVGJ "Ol_maftre-vMJM
b e.-- IVeA e
aC... 0 -. T-0.. ,cmb+n.
a %5.o
.0.. -,
7 0.03
4-g+. .nj....-V.3.
.2.M 24-0..,
120...5.52..
- . 3- 7.-6
- 5.5 - 0..W6
515-06-42-056
m she~nm"e~VR
-S5.7-3.47
C. 'I d.
6~
Legend
he"e_ 56ces.33ed
A
~ ,-
3..suesc...mn.eV.MJ
... 0 -725.3 &..4. -tI.."
248.hc.es30
.-- ,
-5.47 .15.00
31.48 - 56-0
e. f.
~1%
Le..W 2 153..3sLj..,Gs.JVJWJ
-
Figure 2-5: Animal manure based bioenergy production and distribution in India.
The energy potential of a. all the manure products (GJ), b. cattle manure(MJ) , c.
chicken manure (MJ), d. sheep manure (MJ), e. pig manure (MJ), f. goat manure
(Mi)
As one of the most populated countries, India produces a large quantity of municipal
solid waste annually. As shown in figure 2-6, 58% of municipal solid waste produced
in India is biomass based (food, green and wood). Therefore, it is mapped out as a
type of biomass waste in this study.
29
m Food and green
1% 15% * Glass
2%
2 Metal
8% . Paper and carboard
m Plastic
10% * Rubber and leather
m Wood
3% * Other
4%
The random forest learning method that was used to predict the livestock pop-
ulation distribution in the previous subsection can also be used to predict human
population density, and this task was completed by an open source spatial demo-
graphic data platform called World Pop. The municipal solid waste production is
then predicted by multiplying the population density with waste production per day
per capita data provided by the World Bank. According to the World Bank's global
waste management report, the production rate in India was 0.57 kg/capita/day in
2018, and this number is predicted to increase to 0.7 kg/capita/day by 2025 [29].
The compiled MSW distribution map is shown in figure 2-7. Darker areas on the
map indicate regions with higher MSW energy potential. Those are also the re-
gions with high population densities, such as the top three populated states in the
30
P;L AAU 0 1 rI
.41
* I
N3ANW
M" WM
4, 7TAf
,0
U~~N I ~ I~ NOM.
WI PAO VM
Figure 2-7: Energy potential of annual municipal solid waste produced in India in
megajoule
The bioenergy potential of burned agriwaste, animal manure, and municipal solid
waste are shown in Table 2.4. Figure 2-8 shows which type of bioenergy has the
higher potential in each district. According to the map, the majority of districts
have higher animal or municipal solid waste than burned agricultural residues, which
explains the booming interest in anaerobic digestion to produce biogas and bioCNG
at household and industrial scales. Punjab is the only state that has higher burned
agriculture residue than two types of wastes, making it an ideal region to study
the optimization of biofuel production that uses agricultural residues, which will be
discussed full-fledgedly in the next chapter.
31
Table 2.2: The total annual energy potential derived from different types of biomass
Type of biomass waste Energy potential (TJ)
Burned agriwaste 7 x 105
Livestock manure 8.3 x 106
Municipal solid waste 2.4 x 106
WM WW"" MWOAMb M
"M .w
-7
KI
STAN
41
Th,
ti
Figure 2-8: Type of biomass waste that has higher energy potential at each district.
Yellow regions have higher livestock manure ; blue regions have higher municipal solid
waste production, and green regions have higher burned agricultural residues
32
Chapter 3
33
Punjab burning spots
with straw weight (kg)
strawamt
-A-
1139 - 164861
* 164862 - 362621
A,
* 362622 - 655113
't 4 * 655114 - 1834060
* 1834061 -5364110
* 5364111 - 12401200
* 12401201 - 23618700
Figure 3-1: Locations and the amount of burned crop residue in Punjab, 2018
200
180 'i very unhealthy
160
140 * unhealthy
120
100
80
60
16%
I unhealthy for
sensitive
groups
., 16% * moderate
40
7%/a 13%
14% 18%
20
* good
0
Delhi Delhi Delhi Fall Delhi Kolkata Kolkata Kolkata Fall Kolkata
Spring Summer Winter Spring Summer Winter
Figure 3-2: Year-round PM2 .5 concentration in some major cities in India [4]
3.2 Biomass supply chain model
The low energy density of biomass has always been a big hurdle to cost efficient
biomass supply. In India, the challenge is heightened by the compact timing of crop
34
harvesting and planting. If a company wants to collect enough biomass for a year-
round plant operation, the supply chain of biomass should be carefully planned out
ahead the harvesting season. In order to ensure the supply chain model created
in this study is practical in Indian communities, the operation model of a biomass
management company in Punjab (PRESPL) is studied and replicated.
In this model, the identification of biomass suppliers and the recruitment of labor
initiate 4-5 months before the actual harvesting season. Locals are employed and
trained to be biomass collectors. Meanwhile, storage and preprocessing centers are
built based upon the locations of biomass suppliers and potential plant locations.
Once harvesting takes place, employers cut and bale straws, then transport them to
storage centers. At a storage center, the straws will be further cut down and densified.
The preprocessed biomass is transported to the plant for the rest of the year. The
costs of collecting, processing and storing per ton of straw are shown in figure 3-3
100
10
1
W1
0 t 0.1
I-I
0.01
op C
Figure 3-3: The cost of collection, processing and storing per ton of straw-based
agricultural residue
35
3.3 Indirect gasification for bio-synthetic natural gas
(bioSNG) production
70
60
50
40
30
20
10
Figure 3-4: Gap between natural gas production and demand in India from 2000 to
2016 [5]
For the production of bioSNG, two conversion pathways have been commercially
tested: biochemical conversion using anaerobic digestion and thermochemical conver-
sion using gasification. These two methods utilize different feedstock. Biochemical
36
pathway is better at converting manure-based biomass, while thermochemical path-
way performs better at converting cellulosic biomass. Because Punjab has a large
quantity of agricultural residue, a thermochemical conversion technology called Go-
BiGas is adopted for the model.
Gothenburg Biomass Gasification Project (GoBiGas) was the first commercial
bioSNG plant that injected synthetic natural gas into Sweden's national grid. Al-
though the plant is currently shut down due to funding issue, the abundant perfor-
mance and cost data of the plant makes it a suitable subject for research. The plant
used thermal indirect gasification, during which the heat required to sustain endother-
mic gasification reactions was provided from outside the gasifier [33]. As shown in
figure 3-5, a riser column is used to transfer the heat from biomass combustion into
the gasification chamber using circulated bed materials. With this configuration, the
flue gas and the raw product gas are not mixed, so there is minimal N2 present in the
product gas, making gas cleaning and upgrading in later stages much more efficient.
In figure 3-6, the raw gas is shown to be cleaned thoroughly after exiting the gasifier,
as impurities like tar, H2 S and C02 can easily poison and deactivate methanation
catalysts.
The final output from GoBiGas is 97% of CH4 , 1.9% of H 2 and 1.1% of C02, and
the cold gas efficiency of the overall process is calculated as
_L HVSNG x VSNG
71CG = . X 100% (3.1)
LHVio X hbio
where,
According published experimental and simulation results, the cold gas efficiency of
GoBiGas was 65% [34] [7].
37
5
Limestone
~~~'J
Raw gas Flue gas
3 W--
PRE
A
9I
>1 8'
S + K2 CO3 : s
Figure 3-5: Illustration of the flows in the gasification section of the GoBiGas plant
of the bed material (blue), product gas ash (green), and coarse flue gas ash (orange)
[6]
4 12
As one of the first commercialized bioSNG plant, the cost data of the 20MW GoBiGas
has been meticulously recorded [7]. The detailed breakdown of its costs are shown
38
in Table A.1 and Table A.2. After summing up all the components, the capital and
annual operating cost of a 20MW GoBiGas plant are listed out in Table 3.1 and
Table 3.2, respectively. Both tables include values of scale factors for different cost
components. A scale factor (f) is a coefficient that helps determines the cost ratio of
two plants with different capacities using equation 3.4, where C1 and C2 denote the
costs at plant capacity V and V2, respectively.
= (V) (3.4)
C2 V2
Table 3.2: operating costs and scale factors of the 20 MW GoBiGas plant
Reactor systems (RE) and auxiliary equipment (AUX) are two major capital cost
components. The first component consists mostly the manufacturing and purchasing
costs of reactors and chemicals. The second cost component is more miscellaneous.
Expenditure on land, non-reactor facilities, engineering services, and other auxiliary
costs are all included. The total cost of auxiliary equipment and services is actually
higher than the 'cost of reactor systems, but it has a lower scale factor that makes the
cost lower for larger plants.
39
Operating cost consists expenditures associated with personnel(PR), maintenance(MA),
consumables(CS) and other operation-relevant costs (OR). Unlike capital cost, which
only needs to be made in the first year of operation, operating cost recurs annually.
The capital and operating costs of GoBiGas at scale (V) are calculated using the
costs of the 20 MW GoBiGas pilot plant and scale factors, that are listed out in Table
3.1 and 3.2.
The resulting economy of scale curves are nonlinear, meaning that as the scale
of the plant increases, the per unit production cost is reduced. Such nonlinearity
can significantly complicate the optimization model, so the curves are separated into
linear pieces as shown in figure 3-7, and the cost equations are broken into piecewise
linear equations shown in equation 3.7 and 3.8.
500
450 - CapEx
44.-+- piecewise linear CapEx
annual OpEx
400- ---+--- piecewise linear OpEx
y3=0.07x+163
350
-
300
-
250
-
y2=0.12x+91
1 200-
150
-
100- y1=0.26x+37
50 y=b.Olx+l.75
50
Figure 3-7: Linear piecewise breakdown of GoBiGas capital and operating costs
40
0.26x + 3 7 0 < x < 400
CapEx = 0.12x + 91 400 < x < 1500 (3.7)
where,
X = tons of biomass consumed per day
As the original GoBiGas was established in Sweden, to transfer this technology
from Sweden to India, the plant costs should be adjusted according to the social-
economic differences between these two countries. The Energy Sector Management
Assistance Program (ESMAP) administered by the World Bank did a comparative
study on the power sector equipment prices in India and developed countries like
US. The study showed that the most significant cost reductions come from the lower
prices of manufacturing, steel, piping, civil and engineering services in India [35].
Since these findings are applicable to different power systems, they are used to adjust
the GoBiGas cost in India. Feasible cost reductions are listed out in Table 3.3. Most
of the reductions take effect on the costs of auxiliary equipment and services due
to the cheaper prices of raw materials and services in India. The cost of reactor
systems, however, does not get noticeably decreased because a lowered investment in
this section is likely to compromise the plant's performance.
All the cost components in these two countries are plotted comparatively in fig-
ure 3-8 and 3-9. Even though the auxiliary costs are reduced significantly in India,
they are still the largest portion of the capital cost. Similarly as the capital cost, the
plant's operating cost is reduced in India. The main reason for the reduction is that
manpower and consumables like electricity are at a lower cost in India. Rapeseed oil
methyl ester (RME) is a tar scrubbing agent used in the original GoBiGas configura-
tion, and according to a report from Chalmers University of Technology, RME could
be replaced by self-cleaning heat exchangers or scrubber agent distilled from inherent
41
tar products [7]. This new approach is adopted in this cost model, so the cost of
RME is completely eliminated from the operational cost.
Table 3.3: Cost distinctions between Indian and Sweden power plants
Services
Piping, mechanical equipment and insulation
Structural steel
Civil
Auxiliary equipment
Drying and odorization
Methanation U
C02 scrubber
Premethanation
Water-gas shift reaction
H2S scrubber
Olefin hydrogenation U
Compressor
Tar adsorption (AC filter) I
Flue gas system IL
Primary product gas cleaning
Gasification and combustion
Fuel handling system
0 10000 20000 30000 40000
Capital expenditure (thousand $)
a India
42
Maintenance
Personnel
-
Activated carbon/BTX removal
*
Rapeseed oil methyl ester (RME)
electricity
Other consumables
&
Other operational costs
0 5 10 15 20 25
Operation cost ($/MWh)
m India(US$/MWh) m Sweden (US$/MWh)
Figure 3-9: Annual operational cost breakdown of GoBiGas in India and Sweden
3.4 Methodology
Biomass
availability Optimization
GIS origin- using Julia and
Road destination Gurobi solver
network algorithm Transportation
Population
43
3.4.1 Base maps generation
Biomass supplier locations are determined with locations of burned agricultural residues.
The only difference between the two maps is that supplier locations exclude burning
spots that are more than 1km away from the road network. This is based on the
assumption that it becomes impossible for collectors to manually move biomass to
the designated pick up points if the farm is more than 1km away from the nearest
road.
Figure 3-11: Agricultural residue supply spots that are proximate to the road network
Road network
The commercial value of road network data makes it difficult to acquire complete
road network data online. Fortunately, OpenStreetMap, a crowd-sourcing mapmaking
platform, provides open-source data on the global road network. Although the quality
of the data is not as high as commercial products, it is sufficient for the current
model. The data includes different classes of roads that are listed out in figure 3-12.
Roads that are categorized as minor or very small roads are eliminated, because it
is implausible to have heavy-duty trucks to drive on these small-scale roads. After
cleaning up the data, the road network in Punjab appears as in figure 3-13.
44
code layer fclaas Deseription OSwlgs
51lx roads Major roads
5111 roads motorway Motorway/freeway highway=motorway
5112 roads trunk Important roads, typically divided highway=trunk
5113 roads primary Primary roads, typically national. highway=primary
5114 roads secondary Secondary roads, typically regional. highway=secondary
5115 roads tertiary Tertiary roads, typically local. highway=tertiary
512x roads Minor Roads
5121 roads unclassified Smaller local roads highway=unclassified
5122 roads residential Roads in residential areas highway=residential
5123 roads living-street Streets where pedestrians have priority highway=living-street
5124 roads pedestrian Pedestrian only streets highway=pedestrian
513x roads Highway links (sliproads/ramps)
5131 roads motorway-link Roads that connect from one road to another highway=motorwayjink
5132 roads trunk link of the same of lower category. highway=trunklink
5133 roads primary-link highway=primary-link
5134 roads secondary link highway=secondary-link
514x roads Very small roads
5141 roads service Service roads for access to buildings, parking highway=service
lots, etc.
5142 roads track For agricultural use, in forests, etc. Often highway=track without
gravel roads. tracktype specification
5143 roads track-gradel Tracks can be assigned a "tracktype" from 1 ... with tracktype=gradel
5144 roads track-grade2 (asphalt or heavily compacted) to 5 (hardly ... with tracktype=grade2
If every single point in Punjab is proposed as a candidate site for biomass storage
center, the processing time needed for distance generation and optimization will be
extensively long. To reduce the model size and processing duration, sites that are most
45
-0 Rqq
suitable for establishing storage centers are screened out using an original suitability
mapping approach that is described in details below.
To generate a suitability map, the top criteria for a biomass storage center are
listed out first:
To fulfill the first criteria, regions that are occupied by the natural land cover and
urban establishment (figure 3-14.e), crop land (figure 3-14.a, figure 3-14.b) are elim-
inated. Even though figure 3-14.a and 3-14.b both reflect the crop land, 3-14.a are
strictly areas that have demonstrated signs of burning of difference kinds of agricul-
tural residues, while 3-14.b include all the regions that have rice plantation, whether
the crops are burned or not. To ensure that biomass can be easily transported to and
from the storage center, locations that are proximate to the road network are given
higher priority, as shown in figure 3-14.c.
Aside from the adjacency to road network, proximity to biomass supply locations
are just as crucial. To evaluate this, a smoothly surface curve is fitted over each
biomass supply location. The surface value is highest at the location of the point
and diminishes with increasing distance from the point, reaching zero at the search
radius distance from the point. The search radius r is determined by equation 3.9,
where SD is the standard distance of input points from the enter, Dm is the weighted
median of these distances and n is the number of points [371.
1 2
r = 0.9 min (SD, Dm)n- (3.9)
ln(2)
The volume underneath the surface curve equals to the amount of straw available
at the point. These smooth surface curves are called the kernel surfaces and adjacent
surfaces always 'overlay with each other. Adding these overlaid values together gives
rise to the kernel density of biomass at each output grid cell. Point with high kernel
46
.. -* W b. C. 1V
1 m 1 High: 10
10 10 Low: 1
d. e.
and u3- WupndisPennemant Sni and KefWalef I
High 10
Low .
3
M
ForseWhrubIandslapM/Penan WeIadsJtiai
GrasidsiCmpianMNaturd
Croplandstfaen
vegetaioln m oan
Figure 3-14: Suitability filtering maps for determining optimal biomass storage cen-
ters: a.regions with burned biomass, b. rice plantation area, c. proximity to road
network, d. proximity to biomass suppliers, e. land cover map.
47
4 -
-
121
26-29 *d
M 30 -32
density indicates there is more biomass in its neighborhood, and vice versa. Figure 3-
14 a-c have a suitability value assigned to each cell grid. A cell with value 10 means
it's a optimal site under that specific criteria, while 0 means the point is a least
suitable site. Although figure 3-14.e is not directly labeled with suitability values, red
and green regions correspond with value 0 while blue region is 10. The final suitability
map is generated by adding all the filter layers together, as shown in figure 3-15.a, and
the most suitable locations have the highest suitability value. Figure 3-15.b filters out
regions with values between 39 and 40, and these regions are aggregated into points
that have areas greater than 5000 m 2 in figure 3-15.c.
48
Figure 3-16: Potential bioSNG plant locations (highlighted in blue) in Punjab
Demand
49
Punjab regions
with population
density >1300
AOL
Per-km2
1300 -120.0
-1.2091 - 2027.10
-k
2D27.11 - 250.80
20.81 - 3289.70
S329.71 - 407190
4071.91 - 4887.70
487.71 - 5747.00
5747.01 - 6740.50
0740.51 - 802040
SD20.41 - 98699.50
Figure 3-17: Authorized city gas distribution regions in Punjab (highlighted in blue)
and their urban population density
All the information collected from base maps are input into the GIS software ArcMap.
As aforementioned, the Origin-Destination (OD) cost matrix analysis function in the
software is used to measures the distances between assigned origins and destinations.
In the first round of the analysis, biomass supply locations are featured as origins,
while candidate storage centers are destinations. In the second round of the analysis,
candidate storage centers are origins, and potential plant locations are destinations.
Each round of the analysis generates a distance matrix that contains the distances
between all the origins and destinations points.
The objective of the optimization model is to minimize the production cost of bioSNG.
The production cost consists of five factors: feedstock cost (CB), collection cost(Cc),
transportation cost(CT), storage and preprocessing cost(Cs) and plant cost (Cp).
50
Feedstock cost is calculated by multiplying the market price of biomass residue(cb)
with the total amount of biomass being utilized. fij is the amount of biomass trans-
ported between biomass supply location(i)and storage center (j). There are cer-
tain constraints on the amount of biomass being transported. The total transported
biomass needs to fulfill the demand (D). All the biomass transported out of location
i should not exceed its biomass inventory (b ). Similarly, all the biomass transported
into storage center j cannot go beyond its storage capacity (Si).
CB Cbfi,j (3.11)
f ,j = D (3.12)
f , < bi (3.13)
f < S3
5 (3.14)
The labor and tool cost required for harvesting per ton of agricultural residue is
summed into cc. Multiplying this unit cost with total biomass weight gives rise to
the total collection cost.
Cc ccfij (3.15)
CT = TV + Tf (3.16)
The variable cost of transporting one ton of biomass is different between from
supply locations to storage centers (tvi) and from storage centers to the plant(tv 2 ).
51
The reason is that biomass is preprocessed at the storage center and has higher
density afterwards, thus allowing twice as much biomass to be fitted onto the truck.
Therefore, t4 2 can be reduced to half of ti. In eqn. 3.17, subscript k indicates the
variable is associated with plant k. Matrices dij and dj,k contains the distance values
determined by the OD analysis.
The transportation of biomass to storage centers has a limited time window due to
the short transition period between crop seasons. However, the transportation from
storage centers to the bioSNG plant does not need to be constrained within the same
time period, and could be carried out throughout the year. Therefore, right after the
harvesting season, all the vehicles can be assigned to transport biomass from supply
locations to storage centers, and then be used to transport between storage centers
and the plant after the peak collection season. This allows the same set of vehicles
to be used for both stages of transportation, so no fixed transportation investment is
needed for the second stage (tf2 = 0).
C, = cD (3.19)
The cost of the plant consists of its capital cost(Pc) and operating cost(Po).
Operating cost is linearly proportional to the amount of consumed biomass(qk). Po,,v
is the variable operating cost, while pof is the fixed value. Since not all the candidate
plant locations will be selected, a binary variable, Ok, is introduced. During the
52
CP = PC + PO (3.20)
Ok E (0, 1) (3.22)
To reflect the piecewise linearity of the plant's capital cost, the scale of the plant is
expressed by three consecutive intervals. A, and A2 are the lower and upper bounds
of the plant at a small scale (1 = 1), A2 and A 3 are the lower and upper bounds of
the plant at a medium scale (1 2), and finally A3 and A4 are the lower and upper
bounds of the plant at a small scale (1 = 3).
Ok,I = Ok (3.26)
Ok E (0, 1) (3.28)
The variable capital costs (pl,,) are the coefficients of total capital cost equation shown
53
below, and the fixed capital costs (pef) are the constants.
qk,l = D (3.31)
k 1
54
Chapter 4
Results
The bioSNG production cost optimization model is formulated using a dynamic pro-
gramming language called Julia and solved with a commercial optimization solver
Gurobi. The locations of optimal biomass suppliers, storage centers and the plant
output from the model are shown in figure 4-1. Based on the scale result, one 80 MW
plant and two storage centers is the most cost efficient setup. Different components
of the total cost are listed out in Table 4.1. The capital cost and the fixed transporta-
tion cost in the table are annualized costs, which are computed by dividing the total
initial investment by an annualization factor, At,,. A 5% discount rate(r = 5%), 20
years of plant operation (t = 20) and 7 years of truck lifetime (t = 7) are adopted for
calculating At,,.
- 1r)-t +
At,r =r (4.1)
r
CapExa = CapEx/At,r (4.2)
Figure 4-2 shows that annual operation cost and annualized capital cost of Go-
BiGas are the two largest cost components, making transportation and other costs
55
appear insignificant in comparison.
~
0tJp
code
strg
plarI Wae"
PunbJ_ .. bumngspoWaU743N
d
mtrawjaon W ,r..
0 12431 - 107 668697 C.
Figure 4-1: Locations of optimal biomass suppliers, storage centers and bioSNG plant
Feedstock cost
7%
Annual
operation cost
23%
&storage Cost
7%
Preprocessing
Annualized
transportation
Annualized cost
capital cost 8%
37%
Figure 4:-2: Percentage of each cost component towards the total cost
56
4.2 Environmental impact
Table 4.2: Emission of pollutants from open field straw burning [10j
Name of pollutant Unit Emission level
C02 g/kg 1460
CH4 g/kg 1.2
N 20 g/kg 0.07
CO g/kg 34.7
NOx g/kg 3.1
SO 2 g/kg 2
Total particulate matter (TPM) g/kg 13
PM2 .5 g/kg 12.95
PM10 g/kg 3.7
As shown in figure 4-3, C02 is reduced by 60% from converting burned agricul-
tural residues into bioSNG, while other pollutants are reduced by an average of 98%,
meaning that the pollution from trucks' diesel exhaust is trivial compared to biomass
burning.
The emission reduction could be a source of revenue to the plant if the saved C0 2,e
is sold as carbon credit, which is a form of reward to industries that contributes to
57
Table 4.3: Emissions from the process of bioSNG production [11]
Procedure Emission Intensity(gCO /MJ bioSNG)
Pre-processing electricity 4.34
Transportation 0.65
Plant electricity 10.43
RME combustion 1.3
Gas compression into pipeline 1.65
Household usage 63
C02
PM 2.5
aPM 10
TPM
NOx
NMHC
CO
GHG mitigation. India has always been an active player in the carbon market. In
2008, the waste disposal units, plantation companies, chemical plants and municipal
corporations in India produced more than 30 million of carbon credits, which ac-
counted for 20% of the global carbon trading [39]. Since a majority of the carbon
credits produced in India were purchased by European companies in the past, it is
assumed that the carbon credits generated from the biosNG plant will be sold at the
price of European Union Allowance (EUA). Intercontinental Exchange (ICE) predicts
that EUA price will rises to $30/ton by 2022 [8], as shown in figure 4-4. This price is
used to calculate the annual carbon credit income of the plant.
58
35
30
0 25
. 20
<<15
10
5
Year \ month
Figure 4-4: European Union Allowance (EUA) price from 2017 December to 2022
December [8]
In order to determine the profitability of the plant, the levelized cost of the produced
bioSNG needs to be compared with the future market price of domestic natural gas in
India. As India relies greatly on natural gas import, its domestic natural gas price is
strongly influenced by major gas distributers like the Henry Hub. This correlation is
confirmed in figure 4-5, where the Indian natural gas prices almost overlaps with the
Henry Hub prices that were released a quarter earlier, so the Henry Hub price is used
to predict future Indian natural gas price. In figure 4-6, the future Indian natural gas
price are plotted out based on the Henry Hub price prediction provided by Alberta
Energy Regulator [40]. The orange and red lines correspond with the ceiling and the
floor of future gas prices, while the black line remains as the base price. The levelized
cost of bioSNG is compared with the future base price.
59
Pricing time scale for India
c(0 11 N% b
\'&O\
12 12
10 10
8 8
6 6
4 4
2 2
0 0
9
8
7
6
04
3~
2
0
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
-base -high -low
The levelized cost of energy is defined as the net present value of the unit-cost of
produced energy over the lifetime of a generating asset. It helps developers and
investors to understand the economic potential of a project over the long-term. In
60
this case, the levelized cost of bioSNG is calculated as:
where,
F ,Fuel cost =T
CB = Feedstock cost
Cc = Collection cost
The reason that the investment cost in the first year is different from the later
years is that initial investments like plant establishment cost and truck purchases
only need to be made in the first year. On the contrary, collection, feedstock, fuel,
storage center setup, operation and maintenance costs recur annually. As the value
of money deflates with time, the value of future expenditure and generated energy
(Et) are corrected with the discount rate r.
The levelized costs of bioSNG with different plant lifetime projections are calcu-
lated and plotted out in figure 4-7. Assuming that the plant starts its operation at
the beginning of 2019, the vertical axis corresponds with the year when the operation
stops. The lengths of horizontal bars represent the levels of levelized costs, and each
color fraction of a bar indicates a source of revenue that could be used to sustain
61
2039
2028
2027
2026
2025
2024
2023
2022
2021
2020
2019
0 0.5 1 1.5 2 2.5 3 3.5 4
$/M3
2039
2028
2027
2026
2025
2024
2023
2022
2021
2020
2019
0% 20% 40% 60% 80% 100%
mNatural gas market price * Carbon Credit m Shortfall (tariff)
Figure 4-7: Contributions of natural gas market price, carbon credit and tariff towards
the levelized costs of bioSNG as the plant's lifetime increases
the production of bioSNG. For example, the black fraction of bars is amount of the
levelized cost that could be covered by selling bioSNG at the market price of natural
gas, and the red fraction is the amount of cost that has to be covered by tariff or
other sources of external support.
62
the end of 20 years of operation. Even though the India government is known to
distribute funding to biomass plants, it is unreasonable to assume that the plant can
sustain itself by relying so heavily on tariff.
As the plant is shown to be not sustainably profitable in the previous section, this
section examines what parameters have the most significant impact over the final
cost and how much the cost can be varied by the changes in these parameters. Since
the capital cost constitutes a great portion of the total cost, it is chosen as the
main subject of this analysis. As shown in section 3.3.2, capital cost consists of two
variables: reactor system cost and auxiliary equipment and service cost. Figure 4-8
demonstrates how the capital cost curve changes as each of these variables increases
or decreases by 20%, and new capital cost curves are linearized again to be inputted
into the optimization model.
Another parameter considered for the analysis is demand. As the demand in-
creases, the scale of the plant should increase accordingly, thus the cost of production
can be driven down by the economy of scale.
The result of sensitivity analysis is shown in figure 4-9. The relationships are not
linear because as one parameter varies, the selection of supplier and site locations
could completely change. Nevertheless, consistent trends are demonstrated by data
points on all the lines. Reactor and auxiliary capital costs are positively correlated
with the levelized cost of bioSNG. As they each reduces 20%, the levelized cost de-
creases around 1.7-2.5%. Auxiliary-cost has twice as much impact on the final cost,
meaning that minimizing the expense on auxiliary equipment and service is a bet-
ter cost reduction strategy than adopting less expensive reactors. Demand, on the
other hand, has a negative correlation with the cost. If the demand increases 20%,
the levelized cost of bioSNG could be reduced 2.5%, but if the demand decreases
20%, the cost increases 3%. In this case, the nonlinearity comes from the economy
of scale. As the levelized cost of bioSNG is at most reduced by 3% with 20% change
63
reactor -20%
4 auxilay -20%
230ne
50 - b obandine
- reator+20%
-00auxary +20%
300
200
-
1004-
0
'
0 1000 2000 3000 4000 WOO 0 1000 2000 3000 4000 5000
biomass consusr
ption ton/day] biomass consumption [ton/day)
ili auary decrease by 20%cO oastiry hcr*@*@ by 20%
10 y=.22x+04 y1 -0.29x+42.62
00 1000 2000 3000 4000 5000 0 1000 2000 3000 4000 5000
biomass consumption Iton/day] biomass consumption [ton/day
Figure 4-8: Capital cost curves generated from varying reactor system cost and aux-
iliary equipment and service cost
64
4
3
0
CI0 .
0-
Figure 4-9: Change in levelized cost of bioSNG attributed to changes in capital cost
and demand
in the examined parameters, the plant is still unable to operate profitably with these
changes.
65
66
Chapter 5
The first objective of this study was to visualize the availability and distribution
of bioenergy potential in India. This was achieved by mining and reprocessing data
from remote sensing satellite images and census statistics, and then building a website
application to display the generated data. This application provides more refined and
comprehensive illustration of Indian bioenergy potential than any other existing data
sources.
After successfully visualizing the availability of bioenergy in India, it was impera-
tive to determine the economic feasibility of bioenergy/biofuel production system in
the country, so a detailed operation optimization study was carried out using the agri-
cultural residue in Punjab as the feedstock and a Sweden bioSNG production plant
(GoBiGas) as the target technology. The optimization model was programmed as a
mixed integer linear programming problem. Optimal locations of suppliers, storage
centers and plants, plant number and scale and biomass flow patterns are output from
the model. After conducting levelized cost calculation and sensitivity analysis on the
optimization result, it is concluded that GoBiGas is not a profitable technology to be
operated in India. However, this is not representative of all biomass systems. It will
be interesting to run the model with a less capital intensive technology configuration,
such as the heat pipe reformer that is being developed at FAU [41] or the anaerobic
digestion technology, and observe how the result will change.
Currently, the model assumes all the input values are fixed and certain, but this
67
assumption is invalid in real life. There are a multitude of uncertainties associated
with the real-life supply chain, e.g. the uncertainty in biomass availability, road
condition, demand and etc. All these variations combined can result in considerable
deviation from the modeled result. Therefore, uncertainty analysis should be carried
out in the future using techniques like Monte Carlo simulation, so the output is not
just a single value, but instead a probability distribution plot.
Among different sources of uncertainties, the uncertainty in biomass availability
is the most critical, because if a company plans its operations based on the projected
availability data but later finds out the biomass is not here, the whole plant's operation
could paralyze. To enhance the data accuracy, the modeled data should be reinforced
with the field data. More specifically, the farmers should be able to input their
inclination to sell or keep their biomass into the potential mapping platform. The
communication could be done through pre-season interviews or texting. Supplier
locations with positive responses from farmers would be given higher priority during
the optimization.
The ultimate goal for this optimization model is to transforms it into an interac-
tive user interface where the user can input their interested plant configuration, plant
cost and feedstock. The platform will then run the analysis and output the results
online. This is challenging currently because running geospatial analysis and opti-
mization on a large dataset usually requires advanced hardware, software and digital
storage from the local user, but with the emergence of CyberGIS, this task could be a
feasible advancement. CyberGIS is a new software framework that combines cyberin-
frastructure with geospatial and other types of big data analyses. The research in this
field was initiated in 2017 at UIUC with NSF support, aiming to tackle global-scale
problems like renewable energy implementation, population growth and emergency
management. This is a great opportunity to incorporate this new research direction
into our existing model, and enhance its usability and impact in the future.
68
Appendix A
Tables
Table A.1: Investment costs and scale factors for all process sections of GoBiGas
plant
Process systems Cost GoBiGas, kUSD Scale factor low7Scale factor Scale factor high
I Fuel handling system 5544
1.1 External fuel feeding system 0.5 0.6 0.7
1.2 Internal fuel feeding system, including lock hoppers 0.4 0.5 0.6
2 Gasification and combustion 3244
2.1 Reactors and refractory 0.6 0.7 0.8
2.2 Condensate treatment andn steam generation / 0.5 0.6 0.7
3 Primary product gas cleaning 2615
3.1 Product gas cooler / 0.6 0.7 0.8
3.2 Product gas filter / 0.6 0.7 0.8
3.3 Precoating and particle handling system, including bed material storage and feed / 0.5 0.6 0.7
3.4 Product gas scrubber / 0.6 0.7 0.8
3.5 Product gas fan and secondary cooler / 0.6 0.7 0.8
4 Flue gas system 2082
4.1 Flue gas cooler / 0.7 0.8 0.9
4.2 Flue gas filter and flue gas fan 0.7 0.8 0.9
4.3 Ash handling system / 0.7 0.8 0.9
5 Tar adsorption (AC filter) 1168
5.1 Activated carbon beds / 0.7 0.8 0.9
5.2 Regeneration system / 0.5 0.6 0.7
6 Compressor 3804 0.6 0.7 0.8
7 Olefin hydrogenation 997 0.6 0.7 0.8
8 H2S scrubber 1007 0.6 0.7 0.8
9 Water-gas shift reaction 582 0.6 0.7 0.8
10 Premethanation 567 0.6 0.7 0.8
11 C02 scrubber 1933 0.6 0.7 0.8
12 Methanation 2135 0.6 0.7 0.8
13 Drying and odorization 547 0.6 0.7 0.8
Total cost of process systems 26225
69
Table A.2: Auxillary equipment, project costs and their corresponding scale factors
of GoBiGas plant
Auxillary equipment and project costs Cost GoBiGas, kUSD Scale factor low Scale factor Scale factor high
A Auxillary equipment 16117
A.1 Flare / 0.6 0.7 0.8
A.2 Hot water system / 0.4 0.5 0.6
A.3 Instrumentation and constrol system (DCS) / 0.3 0.4 0.5
A.4 Power distribution / 0.4 0.5 0.6
A.5 Electrical and instrument installation / 0.3 0.4 0.5
A.6 Compressed air system / 0.5 0.6 0.7
A.7 Fire protection system / 0.5 0.6 0.7
A.8 Inert gas system / 0.5 0.6 0.7
A.9 Safety and security / 0.3 0.4 0.5
A.10 Laboratory and sampling system / 0.2 0.3 0.4
B Civil 24190
B.1 Ground preparation / 0.3 0.4 0.5
B.2 Foundations / 0.3 0.4 0.5
B.3 Buildings, including lights / 0.4 0.5 0.6
B.4 Explosion protection walls / 0.4 0.5 0.6
B5 HVAC / 0.5 0.6 0.7
C Structural steel 5280 0.4 0.5 0.6
D Piping, Mechanical equipment, and insulation 29330 0.5 0.6 0.7
E Services 50636
El Engineering / 0.2 0.3 0.4
E2 Construction Serivices and conunissioning / 0.2 0.3 0.4
E3 Start-up / 0.2 0.3 0.4
E4 Other project servieves / 0.2 0.3 0.4
Total cost 125554 / /
/
70
Bibliography
71
[10] B. Gadde, S. Bonnet, C. Menke, and S. Garivait, "Air pollutant emissions from
rice straw open field burning in india, thailand and the philippines," Environ-
mental Pollution, vol. 157, no. 5, p. 1554-1558, 2009.
[12] "India to surpass china as world's largest energy growth market: Bp," The
Economic Times, https://economictimes.indiatimes.com/industry/energy/oil-
gas/india-to-surpass-china-as-worlds-largest-energy-growth-market-
bp/articleshow/68010822.cms, Feb 2019.
1151 T. Boden, G. Marland, and R. Andres, "Global, regional, and national fossil-fuel
co2 emissions," Carbon Dioxide Information Analysis Center (CDIAC) Datasets,
2017.
1181 "Scheme to support promotion of biomass based cogeneration in sugar mills and
other industries in the country (up to march 2020), file no.3/141/2017-cpg,"
Ministry of New and Renewable energy, 2018.
1191 "National policy on biofuels 2018," Ministry of New and Renewable Energy, 2018.
[20] K. Natarjan and P. Pelkonen, "Exploiting the unexploited biomass energy in
india through finnish CHP solutions," 2015 4th InternationalConference on In-
formatics, Environment, Energy and Applications, vol. 82, 2015.
[21] N. Z. Atashbar, N. Labadie, and C. Prins, "Modeling and optimization of biomass
supply chains: A review and a critical look," IFA C-PapersOnLine,vol. 49, no. 12,
p. 604-615, 2016.
[221 H. Ghaderi, M. S. Pishvaee, and A. Moini, "Biomass supply chain network design:
An optimization-oriented review and analysis," Industrial Crops and Products,
vol. 94, p. 972-1000, 2016.
72
[23] "Agricultural land (percentage of land area)," The World Bank,
https://data.worldbank.org/indicator/ag.lnd.agri.zs,
2016.
[28] "Database for biomass and waste phyllis 2 by ECN. TNO," https://phyllis.nl/,
2019.
[29] S. Kaza, L. Yao, P. Bhada-Tata, and F. Van Woerden, "What a waste 2.0: A
global snapshot of solid waste management to 2050," The World Bank, 2018.
[30] "National policy for management of crop residues (NPMCR)," Ministry of Agri-
cultural of Government of India, 2014.
[31] N. Jain, A. Bhatia, and H. Pathak, "Emission of air pollutants from crop residue
burning in india," Aerosol and Air Quality Research, vol. 14, no. 1, p. 422-430,
2014.
73
[371 "ArcGIS pro: How kernel density works," https://pro.arcgis.com/en/pro-
app/tool-reference/spatial-analyst/how-kernel-density-works.html,2018.
[381 Energy Sources of Indian Households for Cooking and Lighting. 2012.
[39] J. Joseph, "Carbon credit and how you can make money from it," The Rediff
Interview, https://www.rediff.com/money/2008/feb/05interl.html, 2008.
[40] "Natural gas prices |henry hub price," Alberta Energy Regulator,
https://www. aer. ca/providing-information/data-and-reports/statistical-
reports/henry-hub, 2019.
74