NATIONAL HIGHWAYS AUTHORITY OF INDIA

(Ministry of Road Transport and Highways)

(Government of India)

Engineering Procurement and Construction (EPC)


Agreement
For
Construction of 6 lane flyovers at Boragaon, Gorchuk,
Lokhra & Basistha Junction along with six laning of
approaches from section Ch. Km 146+172 to Km 162+620 on
Guwahati Bypass (NH-37) in the state of Assam under
Bharatmala Pariyojna on EPC Basis

Schedule H

August- 2021

National Highways Authority of India


G-5&6, Sector10, Dwarka,
New Delhi -110075
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

SCHEDULE - H
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

SCHEDULE - H
See Clauses10.1 (IV) and 19.3

Contract Price Weightage

1.1 The Contract Price for this Agreement is Rs. **********


1.2 Proportions of the Contract Price for different stages of Construction of the Project Highway
shall be as specified below:

Weighta
ge in Percenta
percenta ge
Item Stage for Payment
ge to the Weighta
Contract ge
Price
1 2 3 4
Road works 49.20%
A- Widening and strengthening of existing road
including
culverts, (1) Earthwork up to top of the sub-grade 1.56%
Widening and (2) Earthwork in shoulders 0.00%
repair of
culverts. (3) Granular Sub-Base Course 5.06%
(4) Wet Mix Macadam base 6.89%
(5) Bituminous Base Course 17.09%
(6) Wearing Coat 8.37%
(7) Widening and repair of culverts 0.00%
B.1- Reconstruction/New 6-Lane Realignment /
Bypass (Flexible Pavement)
(1) Earthwork up to top of the sub-grade 7.76%
(2) Earthwork in shoulders 0.00%
(3) Granular Sub-Base Course 5.45%
(4) Wet Mix Macadam base 5.98%
(5) Bituminous Base Course 13.83%
(6) Wearing Coat 8.25%
B.2- Reconstruction/New 6-lane realignment /
bypass (Rigid Pavement)
(1) Earthwork up to top of the sub-grade 0.00%
(2) Earthwork in shoulders 0.00%
(3) Sub-Base Course 0.00%
(4) Dry Lean Concrete (DLC) Course 0.00%
(5) Pavement Quality Concrete (PQC) Course 0.00%
C.1- Reconstruction/New Service Road (Flexible
Pavement)
(1) Earthwork up to top of the sub-grade 0.83%
(2) Earthwork in shoulders 0.00%
(3) Granular Sub-Base Course 2.77%
(4) Wet Mix Macadam base 3.43%
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Weighta
ge in Percenta
percenta ge
Item Stage for Payment
ge to the Weighta
Contract ge
Price
(5) Bituminous Base Course 4.92%
(6) Wearing Coat 5.61%
C.2- Reconstruction/New Service Road (Rigid
Pavement)
(1) Earthwork up to top of the sub-grade 0.00%
(2) Sub-Base Course 0.00%
(3) Dry Lean Concrete (DLC) Course 0.00%
(4) Pavement Quality Concrete (PQC) Course 0.00%
D- Reconstruction and New Culverts on existing
road, realignments, bypasses:
Culverts (Length < 6m) 2.20%
Additional Culverts (if any)
Minor Bridges, 4.03% A.1-Widening and repair of Minor Bridges (Length>6
Underpasses, m and <60 m)
Overpasses,
Minor Bridges 0.00%
A.2-New Minor Bridges
(Length>6 m and <60 m)
(1) Foundation: On completion of the foundation work
25.31%
including foundations for wing and return walls,
abutments, piers.
(2) Sub-structure: On completion of abutments, piers
9.18%
up to the abutment/ pier cap including wing/ return/
retaining wall up to top
(3) Super-structure: On completion of the super-
12.66%
structure in all respects including Girder, Deck slab,
bearings
(4) Approaches: On completion of approaches
including Retaining walls, stone pitching, protection 1.24%
works complete in all respect, tests on completion in
all respect and fit for use
(5) Guide Bunds and River Training Works: On
0.00%
completion of Guide Bunds and river training works
complete in all respects
(6) Other Ancillary Works: On completion of wearing
3.47%
coat, expansion joints, hand rails, crash barriers, road
signs & markings, tests on completion in all respect.
B.1-Widening and Repair of Underpasses /
Overpasses
Underpasses/Overpasses 0.00%
B.2- New Underpasses (VUP,LVUP,AUP,SVUP)
/Overpasses
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Weighta
ge in Percenta
percenta ge
Item Stage for Payment
ge to the Weighta
Contract ge
Price
(1) Foundation: On completion of the foundation work
9.68%
including foundations for wing and return walls,
abutments, piers.
(2) Sub-structure: On completion of abutments, piers
2.98%
up to the abutment/ pier cap including wing/ return/
retaining wall up to top
(3) Super-structure: On completion of the super-
7.20%
structure in all respects including Girder, Deck slab,
bearings.
(4) On completion of Retaining / Reinforced earth 26.55%
walls, complete in all respect and fit for use
(5) Approaches and Other Ancillary Works: On
completion of wearing coat, expansion joints, hand
rails, crash barriers, stone pitching, protection works,
road signs & markings, tests on completion in all
respect. 1.73%
Wearing Coat (a) in case of Overpass- wearing coat
including expansion joints complete in all respects as
specified and (b) in case of underpass-rigid pavement
including drainage facility complete in all respects as
specified
B.3 Animal Underpass
Major Bridge 20.87% A.1- Widening and repairs of Major Bridges
(Length>60m)w (1) Foundation: On completion of the foundation work
orks and including foundations for return walls, abutments, 0.00%
ROB/RUB, piers.
Elevated
(2) Sub-structure: On completion of abutments, piers
Sections, 0.00%
up to the abutment/ pier cap
Flyovers
including (3) Super-structure: On completion of the super-
Viaducts, if any structure in all respects including Girder, Deck slab, 0.00%
bearings.
(4) Wearing Coat including expansion joints. 0.00%
(5) Miscellaneous Items like hand rails, crash barrier,
0.00%
road markings etc.
(6) Wing walls/return walls up to top 0.00%
(7) Guide bunds, River Training works etc. 0.00%
(8) Approaches (including Retaining walls, stone
0.00%
pitching and protection works)
A.2 – New Major Bridges:
(1) Foundation: On completion of the foundation work
including foundations for return walls, abutments, 0.00%
piers.
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Weighta
ge in Percenta
percenta ge
Item Stage for Payment
ge to the Weighta
Contract ge
Price
(2) Sub-structure: On completion of abutments, piers
0.00%
up to the abutment/ pier cap
(3) Super-structure: On completion of the super-
structure in all respects including Girder, Deck slab, 0.00%
bearings.
(4) Wearing Coat including expansion joints 0.00%
(5) Miscellaneous Items like hand rails, crash barrier,
0.00%
road markings etc.
(6) Wing walls/return walls up to top 0.00%
(7) Guide bunds, River Training works etc. 0.00%
(8) Approaches (including Retaining walls, stone
0.00%
pitching and protection works)
B.1-Widening and repair of
(a) ROB
(b) RUB
(1) Foundation 0.00%
(2) Sub-structure 0.00%
(3) Super-Structure (Including bearings) 0.00%
(4) Wearing Coat (a) in case of ROB- wearing coat
including expansion joints complete in all respects as
specified and (b) in case of RUB-rigid pavement under 0.00%
RUB including drainage facility complete in all
respects as specified
(5) Miscellaneous Items like hand rails, crash barrier,
0.00%
road markings etc.
(6) Wing walls/Return walls 0.00%
(7) Retaining / Reinforced earth walls 0.00%
(8) Approaches and Other Ancillary Works (wearing
coat, expansion joints, hand rails, crash barriers, road
0.00%
signs & markings, stone pitching, protection works
etc.)
B.2- New ROB/RUB
(a) ROB
(b) RUB
(1) Foundation 0.00%
(2) Sub-structure 0.00%
(3) Super-Structure (Including bearings) 0.00%
(4) Wearing Coat (a) in case of ROB- wearing coat
including expansion joints complete in all respects as
0.00%
specified and (b) in case of RUB-rigid pavement under
RUB including drainage facility complete in all
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Weighta
ge in Percenta
percenta ge
Item Stage for Payment
ge to the Weighta
Contract ge
Price
respects as specified

(5) Miscellaneous Items like hand rails, crash barrier,


0.00%
road markings etc.
(6) Wing walls/Return walls 0.00%
(7) Retaining / Reinforced earth walls 0.00%
(8) Approaches and Other Ancillary Works (wearing
coat, expansion joints, hand rails, crash barriers, road
0.00%
signs & markings, stone pitching, protection works
etc.)
C.1-Widening and repair of Elevated
sections/Flyover/Grade separators
1) Foundation 0.00%
(2) Sub-structure 0.00%
(3)Super-structure (including bearings) 0.00%
(4) Wearing coat including expansion joints 0.00%
(5) Miscellaneous Items (like hand rails, crash barriers
0.00%
road marking etc.)
(6) Wing walls/Return walls 0.00%
(7) Retaining / Reinforced earth walls 0.00%
(8) Approaches and Other Ancillary Works (wearing
coat, expansion joints, hand rails, crash barriers, road
0.00%
signs & markings, stone pitching, protection works
etc.)
C.2-New Elevated section/ Flyovers/ Grade
Separators. Borgaon
(1) Foundation: On completion of the foundation work
including foundations for wing and return walls, 6.13%
abutments, piers.
(2) Sub-structure: On completion of abutments, piers
up to the abutment/ pier cap including wing/ return/ 1.63%
retaining wall up to top
(3) Super-structure: On completion of the super-
structure in all respects including Girder, Deck slab, 4.36%
bearings.
(4) Wearing Coat including expansion joints 0.67%
(5) Miscellaneous Items like hand rails, crash barrier,
0.24%
road markings etc.
(6) Wing walls/Return walls 0.00%
(7) Retaining / Reinforced earth walls 9.82%
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Weighta
ge in Percenta
percenta ge
Item Stage for Payment
ge to the Weighta
Contract ge
Price
(8) Approaches and Other Ancillary Works
0.00%
(Approaches, stone pitching, protection works, etc.)
C.3-New Elevated section/ Flyovers/ Grade
Separators. FO Garchuk
(1) Foundation: On completion of the foundation work
including foundations for wing and return walls, 6.13%
abutments, piers.
(2) Sub-structure: On completion of abutments, piers
up to the abutment/ pier cap including wing/ return/ 1.63%
retaining wall up to top
(3) Super-structure: On completion of the super-
structure in all respects including Girder, Deck slab, 4.02%
bearings.
(4) Wearing Coat including expansion joints 0.67%
(5) Miscellaneous Items like hand rails, crash barrier,
0.24%
road markings etc.
(6) Wing walls/Return walls 0.00%
(7) Retaining / Reinforced earth walls 10.25%

(8) Approaches and Other Ancillary Works


0.00%
(Approaches, stone pitching, protection works, etc.)

C.4-New Elevated section/ Flyovers/ Grade


Separators. FO Lokhara
(1) Foundation: On completion of the foundation work
including foundations for wing and return walls, 10.11%
abutments, piers.
(2) Sub-structure: On completion of abutments, piers
up to the abutment/ pier cap including wing/ return/ 1.77%
retaining wall up to top
(3) Super-structure: On completion of the super-
structure in all respects including Girder, Deck slab, 4.60%
bearings.
(4) Wearing Coat including expansion joints 0.67%
(5) Miscellaneous Items like hand rails, crash barrier,
0.24%
road markings etc.
(6) Wing walls/Return walls 0.00%
(7) Retaining / Reinforced earth walls 10.78%

(8) Approaches and Other Ancillary Works


0.00%
(Approaches, stone pitching, protection works, etc.)

C.5-New Elevated section/ Flyovers/ Grade


Separators. FO Bashishta
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Weighta
ge in Percenta
percenta ge
Item Stage for Payment
ge to the Weighta
Contract ge
Price
(1) Foundation: On completion of the foundation work
including foundations for wing and return walls, 7.05%
abutments, piers.
(2) Sub-structure: On completion of abutments, piers
up to the abutment/ pier cap including wing/ return/ 1.69%
retaining wall up to top
(3) Super-structure: On completion of the super-
structure in all respects including Girder, Deck slab, 5.27%
bearings.
(4) Wearing Coat including expansion joints 0.43%
(5) Miscellaneous Items like hand rails, crash barrier,
0.24%
road markings etc.
(6) Wing walls/Return walls 0.00%
(7) Retaining / Reinforced earth walls 11.36%

(8) Approaches and Other Ancillary Works


0.00%
(Approaches, stone pitching, protection works, etc.)

Other works 20.10% (i) Toll Plaza 0.00%


(ii) Road side drains 0.00%
Lined Drain 40.26%
Unlined Drain 0.00%
(iii) Road signs, safety Devices, Road Furnitures etc. 28.76%
(iv) Road markings & Studs 3.03%
(v) Crash Barrier 1.49%
(vi) Project facilities 0.00%
a) Bus Bays 0.00%
b) Wayside Amenities excluding Slip Roads & but
including all internal roads (Service areas including 0.00%
Truck Lay-Byes)
c) Others (to be specified) 0.00%
(vii) Retaining Wall 0.00%
(viii) RE Wall 0.00%
(ix) Street Lighting 3.08%
(x) Utility Ducts 0.50%
(xi) Noise Barrier at Tunnel Approaches 0.00%
(xii) Boundary wall 0.00%
(xiii) Road side Plantation including Horticulture in
0.00%
Wayside Amenities
(xiv) Protection Works other than approaches to the
bridges, elevated sections/ flyover/ grade separators 0.00%
and ROBs/ RUBs
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Weighta
ge in Percenta
percenta ge
Item Stage for Payment
ge to the Weighta
Contract ge
Price
(xv) ATMS 0.00%
(xvi) Safety & Traffic Management during const. 1.79%
(xvii) Other miscellaneous works including Connecting
21.09%
road & Junction under Grade separator
Electrical 5.80% (i) EHT Line 50.66%
utilities and (ii) EHT Crossings 0.00%
public health
(iii) HT/LT line 39.23%
utilities (Water
Pipe Lines and (iv) HT/LT crossings 10.11%
Sewage Line) (v) Shifting, Re-installation of Street Lighting, High
0.00%
Mast Lighting
(vi) Water pipeline crossings. 0.00%
(vii) Sewage lines 0.00%
(vii) Sewage lines Crossings 0.00%

1.3 Procedure of estimating the value of work done.

1.3.1 Road works.

Procedure for estimating the value of road work done shall be as follows:

Table 1.3.1
Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
A-Widening and strengthening of
Existing Road
(1) Earthwork up to top of the sub-
1.56%
grade Unit of measurement is linear
(2) Earthwork in shoulders 0.00% length. Payment of each stage shall
be made on pro rata basis on
(3) Sub-Base Course 5.06%
completion of a stage in a length of
(4) Non Bituminous Base 6.89% not less than 10 (ten) percent of the
(5) Bituminous Base Course 17.09% total length.
(6) Wearing Coat 8.37%
Cost of ten completed culverts shall
be determined on pro rata basis
with respect to the total number of
(7) Widening and repair of culverts 0.00%
culverts. Payment shall be made on
the completion of at least five
culverts.
B.1- Reconstruction/New 6-Lane
Realignment / Bypass (Flexible
Pavement)
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
(1) Earthwork up to top of the sub-
7.76%
grade Unit of measurement is linear
(2) Earthwork in shoulders 0.00% length. Payment of each stage shall
be made on pro rata basis on
(3) Granular Sub-Base Course 5.45%
completion of a stage in full length
(4) Wet Mix Macadam base 5.98% or 5(five) km length whichever is
(5) Bituminous Base Course 13.83% less.
(6) Wearing Coat 8.25%
B.2- Reconstruction / New 6-lane
realignment / bypass (Rigid
Pavement)
(1) Earthwork up to top of the sub-
0.00%
grade
Unit of measurement is linear
(2) Earthwork in shoulders 0.00% length. Payment of each stage shall
(3) Sub-Base Course 0.00% be made on pro rata basis on
(4) Dry Lean Concrete (DLC) completion of a stage in full length
0.00% or 5(five) km length, whichever is
Course
less.
(5) Pavement Quality Concrete
0.00%
(PQC) Course
C.1- Reconstruction/New Service
Road (Flexible Pavement)
(1) Earthwork up to top of the sub-
0.83%
grade Unit of measurement is linear
(2) Earthwork in shoulders 0.00% length. Payment of each stage shall
be made on pro rata basis on
(3) Sub-Base Course 2.77%
completion of a stage in full length
(4) Wet Mix Macadam base 3.43% or 5(five) km length, whichever is
(5) Bituminous Base Course 4.92% less.
(6) Wearing Coat 5.61%
C.2- Reconstruction/New Service
Road (Rigid Pavement )
(1) Earthwork up to top of the sub-
0.00% Unit of measurement is linear
grade
length. Payment of each stage shall
(2) Sub-Base Course 0.00%
be made on pro rata basis on
(3) Dry Lean Concrete (DLC) completion of a stage in full length
0.00%
Course or 5(five) km length, whichever is
(4) Pavement Quality Concrete less.
0.00%
(PQC) Course
D- Reconstruction & New
Culverts on existing road,
realignments, bypasses
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
Cost of each culvert shall be
determined on pro rata basis with
respect to the total number of
(1) Culverts (Length < 6m) 2.20%
culverts. Payment shall be made on
the completion of at least five
culverts
Cost of each additional culvert shall
be determined on pro rata basis
with respect to the total number of
(2) Additional Culverts 0.00%
culverts. Payment shall be made on
the completion of at least five
culverts
@. For example, if the total length of bituminous work to be done is 100 km, the cost per km of
bituminous work shall be determined as follows:

Cost per km = P x Weightage for road work x Weightage for bituminous work x (1/L)

Where P= Contract Price

L = Total length in km

Similarly, the rates per km for other stages shall be worked out accordingly.

Note: The length affected due to law and order problems or litigation during execution due
to which the Contractor is unable to execute the work, may be deducted from the
total project length for payment purposes. The total length calculated here is only for
payment purposes and will not affect and referred in other clauses of the Contract
Agreement.
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

1.3.2 Minor Bridges and Underpasses/Overpasses

Procedure for estimating the value of Minor bridge and Underpasses/Overpasses shall be as
stated in table 1.3.2:

Table 1.3.2
Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
Cost of each minor bridge shall be
determined on pro- rata basis with
A.1. Widening and Repair of minor respect to the total linear length of the
0.00%
bridges (length >6m and < 60m) minor bridges. Payment shall be
made on the completion of widening
and repair works of a minor bridge.
A.2.- New Minor bridges
Foundation: Cost of each minor
bridge shall be determined on pro-
rata basis with respect to the total
linear length (m) of the minor bridges.
Payment against foundation shall be
(1) Foundation: On completion of the
made on pro-rata basis on completion
foundation work including 25.31%
of a stage i.e. not less than 25% of
foundations for wing and return walls,
the scope of foundation of each
abutments, piers.
bridge.
In case where load testing is required
for foundation, the trigger of first
payment shall include load testing
also where specified.
Sub-structure: Cost of each minor
bridge shall be determined on pro-
rata basis with respect to the total
(2) Sub-structure: On completion of
linear length (m) of the minor bridges.
abutments, piers up to the abutment/ 9.18%
Payment against sub-structure shall
pier cap including wing/ return/
be made on pro-rata basis on
retaining wall up to top
completion of a stage i.e. not less
than 25% of the scope of sub-
structure of each bridge.
Super-structure: Payment shall be
made on pro-rata basis on completion
of a stage i.e. completion of super
structure of at least one span in all
respects as specified in the column of
(3) Super-structure: On completion "Stage of Payment" in this sub-clause.
12.66%
of the super-structure in all respects In case of structures where pre-cast
including Girder, Deck slab, bearings girders have been proposed by the
Contractor, 50% of the stage payment
shall be due and payable on casting
of girders for each span and balance
50% of the stage payment shall be
made on completion of stage
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
specified as above
Approaches: Payment shall be made
(4) Approaches: On completion of
on pro-rata basis on completion of a
approaches including Retaining
1.24% stage i.e. completion of approaches in
walls, stone pitching, protection
all respect as specified in the column
works complete in all respect and fit
of "Stage of Payment" in this sub-
for use
clause.
Guide Bunds and River Training
Works:
(5) Guide Bunds and River Training
Payment shall be made on pro-rata
Works: On completion of Guide 0.00%
basis on completion of a stage i.e.
Bunds and river training works
completion of Guide Bunds and River
complete in all respects
training Works in all respects as
specified
(6) Other Ancillary Works: On
Other Ancillary Works: Payment shall
completion of wearing coat,
3.47% be made on pro-rata basis on
expansion joints, hand rails, crash
completion of a stage in all respects
barriers, road signs & markings, tests
as specified
on completion in all respect.
Cost of each underpass/overpass
shall be determined on pro rata basis
with respect to the total linear length
B.1- Widening and repairs of
0.00% of the underpasses/ overpasses.
underpasses/overpasses
Payment shall be made on the
completion of widening & repair works
of a underpass/overpass.
B.2. New Underpasses/Overpasses

Foundation: Cost of each Underpass/


Overpass shall be determined on pro-
rata basis with respect to the total
linear length (m) of the
Underpasses/Overpasses.
(1) Foundation: On completion of the
Payment against foundation shall be
foundation work including 9.68%
made on pro-rata basis on completion
foundations for wing and return walls,
of a stage i.e. not less than 25% of
abutments, piers.
the scope of foundation of each
Underpasses/ Overpasses.
In case where load testing is required
for foundation, the trigger of first
payment shall include load testing
also where specified.
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
Sub-structure: Cost of each
Underpass/ Overpass shall be
determined on pro- rata basis with
respect to the total linear length (m) of
(2) Sub-structure: On completion of
the Underpasses/ Overpasses.
abutments, piers up to the abutment/ 2.98%
Payment against sub-structure shall
pier cap including wing/ return/
be made on pro-rata basis on
retaining wall up to top
completion of a stage i.e. not less
than 25% of the scope of sub-
structure of each
Underpasses/Overpasses.
Super-structure: Payment shall be
made on pro-rata basis on completion
of a stage i.e. Completion of super-
structure of at least one span in all
respects as specified in the column of
"Stage of Payment" in this sub-clause.
(3) Super-structure: On completion of
7.20% In case of structures where pre-cast
the super-structure in all respects
girders have been proposed by the
including Girder, Deck slab, bearings
Contractor, 50% of the stage payment
shall be due and payable on casting
of girders for each span and balance
50% of the stage payment shall be
made on completion of stage
specified as above
(4) On completion of Retaining / Payments shall be made on pro rata
26.55%
Reinforced earth walls complete in all basis on completion of 20% of the
respect and fit for use total area.
(5) Approaches and Other Ancillary
Works: On completion of wearing
coat, expansion joints, hand rails, Payment shall be made on pro-rata
1.73%
crash barriers, road signs & basis on completion of a stage in all
markings, stone pitching, protection respects as specified
works, tests on completion in all
respect.

1.3.3 Major Bridge works ROB/RUB and Structures.

Procedure for estimating the value of Major Bridge works, ROB/RUB and

Structures shall be as stated in table 1.3.3:


Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Table 1.3.3

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
A.1.- Widening and
Repairs of Major Bridges
Foundation: Cost of each Major Bridge shall
be determined on pro rata basis with respect
to the total linear length (m) of the Major
(1) Foundation: On
Bridge. Payment against foundation shall be
completion of the foundation
made on pro-rata basis on completion of a
work including foundations 0.00%
stage i.e. not less than 25% of the scope of
for return walls, abutments,
foundation of the major Bridge.
piers.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.
(2) Sub-structure: On Sub-structure: Payment against sub-structure
completion of abutments, shall be made on pro-rata basis on completion
0.00%
piers up to the abutment/ of a stage i.e. not less than 25% of the scope
pier cap of sub-structure of major bridge.
Super-structure: Payment shall be made on
pro-rata basis on completion of a stage i.e.
completion of super-structure including
(3) Super-structure: On bearings of at least one span in all respects
completion of the super- as specified. In case of structures where pre-
structure in all respects 0.00% cast girders have been proposed by the
including Girder, Deck slab, Contractor, 50% of the stage payment shall
bearings be due and payable on casting of girders for
each span and balance 50% of the stage
payment shall be made on completion of
stage specified as above
Wearing Coat: Payment shall be made on
(4) Wearing Coat including completion of wearing coat including
0.00%
expansion joints expansion joints complete in all respects as
specified.
Miscellaneous: Payments shall be made on
(5) Miscellaneous Items like
completion of all miscellaneous works like
hand rails, crash barrier, 0.00%
hand rails, crash barriers, road markings etc.
road markings etc.
complete in all respects as specified.
Wing walls/return walls: Payments shall be
(6) Wing walls/return walls
0.00% made on completion of all wing walls/return
up to top
walls complete in all respects as specified.
Guide Bunds, River Training works:
(7) Guide bunds, River Payments shall be made on completion of all
0.00%
Training works etc. guide bunds/river training works etc. complete
in all respects as specified.
(8) Approaches (including Approaches: Payments shall be made on
Retaining walls, stone 0.00% pro rata basis on completion of 10% of the
pitching and protection scope of each stage.
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
works)

A.2. New Major Bridges


Foundation: Cost of each Major Bridge shall
be determined on pro rata basis with respect
to the total linear length (m) of the Major
(1) Foundation: On
Bridge. Payment against foundation shall be
completion of the foundation
made on pro-rata basis on completion of a
work including foundations 0.00%
stage i.e. not less than 25% of the scope of
for return walls, abutments,
foundation of the major Bridge.
piers.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.
(2) Sub-structure: On Sub-structure: Payment against sub-structure
completion of abutments, shall be made on pro-rata basis on completion
0.00%
piers up to the abutment/ of a stage i.e. not less than 25% of the scope
pier cap of sub-structure of major bridge.
Super-structure: Payment shall be made on
pro-rata basis on completion of a stage i.e.
completion of super-structure including
(3) Super-structure: On bearings of at least one span in all respects
completion of the super- as specified. In case of structures where pre-
structure in all respects 0.00% cast girders have been proposed by the
including Girder, Deck slab, Contractor, 50% of the stage payment shall
bearings be due and payable on casting of girders for
each span and balance 50% of the stage
payment shall be made on completion of
stage specified as above
Wearing Coat: Payment shall be made on
(4). Wearing Coat including completion of wearing coat including
0.00%
expansion joints expansion joints complete in all respects as
specified.
Miscellaneous: Payments shall be made on
(5) Miscellaneous Items like
completion of all miscellaneous works like
hand rails, crash barrier, 0.00%
hand rails, crash barriers, road markings etc.
road markings etc.
complete in all respects as specified.
Wing walls/return walls: Payments shall be
(6) Wing walls/return walls
0.00% made on completion of all wing walls/return
up to top
walls complete in all respects as specified.
Guide Bunds, River Training works:
(7). Guide Bunds, River Payments shall be made on completion of all
0.00%
Training works etc. guide bunds/river training works etc. complete
in all respects as specified.
(8) Approaches (including
Approaches: Payments shall be made on pro
Retaining walls, stone
0.00% rata basis on completion of 10% of the scope
pitching and protection
of each stage.
works)
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
B.1.- Widening and repairs
of
(a) ROB
(b) RUB
(i). Foundation: Cost of each ROB/RUB shall
be determined on pro- rata basis with respect
to the total linear length (m) of the
ROBs/RUBs. Payment against foundation
shall be made on pro-rata basis on completion
of a stage i.e. not less than 25% of the scope
(1) Foundation 0.00%
of foundation the ROB/RUB subject to
completion of at least two foundations of the
ROB/RUB. In case where load testing is
required for foundation, the trigger of first
payment shall include load testing also where
specified.
(ii). Sub-structure: Payment against Sub-
structure shall be made on pro-rata basis on
completion of a stage i.e. not less than 25% of
(2)Sub-structure: 0.00% the scope of sub-structure of the ROB/RUB
subject to completion of at least two sub-
structures of abutments/piers up to
abutment/pier cap level of the ROB/RUB
(iii) Super-structure: Payment shall be made
on pro-rata basis on completion of a stage i.e.
(3) Super-structure (Girder +
0.00% completion of super-structure including
Deck slab)
bearings of at least one span in all respects
as specified
(4). Wearing Coat including (iv) Wearing Coat: Payment shall be made on
expansion joints in case of completion of (a) in case of ROB- wearing
ROB. In case of RUB, rigid coat including expansion joints complete in all
0.00%
pavement under RUB respects as specified and (b) in case of RUB-
including drainage facility as rigid pavement under RUB including drainage
specified. facility complete in all respects as specified.
(v). Miscellaneous: Payment shall be made on
(5). Miscellaneous items like
completion of all miscellaneous items like
hand rails, crash barriers, 0.00%
hand rails, crash barriers, road markings etc.
road markings etc
s complete in all respects as specified
(6). Approaches (including (vii). Approaches: Payment shall be made on
Retaining walls, stone completion of both approaches including
0.00%
pitching and protection stone pitching and protection works etc.
works) complete in all respects as specified
B.2- New ROB/ RUB
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
Foundation: Cost of each ROB/RUB shall be
determined on pro rata basis with respect to
the total linear length (m) of the ROB/RUB.
Payment against foundation shall be made on
pro-rata basis on completion of a stage i.e.
(1) Foundation 0.00% not less than 25% of the scope of foundation
of the ROB/RUB.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.

Sub-structure: Payment against sub-structure


shall be made on pro-rata basis on completion
(2) Sub-structure: 0.00%
of a stage i.e. not less than 25% of the scope
of sub-structure of ROB/RUB.
Super-structure: Payment shall be made on
pro-rata basis on completion of a stage i.e.
completion of super-structure including
bearings of at least one span in all respects
as specified. In case of structures where pre-
(3) Super-structure
0.00% cast girders have been proposed by the
(including bearing)
Contractor, 50% of the stage payment shall
be due and payable on casting of girders for
each span and balance 50% of the stage
payment shall be made on completion of
stage specified as above
Wearing Coat: Payment shall be made on
(4) Wearing Coat including completion
expansion joints in case of (a) in case of ROB- wearing coat including
ROB. In case of RUB-rigid expansion joints complete in all respects as
0.00%
pavement under RUB specified and
including drainage facility as (b) in case of RUB-rigid pavement under RUB
specified including drainage facility complete in all
respects as specified.
Miscellaneous: Payments shall be made on
(5) Miscellaneous Items like
completion of all miscellaneous works like
hand rails, crash barrier, 0.00%
hand rails, crash barriers, road markings etc.
road markings etc.
complete in all respects as specified.
Wing walls/return walls: Payments shall be
(6) Wing walls/return walls 0.00% made on completion of all wing walls/return
walls complete in all respects as specified.
(7) On completion of
Retaining / Reinforced earth Payments shall be made on pro rata basis on
0.00%
walls complete in all respect completion of 20% of the total area.
and fit for use
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
(1) On completion of
Retaining / Reinforced earth
walls complete in all respect
and fit for use
Payments shall be made on pro rata basis on
(2) Approaches and Other
completion of 20% of the total area.
Ancillary Works: On
0.00% Payment shall be made on pro-rata basis on
completion of wearing coat,
completion of a stage in all respects as
expansion joints, hand rails,
specified
crash barriers, road signs &
markings, stone pitching,
protection works, tests on
completion in all respect.
C.1- Widening and repairs
of Elevated
Section/Flyovers/Grade
Separators
Foundation: Cost of each structure shall be
determined on pro rata basis with respect to
the total linear length (m) of the structure.
Payment against foundation shall be made on
pro-rata basis on completion of a stage i.e.
(1) Foundation 0.00%
not less than 25% of the scope of foundation
of the structure.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.
Sub-structure: Payment against sub-structure
shall be made on pro-rata basis on completion
(2) Sub-structure: 0.00%
of a stage i.e. Not less than 25% of the
scope of sub-structure of structure.
Super-structure: Payment shall be made on
pro-rata basis on completion of a stage i.e.
completion of super-structure including
(3) Super-structure: On bearings of at least one span in all respects
completion of the super- as specified. In case of structures where pre-
structure in all respects 0.00% cast girders have been proposed by the
including Girder, Deck slab, Contractor, 50% of the stage payment shall
bearings be due and payable on casting of girders for
each span and balance 50% of the stage
payment shall be made on completion of
stage specified as above
Wearing Coat: Payment shall be made on
(4) Wearing Coat including completion of wearing coat including
0.00%
expansion joints expansion joints complete in all respects as
specified.
Miscellaneous: Payments shall be made on
(5) Miscellaneous Items like
completion of all miscellaneous works like
hand rails, crash barrier, 0.00%
hand rails, crash barriers, road markings etc.
road markings etc.
complete in all respects as specified.
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
Wing walls/return walls: Payments shall be
(6) Wing walls/return walls 0.00% made on completion of all wing walls/return
walls complete in all respects as specified.
(7) On completion of
Retaining / Reinforced earth Payments shall be made on pro rata basis on
0.00%
walls complete in all respect completion of 20% of the total area.
and fit for use
(8) Approaches and Other
Ancillary Works: On
completion of wearing coat,
Payment shall be made on pro-rata basis on
expansion joints, hand rails,
0.00% completion of a stage in all respects as
crash barriers, road signs &
specified
markings, stone pitching,
protection works, tests on
completion in all respect.
C.2-New Elevated section/
Flyovers/ Grade
Separators. Borgaon
Foundation: Cost of each structure shall be
determined on pro rata basis with respect to
the total linear length (m) of the structure.
(1) Foundation: On
Payment against foundation shall be made on
completion of the foundation
6.13% pro-rata basis on completion of a stage i.e.
work including foundations
not less than 25% of the scope of foundation
for wing and return walls,
of the structure.
abutments, piers.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.
(2) Sub-structure: On
completion of abutments, Sub-structure: Payment against sub-structure
piers up to the abutment/ 1.63% shall be made on pro-rata basis on completion
pier cap including wing/ of a stage i.e. Not less than 25% of the
return/ retaining wall up to scope of sub-structure of structure.
top
Super-structure: Payment shall be made on
pro-rata basis on completion of a stage i.e.
completion of super-structure including
(3) Super-structure: On bearings of at least one span in all respects
completion of the super- as specified. In case of structures where pre-
4.36%
structure in all respects cast girders have been proposed by the
including Girder, Deck slab, Contractor, 50% of the stage payment shall
bearings. be due and payable on casting of girders for
each span and balance 50% of the stage
payment shall be made on completion of
stage specified as above
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
Wearing Coat: Payment shall be made on
(4) Wearing Coat including 0.67% completion of wearing coat including
expansion joints expansion joints complete in all respects as
specified.
Miscellaneous: Payments shall be made on
(5) Miscellaneous Items like
0.24% completion of all miscellaneous works like
hand rails, crash barrier,
hand rails, crash barriers, road markings etc.
road markings etc.
complete in all respects as specified.
Wing walls/return walls: Payments shall be
0.00%
(6) Wing walls/Return walls made on completion of all wing walls/return
walls complete in all respects as specified
(7) Retaining / Reinforced 9.82% Payments shall be made on pro rata basis on
earth walls completion of 20% of the total area.

(8) Approaches and Other


Payment shall be made on pro-rata basis on
Ancillary Works
0.00% completion of a stage in all respects as
(Approaches, stone pitching,
specified
protection works, etc.)

C.3-New Elevated section/


Flyovers/ Grade
Separators. FO Garchuk

Foundation: Cost of each structure shall be


determined on pro rata basis with respect to
the total linear length (m) of the structure.
(1) Foundation: On
Payment against foundation shall be made on
completion of the foundation
6.13% pro-rata basis on completion of a stage i.e.
work including foundations
not less than 25% of the scope of foundation
for wing and return walls,
of the structure.
abutments, piers.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.
(2) Sub-structure: On
completion of abutments, Sub-structure: Payment against sub-structure
piers up to the abutment/ 1.63% shall be made on pro-rata basis on completion
pier cap including wing/ of a stage i.e. Not less than 25% of the
return/ retaining wall up to scope of sub-structure of structure.
top
Super-structure: Payment shall be made on
pro-rata basis on completion of a stage i.e.
(3) Super-structure: On completion of super-structure including
completion of the super- bearings of at least one span in all respects
4.02%
structure in all respects as specified. In case of structures where pre-
including Girder, Deck slab, cast girders have been proposed by the
bearings. Contractor, 50% of the stage payment shall
be due and payable on casting of girders for
each span and balance 50% of the stage
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
payment shall be made on completion of
stage specified as above

Wearing Coat: Payment shall be made on


(4) Wearing Coat including 0.67% completion of wearing coat including
expansion joints expansion joints complete in all respects as
specified.
Miscellaneous: Payments shall be made on
(5) Miscellaneous Items like
0.24% completion of all miscellaneous works like
hand rails, crash barrier,
hand rails, crash barriers, road markings etc.
road markings etc.
complete in all respects as specified.
Wing walls/return walls: Payments shall be
0.00%
(6) Wing walls/Return walls made on completion of all wing walls/return
walls complete in all respects as specified
(7) Retaining / Reinforced 10.25% Payments shall be made on pro rata basis on
earth walls completion of 20% of the total area.

(8) Approaches and Other


Payment shall be made on pro-rata basis on
Ancillary Works
0.00% completion of a stage in all respects as
(Approaches, stone pitching,
specified
protection works, etc.)

C.4-New Elevated section/


Flyovers/ Grade
Separators. FO Lokhara
Foundation: Cost of each structure shall be
determined on pro rata basis with respect to
the total linear length (m) of the structure.
(1) Foundation: On
Payment against foundation shall be made on
completion of the foundation
10.11% pro-rata basis on completion of a stage i.e.
work including foundations
not less than 25% of the scope of foundation
for wing and return walls,
of the structure.
abutments, piers.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.
(2) Sub-structure: On
completion of abutments, Sub-structure: Payment against sub-structure
piers up to the abutment/ 1.77% shall be made on pro-rata basis on completion
pier cap including wing/ of a stage i.e. Not less than 25% of the
return/ retaining wall up to scope of sub-structure of structure.
top
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
Super-structure: Payment shall be made on
pro-rata basis on completion of a stage i.e.
completion of super-structure including
(3) Super-structure: On bearings of at least one span in all respects
completion of the super- as specified. In case of structures where pre-
4.60%
structure in all respects cast girders have been proposed by the
including Girder, Deck slab, Contractor, 50% of the stage payment shall
bearings. be due and payable on casting of girders for
each span and balance 50% of the stage
payment shall be made on completion of
stage specified as above
Wearing Coat: Payment shall be made on
(4) Wearing Coat including 0.67% completion of wearing coat including
expansion joints expansion joints complete in all respects as
specified.
Miscellaneous: Payments shall be made on
(5) Miscellaneous Items like
0.24% completion of all miscellaneous works like
hand rails, crash barrier,
hand rails, crash barriers, road markings etc.
road markings etc.
complete in all respects as specified.
Wing walls/return walls: Payments shall be
0.00%
(6) Wing walls/Return walls made on completion of all wing walls/return
walls complete in all respects as specified
(7) Retaining / Reinforced 10.78% Payments shall be made on pro rata basis on
earth walls completion of 20% of the total area.

(8) Approaches and Other


Payment shall be made on pro-rata basis on
Ancillary Works
0.00% completion of a stage in all respects as
(Approaches, stone pitching,
specified
protection works, etc.)

C.5-New Elevated section/


Flyovers/ Grade
Separators. FO Bashishta

Foundation: Cost of each structure shall be


determined on pro rata basis with respect to
the total linear length (m) of the structure.
(1) Foundation: On
Payment against foundation shall be made on
completion of the foundation
7.05% pro-rata basis on completion of a stage i.e.
work including foundations
not less than 25% of the scope of foundation
for wing and return walls,
of the structure.
abutments, piers.
In case where load testing is required for
foundation, the trigger of first payment shall
include load testing also where specified.
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
(2) Sub-structure: On
completion of abutments, Sub-structure: Payment against sub-structure
piers up to the abutment/ 1.69% shall be made on pro-rata basis on completion
pier cap including wing/ of a stage i.e. Not less than 25% of the
return/ retaining wall up to scope of sub-structure of structure.
top
Super-structure: Payment shall be made on
pro-rata basis on completion of a stage i.e.
completion of super-structure including
(3) Super-structure: On bearings of at least one span in all respects
completion of the super- as specified. In case of structures where pre-
5.27%
structure in all respects cast girders have been proposed by the
including Girder, Deck slab, Contractor, 50% of the stage payment shall
bearings. be due and payable on casting of girders for
each span and balance 50% of the stage
payment shall be made on completion of
stage specified as above
Wearing Coat: Payment shall be made on
(4) Wearing Coat including 0.43% completion of wearing coat including
expansion joints expansion joints complete in all respects as
specified.
Miscellaneous: Payments shall be made on
(5) Miscellaneous Items like
0.24% completion of all miscellaneous works like
hand rails, crash barrier,
hand rails, crash barriers, road markings etc.
road markings etc.
complete in all respects as specified.
Wing walls/return walls: Payments shall be
0.00%
(6) Wing walls/Return walls made on completion of all wing walls/return
walls complete in all respects as specified
(7) Retaining / Reinforced 11.36% Payments shall be made on pro rata basis on
earth walls completion of 20% of the total area.

(8) Approaches and Other


Payment shall be made on pro-rata basis on
Ancillary Works
0.00% completion of a stage in all respects as
(Approaches, stone pitching,
specified
protection works, etc.)

Note: (1) In case of innovate Major Bridge projects like cable suspension/cable stayed/
Extra Dozed and exceptionally long span bridges, the schedule may be modified as per
site requirements before bidding with due approval of Competent Authority.

(2) The Schedule for exclusive tunnel projects may be prepared as per site
requirements before bidding with due approval of Competent Authority.
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

1.3.4 Other works.

Procedure for estimating the value of other works done shall be as stated in table 1.3.4

Table 1.3.4

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
Unit of measurement is each
completed toll plaza. Payment of each
(i) Toll Plaza 0.00% toll plaza shall be made on pro rata
basis with respect to the total of all toll
plaza.
(ii) Road side drains 0.00%
Lined Drain 40.26% Unit of measurement is linear length in
km. Payment shall be made on pro
(iii) Road signs, safety
28.76% rata basis on completion of a stage in
Devices, Road Furnitures etc.
a length of not less than 10% (ten per
(iv) Road markings & Studs 3.03% cent) of the total length.
(vi) Crash Barrier 1.49%
(vii) Project facilities 0.00%
a) Bus Bays 0.00%
b) Wayside Amenities
excluding Slip Roads & but Payment shall be made on pro rata
including all internal roads 0.00% basis for completed facilities.
(Service areas including Truck
Lay-Byes)
c) Others (to be specified) 0.00%
(viii) Retaining Wall 0.00% Payments shall be made on pro rata
basis on completion of 20% of the
(ix) RE Wall 0.00% total area.
3.08% Payment shall be made on pro rata
(x) Street Lighting
basis on completion of a stage in a
0.50% length of not less than 10% (ten per
(xi) Utility Ducts
cent) of the total length.
(xii) Noise Barrier at Tunnel Unit of measurement is linear length.
0.00% Payment shall be made on pro rata
Approaches
basis on completion of a stage in a
(xiii) Boundary wall 0.00% length of not less than 10% (ten per
cent) of the total length.
Payment shall be made on pro rata
basis on completion of a stage in a
(xiv) ATMS 0.00%
length of not less than 10% (ten per
cent) of the total length.
Payment shall be made on pro rata
(xv) Rain Water Harvesting 0.00%
basis for completed facilities.
(xvi) Road side Plantation Payment shall be made on pro rata
including Horticulture in 0.00% basis on completion of a stage in a
Wayside Amenities length of not less than 10% (ten per
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
(xvii) Protection Works other cent) of the total length.
than approaches to the
bridges, elevated sections/ 0.00%
flyover/ grade separators and
ROBs/ RUBs

(xviii) Safety & Traffic 1.79% Payment shall be made on


Management during const. prorate basis every six months.

(xix) Other miscellaneous


works including Connecting 21.09% Payment should be made on pro rata
road & Junction under Grade basis on completion of each stage
separator

1.3.4 Electrical utilities and public Health Utilities (Electrical, Water pipe lines and
sewage lines)

Procedure for estimating the value of other works done shall be as stated in table 1.3.4:
Table 1.3.5

Percentage -
Stage of Payment Payment Procedure
Weightage
1 2 3
Unit of measurements is as per completed
activities. Cost per Activity shall be determined
on prorata basis as per its weightage with
reference to total cost of EHT line. Payment
shall be made for completed activity.
(The average weightage of major activities
(only for payment pupose) in shifting work is
(i) EHT Line 50.66%
(i) Erection of Poles-20%
(ii) Conductor stringing including laying of
30%,
(iii) DTR erection (if involved)-15% and
(iv) Charging of line including dismantling and
Site clearnance-35% (with DTR) and 50%
without DTR)

Cost of each crossing shall be determined on


pro-rata basis with reference to total no. of
(ii) EHT Crossings 0.00% crossing. Payment shall be made for not less
than 25% of the crossing subject to a
minimum of 4 crossings.
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Unit of measurements is as per completed


activities. Cost per Activity shall be determined
on prorata basis as per its weightage with
reference to total cost of LT/Ht line. Payment
shall be made for completed activity.
(The average weightage of major activities
(only for payment purpose) in shifting work is
(i) Erection of Poles-20%
(iii) HT/LT line 39.23%
(ii) Conductor stringing including laying of
30%,

(iii) DTR erection (if involved)-10% and

(iv) Charging of line including dismantling and


Site clearnance-40% (with DTR) and 50%
without DTR)
Cost of each crossing shall be determined on
pro-rata basis with reference to total no. of
(iv) HT/LT crossings 10.11% crossing. Payment shall be made for not less
than 25% of the crossing subject to a
minimum of 10 crossings.
Unit of measurement is as per completed
activities. Cost per activity shall be determined
on pro-rata basis as per its weightage with
reference to total cost of shifting, re-
(v) Shifting, Re-installation of
installation of Street lights. Payment shall be
Street Lighting, High Mast 0.00%
made for completed activity. (The average
Lighting
weightage or major activities (only for payment
purpose) in shifting works is laying -50%,
including all miscellaneous works and
dismantling and site clearance 50%)

Cost of each crossing shall be determined on


pro-rata basis with reference to total no. of
(vi) Water pipeline crossings. 0.00% crossings. Payment shall be made for not less
than 25% of the crossings subject to a
minimum of 8 crossings.

Unit of measurement is as per completed


activities. Cost per activity shall be determined
on pro-rata basis as per its weightage with
reference to total cost of pipe line. Payment
shall be made for completed activity. (The
(vii) Sewage lines 0.00%
average weightage of major activities (only for
payment purpose) in shifting working is laying
pipe-50%, charging of line including all
miscellaneous works and dismantling and site
clearnace-50%)
Construction of 6 lane flyovers at Boragaon, Gorchuk, Lokhra & Basistha Junction
along with six laning of approaches from section Ch. Km 146+172 to Km 162+620
Schedule- H
on Guwahati Bypass (NH-37) in the state of Assam under Bharatmala Pariyojna on
EPC Basis

Cost of each crossing shall be determined on


pro-rata basis with reference to total cost of
crossings. Payment shall be made for
completed activity. (The average weightage of
(vii) Sewage lines Crossings 0.00%
major activities in shifting working is laying
pipe-50%, charging of line including all
miscellaneous works and dismantling and site
clearnace-50%)

2. Procedure for payment for Maintenance

2.1 The cost for maintenance shall be as stated in Clause 14.1.1.

2.2 Payment for Maintenance shall be made in quarterly instalments in accordance


with the provisions of Clause 19.7