PRESSURE GAUGE Project no:

CALIBRATION & Project name:


INSPECTION CHECKLIST Document no:
Tag No System/Sub system
Model no Layout Drawing No
Serial No Data Sheet No
Cal Range P&ID No.
Manufacturer Service
Calibration Date Due Date
ITEMS OK Abnormality N/A
INSPECTION CHECK LIST
Check instrument nameplate details against data sheet
Check instrument has no physical damage
Check isolation, block and bleed valves
Check no water ingress/ condensation
Calibrate the gauge and fill the calibration sheet to validate accuracy
CALIBRATION
Raise input signal & record corresponding output signal at reading of 0%, 25%, 50%, 75%,
100% of range.
Lower input signal & record corresponding output signal at reading of 100%, 75%, 50%,
25%, 0% of range.

TEST EQUIPMENT USED:


INPUT PERFORMANCE DATA
1.
Raising Falling
2. Step Actual Output Output Error Actual Output Output Error
% ( ) (Ideal) (Meas.) % ( ) (Ideal) (Meas.) %
3.
0
4.
25

Comment 50

75

100

TESTED BY CHECKED BY APPROVED BY


NAME
DATE
SIGN