Professional Documents
Culture Documents
The Dam Design Report is one of the requirements to accompany the water permit application.
The outline provided below complies with the Water Resource Management Rules (2007)
Section 64.
The dam design report should be complemented by the Environmental and Social Impact
Assessment Report and the Hydrological Assessment Report as annexes to the design report.
However, the main findings and results of the ESIA and HAR should be included in the Dam
Design Report.
The dam design report presented below is customised to the case of a small earth embankment
dam. The same report outline should be followed for other structures (mass gravity dams, pans,
rock catchments, sand dams, sub-surface dams) but should be customised appropriately for the
specific type of structure.
A. Executive Summary
B. Introduction
o Dam name;
o Drainage area;
o Designer / engineer;
o Dates: design completed, planned construction.
C. Purpose
Brief description of the purpose of the project and the expected benefits.
D. Reference Drawings
List of Reference Drawings, listing their subjects (titles) and reference numbers.
E. Hydrological Assessment
This information should be consistent with and drawn from the Hydrological Assessment
Report.
o Climatic conditions
o Catchment features
o Hydrological analysis
o Storage capacity (m33), dead storage volume (m33), net storage volume (m33);
o Fetch (m);
H. Details of Embankment
o Core slopes;
o Details of embankment fill: volumes and type of material of core fill (m33), shell
fill (m33) filter material (sand, gravel) (m33), rock-fill (m33), rip-rap (m33);
I. Details of Spillway
o Number of spillways;
o Slope(s);
o Fencing;
o Pump houses;
o Valve chambers;
N. Cost Estimate
O. Construction Schedule
o Construction schedule.
Figure 19-1 shows an elaborate example of a bar chart construction schedule for the
construction of a new dam.
P. Operational Rules
This material should be consistent with and drawn from the Dam Safety Plan (EAP).
19.6.1 Introduction
Section 66 of the WRM Rules (2007) requires the submission of a Dam Completion Report to
WRMA. The report should be provided to the dam owner and users in addition to WRMA. The
Report should be prepared by the engineer or technical staff involved in the project.
The outline of the Dam Completion Report, presented below, also meets the requirements of
the Dam Operation Report as anticipated in Section 66 of the WRM Rules (2007). It is possible
to submit one report that comprehensively addresses the as-constructed conditions and the
operational aspects.
o Location.
B. As-Constructed Details
C. As-Constructed Drawings
o Catchment protection.
E. Emergency Procedures
F. Recommendations
o Measures to minimise and manage water use conflicts, should they arise;
REFERENCE:
1. Ministry of Water, Sanitation and Irrigation-Kenya.
http://smalldamsguidelines.water.go.ke/technical_reports/