You are on page 1of 6

How good do piping

system welds really need to be?

Using fracture
mechanics to
determine
the required
inspection level
By Walter J. Sperko, P.E.

A nyone who fabricates pressure pip-


ing (or almost any construction) by welding
knows that various codes and customer
specifications limit the extent of cracking, in-
complete penetration, incomplete fusion,
undercut, reinforcement, porosity, and slag
permitted in a weld.
Codes and customers also specify the
method of detection of such defects—visual
inspection is always required, and some-
times it is supplemented by radiographic,
ultrasonic, magnetic particle, or liquid pene-
trant examination.
Where do these requirements and crite-
ria originate? How do they relate to the
design?
The inspection requirements and accept-
ance criteria found in the American Society
of Mechanical Engineers (ASME) piping
codes were established based on the com-
bined opinion of many distinguished engi-
neers who sat on various committees many
years ago.
There is no real engineering basis for the
flaws that are permitted in today’s piping
codes; the acceptance criteria in the codes
are more weld quality control standards
than anything. In fact, nobody could
have established engineering-based cri-
teria as recently as 20 years ago, because
the tools that are available today were
not available then.
Today, an engineer can determine
how good a weld really needs to be by
using fracture mechanics analysis. Frac-
ture mechanics traditionally has been a
fairly esoteric discipline, but because of
the need to put this tool to use in the
structural steel, nuclear, petrochemical,
and chemical processes industries, it
has been simplified and made more
user-friendly.
Fracture mechanics allows an engi-
neer to consider the size of a flaw at any
location, the stress across the flaw, and
the fracture resistance (i.e., the tough- Figure 1
ness). Before discussing the available
tools, however, it is important to review This photo was taken looking down into a valve pit of the piping system. The leaking
a few case studies to see how a couple steam is typical of all the steam leaks.
of flawed piping joints behaved under Figure 1 shows a view looking process was videotaped for future pre-
some severe conditions. downward into a valve pit of the pip- sentation to a jury because few jurors
ing system. The leaking steam is obvi- could be expected to understand frac-
Flawed Pipe ous and typical of all the steam leaks. ture mechanics.
Joint Failures Catastrophic failure never occurred, The demonstration assembly was
Piping Leaks. In 1994, this writer although the size of the leaks increased two 10-foot lengths of 24-inch Amer-
was asked to help resolve a dispute over time. Regular repairs were made be- ican Society for Testing and Materials
between an engineer who designed a cause the rate at which make-up water (ASTM) A53 Grade B seamless stan-
piping system and the owner of the sys- could be put into the system was lim- dard weight (3⁄8-inch-thick) pipe with
tem. The steel piping system distributed ited, and, when a leak occured inside a caps welded on one end of each piece
hot water at 400 degrees Fahrenheit and building, the heat from the leaking steam (see Figure 2). These lengths were
600 pounds per square inch (psi) to eventually became unbearable. welded together so that a “bad weld”
provide space and hot water heating on Fracture mechanics analysis can ex- existed in the middle of the assembly
a local government-owned campus of plain this behavior by showing that, al- (see Figure 3).
buildings. though the stress was high and the flaws The objective was to create a weld
The original underground piping were large, steel is very tough at 400 de- with incomplete penetration about 25
system was found to be leaking shortly grees Fahrenheit, and catastrophic fail- percent of the wall thickness in depth
after its first year of operation in the ure will not occur. around the entire circumference of the
1960s, and it has leaked chronically in Incomplete Penetration. The sec- pipe.
various locations ever since. The leaking ond case study was on a chilled water This weld condition was verified by
superheated water provided an attractive system in a 60-story office building. Al- both radiographic and ultrasonic in-
Yellowstone-like campus environment though radiography of the system was spection. Both inspections indicated
—complete with smoldering geysers— not part of the contract or code require- incomplete penetration in the root,
for the residents and the employees. ments, the customer radiographed many and ultrasonic inspection measured it
The replacement piping system also welds and found incomplete penetration, as being between 1
⁄ and 33⁄ 2 inch deep.
8

started leaking within one year of which he believed to be unacceptable. The next step was to pressurize the
installation. The essential problem with A demonstration was conducted in assembly until it failed and observe
the system was lack of control over the September 1992 to show that circum- whether the assembly failed at the im-
water chemistry, which caused corro- ferential pipe butt welds can have sig- perfect weld or elsewhere.
sion fatigue throughout the system nificant weld imperfections and still be Engineering theory says that the
but attacked the piping preferentially entirely suitable for typical chilled water stress in the pipe caused by pressure is
at the welds. system service conditions. The entire twice as high in the circumferential or
General Arrangement of Test Assembly of the pipe. The water temperature dur-
ing testing was about 60 degrees F.
The test assembly was pressurized
10 Feet 10 Feet
Water Inlet Air Outlet until it failed. The burst pressure was
2,250 PSI, and failure occurred in the
Bad Weld axial (hoop stress) direction as predicted
24 Good Weld Good Weld
Inches by fracture mechanics (see Figure 5).
The failure was quite dramatic, shooting
water more than 100 feet into the air.
3/ Inch
8 Gross plastic deformation of the pipe
was obvious during the test, mostly in
Support Support the form of swelling. The diameter of the
pipe near the weld grew from 24 to 2612⁄
Figure 2 inches. The wall of the pipe at the point
of failure was less than 31⁄ 6 inch thick.
Weld Reinforcement Do these results mean that weld
quality in circumferential butt welds in
3/ Weld Metal piping is unimportant? Absolutely not.
8 Inch Outside of Pipe
,
,, The stresses in piping systems are
complex. It is possible for a piping sys-
,,
,
tem to have high stresses at some welds
and low stresses at others.

Are Extra


3/ Inside of Pipe
Examinations
32 Inch
Cost-Effective?
Incomplete Penetration
Weld quality is a serious concern
when stresses are high and less of a
Figure 3
concern when stresses are low. This
“hoop” direction as it is in the axial di- the middle of the assembly, across the observation currently is not taken into
rection. This means that, theoretically, bad weld (see Figure 4). account by ASME codes and rarely by
the pipe will split down its length when This stress was compressive at the engineers when the extent of nonde-
overpressurized rather than across the top of the pipe. It pushed the imperfect structive examination or the acceptance
imperfect circumferential weld—provid- weld together, and the stress was tensile criteria are established.
ed the imperfection is not too large. at the bottom of the pipe, where it com- Because welds that meet radiograph-
ic or ultrasonic examination require-
Fracture mechanics predicted that the bined with the pressure stresses to pull
ments cost anywhere from 25 to 200
incomplete penetration could be as deep the weld apart.
percent more than do welds that are not
as 40 percent of the pipe wall thickness, To make the local stress across the
required to be so examined, radiograph-
and failure would still occur in the hoop bad weld as high as possible, the pipe was
ic or ultrasonic examination of welds
direction rather than across the bad cir- rotated so that the deepest incomplete
that are not highly stressed wastes time
cumferential weld. penetration in the bad weld was located
and money unless special circumstances
Piping in operation has both pres- at the bottom of the pipe during the test. justify the added cost.
sure stress and bending stress caused by According to the design rules of Why do these extra inspections cost
the weight of the pipe and its contents ASME B31.1, Power Piping, and B31.9, more? In addition to the direct addi-
as it hangs between supports. Bending Building Services Piping, 24-inch A53 tional cost of performing radiographic
stresses also result from thermal growth Grade B seamless pipe with a 0.375-inch or ultrasonic examination, some factors
of a pipe that is heated or cooled while nominal wall thickness may be used at a that contribute to increased cost of mak-
in service. These bending stresses change maximum pressure of about 400 PSI. ing “reduced-flaw” welds are:
only the axial stresses; they do not change Using the code safety factor of 4, the
1. Fewer welders available who have
the circumferential stress. pipe should withstand at least 1,600 PSI
the necessary skill do the work.
In this demonstration, a small amount before failure occurs.
of bending stress was added to the pres- Based on the actual tensile strength 2. More time used by welder to pre-
sure stress by supporting the 20-foot of the pipe, failure was predicted to pare ends and preclean.
assembly at each end. This resulted in a occur between 2,000 and 2,250 PSI, 3. More time used by welder to get
bending stress of about 1,000 PSI in depending on the exact wall thickness perfect fit-up and alignment.
4. More time used by welder to
Bending Stress Distribution
make and prepare tack welds.
1,000 PSI
5. More time used by welder to
make root pass. (Sometimes, two weld-
ers are needed.)
0 PSI
6. More time used by welder to get
perfect layers of weld metal, including
Compressive
cleaning between layers and contouring
previous layers of weld.
7. More time spent on preparing the
cover pass for examination.
8. Additional supervision and/or
inspection personnel to verify that the
welders are doing the job so that the Tensile
examinations pass.
Additional examinations increase a Support Support
fabricator’s or contractor’s labor costs
for which they should be compensat- Figure 4
ed. A customer who wants welds that In this example, a little bending stress was added to the pressure stress by supporting
have been demonstrated to contain the 20-foot assembly at each end.
fewer flaws should so specify—and be
willing to pay for what it takes to Unfortunately, few engineers who
make such welds. are involved in commercial or industri-
In fact, the B31 Code Sections typi- al piping recognize that this technolo-
cally specify something comparable to gy is available to them, and even fewer
that found in B31.1, paragraph 136.1: use it in establishing the extent of
nondestructive examination to be
The degree of examination and applied.
the acceptance standards beyond Fracture mechanics recognizes the
the requirements of this code shall connection between the size of any
be a matter of prior agreement be-
flaw, the stress across the flaw, and the
tween the manufacturer, fabrica-
toughness of the material. Because no
tor, or erector and the owner.
weld—or base metal, for that matter—
The codes make the engineer re- is perfect, there is always some toler-
sponsible for specifying the extent and ance for flaws.
the acceptance criteria for any nonde- The reason that more piping sys-
structive examination, beyond that tems do not fail catastrophically is that
required by code, that he believes are the stress is sufficiently low and/or the
necessary to ensure the integrity of any toughness of the material is sufficiently
piping system, and he is obligated to high. Most piping failures show up as
do that before the system is fabricated leakage—as was clearly the case in the
and installed. 400-degrees-F, 600-PSI system de- Figure 5
scribed earlier.
Uses for Fracture This NPS 24 standard-weight seamless
Mechanics What the Codes Say pipe contains a bad circumferential
weld. However, as indicated by the
The stress level at any weld deter- The codes recognize that every weld arrow, the failure was not near the weld
mines the quality of weld needed, and has flaws, and the codes permit them (under the white tape).
that, in turn, determines the extent of to some extent in all new construction.
inspection justified. The tool that is For example: not only slag, porosity, and undercut,
available to assist the engineer in mak- 1. ASME B31.1 and ASME Section but also 112⁄ inches of incomplete pene-
ing the correct decision about the ex- III permit some slag inclusions, porosi- tration in any 6 inches of weld length
tent of inspection required and the ac- ty, and undercut. for normal fluid service.
ceptance criteria is fracture mechanics. 2. ASME B31.3 and B31.9 permit 3. American Petroleum Institute
Relating Service Conditions to Examinations Class 1 piping, and it should be applied
to other piping systems only by knowl-
Weld Type
Service edgeable parties.
Condition Longitudinal Circumferential Branch
Fillet 3. The Metals Properties Council
Groove Groove Groove
Hoop stress > 80% of the RT or UT N/A N/A N/A (MPC) of the Welding Research Coun-
allowable cil has developed software for analysis
Hoop stress > 50% and MT or PT N/A N/A N/A of flaws in welds in vessels and piping.
≤ 80% of the allowable
Sustained stresses due to N/A RT or UT VT fit-up and MT or PT
4. API is in the final stages of issu-
combined pressure, Backgouge ing RP-579, Recommended Practice for
dead weight, or other by owner Fitness for Service, which will contain
non-self-limiting loads
> 80% of the nonintensified methods for evaluating flaws in piping
allowable and vessels.
Dynamic loads that will RT or UT RT or UT VT fit-up and MT or PT All of these references and materials
exceed 80% of the Backgouge
allowable stress by owner
are available to the public, except for the
MPC software, which is available only
Toxic service (when specified RT or UT RT or UT VT fit-up and MT or PT
by the owner) Backgouge to members of MPC.
by owner Although the maintenance and re-
Welds subject to more than N/A RT or UT VT fit-up and MT or PT pair codes are not written for new con-
7,000 thermal cycles and the Backgouge
calculated stress range at the by owner
struction, the concepts and methodolo-
weld is > 80% or the allowable gies they use certainly are reasonable for
Sustained stress caused by N/A Visual examination at Visual examination at N/A use in determining the need to perform
pressure + dead weight and fit-up by owner’s or fit-up by owner’s or nondestructive examinations beyond
any other non-self-limiting independent inspector independent inspector
loads > 50% but not > 80% of engaged by owner engaged by owner those required by code.
the nonintensified allowable To this end, the writer has prepared
stress at temperature a concept table that relates service con-
Sustained stress caused by N/A Visual examination at Visual examination at N/A ditions to the extent of inspection (see
pressure + dead weight and fit-up by independent fit-up by independent
any other non-self-limiting inspector engaged inspector engaged Figure 6). This table recognizes that
loads > 25% but not > 50% of by contractor by contractor the stresses in piping systems come from
the nonintensified allowable different sources (pressure, dead weight,
stress at temperature
thermal expansion, hydraulics, etc.) and
Sustained stress caused by N/A Visual examination at Visual examination at N/A
pressure + dead weight and fit-up by contractor’s fit-up by contractor’s that the extent of inspection should be
any other non-self-limiting in-house inspector in-house inspector related to the nature of these loads and
loads < 25% of the
nonintensified allowable
to their magnitude, as well as to the na-
stress at temperature ture of the fluid being handled.
General Notes:
This approach also recognizes that
(A) All welds shall be given a visual examination in addition to the type of examination specified. a visual inspection of pipe welds at fit-
(B) RT - radiographic examination; UT - ultrasonic examination; MT - magnetic particle examination;
PT - liquid penetrant examination; VT - visual examination. up (after the joint has been cut,
(C) Surface examination (MT, PT, or VT) shall apply to the outside surface and inside surface, where readability beveled, and tack-welded together but
accessible, of longitudinal groove welds.
(D) Weld types apply to welds in pipe and fittings. before the root pass is put in) goes a
long way toward ensuring adequate
Figure 6 weld quality. In fact, the most cost-
(API) 1104 permits not only slag and known. This method includes consider- effective inspection method is to have
porosity, but incomplete penetration up ations for fatigue and dynamic loading. someone, in addition to the welder
to 2 inches in 12 inches of weld length, In the maintenance and repair codes: who will be making the weld, inspect
incomplete fusion, and cold laps up to the fit-up.
1. British Standard PD-6493 pro-
2 inches in 12 inches of weld length. It
vides a generic method for evaluation of Taking the Steps
also permits crater cracks up to 53⁄ 2 inch
flaws in any welded structure. Piping system designers should
in length. Interestingly, API 1104 is
not as tolerant of undercut as the B31 2. ASME Section XI, Inservice In- evaluate their systems in terms of the
Code Sections. spection of Nuclear Power Plant Com- fluids being handled, the stresses in
API 1104 also has a procedure for ponents, Code Case N-494, provides a the system (especially at changes in
evaluating crack-like flaws using fracture complete method for evaluating flaws in direction), the number of pressure and
mechanics if the toughness of the steel is piping. This code case was written for temperature cycles that the system will
Reprinted with permission from the Mach/April 1999 issue of PRACTICAL WELDING TODAY • 833 Featherstone Road, Rockford, IL 61107
815-399-8700 • Fax:815-399-7279 • Web Site: www.fmametalfab.org • E-mail: info@fmametalfab.org
experience, and any unusual service or erated (it is not flammable, explosive, Until then, the industry must de-
operating conditions. toxic, etc.). If leakage is not tolerable, pend on the education, experience, and
Establishing the typical stress then additional nondestructive examina- judgment of design engineers to deter-
throughout the system and finding the tions that reduce the largest expected mine the level of weld quality required
high-stress locations are the first steps in flaw size must be specified. in piping systems. l
using a fracture mechanics approach to If examinations beyond those specified Walter J. Sperko, P.E., is President of
determining the required weld quality. by code are necessary, the designer should Sperko Engineering Services, Inc., 4803
The second step is to approximate or specify the additional requirements in the Archwood Drive, Greensboro, North
specify the toughness of the material at purchase order. The designer should Carolina 27406, phone 336-674-0600,
each set of operating conditions. These understand that the customer will have to fax 336-674-0202, e-mail sperko@asme.org.
include normal operating conditions, pay not only for the nondestructive exam- Sperko is also the technical consultant to
start-up conditions, and any excursions. ination but also for the cost of making the NCPWB. Sperko Engineering pro-
The last step is to determine, through welds that have fewer and smaller flaws vides engineering consulting in weld-
fracture mechanics and a suitable safety than might otherwise be allowed. ing, metallurgy, corrosion, and quality
margin, the largest flaw that can be tolerat- The work that is currently being done assurance with specialization in pip-
ed before catastrophic failure will occur. in the maintenance and repair codes may ing/pressure vessels.
If the permissible flaw is large eventually filter into the new-construc-
enough that the pipe will leak before it tion codes, and it is likely that someday Although Sperko is a member of several
fails catastrophically (similar to the first the extent of nondestructive examina- ASME and AWS committees, any code
case study), there is little justification for tion and the applicable acceptance crite- interpretations in this article should be
additional nondestructive examination, ria found in those codes will be related considered his personal opinions and not
provided leakage of the fluid can be tol- to service conditions. the official opinion of ASME or AWS.

You might also like