Professional Documents
Culture Documents
3.11 PORTS
Summary
31 projects in 9 major
Rs. 12,828 crore 2%
ports
32 Sagarmala is the flagship programme of the Ministry of Shipping to promote port-led development in
the country
As part of MIV 2030, Major Ports need to undertake 423 MTPA capacity addition.
A total investment cost of over INR 33,400 Cr. has been envisaged for this capacity
expansion. Out of this, approximately 95% capacity expansion is likely to be planned
under Public Private Partnership (PPP)/ Captive mode by Major Ports33.
With 12 major ports, the aggregate asset capacity under the purview of Central line
ministry (MoPSW,) directly held by the Port Trusts34 is around 1,494 MMTPA, as on March
31, 202035. Of this, the total capacity under PPP mode/ captive use is estimated at around
664 MMTPA (~44% of total capacity), while the capacity under the purview of respective
Port Trusts is around 830 MMTPA (~56% of total capacity).
Approach to monetisation
In the case of port assets, monetisation potential has been arrived at based on key
development and maintenance projects envisaged over FY 2022-25 for private sector
investment through PPP mode. Key projects include additional berths, mechanisation,
development of oil jetty, container jetties, O&M of container terminal, O&M of
International cruise terminal and development of marina. The proposed capex (in Rs
crore), as estimated by the Ministry of Ports, Shipping & Waterways, has been taken
as the basis for estimation of indicative monetisation value. Further, the actual capex
outlay has been assumed to take place over a three year period from the date of
expected award and in certain cases in two phases.
The primary model for monetisation of ports and shipping assets is by way of grant
of PPP concessions.
However, the actual investment towards the development of assets will be phased out
over a defined time period as laid out under the contract. Since the same cannot be
reasonably determined at this point in time, for the purpose of NMP, the actual investment
has been assumed to be phased out over 3 year period from the target year of award.
Hence, during the NMP period of FY22-25, monetisation value of Rs. 12,828 crore has
been considered on account of estimated capex towards identified the 31 projects.
Total No of
S.No. Port FY22 FY23 FY24 FY25
Projects
1 Paradip Port 4 2 2
2 Deendayal Port (Kandla) 4 2 2
3 JNPT(Mumbai) 3 1 2
4 Mormugao Port 3 1 2
5 Mumbai Port 2
Shyama Prasad Mukerji Port
6 4 1 1 2
Kolkatta (Khidderpore)
Shyama Prasad Mukerji Port
7 3 1 1 1
Kolkatta (Haldia)
8 Visakhapatnam Port 4 1 2 1
V. O. Chidambaranar Port
9 3 2 1
(formerly Tuticorin)
10 New Mangalore Port 1 1
Total 31 13 10 3 5
Estimated
Target
S. No. Project Name Port Investment
award
(Rs. Cr.)
Estimated
Target
S. No. Project Name Port Investment
award
(Rs. Cr.)
96
Conversion of 2 Berths as container
5 SMP, KDS (Phase-1), 86 Jan ,2022
Jetty at Kidderpore dock (PPP)
(Phase-2)
O&M of Proposed Mormugao Port 102 (EPC),
6 Mormugaon Dec, 2021
International Cruise Terminal (PPP) 22 (PPP)
7 Oil Jetty No. 9 Kandla 123 March,2022
Berth No.14 Mechanized Fertilizer
8 Kandla 300 Dec,2021
Handling Facility
9 Container Terminal JNPT 863 Sep, 2021
10 Berth No. 9 VOCPT 435 Sep,2021
11 NCB-III Berth VOCPT 420 Dec, 2021
12 WQ-7&8 Visakhapatnam 288 Jan, 2022
Development of Marina
13 Mumbai 357 Oct, 2021
(PPP),Capacity:300 yacht
Total (FY22) 6,942
Estimated
Target
SN Project Name Port Investment
award
(Rs. Cr.)
Estimated
Target
SN Project Name Port Investment
award
(Rs. Cr.)
! Major Port Authorities Act 2021 enables Major ports to transform effectively for
the future. Key areas to be implemented on the ground as per the Major Port
Authorities Act 2021 are36:
! An evolved framework and MCA for PPP projects in major ports was approved
by the Cabinet in 2018 to make investments in the ports sector more attractive.
The amendments approved by the Cabinet include dispute resolution mechanism
(SAROD37–Ports), relaxed exit clause for developers.
ii. Concessionaire to pay royalty on “per MT of cargo / TEU handled” basis; this
would be inflation-indexed annually, with port operator to pay royalty on actual
and not notional income. Ministry has recently constituted an empowered
committee to review the MCA and recommend amendments (if any).
iii. Providing an exit route to developers for complete stake sale post two years
of project completion date
These initiatives will help usher in increased private sector interest and also result in
improved operational efficiencies with reduction in turnaround time at Major Ports.
36 maritime-india-vision-2030.pdf (maritimeindiasummit.in)
37 SAROD – Society for Affordable Redressal of Disputes is a dispute resolution mechanism similar to
SAAROD in the highways sector