Professional Documents
Culture Documents
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 1 of 67
SPECIFICATION FOR
WELDING (PIPING)
4
3
2
1
0 1400/05/23 Issued for Comment M.N. B.M.
Rev. Date Status Prepared. Checked. Approved AC
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 2 of 67
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 3 of 67
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 4 of 67
• EPC Contractor: Butane Procurement & Engeneering Services Company, Shall Mean
the Contractor Responsible For Engineering, Procurement & Construction of the Project.
• Will: Is normally used in connection with the action by the "company" rather than by a
contractor, supplier or vendor.
2. SCOPE
This specification defines Buyer's minimum requirements for shop and field welding and heat
treatment of equipment and fabricated production systems.
All works should conform to the requirements of this specification, other Buyer specifications
referenced herein, and all other contract documents in conjunction with all applicable codes
and standards, sound engineering principles and good fabrication and construction practices.
3. REFERENCE STANDARDS
Throughout this specification the latest editions of following codes and Standards are referred
to:
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 5 of 67
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 6 of 67
4. WELDING REQUIREMENTS
4.1 General
All welding and related activities shall satisfy the requirements of this
specification.
WPS’s shall be established for all welding which will be used in the fabrication of
piping systems.
WPS, PQR and WPQ should be qualified in accordance with the requirements of
ASME sec.IX
No welding shall be performed until the WPS’s have been reviewed by client and
qualified by PQR.
Contamination of weld bevels and surrounding areas with low melting point metals
such as copper, zinc, etc. are not acceptable.
Test required for qualification of WPS shall be organized by the executor taking
the followings into consideration:
Weld performance, preparation of test specimens, and conducting of the tests shall
be in the presence of the third party inspector and follow Inspection Test Plan.
After completion of mechanical test three copies of WPS and PQR (‘s) approved
by the inspector shall be submitted to the client.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 7 of 67
The executor shall submit to the third party inspector a list containing names of the
welders to be qualified at least one week before date of the test.
The surfaces to be welded shall be smooth, uniform, and free from laminations,
tears, scale, slag, grease, paint and other deleterious material.
The joint design and spacing between abutting ends shall be in accordance with the
procedure specification used.
The alignment of the abutting ends shall minimize the offset between surfaces. For
pipe ends of the same nominal wall thickness, the offset shall not exceed 1.59mm.
If a larger offset is caused by dimensional variations it shall be equally distributed
around the circumference of the pipe.
When the pipe is welded above ground, the working clearance around the pipe at
the weld should not be less than 406mm.When it is welded in a trench; the bell hole
shall be large enough to provide the welder or welders with ready access to the
joint.
The procedure specification shall specify the pre and post heat treatment practices
to be followed when materials or weather conditions make either or both treatments
necessary.
Mn Cr + Mo + V Cu + Ni
+ +
C.E. = C+ 6 5 15
Prepared by: Approved by:
Date: Date:
Sign: Sign:
Engineering Services for
Abadan Petrochemical Plant
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 8 of 67
The inter-pass temperature shall be measured within the joint bevel. The minimum
inter-pass temperature shall not be less than the specified preheat temperature. The
maximum inter-pass temperature shall not exceed the highest of maximum
qualified or 250 C for carbon steels.
All welding inside Site fence shall be performed per ASME B31.3, ASME Sec IX
and Pipeline welding shall be performed per API1104.
All extra low hydrogen consumables for carbon steels shall be delivered according
to manufacturer data sheets and with certification. Certificates should contain
chemical analysis of weld metal including C, Si, Mn, P, S and any other
intentionally added element, stated in the data sheet .Level of impurities maximized
in the data sheet or classification code should be stated, but may be given as
guaranteed maximum. The data sheets should contain guaranteed values on
mechanical and impact test results as long as the welding is carried out within the
recommended range. If the consumables shall be used for welds in PWHT
condition, then the properties shall also be documented in PWHT condition.
Filler metals and fluxes shall be stored and handled to avoid damage to them and
to the containers in which they are shipped. Filler metals and fluxes that show signs
of damage or deterioration shall not be used.
The shielding atmosphere to be used shall be qualified for the material and the
welding process.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 9 of 67
Shielding gases shall be kept in the containers in which they are supplied and
should be stored away from extremes of temperature.
The test records of all welders and welding operators shall be available at all times
at the work location for review by client/inspectors.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 10 of 67
• Preheating may also be required for steel having lower carbon or carbon
equivalent when conditions exist that either limit the welding technique or
tend to adversely affect the quality of the weld.
• When the ambient temperature is below five degree Celsius
• When the risk of cracks exists in the HAZ
• For weld repair
• For completing an incomplete weld left at the end of the previous working
day
• For welding of various fitting/appurtenances to the pipe having different
wall thickness or of different types of material unless during the
establishment of the weld procedure, it is determined that the preheating is
not necessary.
Generally welds in carbon steels having carbon content in excess of 0.32% (Ladle
Analysis) or a CE in excess of 0.65% (Ladle analysis) shall be stress relieved as
prescribed in BPV Code, sec. VIII.
All welding inside Site fence shall be performed per IPS-C-PI-290, ASME B31.3,
ASME Sec IX and Pipeline welding shall be performed per IPS-C-PI-270,
API1104.
4.5 Welding Requirements for Crude Oil Line Pipe in Sour Gas Service
Welding procedure shall be used to produce weldments according to the NACE
MR0175/ISO15156
Welding procedure qualifications on carbon steels that use controls other than
thermal stress relieving to control the hardness of the weldment shall also include
a hardness traverse across the weld, HAZ, and base metal to ensure that the
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 11 of 67
Welding rods, electrodes, fluxes, filler metals and carbon and low alloy steel
welding consumables with more than 1% Ni shall not be used.
5. WELDING OF PIPELINE
Basic welding consumables shall meet the requirements of the base material and
shall be selected such that the deposited weld metal exhibits mechanicals properties
equal to or in excess of the base material, as demonstrated in the welding procedure
qualifications.
Each tin or packet of electrodes or reel of filler wire and bag of flux shall be clearly
marked with the respective batch number.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 12 of 67
Each manufacturer brand and type of consumable, to be used on the works. Shall
pass a welding procedure qualification test in accordance with this specification.
Filler metals shall conform to the welding specifications for the various materials,
each lot of electrodes and wire should have certificates.
Electrodes shall be baked immediately before use at 300°C (± 30°C) for one hour
or in accordance with Manufacturers recommendations. This requirement may be
waived when the electrodes are removed from a hermetically sealed package
immediately before use. Plastic wrapped cartons are not considered to be
hermetically sealed. After drying as described.
· AWS A5.1
· AWS A5.5
· AWS A5.18
AWS classification carbon steel electrodes shall be used for welding pipes
manufactured according to API 5L.
Low hydrogen electrodes shall be used for repairing & welding tie-ins.
To maintain the low hydrogen content as specified above, electrodes shall be baked
immediately before use at 300°C (± 30°C) for one hour or in accordance with
Manufacturers recommendations. After drying as described above, electrodes may
be transferred to an intermediate storage cabinet maintained at approximately
150°C.
Prepared by: Approved by:
Date: Date:
Sign: Sign:
Engineering Services for
Abadan Petrochemical Plant
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 13 of 67
For welding of API 5L Gr. X 42, API 5L Gr. B electrode E-6010(uphill) pass shall
be used for root & E-7010 (downhill) shall be used for another passes.
For welding of API 5L Gr. X 52 electrode E-6010(uphill) pass shall be used for
root & E-7010 (downhill) shall be used for another passes.
For welding of API 5L Gr. X 60 and upper grades electrode E-6010 for root pass
& E-8010 or equivalent for another passes shall be used.
Shielding gases shall be kept in the containers in which they are supplied and
should be stored away from extremes of temperature.
Shielding and purging gases employed in welding shall have a normal composition
and purity according to the indications of the welding procedure specification.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 14 of 67
Where hydrostatic test performing is not possible (e.g. in tie in location) uphill
technique shall be performed.
Generally use of backing rings is not allowed, but in especial case Client
Engineer approval is necessary before use of back weld, where metallic backing
material is permitted, the P No. or its nominal chemical composition shall be
specified in WPS and or the applicable fabrication drawings. For joint between
similar materials the chemical composition of backing material shall much the
nominal base metal chemical composition.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 15 of 67
Any of the essential variables listed below are changed; welding procedure must
be completely prequalified. Essential variables according to IPS-C-PI-270 include:
· Welding Process
· Base material
· Joint Design
· Position
· Electric Characteristics
· Direction of welding
· Shielding Flux
Prepared by: Approved by:
Date: Date:
Sign: Sign:
Engineering Services for
Abadan Petrochemical Plant
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 16 of 67
· Speed of travel
· Number of welders
Extension and Type of qualification test shall be finalized and approved by client
Inspection and shall be carried out under supervision of client’s inspection and in
laboratory approved by client.
The Contractor shall submit his recommended welding procedure for welding and
repair welding activity of the projects containing all essential variables as required
by API IPS-C-PI-270/API 1104 for pipeline. Before the qualification test, detailed
WPS shall be prepared and submitted to the Client Engineer for review and
approval.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 17 of 67
contract all existing welding procedures shall be prequalified by the contractor, and
submitted for approval by the Client.
Test required for qualification of WPS shall be organized by the Contractor taking
the following in consideration.
All materials and equipments required for preparation of test piece and welding
including measuring instruments (Ampere/Volt meter), etc., shall be supplied by
the Contractor unless otherwise specified.
After completion of welding, The Contractor shall prepare test specimens for
delivery to an approved test center.
Weld performance, preparation of test specimens and conducting of the NDT and
mechanical test shall be in the presence of the third party inspector and shall be
organized by the Contractor.
All expenses involved in preparation of test weld, test specimens and conducting
NDT and mechanical test shall be incurred by the Contractor unless otherwise
specified.
Test pieces to qualify the welder(s) shall be selected from pipe diameter, wall
thickness ranges and position of welding that will be involved in production
welding according to relevant standard.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 18 of 67
Records of the non-destructive and destructive tests that establish the qualification
of a welding procedure shall be signed by the Contractor and the
To weld the test joint for butt welds, two pipe nipples shall be joined, following all
the details of the procedure specification.
To weld the test joint for a fillet weld, a fillet weld shall be made to one of the
configurations shown in sec2 of API STD 1104, following all the details of the
procedure specification.
Preparation of test specimens for butt weld or fillet weld joint, should be according
to API 1104
The minimum number of test specimens and the tests to which they shall be
subjected are given in the Table 2 of API STD 1104.
5.7.4.1 General
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 19 of 67
SSC and HIC test is necessary for qualification of welding procedures in sour
services.
The Contractor shall arrange welding for welding procedure qualification tests at
least ten days before the commencement of such operation on Site.
Buy Back Contractor QC's responsibilities are remained and third party
duties does not withdraw buy back contractor responsibilities.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 20 of 67
Where contract materials have been supplied in the same dimensions by more than
one manufacturer, a qualification test shall be performed based on Authorized
Client’s Representative order using two pipes form different manufacturers. This
may be used to qualify the procedure for use on the pipes from each manufacturer
provided the specified range and number of tests in the heat affected zone are taken
from both sides of the weld.
Procedures shall be qualified for each combination of diameter and nominal wall
thickness of contract materials according to essential variable of relevant standard.
Details of the filler metal sizes, classification and manufacturer/brand identity shall
be given together with a sketch showing the location, minimum number, deposition
sequence and characteristics (stringer or weave) of each weld bead.
The ranges of voltage and amperage shall not vary from the aim values by more
than + 10 percent.
On completion of welding, all procedure qualification test pieces shall be left cold
for at least 24 hours and shall then be subjected to NDT, this shall be carried out
prior to sectioning for mechanical testing.
Prepared by: Approved by:
Date: Date:
Sign: Sign:
Engineering Services for
Abadan Petrochemical Plant
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 21 of 67
Prior to sectioning for destructive testing, all test welds shall be inspected by
radiography according to NDT specification. Only test welds passing radiographic
examinations shall be taken for destructive testing.
Post-weld heat treatment, if required, shall be performed after 24 hours has elapsed,
but before & after PWHT, NDT shall be performed.
· The supplementary Phased Array testing shall always be carried out for test welds
made in whole or in part by the GMAW, GTAW processes.
Followings are the additional requirements for such tests for API 5L grade B and
above (or its equivalent) are to be utilized in this Project.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 22 of 67
· Tensile Test
If any tensile strength-test specimen breaks outside the weld or fusion zone in the
parent metal at a stress level less than the minimum specified tensile strength of
the pipe metal, the reason for this shall be established before the qualification tests
are repeated.
The tensile strength of the weld, including the fusion zone of each specimen, shall
be greater than or equal to the specified minimum tensile strength of the pipe
material but need not be greater than or equal to the actual tensile strength of the
material. If the specimen breaks outside the weld and fusion zone (that is, in the
parent pipe material) and meets the minimum tensile-strength requirements of the
specification, the weld shall be accepted as meeting the requirements.
· Nick-break Test
The Nick-break test specimens shall be approximately 9 in. (230 mm) long and
approximately 1 in. (25 mm) wide and may be machine cut or oxygen cut. They
shall be notched with a hacksaw on each side at the center of the weld, and each
notch shall be approximately 1/8 in. (3 mm) deep. Nick-break specimens prepared
in this manner from welds made with certain mechanized and semiautomatic
processes may fail through the pipe instead of the weld. When previous testing
experience indicates that failures through the pipe can be expected, the external
reinforcement may be notched to a depth of not more than 1/16 in. (1.6 mm),
measured from the original weld surface. At the company’s option, Nick-break
specimens for qualification of a procedure using a semiautomatic or mechanized
welding process may be macro-etched prior to being nicked.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 23 of 67
the other end with a hammer. The exposed area of the fracture shall be at least 3/4
in. (19 mm) wide.
· Bend test
The root- and face-bend test specimens shall be approximately 9 in. (230mm) long
and approximately 1 in. (25 mm) wide, and their long edges shall be rounded. They
may be machine cut or oxygen cut. The cover and root-bead reinforcements shall
be removed flush with the surfaces of the specimen. These surfaces shall be
smooth, and any scratches that exist shall be light and transverse to the weld.
The root- and face-bend specimens shall be bent in a guided-bend test jig. Each
specimen shall be placed on the die with the weld at mid span. Face-bend
specimens shall be placed with the face of the weld toward the gap, and root-bend
specimens shall be placed with the root of the weld toward the gap. The plunger
shall be forced into the gap until the curvature of the speci-men is approximately
U-shaped.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 24 of 67
Side-bend Test
The side-bend test specimens shall be approximately 9 in. (230 mm) long and
approximately 1/2 in. (13 mm) wide, and their long edges shall be rounded. They
shall be machine cut, or they may be oxygen cut to approximately a 3/4 in. (19 mm)
width and then machined or ground to the 1/2 in. (13 mm) width. The sides shall
be smooth and parallel. The cover and root-bead reinforcements shall be removed
flush with the surfaces of the specimen.
The side-bend specimens shall be bent in a guided-bend test jig. Each specimen
shall be placed on the die with the weld at mid span and with the face of the weld
perpendicular to the gap. The plunger shall be forced into the gap until the
curvature of the specimen is approximately U-shaped.
Each side-bend specimen shall meet the root and face-bend test requirements
specified in above mentioned requirements for root and face bend test.
· Hardness Test
One test specimen after being polished and etched for macro examination shall
undergo a Vickers hardness test.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 25 of 67
For vertical- down welding, the specimen shall be taken from the 3 o’clock
position. The test to be carried out in accordance with ASTM E92 standard with a
10 kg load, although a 5 kg load will often be necessary for the narrow heat affected
zones. Make two zone traverses, one across the root and one across the cap region
of the weld. For pipe 16 millimeter or over in thickness, make an additional traverse
midway between the other two. Each traverse shall consist of at least eight
impressions: Two in each heat-affected zone (H.A.Z), two in the weld metal and
one in the parent metal each side of the weld.
Carbon steel welds subject to sour service shall have a maximum Brinell hardness
of 200 HRB. Hardness profile and metallographic test result shall be prepared.
Toughness Test
A sample shall be cut from the completed joint at approximately the 3 o’clock
position for Charpy V-Notch impact test of the weld metal and the Heat-Affected
Zone. Three specimens shall be prepared from the sample and notched. Charpy V-
notch tests shall be carried out in accordance with the latest edition of ASTM A370.
Impact testing shall be carried out when the nominal pipe wall thickness exceeds 5
mm. Three values shall be obtained from each of the weld centre line, fusion line
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 26 of 67
and the fusion line +2 mm. The specimens shall be taken from the mid-thickness
with the notch in a radial orientation. When the pipe dimensions preclude the
preparation of a rectangular (5 mm x 10 mm) cross- section specimen a rectangular
cross-section specimen shall be prepared with the maximum feasible thickness.
In each case the impact energy shall satisfy the requirements specified for a 5 x 10
mm specimen. When the wall thickness is over 20 mm a test series at the same
locations shall also be made at the root side of the weld. Testing shall be carried
out at a temperature determined in accordance with Table 7.
Testing Records
Records of the non-destructive and destructive tests that establish the qualification
of a welding procedure shall be signed by the Contractor and the Authorized
Client’s representative(s)/Engineer and be maintained as long as that procedure is
in use. Forms for such records shall include the details of each qualified procedure
together with its complete results of the qualification tests.
These forms shall not contain information less than those that appear on our
proposed formats as attached to this specification.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 27 of 67
The purpose of the welder qualification test is to determine the ability of welders
to make sound butt or fillet welds using previously qualified procedures.
Each welder shall be qualified in accordance with the requirements of API 1104
and IPS-C-PI-270
The Contractor shall use only skilled workmen for welding. Each welder employed
by the Contractor shall be required to pass a welding test for the type and methods
of welding he will do including attachment welds. No welder shall do any phase of
welding on the pipeline for which he has not been tested and previously approved
by Client.
The CONTRACTOR shall furnish welding materials and equipment the same as
those to be used on the line. He shall also furnish coupon cutting machine and
testing equipment, and the pipe for test nipples of the same size and grade as to be
used on the line. Contractor shall prepare all test nipples. The welder shall make a
Prepared by: Approved by:
Date: Date:
Sign: Sign:
Engineering Services for
Abadan Petrochemical Plant
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 28 of 67
test weld under simulated field conditions or on the lay barge as appropriate. The
weld shall be examined and tested by Contractor and witnessed and approved by
Client.
Full size pipe nipples shall be used. Grouping on pipe diameter and/or wall
thickness according to IPS-C-PI-270/API 1104 is acceptable.
Manual welders shall be separately qualified for each welding position encountered
on the job, in a same way as for the welding procedure qualification test.
For butt welds, all welders, including welders for automatic welding, shall be
qualified by nondestructive tests. Finished coupons shall be visually examined,
fully radio graphed and, then in the case of automatic (except SAW) or
semiautomatic welds, ultrasonically tested.
Welders for mechanized welding shall be approved for all parts of the welding
operation.
Test welds shall meet the acceptance standards stated in this Specification.
Welders having participated in the execution of the welding joints for successful
qualification of the welding procedure in accordance with section 8 shall be
considered as qualified.
For manual metal arc welding, a change in electrode trade name requires welder
re-approval for butt welds, unless specific approval is obtained from Client.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 29 of 67
Any welder found responsible for a high level of defects/repairs in production shall
be removed from production. At the discretion of Client the welder in question may
be retested after an agreed period of retraining.
Arc-air gouging shall be carried out by personnel who have previously satisfied
Client that they are competent to do so and in accordance with an approved
procedure.
The welder shall perform the qualification test welding in accordance with
approved WPS. A pipeline welder shall qualify for welding by performing a test
on contract material. He will be qualified to weld only in the same position as the
test weld. All tests shall be conducted in the presence of the third party inspector,
Client Engineer. A welder qualification shall be valid for a period of six months.
The Contractor shall submit a list of qualified welders to the Authorized Client’s
Representative /Engineer and right of welding shall be restricted to the enlisted
welders only.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 30 of 67
The welding third party inspector may remove any welder and disqualify him from
any welding activity if in his opinion:
· A record of qualified welders, showing the date and results of the tests shall be
retained during the construction involved.
5.8 Welding Requirements For Line Pipe in Sour Service acc. To NACE
MR-01-75/ISO 15156
Welding procedure shall be used to produce weldments with hardness below
22HRC
Welding procedure qualifications on carbon steels that use controls other than
thermal stress relieving to control the hardness of the weldment shall also include
a hardness traverse across the weld, HAZ, and base metal to ensure that the
procedure is capable of producing a hardness of 22 HRC maximum in the condition
in which it is used.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 31 of 67
Welding rods, electrodes, fluxes, filler metals and carbon and low alloy steel
welding consumables with more than 1% Ni shall not be used.
All welding operations shall be performed upon the third party inspector, /Client
Engineer approval.
The Contractor shall make all necessary provisions for the supervision personnel
for the inspection of welding operations before, during and after such operations,
in a safe and convenient manner.
Before any production welding is started, a detailed WPS and PQR shall be
qualified and/or established related to intended specific project.
Joint preparation shall be made according to ANSI B31.8, ANSI B 31.4 and WPS
as applicable.
Material to be welded shall be cut to the required size and shaped for welding pipe
such as thermal, cold and plasma cutting. The cut edges shall be dressed back by
machining or grinding. Before welding, all foreign matter shall be removed from
the beveled ends. If any of the ends of the pipe joints are damaged to the extent that
Prepared by: Approved by:
Date: Date:
Sign: Sign:
Engineering Services for
Abadan Petrochemical Plant
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 32 of 67
satisfactory welding contact cannot be obtained, the damaged pipe ends shall be
cut and beveled to the satisfaction of the third party inspector with a beveling
machine.
Preheat and post weld heat treatment (if required) shall be performed if
specified in the relevant WPS.
The surfaces to be welded shall be smooth, uniform and free from laminations,
tears, scale, slag, grease, paint and other deleterious material that might adversely
affect the welding.
Current return cables of welding equipment shall be connected directly to the pipe
on which the welding is to be done.
If the pipe size exceeds 10 inches at least two welders shall weld simultaneously
around the pipe circumference
Arcs shall be struck only on fusion faces or on striking plates provided as an aid to
arc starting.
Stray arc strikes shall be removed by grinding away all material which has been
affected by the arc heat. Where this results in the minimum thickness being below
tolerance, the section of pipe containing the arc strike shall be removed. Weld
repairs or build-up shall not be made on the base pipe.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 33 of 67
A circular cap to prevent entry of foreign material, of a design which will not
damage pipe ends, shall be used to cover the open ends of the pipe and shall be
placed on the line during interruptions in the work expected to last more than two
hours. Caps shall not be removed until recommencement of the work. All open
ends of pipe strings shall be capped off and sealed when welding is completed.
- In the rain
- In snow or sleet
When the item to be welded is wet with rain or dew, or covered with snow, frost,
or ice shall be removed and the surface dried completely prior to beginning
welding.
The third party inspector shall decide if weather conditions despite all precautions
and proper arrangement are suitable for welding operations, or not.
Shelters and windshields to the satisfaction of third party inspector shall be used.
5.9.3 Alignment
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 34 of 67
The alignment of abutting ends shall minimize the offset between surfaces. For
pipe ends of the same nominal thickness, the offset should not exceed 1/8 in. (3
mm). Larger variations are permissible provided the variation is caused by
variations of the pipe end dimensions within the pipe purchase specification
tolerances, and such variations have been distributed essentially uniformly around
the circumference of the pipe. Hammering of the pipe to obtain proper lineup
should be kept to a minimum.
5.9.4 Matching
For pipes having different wall thicknesses, the inside or outside offset shall not
exceed 1.5 mm.
The minimum allowable distance between girth welds shall be the external
diameter of the pipe or 500 mm, whichever is the larger.
In case of pipes of different wall thickness, the pipe with the higher wall thickness
shall govern.
5.9.6 Clearance
When the pipe is welded above ground, the working clearance around the pipe at
the weld should not be less than 16 in.(400 mm)
When the pipe is welded in a trench, the bell hole shall be large enough to provide
the welder or welders with ready access to the joint.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 35 of 67
During position welding, the pipe shall be kept perfectly still and free from
vibration.
Welded sections of the pipe shall not be moved until all welds are completed and
are cooled.
Line-up clamps, holding devices, etc. shall be used for butt welds to avoid tack
welding in the groove and to optimize alignment. Internal line-up clamps of a type
acceptable to the Client shall be used for pipe sizes of 8 inches and larger. External
line-up clamps may be used for pipe sizes 6 inches and smaller. For tie-in welds,
external line-up clamps may be used for all pipe sizes.
Internal line-up clamps shall remain in place at least until the root pass is completed
around the full circumference.
External line-up clamps shall not be removed until a minimum of 50% of the root
pass, uniformly spaced around the circumference, has been completed.
Root bead segments used with external line-up clamps shall be cleaned, ground
down to a feather edge at both ends and visually inspected prior to completion of
the root pass. Any such segment which is not in accordance with the
acceptance standards shall be removed before completion of the root pass .
The pipe joint shall not be moved until after the second weld pass (hot pass) has
been made.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 36 of 67
An internal line-up clamp shall be held firmly in position at least to the end of the
root bead completion.
Under no circumstances shall the internal line-up clamp be removed before the
completion of the root bead.
Any movement of the joint and/or removal of the internal line-up clamp during the
welding of the root bead shall be the cause for rejection of the weld.
External line-up clamps shall not be removed until a minimum of 50% of the root
pass, uniformly spaced around the circumference, has been completed.
The Contractor shall preferably keep the partition distance between the line
welding groups such that a welding joint does not exercise any thermal shock. The
maximum distance between root-bead-team & the finish bead-team shall be such
that all the welds, which have started, are finished by the end of the same working
day. Second pass shall be performed maximum 5 minutes after root pass.
The Contractor shall supply suitable skids in sufficient number as approved by the
third party inspector to support the pipe for safe welding.
If the pipe is to be supported over the trench, the skids shall be of sufficient length
to prevent the trench from collapsing.
The Contractor shall repair or replace the defective parts to the third party inspector
Approval.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 37 of 67
In welding basic low hydrogen electrodes shall be used for hot, fill and finish
beads; all passes shall be of Up-Hill direction.
Tie-ins of all kinds shall be started and finished in the same working day.
The third party inspector presence at all Tie-Ins is mandatory, therefore the
Contractor shall notify the third party inspector with at least 48 hours before the
operation of the exact place and starting time of tie-in activity.
The absence or delay of third party inspector during Tie-In operation will be the
cause of stand-by claim for the Contractor. The Contractor shall never
Start/Complete the tie-in operation in the absence of third party inspector unless
otherwise a different procedure is mutually agreed between all parties involved
(Client, third party inspector, Contractor)
Use of artificial objects and/or application of heat for proper adjustment of the root-
gap in the abutting joints.
Misalignment and where inherent stresses are set up after completion of weld.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 38 of 67
All welds that are inspected must either meet the standards of acceptability of IPS-
C-PI-270/API 1104 or be appropriately repaired and re-inspected. The results of
the inspection shall be used to control the quality of welds.
Client has the right to request destructive tests for each production weld (Maximum
1% of weld joints) which all cutting, tests and re-joining costs are in contractor
responsibilities.
Edge preparations for tie-in welds shall also receive magnetic particle examination.
During production welding the welding parameters shall be checked against the
WPS.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 39 of 67
All welds shall be visually inspected and cracks, craters, pinholes, weld spatter,
residual slag or arc strikes shall not be acceptable.
Butt welds shall be inspected radio graphically, and where appropriate inspected
by phased area testing. All fillet welds shall be tested using wet magnetic particle
inspection.
Category 1
Category 2
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 40 of 67
Preheating of the parent metal prior any welding, tack welding and thermal cutting
may be necessary to avoid cold cracking of certain Ferritic steels in the weld and
HAZ.
The weld area shall be protected from draughts, and insulation shall be provided
on adjacent areas where this is necessary to maintain the required temperature of
preheating during welding.
In all cases a minimum preheat of 50°C shall be used. The inter-pass temperature
shall not be permitted to drop below the minimum preheat temperature. The inter-
pass temperature shall not be allowed to exceed 300°C.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 41 of 67
Ovens or storage cabinets with automatic heat controls and temperature read out
equipment shall be provided to maintain low hydrogen welding electrodes and
welding flux at the required temperature.
After removal from an oven, all low-hydrogen electrodes shall be kept in a storage
cabinet or quiver.
Electrodes not used within 4 hours, or for some reason exposed to adverse
atmospheric conditions, shall be baked again in accordance with the above
conditions. Electrodes may be baked twice only. If these electrodes are not used
within four hours after the second baking treatment, they shall be discarded.
• Gas Ring
• Electric Resistance
Prepared by: Approved by:
Date: Date:
Sign: Sign:
Engineering Services for
Abadan Petrochemical Plant
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 42 of 67
• Induction Heating
• Gas Torch
The choice of above method is dependent on local conditions. The procedure used
shall ensure an even temperature distribution around and through the joint to the
satisfaction of third party inspector but shall not nevertheless, interfere with access
for welding. Where using gas torch, care to be taken to avoid excessive local
heating of the pipe surface, hence a skilled labor is to be employed to the
satisfaction of third party inspector.
Where induction heating is proposed for the application of either preheat or post-
weld heat treatment, the equipment and the procedure to be used shall be approved
by the Authorized Client’s Representative. In particular, the Contractor shall
demonstrate to the satisfaction of the Authorized Client’s Representative that
heating rates and required temperatures can be properly controlled and that
adequate precautions have been taken against overheating.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 43 of 67
Post weld heat treatment procedures shall be submitted to the Client for approval
along with the WPS and WPQT record, prior to the commencement of work.
Pipe ends shall be covered. When stress-relieving welds, to avoid draughts inside
the pipe. Threads and gasket surfaces shall be protected from oxidation during heat
treatment, if there is no subsequent machining operation which will remove any
damage.
All machined surfaces shall be protected from scaling during PWHT using a
suitable protective coating.
PWHT is mandatory for wall thickness equal or greater than 19 mm except sour
service. For sour service post weld heat treatment (PWHT) is required for the
pipeline sections in wall thickness equal to or greater than 12.7 mm. for thickness
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 44 of 67
less than 12.7 mm if HIC and SSC tests in relevant PQR would be accepted, PWHT
is not required, otherwise it is mandatory.
For field welding if the service is sour the extent of hardness test is as below:
If PWHT is mandatory the extend of hardness test is 100% for cap(Weld metal and
HAZ)
If PWHT is not mandatory the extend of hardness test is 10% for cap(Weld metal
and HAZ)
The procedure shall specify whether preheating or post weld heat treatment (if any)
must be performed when materials welding consumables, thickness, weather
condition & mechanical resistant’s make either or both of them necessary .all
welding procedures specifying PWHT must indicate the following cycle:
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 45 of 67
Welding machines shall be of suitable size and type for the work and shall be
maintained in such condition as to ensure acceptable welds, continuity of operation
and safety of personnel.
The Contractor shall take necessary precautions to ensure that no arcing occurs
between the ground leads of the welding machines and the pipe.
Welding machines shall be operated within the amperage, and voltage specified in
the qualified welding procedures. A welding machine which does not meet the
requirements shall be repaired or replaced by the Contractor. All welding machines
shall be calibrated prior to commencement of fabrication.
All filler materials used in welding operations shall conform to those specified by
the relevant welding procedure.
Electrodes’ coating shall show no cracking and sticking marks. If so, the whole
batch of the defective electrodes shall be rejected by QC of Contractor/ third party
inspector Cellulose-base electrodes shall not have moisture content higher than the
maximum value specified by the manufacturers or the third party inspector. This
type of electrodes shall not be kept in high temperature ovens for losing their
minimum required moisture content as specified by the manufacturer or the third
party inspector.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 46 of 67
All welding consumable shall be selected to produce welds with yield strength
exceeding that specified for the parent material where steels with different
specified properties are joined .
The weld metal yield strength shall match or exceed that of the higher strength
grade.
Electrodes shall be supplied fully sealed packages and stored in a dry storage room
with a maximum relative humidity of 50%. All manual types of electrodes shall be
properly identifiable up to the time of usage, each electrode being distinguishable
by proper coding. If the coding is destroyed by baking, handling, or other causes,
the electrodes shall not be used.
The weld metal yield strength shall match or exceed that of the higher strength
grade.
6. WELDING OF PIPING
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 47 of 67
The covered electrodes used shall be 2.4mm, 3.2mm, 4.0 mm, or 5.0mm in dia.
However, diameters more than 2.4mm or 3.2 mm dia. Size shall not be used for the
root pass.
When joining similar materials, the deposited metal shall match the chemical and
mechanical properties of the base metal as far as possible. However, AISI Type
347 filler metal shall be used for welding Type 321 material.
When joining dissimilar austenitic stainless steels, the filler metal may match either
base metal.
When joining austenitic stainless steels to Ferritic steel, the filler metal shall be
selected as follows:
Argon gas used in GTAW process for shielding purposes shall be 99.995% pure.
The purity of the gas shall be certified by the manufacturer. The rate of flow for
shielding purposes shall be established through procedure qualification tests. This
rate may be 0.34-0.57 M3/H (12-20 ft3/h).
Argon gas with a purity level of 99.995% shall be used for purging.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 48 of 67
Initial purging shall be maintained for sufficient period of time so that at least 4-5
times the volume between the dams is displaced, in order to completely remove the
entrapped air. In no case should the initial purging period be less than 10 minutes.
High gas pressure should be avoided.
After initial purging, the flow of the backing gas should be reduced to a point where
only a slight positive pressure prevails. For systems which have a small volume up
to 0.014 m3 (½ cubic foot) to be purged, a gas flow rate of 0.17 M3/H (6 ft3/h) is
usually adequate. Systems of larger volume may require higher flow rates and these
should be established during procedure qualification tests.
Gas backing (purging) is not required for socket type of welded joints.
Dams, used for conserving inert gas during purging, shall be removed after
completion of the welding. Wherever, removal of dams is not possible after
welding, use of water soluble dams should be made.
All welding shall be carried out by using one or a combination of the following
processes:
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 49 of 67
For the root pass on 1¼ Cr and higher low alloy steel pipe, or an austenitic stainless
steel pipe, GTAW shall be performed with back shielding, such as Aragon gas in
the pipe, except when the flux cored welding electrodes are used for the austenitic
stainless steel pipe.
The Construction Sub-contractor who will do the actual welding work for piping
shall prepare the detailed Welding Procedure Specifications (WPS) and Procedure
Qualification Records (PQR) in accordance with ASME BPV Code section IX and
requirements of this specification for Client's review and approval, upon request.
• This metal group includes carbon steel pipe, ASTM A53, A106 Gr. B,
A134, API 5L-B, API 5L X60 and other weld able carbon steel materials.
• All pressure retaining welds and attachment welds to the pressure retaining
parts shall be made by Shielded Metal Arc Welding (SMAW) using Low
Hydrogen Type Electrode (AWS E7016/E7018)
• E6010 electrodes may be used for welding the root pass and the subsequent
pass in all carbon steel butt welds, except:
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 50 of 67
• Sour services
Other uses of E6010 electrodes require advance written approval from the
Client.
• Root pass of girth butt weld and branch connection weld , where the
complete penetration is required , shall be made by GTAW using AWS ER-
70S- 6 or ER70S-G .
• Filler pass and cover pass shall be made by GTAW or SMAW for smaller
• All weld areas must be cleaned of all foreign substances to avoid the
adverse effects caused by such contamination. (on galvanized pipe work,
the zinc in the area of the joint must be removed for 40 mm each side of the
welding groove prior to the welding operation. If welding requirements is
specified)
• Welding Procedure of Carbon Steel Pipe for Low Temperature Service
• This metal group includes low temperature carbon steel and low alloy steel
pipe, ASTM A333 Grade 3, 6, 7 and other carbon/low alloy steel pipe
qualified for service to -100 °C.
• The specifications given for metal group in Paragraph 5.2 (Carbon Steel
Pipe) shall also apply to this metal group and, in addition, the Charpy
impact tests shall be included in the welding procedure qualification.
• Consideration should be given to the use of low hydrogen type to produce
welds with the necessary impact properties.
• Root pass of girth butt weld and branch connection weld, where the
complete penetration is required, shall be made by GTAW process.
• Filler pass and cover pass shall be made by GTAW or SMAW. For smaller
diameter piping (2" and smaller), all GTAW process shall be done.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 51 of 67
• This metal group includes austenitic stainless steels ASTM A182, A312,
A358, A403 and other similar materials used in the fabrication of piping
systems.
• Root pass of girth butt weld and branch connection weld, where the
complete penetration Is required, shall be made by GTAW process, with
the underside of the weld purged with argon gas. Other methods and
processes may be used only when approved by Client.
• Filler pass and cover pass shall be made by GTAW or SMAW. For smaller
diameter piping (2" and smaller), all GTAW process shall be done.
• Weld Metal:
- The deposited weld metal shall have chemical & Physical properties at least
equal to that of the base metal.
- For welding of dissimilar stainless steel (for example Type 316 to 304), the
deposited weld metal shall be according to proper filler metal based on
AWS classification like as E-316 / ER-316 or E-308 / ER-308.
- For welding of stainless steel to carbon steel, a high alloy electrode shall be
used which will produce a sound ductile weld. AWS Classification E309-
16 /E-309L-16 or ER309 / E-309L Electrode must be used.
- Stainless steel shall not be welded to galvanized steel for any purpose.
• Internal back shielding with pure Argon gas (min. 99.9%) shall be required
during the welding. Back shielding with Nitrogen gas shall not be
permitted.
• Maximum inter-pass temperature during welding shall be 150°C.
• The welding joints shall not utilize a backing strip
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 52 of 67
• All requirements for low temperature toughness test for metals shall be
according to table 323.2.2 of ASMEB 31.3
Root pass of girth butt weld and branch connection weld, where the complete
penetration is required, shall be made by GTAW process. Other methods and
processes may be used only when approved by Client.
Filler pass and cover pass shall be made by GTAW or SMAW. For smaller
diameter piping (2" and smaller), all GTAW process shall be done.
Internal back shielding with Argon gas (min. 99.9%) shall be required during
the welding. Back shielding with Nitrogen gas shall not be permitted.
All welding procedure used for the piping work shall be qualified before
production welding, Construction Subcontractor shall carry out the welding
procedure qualification test and shall submit the complete document as WPS
and PQR to Client's review and approval. Also unless otherwise stated in the
contract documents, for each contract all existing welding procedures shall be
re-qualified by the contractor, and submitted for approval by the Client.
Welding sampling testing for PQR shall be at "H" level in inspection state.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 53 of 67
All equipment, tools, test materials and labors required to carry out procedure
qualification test shall be supplied and prepared by the Construction consultant.
The base metal may consist of plate, pipe or other product forms. Qualification
in plate also qualifies for pipe welding and vice versa.
The welding process and electrodes shall be suitable for use in the positions
permitted by the WPS. A welder or welding operator making and passing the
WPS qualification test is qualified for the position tested.
WPS qualified on groove welds shall be applicable for weld repairs to groove
and fillet welds and for weld buildup under the following provisions:
Tension test specimens shall conform to one of the types illustrated in QW-
462.1 (a) through QW-462.1 (e) and shall meet the requirements of QW-153 in
ASME Sec. IX. Tension test procedure and acceptance criteria shall be in
accordance with QW-152 and QW-153 of ASME Sec. IX respectively.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 54 of 67
Test specimens shall conform to one of the types illustrated in QW-462.2, QW-
462.3 (a) and QW-462.3 (b) and shall meet the requirements of QW-163 in
ASME Section IX. Guided-bend test procedure shall be in accordance with
QW- 162 of ASME Section IX.
The impact test specimens shall be prepared only when required by WPS and
concerned code for the material.
The test procedure and apparatus shall conform the requirements of ASME
SA370
Hardness requirements for welds shall be as per the WPS. Hardness testing
shall be carried out by Vickers hardness tester during welding procedure
qualification. In all other cases, hardness testing may be carried out by Vickers,
Brinell, or Rockwell hardness tester as agreed by Client.
On production welds for P5 and P6 group material, a Brinell hardness test shall
be taken on ten percent of the butt-welds in each P-groups material for all air
hardening filler metal. If less than ten welds are made per P-group, one weld
shall be tested. Brinell hardness shall not exceed 225 BHN (20 HRC).
Carbon steel welds subject to sour service shall have a maximum Brinell
hardness of 200 HRB. Hardness profile and metallographic test result shall be
prepared.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 55 of 67
The Brinell hardness testing shall be limited to piping greater than nominal pipe
size of 4" and a wall thickness over 6.35 mm.
Post weld heat treatment shall be repeated, if the Brinell hardness after PWHT
exceeds the maximum limits specified. Take repeating of PWHT for carbon
steel shall be maximum two times and more than two times is not permitted.
Specimens for hardness testing from test pieces in the 5G and 6G positions
shall be taken from the weld area of weld representing the minimum heat input
Hardness test results and locations shall be recorded. The third party inspector
shall be permitted to witness hardness testing and shall have access to test
results.
SSC and HIC test is necessary for qualification of welding procedures in sour
services.
The test records of all welders and welding operators shall be available at all times
at the work location for review by buy back supervisor and third party inspector
Each welder or operator shall be identified by means of a stamp. The stamp shall
be applied 100mm maximum near the weld. It is forbidden to mark the internal part
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 56 of 67
of pipes in case of design temperature -10°C and below and for thickness 5 mm
and below. Other means than stamp shall be used to identify the welders. The
symbol assigned to each welder, shall be marked clearly visible on the welder's
helmet, or on the working clothes, to identify each welder without asking his
identification documents.
Construction consultant shall keep a record of welders working at shop and at field,
and to be submitted to Client for review. If the qualification of any welder or
welding operator is found expired all affected welds shall be traced and examined
to the satisfaction of Client.
During welding the maximum heat input in each pass shall be the same one used
during the relevant procedure qualification record.
Each welder performing welds for which preheating is required, shall have
availability to the equipment for heating and for temperature checking.
When GTAW process is used, the arc shall be extinguished on the edge of the
bevel, keeping the molten pool under gas shielding until it solidifies.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 57 of 67
All welding shall conform to the requirements of Section IX of ASME Boiler and
Pressure Vessel Code.
Stress relieving according to the applied code and approved procedure shall be
carried out.
Welders shall be equipped with clean gloves (especially for S/S materials), safety
glasses & safety shoes.
• In the rain
• In winds of 10 m/s or more (3 m/s or more for GTAW)
• When the relative humidity is 90% or more
• In snow or sleet
However, where necessary protection from the weather is provided, welding may
be performed.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 58 of 67
When the item to be welded is wet with rain or dew, or covered with snow, frost,
or ice shall be removed and the surface dried completely prior to beginning
welding.
When paint materials with zinc dust are used for painting near the austenitic
materials, the painting shall be performed after completion of welding and heat
treatment of austenitic materials. If these types of work must be performed in
parallel, the austenitic materials shall be strictly protected from any adhesion of the
paint or mist.
Machining, grinding or thermal cutting shall make weld bevels. The surfaces shall
be reasonably smooth and true for good fit-up. Materials that require preheat for
welding shall be preheated in the same manner for tack welding, thermal cutting or
gouging. Weld bevel’s preparation shall be in accordance with ASME B31.3.
Double-welded butt joints are preferred and shall be used whenever possible and
for all pipe of 30" OD and larger, where accessible.
Prepared by: Approved by:
Date: Date:
Sign: Sign:
Engineering Services for
Abadan Petrochemical Plant
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 59 of 67
During the welding operation, edges of the plates or pipes shall match accurately
and retained in constant distance all around the joint. “Gap Gauge" shall be used
for measurement.
In austenitic stainless steel and nickel alloy the cutting for the edge preparation
shall be performed by machining, or grinding, or by plasma-arc with subsequent
light grinding. The grind wheels shall be of a suitable type for stainless steel and
shall not have been previously used for carbon steel. The brushes (both manual and
mechanical) shall have chromium nickel austenitic stainless steel wires.
Components to be welded shall be aligned and spaced as per the requirements laid
down in applicable code. Special care must be taken to ensure proper fitting and
alignment when the welding is performed by GTAW process. Flame heating for
adjustment and correction of ends is not permitted unless specifically approved
by Client.
Consumable backing inserts are not permitted unless in the inevitable situations.
At this condition all qualification requirements shall be considered based on
paragraph 328.2 of ASME B31.3
A wire spacer of suitable diameter may be used for maintaining the weld root
opening while tacking, but it must be removed after tack welding and before laying
the root bead.
For pipes of wall thickness 5 mm and above, the ends to be welded shall be secured
in position with the aid of couplers, yokes and “C” clamps, to maintain perfect
alignment. Yokes shall be detached after the completion of weld, without causing
Prepared by: Approved by:
Date: Date:
Sign: Sign:
Engineering Services for
Abadan Petrochemical Plant
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 60 of 67
any surface irregularity. Any irregularity caused on the pipe surface must be
suitably repaired to the satisfaction of Client.
Tack welds, for maintaining the alignment, of pipe joints shall be made only by
qualified welders. They shall be made with same type of electrode which is used
for the root pass, executed carefully and shall be free from defects. All defective
tack welds must be removed prior to the actual welding of the joints.
Tack welds should preferably not touch the root of the weld preparation to avoid
damage to the root area. The use of bridge pieces is recommended.
All surfaces to be welded shall be cleaned thoroughly and any paint, oil, rust, dirt,
scale moisture, or any other foreign matter that would be detrimental shall be
removed from at least 10 mm from the groove end prior to the welding.
Flux, weld spatter and slag shall be removed from weld beads before starting to
deposit a succeeding pass
6.5.6 Welding
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 61 of 67
Tack-welds shall be made with the same type of electrode that is used for the root
pass. Permanent back-up rings are not permitted. If back-up rings are used and then
removed, the weld area shall be dressed and examined for cracks by the magnetic
particle method or by the liquid penetrate method if the base material is non-
ferromagnetic.
The striking of the arc must not be performed on the pipe wall outside the bevel (a
suitable plate may be used for this purpose)
Once the welding has been started and until the joint has been completed, care shall
be taken to avoid displacements, shocks, vibration or stresses, which could damage
the weld.
On butt welds, the weld reinforcement shall be in accordance with applicable code
requirements. The width of the weld face shall cover completely the groove of the
joint. On fillet welds, the weld profile shall be regular, at about 45°.
For socket welds and for slip-on flanges at least two passes shall be performed.
The inter-pass temperature of the joint during execution shall not be decreased
below the minimum required preheating temperature and the completion of the
weld should be carried out without interruption.
For GTAW technique, the purity of the gas shall be monitored continuously.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 62 of 67
Volume and the width of each pass shall be limited, using low current and stringer
bead technique whenever possible; anyway the bead width shall not be larger than
three times the electrodes size.
On-plot use of low hydrogen electrodes for root (where are access to root pass) and
filling passes shall be considered when SMAW process is subjected.
Defects ascertained through the inspection methods, which are beyond acceptable
limits shall be removed after the joint is completely radio graphed, by the process
of chipping and grinding.
When the entire joint is judged unacceptable, the welding and HAZ shall be
completely cut and the edges are suitably prepared as per required alignment
tolerances. The re-welded joint shall again be examined following standard
practices.
Weld beads shall be properly contoured to permit complete fusion at the sides of
the bevel, and to minimize slag inclusions.
Internal and external weld reinforcement and finish shall be as required by the
applicable code.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 63 of 67
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 64 of 67
The packages of welding materials shall not be opened prior to their use or to
drying.
Covered arc welding electrodes (except for high cellulose) shall be dried in a
heating oven in accordance with the manufacturer's recommendation prior to use.
Immediately after drying, these electrodes shall be stored either in a portable dryer
or in a keeping oven.
Electrodes coated with high cellulose and flux cored welding electrodes used for
GTAW are not required to be dried. However, wet electrodes coated with high
cellulose shall be annulled.
During welding, all covered arc welding electrodes shall be kept in a quiver or its
equivalent. The electrodes shall not be laid directly on the ground or on any other
damp place.
Electrodes (except for electrodes coated with high cellulose, and flux cored
welding electrodes) exposed to the atmosphere for more than 4 hours shall be re-
dried.
When the day's work has been completed, the electrodes shall be collected and
stored in a heating cabinet. This process shall be done only for twice, remaining
electrodes are not acceptable for using.
Electrodes and filler wires shall be kept clean, dry, and properly stored according
to the manufacturer’s recommendation. No electrodes or filler wires may be used
which are damp, greasy, or oxidized. Repacking of electrodes are not normally
allowed and if in certain cases required, the Construction consultant shall get prior
Prepared by: Approved by:
Date: Date:
Sign: Sign:
Engineering Services for
Abadan Petrochemical Plant
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 65 of 67
approval of the Client. Electrode shall be stored in a sheltered area and ventilated
during storage namely in electrode room. The electrode room shall be shelved.
The buy back supervisor third party inspector shall have the right to inspect all
welds by nondestructive means or by removing welds and subjecting them to
mechanical tests.
The inspection should be made before, during and after welding. The frequency of
inspection shall be specified.
Only level II or III personnel shall interpret test results. Level I and II
nondestructive testing personnel shall be recertified at least every three years. Level
III Nondestructive personnel shall be recertified at least every five years.
For RT testing of seam welds with sweet services, AGFA D7 type and for those
with sour services AGFA D4 type shall be used as radiograph.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 66 of 67
Extent of RT for wellhead shall be 100% and just for burn pit it could be 10%.
Extent of visual inspection and NDT other than RT for piping systems, the shall be
in accordance with ASME B31.3 standard.
VCM UNLOADING
STATION
Contract No.:
Document No.: Rev.:00 Page 67 of 67
Before repairs are made, injurious defects shall be entirely removed to sound metal.
All slag and scale shall be removed.
The same area on a weld shall not be repaired more than twice.
Minor surface flaws may be removed by grinding, provided the pipes minimum
wall thickness is not violated.