Professional Documents
Culture Documents
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 1 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 2 of 54
MAN TSC 6001 DD QC PRC 0006 01
Revision Index
Revisions Revisions
Page Page
00 01 02 03 04 05 06 00 01 02 03 04 05 06
1 X X 51 X
2 X X 52 X
3 X 53 X
4 X 54 X
5 X 55
6 X 56
7 X 57
8 X 58
9 X 59
10 X 60
11 X 61
12 X 62
13 X 63
14 X 64
15 X 65
16 X 66
17 X 67
18 X 68
19 X 69
20 X 70
21 X 71
22 X 72
23 X 73
24 X 74
25 X 75
26 X 76
27 X 77
28 X 78
29 X 79
30 X 80
31 X 81
32 X 82
33 X 83
34 X 84
35 X 85
36 X 86
37 X 87
38 X 88
39 X 89
40 X 90
41 X 91
42 X X 92
43 X 93
44 X 94
45 X 95
46 X 96
47 X 97
48 X 98
49 X 99
50 X 100
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 3 of 54
MAN TSC 6001 DD QC PRC 0006 01
Table of Contents
1- Introduction ..................................................................................................... 6
1-1- Project Description ............................................................................................... 6
1-2- Scope ..................................................................................................................... 6
1-3- Purpose .................................................................................................................. 6
2- General Information ....................................................................................... 6
2-1- Terms and Definitions .......................................................................................... 6
2-2- Abbreviation ......................................................................................................... 7
2-3- Language ............................................................................................................... 8
2-4- Unit8
2-5- Refrence Project Documents & Specifications..................................................... 8
3- Radiographic Testing (RT) ............................................................................ 8
3-1- PERSONAL QUALIFICATION .......................................................................... 8
3-2- EQUIPMENT ....................................................................................................... 9
3-3- PENETRAMETER ............................................................................................... 9
3-4- RADIOGRAPHY TECHNIQUE ....................................................................... 10
3-5- I.Q.I Sensitivity ................................................................................................... 12
3-6- FILM DENSITY ................................................................................................. 12
3-7- GEOMETRIC UNSHARPNESS........................................................................ 12
3-8- QUALITY (As Per ASME Sec. V -T 281) ......................................................... 13
3-9- IDENTIFICATION AND LOCATION OF MARKS ON RADIOGRAPHS.... 13
3-10- STORAGE AND PROTECTION OF FILM .............................................. 13
3-11- ACCEPTANCE CRITERIA........................................................................ 14
4- Liquid Penetrant examination (PT) ............................................................ 14
4-1- APPLICABILITY ............................................................................................... 14
4-2- PERSONAL QUALIFICATION ........................................................................ 14
4-3- SURFACE PREPARATION .............................................................................. 14
4-4- DRYING ............................................................................................................. 15
4-5- EXAMINATION METHOD .............................................................................. 15
4-6- DEVELOPING ................................................................................................... 16
4-7- EXAMINATION METHOD .............................................................................. 16
4-8- EVALUATION OF INDICATIONS ................................................................. 17
4-9- ACCEPTANCE CRITERIA ............................................................................... 17
5- Vacuum-Box Testing (VBT)......................................................................... 17
5-1- SCOPE ................................................................................................................ 17
5-2- METHODS ......................................................................................................... 18
5-3- GENERAL REQUIREMENTS .......................................................................... 18
5-4- VACUUM PRESSURE TECHNIQUE .............................................................. 19
5-5- Acceptance Criteria ............................................................................................. 20
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 4 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 5 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 6 of 54
MAN TSC 6001 DD QC PRC 0006 01
1- Introduction
1-1- Project Description
Negin Mokran Development Petrochemical Co. (NMPC) has decided to develop
a third hub of Petrochemical Industries in Chabahar Free Trade-Industrial Zone.
Based on detailed investigation, 1,200 hectares of Chabahar Free Trade-
Industrial Zone with dimensions of 2.7 × 4.4 Km has been allocated for
petrochemical zone.
Mokran Abniroo "MAN" is a company organized and exists under the laws of
the Islamic Republic of Iran and is a sub-company of NMPC, desires to
establish “Interconnecting Utilities and Offsite of MOKRAN Petrochemical
Complex - Stage 1".
1-2- Scope
Purpose of this procedure is to define activities, communication,
correspondence routes between Owner/MC, Contractor and TPI and
requirements for performing ND procedure on storage tank for Interconnecting
Utilities and Offsite of MOKRAN Petrochemical Complex.
Thus, considering this procedure by all involved parties expected to:
o Improve level of communication and collaboration between Owner,
contractor and TPI.
o Understanding of practices/activities which shall be executed by whole
parties and the tasks related to inspections of the project is being
facilitated.
1-3- Purpose
MOKRAN AB-NIROO Company (Owner) intends to build an Interconnecting
Utilities and Offsite of MOKRAN Petrochemical Complex, (hereinafter in this
document referred to as "Plant") in CHABAHAR, IRAN.
2- General Information
2-1- Terms and Definitions
In this project Owner, Contractor and title of project have been described as
follows:
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 7 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 8 of 54
MAN TSC 6001 DD QC PRC 0006 01
MAN-TIV-EPC-F310-00-01 Contract
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 9 of 54
MAN TSC 6001 DD QC PRC 0006 01
3-2- EQUIPMENT
SOURCE: Radiographic testing will be performed using a source of Gamma–
Ray Ir192.
FILM: Radiographic films shall be type II (M/X 125, or D4 or Equivalent) as
described in ASTM E-94.
3-3- PENETRAMETER
Wire type I.Q.I shall be used to judge the radiographic sensitivity. Wire
penetrometer shall be in accordance with SE-747.
Penetrometer Selection:
I.Q.I.s shall be selected from either the same alloy material group or grade as
identified in SE-1025 or from an alloy material group or grade with less
radiation absorption than the material being radio graphed.
The designed essential wire diameter shall be selected so that code
requirements are obtained. (According to Table T-276 ASME SEC. V, Article
II).
For Welds with reinforcement the thickness on which the penetrometer is based
is the nominal single-wall thickness plus the estimated weld reinforcement by
the referencing code section.
For welds without reinforcement the thickness on which the penetrometer is
based on the nominal single-wall thickness.
Backing rings or strips are not to be considered as part of the weld thickness in
penetrometer selection.
Penetrometer shall be set at the end of film location. The penetrometer shall be
placed on the welds so that the wire perpendicular to length of the welds. The
penetrometer shall be put on source side of the object & whenever is not
possible, it shall be put as a film side by placing lead letter “F” adjacent to it.
The number of I.Q.I.s shall be specified according to ASME SEC. V- Art. 2 –
T277.
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 10 of 54
MAN TSC 6001 DD QC PRC 0006 01
Note: The maximum length of film used should be 0.7 ~ 0.9 SFD. When
collimator is used for Gamma-Ray, the extent of radiation cone should be in
attention.
Double Wall Technique
By using this technique, the radiation passes through two walls and it is applied
either for single-wall viewing in contact with the film or both wall viewing.
Double Wall- Single Image Technique (DWSI)
Usually parts with more than 3½" (89 mm) in nominal outside diameter,
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 11 of 54
MAN TSC 6001 DD QC PRC 0006 01
Notes:
A. Prior to radiographic examination the concerned welds will be visually
acceptable.
B. Weld will be prepared by any suitable manner to ensure a suitable
radiographic contact.
C. The film shall be Centered on the weld and of sufficient width to permit
insertion of identification markers and penetrometer.
- As close to the surface of the welds as practical.
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 12 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 13 of 54
MAN TSC 6001 DD QC PRC 0006 01
Material Thickness
Max. Ug
(mm)
Under 50.8 0.51
50.8 through 76.2 0.76
Over 70.6 through 101.6 1.02
Greater than 101.6 1.78
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 14 of 54
MAN TSC 6001 DD QC PRC 0006 01
Radiographs will be bonded by the vendor for the duration of the works and
field in suitable boxes with appropriate reports and proper works.
All radiographs, including any showing unacceptable quality period to repair
shall be delivered to the company upon completion of the work.
Films should be handled only at their edges, and with dry, clean hands to avoid
finger marks on film’s surface.
Sharp bending, excessive pressure, and rough handling of any kind must be
avoided.
3-11- ACCEPTANCE CRITERIA
Welds examined by radiography shall be interpreted and evaluated for
acceptance or rejection as per UW 51(b) of ASME Section VIII Div. (1) (refer
to API 650, Clause 8.1.5).
Refer to Annexure D for excerpts from ASME Section VIII Div. (1) for quick
reference.
4- Liquid Penetrant examination (PT)
4-1- APPLICABILITY
Any surface in as weld, as rolled, as ground, as forged, as machined condition
or any case in the condition required by construction drawing.
4-2- PERSONAL QUALIFICATION
All personnel employed shall be instructed and examined in accordance with
requirements of T-170 of ASME Sec. V.
4-3- SURFACE PREPARATION
The surface to be inspected shall be finished to the drawing requirements.
Where the drawing does not specify otherwise, as welded, as rolled, as cast, as
forged surface condition shall be considered suitable for inspection. Surface
preparation by grinding, machining or other methods may be necessary where
surface irregularities.
Prior to dye-penetrant examination, the surface to be examined and al adjacent
areas within at least 25 mm shall be dry and free of any dirt, grease, lint, scale,
welding flux, weld spatter, oil or other extraneous matter that could obscure
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 15 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 16 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 17 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 18 of 54
MAN TSC 6001 DD QC PRC 0006 01
5-2- METHODS
The leak testing methods that use in storage tanks normally described as
follows:
- Vacuum box technique
- Penetration oil technique
5-3- GENERAL REQUIREMENTS
The leak testing shall be performed before hydrostatic testing. For the leak
testing the following items shall be checked before testing:
- Personal qualification / certificate
- Calibration of equipment / tools
- Extent of examination
- Acceptable test sensitivity of leakage rate
- The test surface shall be free of oil, grease, Paint or other
contaminations that might mask a leak
- The pressure or vacuum limitation unless specified in specification
shall not exceeding 25 percent of the design pressure
- When dial indicating and recording pressure gages are used in leak
testing they should preferably have the dial graduated over a range
of about double the intended maximum pressure, but in no case
shall the range be less than 1 ½ no more than four times that
pressure. The all dial indicating and recording type gages used
shall be calibrated against a standard deadweight tester, a
calibrated master gage, or a mercury column, and recalibrated at
least once a year when in used
The temperature of the surface of the parts to be examined shall not be below 5
°C nor above 50 °C throughout the examination. Local heating or cooling is
permitted provided temperatures remained within the range of 5 °C to 50 °C
during the test.
The area under test is acceptable when no continuous bubble formation is
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 19 of 54
MAN TSC 6001 DD QC PRC 0006 01
observed. When leakage is observed, the position of the leak (s) shall be
marked. The component will then be depressurized and the leak (s) repaired.
After repair has been made, the area or areas shall be retested in accordance
with the requirements of this procedure.
After testing, surface cleaning may be required for product serviceability.
This procedure co Each vacuum-box operator shall meet the following
requirements:
a. Has vision (with correction, if necessary) to be able to read a Jaeger
Type 2 standard chart at a distance of not less than 300 mm (12 in.).
Operators shall be checked annually to ensure that they meet this
requirement; and
b. is competent in the technique of the vacuum-box testing, including
performing the examination and interpreting and evaluating the results;
however, where the examination method consists of more than one
operation, the operator performing only a portion of the test need only be
qualified for that portion the operator perform should be used for testing
of bottom plates and floating roof.
5-4- VACUUM PRESSURE TECHNIQUE
Process description Vacuum testing is conveniently performed using a metal
testing box 6” wide by 30” long with a glass window in and top the open bottom
is sealed against the tank surface by a sponge rubber gasket. Suitable
connections, valves, and gauges should be provided. Approximately 30” of the
weld seams under test is brushed with a soap solution or linseed oil. In freezing
weather, a non-freezing solution may be necessary. The vacuum box is placed
over the coated section of the seam, and a vacuum is applied to the box. The
presence of porosity in the seam is indicated by bubbles or foam produced by
air sucked through the welded seam. A vacuum can be drawn on the box by any
convenient method, such as connection to a gasoline or diesel motor intake
manifold or to an air ejector or special vacuum pump. The gage should register
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 20 of 54
MAN TSC 6001 DD QC PRC 0006 01
a partial vacuum of at least 2 PSIG. The temperature of the surface of the parts
to be tested shall not be below 5 °C nor above 50 °C throughout the
examination. Local heating or cooling is permitted provided temperatures
remained within the range of 5 °C to 50 °C during the test.
Application The above test shall be used for bottom plates and roof plates and
also suitable to use for testing of weld between annular plates and lowest shell
plates.
5-5- Acceptance Criteria
Through-thickness leaks of any sort are treated as unacceptable in API 650. The
leaks are classified under the following two categories:
1. A through-thickness leak is indicated by continuous formation or growth
of a bubble(s) or foam, produced by air passing through the thickness.
2. A large opening leak is indicated by a quick bursting bubble or spitting
response at the initial setting of the vacuum box.
Both the leaks are unacceptable and shall be repaired and tested again.
6- PENETRATION OIL Test
This technique shall be used for leakage testing of follow weld seams:
- Lower most course to annular plates
- Vertical and horizontal joints of upper most courses.
- Compart / rim plates to deck plates
Spray all of the joints from the one side with highly penetrating oil, such as
automobile spring oil and carefully examined the other side of the joints for.
7- Pneumatic Testing of Reinforcement Pads
All reinforcement pads provided as compensation against openings made on the
tank shall be subjected to pneumatic testing before the final hydrostatic testing
of the tank. Reinforcement pads are required for nozzles of 65 NB (3”) and
above. Reinforcement pads so provided shall have tell-tale holes, intended to
facilitate the escape of hot gases during welding, to detect any leaks during
hydrostatic testing, and to detect leaks from nozzle or manway welds during
service, which can be used for pneumatic testing of pads as well.
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 21 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 22 of 54
MAN TSC 6001 DD QC PRC 0006 01
all welds between the pad, manhole/nozzle, and shell, from both inside and
outside the tank. The welds that are to be tested using the film solution are
indicated in below Figure.
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 23 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 24 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 25 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 26 of 54
MAN TSC 6001 DD QC PRC 0006 01
pass.
8-4- VISUAL INSPECTION OF WELDS
All welds shall be visually examined in accordance with the drawings and
specification requirements. Visual inspection shall be reported and the QC
welding engineer shall be informed about visually rejected welds to take action
prior to NDT.
Profile of external reinforcement.
A. Weld metal to be properly fused with the base metal without undercutting
or overlapping at the weld toe.
B. The edge of all welds shall merge with the surface of the plate without a
sharp angle. The maximum acceptable undercutting is 1/64 “ of the base
metal for vertical butt joints and for horizontal butt joints undercutting
not exceeding 1/32 “ in depth is acceptable.
C. The reinforcement of the welds on all butt joints on each side of the plate
shall not exceed the following thickness.
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 27 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 28 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 29 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 30 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 31 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 32 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 33 of 54
MAN TSC 6001 DD QC PRC 0006 01
The scanning shall be performed at a gain setting of two times (6dB) the
Reference Level.
NOTE: Evaluation of indication shall be performed at Reference Level
Sensitivity setting.
9-6- ACCEPTANCE/ REJECTION CRITERIA
As per ASME Sec. VIII-Div. 2 App. 12; Imperfections which produces a
response greater than 20% of the Reference Level shall be investigated to the
extent that the operator can determine the shape, identity, and the location of all
such imperfections and evaluate them in terms of the acceptance standards
given in (a) and (b) below:
a. Indications characterized as Cracks, Lack of Fusion or Incomplete
Penetration are unacceptable regardless of lengths.
b. Other imperfections are unacceptable if the indications exceed the
Reference Level amplitude and have length which exceeds:
1) ¼ in for t up to ¾ in.
2) 1/3 t for t from ¾ in to 2¼ in.
3) ¾ in for t over 2¼ in.
Where, t is the thickness of the weld excluding any allowable
reinforcement. For a butt weld joining two members having different
thicknesses at the weld, t is the thinner of these two thicknesses. If a full
penetration weld includes a fillet weld, the thickness of the throat of the
fillet shall be included in t.
9-7- EXAMINATION OF REPAIRS
Repaired area shall be examined by the same method used for original detection
of discontinuities.
9-8- EXAMINATION REPORT
A report shall be contained the following information:
a. Identification of item under examination;
b. Surface condition;
c. Date of examination;
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 34 of 54
MAN TSC 6001 DD QC PRC 0006 01
d. Identity of technician;
e. Flow detection equipment used;
f. Angle and frequency of probes used;
g. Specification for examination, including test sensitivity;
h. Specification for acceptance / rejection criteria;
i. Results obtained including a full size, cross section view of weld with
position of all reportable defects accurately shown, and a plan view
showing the accurate longitudinal position of all defects from a known
datum;
j. Any other information which will aid reproduce ability of the
examination or will assist in interpretation of the results
9-9- APPENDIX 1
SB ≈ 2d cos Ø
which:
SB is Time Base Range
d is part thickness
Ø is probe angle
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 35 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 36 of 54
MAN TSC 6001 DD QC PRC 0006 01
GENERAL NOTES:
a. Holes shall be drilled and reamed a minimum of 1-1/2 in. deep,
essentially parallel to the examination surface.
b. Alternatively, the block may be constructed as shown in Fig. T-441.1. of
ASME Sec. V.
c. Curved surfaces: for curved surfaces, two curved blocks, one for each
representative curvature; or two sets of calibration reflectors oriented 90°
from each other shall be used.
d. Notches may be provided as required.
e. The tolerance for hole diameter shall be ± 1/32 in. The tolerance on
notch depth shall be +10 and -20%. The tolerance on hole location
through the thickness shall be ± 1/8 in.
NOTE (1): For each increase in weld thickness of 2 in. or fraction thereof over 10
in., the hole diameter shall increase 1/16 in.
10- Magnetic Particle Testing (MT)
This procedure describes the method used by SADID for inspection by Magnetic
Particle Testing of all forms of materials where this type of inspection is required /
recommended.
10-1- PERSONNEL
All personnel employed shall be instructed and examined in accordance with
requirements of T-170 of ASME Sec. V or SADID Written Practice.
10-2- MATERIALS TO BE EXAMINED
Bevels
Areas where temporary supports have been welded after removal of supports
Forgings
But and Nozzles Welding
10-3- SURFACE PREPARATION
Satisfactory results may generally be obtained when the surfaces are in the as-
welded, as-cast, as-rolled or as-forged condition. However, surface preparation by
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 37 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 38 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 39 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 40 of 54
MAN TSC 6001 DD QC PRC 0006 01
±2°.
Test Specimen:
The thickness of the specimen shall be such that no bulge or marking showing the
effect of the test force appears on the side of the piece opposite the indention.
Minimum thickness requirement for hardness test is given in table 5 of ASTM E10.
The surface on which the indentation is to be made, shall be filed, ground, machined
or polished with abrasive material so that the edge of the indentation shall be clearly
defined to permit measurement. Care should be taken to avoid overheating or cold
working the surface.
Test Force: Typically, standard test force for a intender of 10 mm diameter is 29.42
and 14.7 KN. For another ball diameter see table 3 (ASTM E10) time duration for
applying full test force is 10 to 15 S.
11-3- EVALUATION OF INDENTATION
When indentation is made on a curved surface, the minimum radius of curvature of
the surface shall not be less than 2½ times the diameter of the ball. The measurement
of the indentation shall be taken as the mean of the major and minor axes (“d” in Fig.
1). A number which is proportional to the quotient, obtained by dividing the test
force by the curved area of the indention which is assumed to be spherical.
2𝐹𝐹
𝐻𝐻𝐻𝐻 = 0.102 ×
𝜋𝜋𝜋𝜋�𝐷𝐷 − √𝐷𝐷2 − 𝑑𝑑2 �
Where
“D” is diameter of the ball in mm,
“F” is test force in N
and “d” is mean diameter of the indentation.
d D
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 41 of 54
MAN TSC 6001 DD QC PRC 0006 01
The values which are calculated according to the equation by considering different
values of the “d” and ball diameter are given in table 2 of ASTM E10.
11-4- EXAMINATION
On each circumferential weld (outside)
On each circumferential weld (Inside)
In the zone where repairs have been made by manual welding
In zones where temporary supports have been welded and subsequently removed
(according to the inspector judgment).
Hardness value for each type of weld shall be checked in 3 point included weld HAZ
and base metal and average of these values shall be determined and record for
compare with allowable value.
For carbon steel the measure values of hardness shall not exceed 225 HB.
11-5- CERTIFICATION
All hardness examination shall be certified on a relevant report inserted on Final
Book.
11-6- RESULTS
If hardness values exceed the max. allowable values section 6, an additional 2 tests
shall be on same weld. If either of the tests indicates excessive hardness, the weld
shall be made rejected and it is necessary to perform a new PWHT to correct the
excessive hardness, after approval by purchaser.
After PWHT, the weld shall be retested for hardness verification as detailed above.
12- REPORT Formats
12-1- NDT Reports
For all NDTs performed at the site, original reports shall be provided with due
endorsement from the contractor or consultant or client as applicable.
Reports shall contain details of components or welds radiographed with unique
identifications provided to each of the weld seams or components.
The personnel deputed to carry out NDTs and prepare the report shall be qualified
adequately for the envisaged works and provide evidence of proper qualifications.
Details of the examination techniques, equipment, consumables, and extent of testing
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 42 of 54
MAN TSC 6001 DD QC PRC 0006 01
shall be presented in detail in the report. When technique sheets have been separately
approved, reports need only contain a reference to these sheets.
01
As in other reports, both performance date and report date shall be clearly indicated.
When records consist of more than one page, all pages shall be numbered as “page x
of y” and have the report number on all pages to ensure inclusion of the complete
report.
The report shall clearly indicate the stage at which the NDT was carried out. For
example, when a heat treatment or forming is required in manufacturing, NDT
reports shall indicate whether the required examination was carried out before or
after the heat treatment operation.
Acceptance or rejection criteria adopted in the evaluation also shall be indicated in
the report.
The minimum achieved sensitivity levels or calibration standards along with the
acceptance criteria shall be recorded in the report.
Below table is the list of QC formats preceding the formats themselves implemented
at the site for performing quality controlling and quality assuring course of
activities:
Format
Row Report Title Number Remark
Rev.
01 Radiographic Test (RT) Report QC-ME-IF-011-00 Rev:00
02 Dye Penetrant Test (PT) Report QC-ME-IF-014-00 Rev:00
03 Vacuum-Box Testing (VB) Report QC-ME-IF-025-00 Rev:00
04 Penetration oil test (Pen. Oil) report QC-ME-IF-015-00 Rev:00
05 Weld Visual Inspection Report QC-ME-IF-010-00 Rev:00
06 Ultrasonic Test (UT) Report QC-ME-IF-012-00 Rev:00
07 Magnetic Particle Test (MT) Report QC-ME-IF-013-00 Rev:00
08 Post Weld Heat Treatment (PWHT) Report QC-ME-IF-016-00 Rev:00
09 PWHT Completion Checklist QC-ME-IF-032-00 Rev:00
10 Hardness Survey Report QC-ME-IF-017-00 Rev:00
11 NDT Completion Checklist QC-ME-IF-033-00 Rev:00
12 NDT REQUEST QC-ME-IF-046-00 Rev:00
Interconnecting Utilities and Offsite of MOKRAN
Petrochemical Complex - Stage 1
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 43 of 54
MAN TSC 6001 DD QC PRC 0006 01
01
Radiographic Test (RT) Report QC-ME-IF-011-00 Rev:00
Project
FIN No.: Report No.:
Name:
Tank Name: Contractor: TIV Energy Co. Date:
Contract
Tank No: Subcontractor:
No:
Tank No. Drawing No. Request no.
Weld Map Ref: Procedure No.
Radiographic Details
Source Film Type SFD
Source Strength Film Brand Density
Source Size IQI Sensitivity
Screen Technique SWSI DWSI DWDI
Material Weld Condition As Welded After PWHT
Description of Welds Radiographed
Film Type of
Welder
ITEM 1 ITEM 2 Size Result Defect and Remarks
ID
(mmxmm) Location
Description /
Work order
RT
Weld Material
ACCEPTED
RE-SHOOT
No
RE-TAKE
REPAIR
No. Type
No. Size Thk. Size Thk.
(mm) (mm) (mm) (mm)
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 44 of 54
MAN TSC 6001 DD QC PRC 0006 01
01
Dye Penetrant Test (PT) Report QC-ME-IF-014-00 Rev:00
Project
FIN No.: Report No.:
Name:
Tank Name: Contractor: TIV Energy Co. Date:
Tank No: Subcontractor: Contract No:
Tank No. Drawing No. Request no.:
Weld Map Ref: Procedure No.
Dye Penetrant Test Details
Equipment Type Cleaner Type
Material Cleaner Application
Surface Condition Developer Type
Penetrant Type Development Time
Dwell Time Stage Before PWHT After
PWHT
Method Color Fluorescent dye Lighting: Natura Artificial Ultraviolet
dye l
Description of Welds Tested
Serial No. Joint Location Indication Defect Size Evaluation
No.
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 45 of 54
MAN TSC 6001 DD QC PRC 0006 01
01
Note:
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 46 of 54
MAN TSC 6001 DD QC PRC 0006 01
01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 47 of 54
MAN TSC 6001 DD QC PRC 0006 01
01
Weld Visual Inspection Report QC-ME-IF-010-00 Rev:00
Notes:
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 48 of 54
MAN TSC 6001 DD QC PRC 0006 01
01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 49 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 50 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 51 of 54
MAN TSC 6001 DD QC PRC 0006 01
01
PWHT Completion Checklist QC-ME-IF-032-00 Rev:00
Notes:
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 52 of 54
MAN TSC 6001 DD QC PRC 0006 01
01
Hardness Survey Report QC-ME-IF-017-00 Rev:00
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 53 of 54
MAN TSC 6001 DD QC PRC 0006 01
Document No.: Owner Cons. Unit-Sub Unit Phase Dis. Doc. Seq. Rev.
Page 54 of 54
MAN TSC 6001 DD QC PRC 0006 01
01
NDT REQUEST QC-ME-IF-046-00 Rev:00
UT MT OTHER:
Thk.(mm)/ Remark
Item SUBJECT Location Weld No. Welder Code Material
Dia.(in.) s
1
2
3
4
5
6
7
8
9
10
11