Professional Documents
Culture Documents
Shallow Deep
Foundations Foundations
Df ≤ 3 B Df > 3B
Advantages of shallow foundations Advantages of deep foundations
Cost (affordable). Settlement (minimum).
Construction procedure (simple). Bearing capacity (high).
Material (mostly concrete).
Labour (doesn’t need expertise).
1.1 Classification of piles according to load transmission:
Qs = Ca . As
Ca (adhesion) = α c1
α = 0.30 to 0.40 for bored piles & Table 1.1 for driven piles
As = perimeter x length = O . L
Table 1.1: Cohesion and adhesion values for driven pile types
Pile type Cohesion (kn/m2) Adhesion (kn/m2)
Zero to 12.5 Zero to 12.5
12.5 to 25.0 12.5 to 24.0
Wood Or Concrete
25.0 to 50.0 24.0 to 37.5
Piles
50.0 to 100 37.5 to 47.5
100 to 200 47.5 to 65.0
Zero to 12.5 Zero to 12.5
12.5 to 25.0 12.5 to 23.0
Steel piles 25.0 to 50.0 23.0 to 35.0
50.0 to 100 35.0 to 36.0
100 to 200 36.0 to 37.5
2.1 Static equation:
Qs2 = (Po . kHC) . As . tan δ = 8.40 x 1.00 x 6.28 x tan 24.75 = 24.31 ton
• Pob = ∑γ1 . Hc
• 20 dia = 20 x 0.40 = 16.00 m & L = 17.50 m >>>> Hc = 8.00 m.
• Po = ∑γ1 . Hc = 1.80 x 2.00 + 0.80 x 6.00 = 8.40 t/m2
• kHC = 0.70 to 1.50 for bored pile ≈ 1.00
• As = O . L = (π d) . L = (π x 0.40) x 5 = 6.28 m2
• δ = 0.75 Φ for bored pile = 0.75 x 33 = 24.75o
0.42
Powt = γpile . A . L = 2.50 x π x 20.00 = 6.28 ton.
4
Qu 62.90
Qall = = = 31.45 ton..
F.S 2.00
For pile capacity in tension:
Qu = Qs + Powt
Load (ton) zero 25 50 75 100 125 150 175 185 195 zero
Settlement
zero 1.25 2.50 3.75 6.50 10.5 17.5 32.5 40.0 50.0 35.0
(mm)
Solution
1. Using empirical rules, and plotting the Load-Settlement curve
Sett. (mm) 1.25 2.50 3.75 6.50 10.5 17.5 32.5 40.0 50.0
Δy (213−169) x 10−3
b= = = 4.40 x 10-3
Δx 10
1 1
Qu = = = 189.40 ton
1.20 b 1.20 x (4.40 x 10−3)
Qu 189.40
Qall = = = 94.70 ton
FS 2.00
2.3 Using results of Standard penetration test (SPT)
It is used for both driven and bored piles in cohesionless soil
For driven piles
Qall = 90 N (πR2) + N' (2πRL)
Depth 1 2 3 4 5 6 7 8 9 10 11
Spt 8 11 14 23 28 31 33 36 41 50 55
Soil Clay Sand Sand
6R+2R 6R 2R
Solution
36+41+50
N= = 42.33 ≤ 50
3
23+28+31+33+36+41
N': = 32.
6
Where:
S0: Total settlement of single pile.
Sall.: Allowable settlement of single pile.
Ss: Elastic compression of pile.
Spp: Settlement of single pile due to end bearing.
Sps: Settlement of single pile due to friction.
L
Ss = (Qb+ αf . Qs)
A . Ep
Where:
Qb ult Qs ult
Qb = & Qs =
F.s F.s
L: Pile length & A: Area of pile cross section
Ep: Modulus of elasticiy of pile material ≈ 2.10 x 106 t/m2 (for concrete).
α: Coefficient depends on distribution of skin friction along pile length.
Cb . Qb 0.12 x 4.03
Spp = = = 0.0094 m
d . qp 0.30 x 171
For bored piles in sand, Cb = 0.12
qp = Pob . Nq = 5.70 x 30 = 171 t/m2.
Cs ∗ Qs 0.26 x 14.86
Sps = = = 0.0013 m.
Lo ∗ q p 18 x 171
Lo 18
Cs = (0.93 + 0.16 . ) . Cb = (0.93 + 0.16 x ) x 0.12 = 0.26
d 0.30
𝜃 𝑚 𝑛−1 +𝑛 𝑚−1 d
Ge = 1 − & θ= tan -1
90 𝑚.𝑛 S
Where:
m: Number of rows in group. n: Number of columns in group.
D: diameter of pile. S: spacing between piles.
Calculation of pile group capacity in cohesive soil
Where:
So: Settlement of single pile.
B: Width of pile group (B<A).
d: Pile diameter
(b) In Cohesive soil
(b) In Cohesive soil
Cc . H σo+ Δσ
Sgroup (ΔH) = . log OR Sgroup (ΔH) = mv . Δσ . H
1+eo σo
Where:
Cc: Compression index.
mv: Coefficient of volume compressibility.
H: Thickness of clay layer.
eo: Initial void ratio.
σo: Initial overburden pressure at center line of clay layer = Σγ.H
Δσ: Change in stress at center line of clay layer.
Qall (group) Qall (group)
For, σ = >>> Δσ =
A.B A+Z . (B+Z)
Two methods are illustrated here:
1. Rigid method.
2. Elastic center method.
Solved Example
6. A pile group of 16 piles spaced at 80
cm both ways is subjected to vertical
load of 480 ton acting at eccentricity
ex = 0.30 m and ey = 0.20 m to the
centre of gravity of the pile cap. Using
rigid method, find the axial force in
each of the piles beneath the cap.
Solution:
ΣP = 480 ton.
Mx = ΣP . ey = 480 x 0.20 = 96 m.t.
My = ΣP . ex = 480 x 0.30 = 144 m.t.
ΣP y x
Qact/pile = ± Mx. ± My.
n Σy2 Σx2
𝚺𝐏 𝐱 Qact/
𝐲
Pile x y X2 Y2 Mx. My.
𝚺𝐱𝟐
𝐧 𝚺𝐲𝟐 pile
1 1.2 1.2 1.44 1.44 30 9 -13.5 25.5
2 0.4 1.2 0.16 1.44 30 9 -4.5 34.5
3 0.4 1.2 0.16 1.44 30 9 4.5 43.5
52.5<Qall
4 1.2 1.2 1.44 1.44 30 9 13.5
(comp.)
5 1.2 0.4 1.44 0.16 30 3 -13.5 19.5
6 0.4 0.4 0.16 0.16 30 3 -4.5 28.5
7 0.4 0.4 0.16 0.16 30 3 4.5 37.5
8 1.2 0.4 1.44 0.16 30 3 13.5 46.5
9 1.2 0.4 1.44 0.16 30 -3 -13.5 13.5
10 0.4 0.4 0.16 0.16 30 -3 -4.5 22.5
11 0.4 0.4 0.16 0.16 30 -3 4.5 31.5
12 1.2 0.4 1.44 0.16 30 -3 13.5 40.5
7.5<Qall
13 1.2 1.2 1.44 1.44 30 -9 -13.5
(tension)
14 0.4 1.2 0.16 1.44 30 -9 -4.5 16.5
15 0.4 1.2 0.16 1.44 30 -9 4.5 25.5
16 1.2 1.2 1.44 1.44 30 -9 13.5 34.5
Σ 12.8 12.8 480 = ΣP
The column loads are transferred to groups of piles through pile caps.
Note that:
Pile caps are designed as reinforced concrete footings.
It should have considerable thickness, to be stiff enough to distribute the
column load equally on the piles. (dmin = 2 pile diameter).
The heads of reinforced concrete piles should be stripped down and the
reinforcement bonded into the cap to give the required bond length.
The piles should be embedded for a depth not less than 8 cm in the caps.
Caps should project 5 - 10 cm or half pile diameter beyond face of piles.
The soil under the pile caps is not considered to offer any support.
Determine the approximate number of piles
Pcol(working) x 1.10
n=
Qall/pile x Ge
(Assume Ge = 0.70, in case of piles rested on clay).
Arrange piles, using S = (3:8) d & e = d
Determine the ultimate load/pile
1.50 x Pcol(working) x 1.10
Qult/pile =
Number of piles
Determine the cap depth from moment, punch and shear
(dmin = 2 pile diameter).
Determine the reinforcement
Solved Example
7. Design an isolated pile cap to support a column 40 x 80 cm2, with axial
load of 250 ton, the pile of 50 cm diameter and capacity of 80 ton.
Solution:
Arrange piles:
S = 3.00 d = 1.50 m & e = d = 0.50 m.
Mu ( I - I ) = 2 x Qu/pile x z1
1.50 0.80
= 2 x 103.125 x ( - ) = 72.19 m.t/B
2 2
Mu
d = c1 x
Fcu x B
72.19 x 105
= 5.00 x = 53.74 cm.
250 x 250
1.50 0.40
Mu ( II - II ) = 2 x Qu/pile x z2 = 2 x 103.125 x ( - ) = 113.44 m.t/L
2 2
Mu 113.44 x 105
d = c1 x = 5.00 x = 67.36 cm.
Fcu x L 250 x 250
Fcu
qsh/allowable = 0.49 x = 6.33 kg/cm2
γ𝑐
z1
Qu ( I - I ) = 2 x Qu/pile x
dia
10
= 2 x 103.125 x = 41.25 t/B
50
Qu 41.25 x 1000
Qsh/actual = = = 1.65 kg/cm2
B.d 250 x 100
z1 30
Qu ( II - II ) = 2 x Qu/pile x = 2 x 103.125 x = 123.75 t/B
dia 50
Qu 123.75 x 1000
qsh/actual = = = 4.95 kg/cm2 >>> Shear is safe
L.d 250 x 100
Depth of pile cap:
(c) Punching
a Fcu 40 250
qp/allowable = ( + 0.50) x ==( + 0.50) x = 12.91 kg/cm2
b γ𝑐 80 1.50
Qu/Punch = 1.50 x Pcol(working) – ΣQu/piles = 1.50 x 250 = 375 ton.
Area of Punch = perimeter x d = (2(b+d) + 2(a+d)) x d
= (2x (0.80+1.00) + 2x (0.40+1.00)) x 1.00 = 6.40 m2
Qu/punch 375
qp/actual = = = 58.59 t/m2 = 5.60 kg/cm2 >>> Punch is safe
Ap 6.40
Reinforcement of pile cap
Minimum Reinforcement
0.15 0.15
As min = xbxd= x 100 x 100 = 15 cm2/m.
100 100
Long Reinforcement
Mu (I−I) 72.19 x 105
As (I – I) = = = 24.27 cm2/B = 9.71 cm2/m.
Fy x d x j 3600 x 100 x 0.826
Short Reinforcement
Mu (II−II) 113.44 x 105
As (II – II) = = = 38.15 cm2/L = 15.26 cm2/m.
Fy x d x j 3600 x 100 x 0.826
Assume pile diameter and length. In case of piles rested on sand, it should penetrate sand
layer with length at least 3 dia.
Calculate allowable pile capacity using 2 methods at least.
Check that settlement of single pile < allowable settlement. Or, re-dimension piles.
Assume spacing between piles from ( 3 : 8 ) dia., and arrange piles such that “Center of
loads matching the center of piles – as much as possible”.
Check that group capacity > 1.10 actual working loads. Or, re-space piles.
Check that settlement of group < allowable settlement.
Model raft on piles.
Calculate actual load to each pile and check for both maximum compression and tension.
Input column loads, it is preferred to be distributed not concentrated.
Assume thickness of raft, at least 2 dia and define it as a thick shell.
Constrain the raft in x-y directions only.
Ignore the presence of soil.
Consider pile as a spring, with stiffness k = allowable load/allowable settlement (single).