ASSEMBLY MANUAL
15.07.2019
TEMPATURE
CONTROL SYSTEM SGS-ENG-001-072019
CONTENTS
1.1Cables Assembly To Silo..............................................................................2
21.2.Slave Box Assembly To Silo Roof .............................................................2
2. Equipment List..............................................................................................3
2.1.Heat Control Cable’s Structure………..……................................................................3
2.2. Slave Card’s Structure.................................................................................................... 5
2.3. Master Or Pc Card’s Connection……………..............................................................7
2.4. Master Card’s Structure................................................................................................ 9
2.5. Connecting The Supply To Master Card................................................................10
1.2.Slave Box Assembly to Silo Roof
2.1.Heat Control Cable Structure
2.2. Slave Card
2.3. Master Card
2.4. Feeder Part
2.1.Heat Control Cable Structure
Cables assembling to silo are shown on figure.1.1 and figure.1.
Figure.1.2:View of heat control cable’s part which is ready to assemble.
Heat control cable consist of 3 wire as can be seen on figure 2.1 these are
respectively;
MYSILO Grain Storage Systems 5
Figure.2.1:Heat control cables connection and structure
1.The color red +5V input.
2.White data input
3.Black (‐)minus input.These connect to slave card respectively;
Red+5V input
White Appropiriate number prop input.
Black Ground input
Make sure the cables are connected correctly ,otherwise these entries would
damage both the card and cables so it will lead to not give the measurement of
heat.
2.2.Structure Of Slave Card
Section1:Connecting heat cencor cables.In this section the cables connect the
place with according the custom of the slave card +5v,prop and ground input
respectively. (Figure.2.3).
Section2:Connecting the data lines.Data line’s cable’s outer sheath consist of
purple color. This cable consist of two wires and this cable move the data.These
cables consist of red and gren colors and marked with “B” with“A”letters in board.
Connect these cables the wires to where the same with letters and colors.
Section3:Power line connection.This part is important too. Circuit card supply
is 24V.These cables must be connect in places where is 24v and 0v according to the
appropriate color and suitable polarized.
Figure.2.3:Heat cables connect the cables to the card after inserted it into the next
version.
Master card where there is no connection to computer must be mounted to
silo which is height of 1.5 m from ground. (Figure.2.8).When connected to the
computer,it should be mounted somewhere near the computer. Master card’s
circuit diagram and connection type is seen on figure.2.7.
Figure.2.5:Master card’s cables without installing version.
Figure.2.6:Master card’s cables after installed version.
2.4.Master Card Structure
Card’s structure is seen on figure.2.6.Card’s connection consist of two section
“2”.
Section1:The data of card is output line.This line is shown data output which
is required to communicate with slave cards where is located on silo’s upper.Purple
color cable’s gren(B) and red (A) edges should be connected respectively and other
edges should be taken to connect the card.
Section2:24V supply fort he card needs to work.These edges should be
connected in place where is on card respectively to be “+24V”and“0V”and not to be
confused their directions.Master card also makes the slave cards’ supplies from 24
Switching power supply is used as a supply 24 volt input and 24 volt output.
Shape of power supply connection is seen on figure.2.9.The connection should be
made in this way and cconnected to Master card.
Figure.2.9:Supply the heat control system.
Figure.2.10:Heat control system’s supply part of photo.