According to IFC drawing for boys & girls school (HA-176388-001, HA-176389-001, HA-176413-001, 176431-001, HA-176432-001, HA-
176456-001)
We have a conflict in door type D2 which is located in second floor both school as highlighted in attached (HA-176389-001, HA-176432-001,
A4 plan), its shown that the door type D2 have a glass sides, but in the doors schedule drawing (HA-176413-001, HA-176456-001) its shown
the door without any glass sides.
ABC propose to follow the regular door type D2 as IFC door schedule (HA-176413-001, HA-176456-001), without glass sides.
Note: first floor for both schools shown the same door without glass sides as attached.
11/20/2019
Engineering Manager - Engr.Mohammed Rassem Signature: Date:
For Contractor:
Project Manager - Engr.Ahmad Farouk Signature: Date: 11/20/2019
Reviewed for General Acceptance. This review does not relieve the Contractor of his responsibility for making the work conform to the requirements of the Contract
Response:
For PMT/CMT
Name: Signature: Date:
For SAPMT
Name: Signature: Date:
Note: This form cannot modify contract cost or time, if contractor belives that response creates a change in scope and effecting cost and/or time, contractor should submit a "Request for Change"
Response Received:
For Contractor:
Name: Signature: Date: