SOUTH DHAHRAN HOME OWNERSHIP PROJECT

Request For Information (RFI)

RFI #: 01/16/00014/RFI/0168 Rev #:00 Date: 20-Oct-19

Contractor: Ashi and Bushnag Co. Ltd Contract No.: 6600042949


Contract Title: SDHO Private School
Stru Plu HVA Infr LndSc Other
✘ Arch. FF Elec.
Disipline: c. mb. C a. p. ____________

RFI Title: LAYOUT OF FLOOR FINISHES


RFI Description:

According to IFC drawings for boys and girls school (HA-176458-001, HA-176458-002, HA-176415-001, HA-176415-002).

It’s shown in the finishes schedule that the floor finishes of the (Halls, classrooms and SC.Lab) for both schools as two type of materials,
and the specifications (GEN-E0004 SECTION 093100, DIV09-37 OF 78) refering us to drawing (HA-329256 sheets 001) which is not in our
IFC.
Please advise us with the finishing design layout for the areas that are mentioned above.

HA-176458-001, HA-176458-002, HA-176415-001, HA-176415-002, GEN-E0004 SECTION 093100, DIV09-37 OF 78


Attachements:

Initiator: Tech. Engineer - Abdulmohsin.A.Sanki Signature: Date: 10/20/2019

10/20/2019
Engineering Manager - Engr.Mohammed Rassem Signature: Date:

For Contractor:
Project Manager - Engr.Ahmad Farouk Signature: Date: 10/20/2019

Distribution: ✘ SAPMT ✘ PMT / CMT

Reviewed for General Acceptance. This review does not relieve the Contractor of his responsibility for making the work conform to the requirements of the Contract

Response:

For PMT/CMT
Name: Signature: Date:
For SAPMT
Name: Signature: Date:

Note: This form cannot modify contract cost or time, if contractor belives that response creates a change in scope and effecting cost and/or time, contractor should submit a "Request for Change"

Response Received:
For Contractor:
Name: Signature: Date:

Distribution: ✘ SAPMT ✘ PMT / CMT