You are on page 1of 10

DAILY MANPOWER & SITE WORKS REPORT (JGC)

Date :- / / 2022

SR Manpower Type
Company Name Assigned Work Remarks
#
Direct Indirect
TCC (civil works)

1 Site engineer

2 Supervisor

3 Quality Control Inspectors

4 safety officer

5 Permit Receiver(WPR)

6 Foreman

7 Mason

8 Carpanter

9 Steel fixer

10 Painter (Coating)

11 General Labour

12 Flag man

13 Drivers

14 Operators

Total Manpower(A) :-

RAMZ (Earthwork)

1 Supervisor

2 Foreman

3 Flagman

4 Drivers

5 Operators

Total Manpower(B) :-
Net Total (A+B) =
MORNING SITE ACTIVITY REPORT (JGC)
Date :- / / 2022

SR MANPO
LOCATIONS WORK DESCRIPTION TARGET DONE
# WER

INSIDE HdGP PIPE FOUNDATIO

Investigation is not finalize by Saudi Aramco


1 WPR HDGP Safety Diparment

2 MASON

3 SCAFFOLDER

4 STEEL FIXER

5 CARPAINTER

6 HELPER

7 EXCAVATOR OPERATOR

8 JCB OPERATOR
SR MANPO
LOCATIONS WORK DESCRIPTION TARGET DONE
# WER
Total Manpower(A) :- Nil Tomorrow Plan : If permit will issued by issuer then excavational activity would be start
inside plant for PB foundations (F-70, F-71 & F-72)

OUTSIDE SLEEPER FOUNDATION

1 Bitumen coating work ongoing Sleepers 83,


84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95 & 14 pipe sleeper 3Rd and 4Th coat try
1 WPR 96 to comple

2 Surface preparation ongoing for pipe sleeper


2 MASON and SL .80.98.108. surface preparation try complet

1
3 SCAFFOLDER Housekeeping also on going parallel

1
4 STEEL FIXER Start to back filling FOR Pipe Sleeper,

1
5 CARPAINTER SL 107.106.105.104,103,102,101,100,99,97, 1ST Layer BACK FILL TRY TO Complet
6 HELPER 12
7 EXCAVATOR OPERATOR 1

8 FORMAN

9 JCB OPP 1
SR MANPO
LOCATIONS WORK DESCRIPTION TARGET DONE
# WER Tomorrow Plan :
14 nos sleeper foundation will paint tomorrow & surface
20 preparation also parallal. If coating Inspection done then start bakcfill activity. PB 2
Total Manpower(B) :- foundation F74.75 stat the send bendig

OUTSIDE SCRAPPER AREA

1
1 WPR 4 SL Precast Installation Ongoing 4 SL Installection TRY TO Complet

1
5 CARPAINTER SL, 145,143,142,141,
5
6 HELPER

1
7 STEEL FIXER

8 TRELER DRIVER

1
9 Regger

1
10 Caren opp

1
11 surveyor
SR MANPO
LOCATIONS WORK DESCRIPTION TARGET DONE
# WER

Total Manpower(C) :- 11
Tomorrow Plan :
If Generator will arrive at site then we will start surface
preparation activity for 9 pipe sleeper foundations
Net Total (A+B+C) = 31
AFTERNOON SITE ACTIVITY REPORT (JGC)
Date :- / / 2022

SR# LOCATIONS MANPOWER WORK DESCRIPTION TARGET DONE

INSIDE HdGP PIPE FOUNDATIO

Investigation is not finalize by Saudi Aramco


1 WPR HDGP Safety Diparment

2 MASON

3 SCAFFOLDER

4 STEEL FIXER

5 CARPAINTER

6 HELPER

7 EXCAVATOR OPERATOR

8 JCB OPERATOR
SR# LOCATIONS MANPOWER WORK DESCRIPTION TARGET DONE

Total Manpower(A) :- Nil Tomorrow Plan : If permit will issued by issuer then excavational activity would be start
inside plant for PB foundations (F-70, F-71 & F-72)

OUTSIDE SLEEPER FOUNDATION

Bitumen coating work ongoing, Sleepers 83,


1 84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95 & 14 pipe sleeper 3rd and 4th coat try
1 WPR 96 comple Done

2 Surface preparation ongoing for pipe sleeper pipe sleepe surfacepreparation try
2 MASON and SL 80,98,108 comple Done

1
3 SCAFFOLDER Housekeeping also on going parallel ONLY 2PIS. PIPE SLEEPER Sl 98,108 DONE

1
4 STEEL FIXER SL 107.106.105.104,103,102,101,100,99,97 1ST Layer BACK FILL TRY TO Comple cuntinue

1
5 CARPAINTER

12
6 HELPER

1
7 EXCAVATOR OPERATOR
SR# LOCATIONS MANPOWER WORK DESCRIPTION TARGET DONE

Forman

1
8 JCB OPERATOR

Tomorrow Plan :
20 14 nos sleeper foundation will paint tomorrow & surface
Total Manpower(B) :- preparation also parallal. bakcfill activity. continue

OUTSIDE SCRAPPER AREA

1
1 WPR 4 SL Precast Installation Ongoing 4 SL INSTALLATION COMPLETED Done

1 SL 145,143,142,141, also 4, pis, pipe sleeper


5 CARPAINTER unloding Done

4
6 HELPER

1
7 forman

1
8 TRELER DRIVER

1
9 regger
SR# LOCATIONS MANPOWER WORK DESCRIPTION TARGET DONE

1
10 caren opp

1
11 surveyor

Total Manpower(C) :- 11
Tomorrow Plan :
If Generator will arrive at site then we will start surface
31 preparation activity for 9 pipe sleeper foundations also reber clean
Net Total (A+B+C) = Manpower

You might also like