You are on page 1of 1

BGB SHIMANTO TOWER PROJECT

DAILY REPORT Weather: C 27 33

Project Name: Construction of Shimanto Tower Date: 02-Sep-21, Thursday

Work Location: 4th Floor Slab Day: Day No 3 After last slab casting:
`
No. of
AWR-Genesis JV Work Force Working at PMC/ Consultant Representing
Man
Accountant +Store 3 Project Staff Arch. Mainul Quader Volumezero Ltd.
Supervisor 2 Project Staff Engr. Mahfuzur Rahman Volumezero Ltd.
Site Assistant 6 Project Staff Engr. Motaharul Islam Volumezero Ltd.
Electrician 2 Project Staff
Welder 1 Project Staff
Foreman 4 Project
Contractor AWR-Genesis JV
Rebar & Shutter 0
Column & Wall rebar febrication 10 Slab & Column Rebar Engr. Saifur Rahman AWR-Genesis JV
Materials Shifting (Shutter+ Rebar) 10 GF & 1st floor to 2nd Floor roof Engr. Monirul Islam AWR-Genesis JV
Col & Wall Rebar Binding 20 2nd floor Engr. Mamun AWR-Genesis JV
Column & Wall Shutter 0 Outside shutter Engr. Bodiuzzaman AWR-Genesis JV
Safety Scaffold 5 3rd Floor Slab Engr. Avi Shikder AWR-Genesis JV
Curing & Cleaning 2 Cleaning & Curing Engr. Fayej Ahmmed AWR-Genesis JV
Brick Works 0 Temporary Wall at GF
Pipe Painting 0 Scaffold pipe
On Rest 5
Total: Project staff-20 Worker -51 Total -71

Project status & Update Next Target of slab casting is 4-Oct-2021


10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Shutter Materials ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||100%


Column 35 Total Shear Wall
Shutter 0% Shutter 0%
Rebar Binding |||||||||||||||||||||||23% Rebar Binding |||||||||||||13%
Casting 0% Casting 0%
Beam Lift Wall
Shutter 0% Shutter 0%
Rebar Binding 0% Rebar Binding 0%
Casting 0% Casting 0%
Slab Casting All Stair
Shutter 0% Shutter 0%
Rebar Binding 0% Rebar Binding 0%
Casting 0% Casting 0%
Floorwise Progress of 4th Floor Slab
Overall |||||2%
Describe day's activities, location of work etc.
1 Column & Wall stirrup making & Rebar febrication going on
2 SW-1,2,3,4 rebar binding going on
3 LC-1,2,3 rebar binding going on
4 19 Columns rebar binding going on
5 Number of worker decreased
6
7
Remarks:

Preparecd By
Volumezero Ltd.
Project Management Consultant

You might also like