You are on page 1of 1

BGB SHIMANTO TOWER PROJECT

DAILY REPORT Weather: d 27 32

Project Name: Construction of Shimanto Tower Date: 04-Sep-21, Saturday

Work Location: 3rd Floor Slab Day: Day No 5 After last slab casting:
`
No. of
AWR-Genesis JV Work Force Working at PMC/ Consultant Representing
Man
Accountant +Store 3 Project Staff Arch. Mainul Quader Volumezero Ltd.
Supervisor 2 Project Staff Engr. Mahfuzur Rahman Volumezero Ltd.
Site Assistant 6 Project Staff Engr. Motaharul Islam Volumezero Ltd.
Electrician 2 Project Staff
Welder 1 Project Staff
Foreman 4 Project
Contractor AWR-Genesis JV
Rebar & Shutter 0
Column & Wall rebar febrication 6 Slab & Column Rebar Engr. Saifur Rahman AWR-Genesis JV
Materials Shifting (Shutter+ Rebar) 20 GF & 2nd floor to 3rd Floor roof Engr. Monirul Islam AWR-Genesis JV
Col & Wall Rebar Binding 63 3rd Floor Engr. Mamun AWR-Genesis JV
Column & Wall Shutter 18 Column & Wall shutter Engr. Bodiuzzaman AWR-Genesis JV
Safety Scaffold 0 3rd Floor Slab Engr. Avi Shikder AWR-Genesis JV
Curing & Cleaning 2 Cleaning & Curing Engr. Fayej Ahmmed AWR-Genesis JV
Brick Works 6 Temporary Wall at GF
Pipe Painting 8 Scaffold pipe
On Rest 0
Total: Project staff-20 Worker -127 Total -147

Project status & Update Tentative 1st Phase Vertical casting on 06-Sep-21
10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Shutter Materials ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||100%


Column 35 Total Shear Wall
Shutter ||||||||9% Shutter ||||||7%
Rebar Binding |||||||||||||||||||||||||||||||||||||||||||||||||||||||56% Rebar Binding |||||||||||||||||||||||||||||||||||||||||||||||||50%
Casting 0% Casting 0%
Beam Lift Wall
Shutter 0% Shutter 0%
Rebar Binding 0% Rebar Binding ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||67%
Casting 0% Casting 0%
Slab Casting All Stair
Shutter 0% Shutter 0%
Rebar Binding 0% Rebar Binding 0%
Casting 0% Casting 0%
Floorwise Progress of 3rd Floor Slab
Overall |||||||||||||||||||||||||||10%
Describe day's activities, location of work etc.
1 Column & Wall stirrup making & Rebar febrication going on
2 SW-1,2,3,4 rebar binding going on
3 LC-1,2,3 rebar binding going on
4 19 Columns rebar binding going on
5 Column C2H, C2J and Shear Wall 3 shuttering going on
6
7
Remarks:

Preparecd By
Volumezero Ltd.
Project Management Consultant

You might also like