Project Name: Rehab.

/Widening of Lubao-Floridablanca via San Antonio Road


Location: Lubao-Floridablanca, Pampanga

BACK-UP COMPUTATION (AGGREGATE BASE COARSE)

Station Area (sq.m) Average Area (sq.m) Distance Volume


0+000 0.915 0.00 0.00 0.00 m³
0+040 0.086 0.501 40.00 20.02 m³
0+080 0.395 0.241 40.00 9.62 m³
0+120 1.564 0.980 40.00 39.18 m³
0+160 1.574 1.569 40.00 62.76 m³
0+200 1.597 1.586 40.00 63.42 m³
0+240 1.593 1.595 40.00 63.80 m³
0+280 1.639 1.616 40.00 64.64 m³
0+320 1.421 1.530 40.00 61.20 m³
0+360 1.416 1.419 40.00 56.74 m³
0+400 1.386 1.401 40.00 56.04 m³
0+440 1.544 1.465 40.00 58.60 m³
0+474.70 0.000 0.772 34.70 26.79 m³
0+478.55 0.000 0.000 3.85 0.00 m³
0+480 1.309 0.655 1.45 0.95 m³
0+520 1.593 1.451 40.00 58.04 m³
0+560 1.187 1.390 40.00 55.60 m³
0+600 1.569 1.378 40.00 55.12 m³
0+640 1.581 1.575 40.00 63.00 m³
0+680 1.851 1.716 40.00 68.64 m³
0+720 1.909 1.880 40.00 75.20 m³
0+760 1.957 1.933 40.00 77.32 m³
0+800 1.659 1.808 40.00 72.32 m³
0+840 1.646 1.653 40.00 66.10 m³
0+880 1.710 1.678 40.00 67.12 m³
0+920 1.651 1.681 40.00 67.22 m³
0+960 1.853 1.752 40.00 70.08 m³
1+000 1.603 1.728 40.00 69.12 m³
1+040 2.320 1.962 40.00 78.46 m³
1+080 2.320 2.320 40.00 92.80 m³
1+120 2.320 2.320 40.00 92.80 m³
1+160 2.320 2.320 40.00 92.80 m³
1+200 1.651 1.986 40.00 79.42 m³
1+240 1.545 1.598 40.00 63.92 m³
1+280 1.726 1.636 40.00 65.42 m³
1+320 2.134 1.930 40.00 77.20 m³
1+360 2.100 2.117 40.00 84.68 m³
1+400 1.808 1.954 40.00 78.16 m³
1+440 1.682 1.745 40.00 69.80 m³
1+480 1.883 1.783 40.00 71.30 m³
1+520 1.847 1.865 40.00 74.60 m³
1+560 1.871 1.859 40.00 74.36 m³
1+600 1.870 1.871 40.00 74.82 m³
1+640 1.906 1.888 40.00 75.52 m³
1+680 1.888 1.897 40.00 75.88 m³
1+720 1.870 1.879 40.00 75.16 m³
1+760 1.871 1.871 40.00 74.82 m³
Project Name: Concreting of Purok 3, Villa Carmela Road
Location: San Agustin, Guagua, Pampanga

BACK-UP COMPUTATION (AGGREGATE BASE COARSE)


ROAD 1
Station Area (sq.m) Average Area (sq.m) Distance Volume
0+000 0.000 0.00 0.00 0.00 m³
0+040 0.170 0.085 40.00 3.40 m³
0+062.40 1.070 0.620 22.40 13.89 m³
ROAD 2 17.29
Station Area (sq.m) Average Area (sq.m) Distance Volume
0+000 0.000 0.00 0.00 0.00 m³
0+040 1.010 0.505 40.00 20.20 m³
0+083.80 0.920 0.965 43.80 42.27 m³
ROAD 3 62.47
Station Area (sq.m) Average Area (sq.m) Distance Volume
0+000 0.450 0.00 0.00 0.00 m³
0+040 0.450 0.450 40.00 18.00 m³
0+065.80 0.450 0.450 25.80 11.61 m³
29.61

R1 17.29
R2 62.47
R3 29.61
109.37
x 1.10
120.3015

TOTAL VOLUME OF AGGREGATE BASE COARSE : 120.00 m³

Prepared by:

Engr. Maria Weena S. Chu


Engineer II
PERT - CPM
Project Name: #REF!
Location: ###
Calendar Days: ### Calendar Days

0 0 0 0 2 2 2 4 6 6 6 12 12
START A B C D
0 0 0 0 0 2 2 0 6 6 0 12 12
Mobilization/ Embankment/ Aggregate 0.15m thk. PC
Demobilization Filling Materials Base Coarse (RMC 3500 ps

ES DURATION EF
TASK
LS LF

Legend:
ES Early Start
LS Late Start
EF Early Finish
LF Late Finish

PLANNING AND PROGRAMMING DIVISION


Prepared By: RECOMMENDING APPR

EDGARDO D. TICSAY ARMANDO S


Engineering Assistant/Project Engineer Provincial E
33 45 45 0 45
D END
0 45 45 0 45
0.15m thk. PCCP
(RMC 3500 psi @ 28Days)

ON
MMENDING APPROVAL: APPROVED:

ARMANDO S. AUSTRIA HON. LILIA G. PINEDA


Provincial Engineer GOVERNOR
62 78

35

0 2 2
C

2 15 17
B
2 0 17