Professional Documents
Culture Documents
Project
Project Project
Project Plan Management
Definition Close
and Control
Quality Management
Risk Management
Change Control and Issue Management
Configuration Management
1
iterative processes (e.g., weekly status reporting) and continuous processes that
require attention in a non-scheduled manner (e.g. risk management).
◼ Project Close
The Project Close Phase covers three main areas: delivery of the project deliverables
to the client, closing the project, and conducting post-implementation reviews.
2
Perform Quality Control Activities
The purpose of quality control is to identify defects and have them corrected. Quality
control is the responsibility of each project team member. It must occur throughout
the project, and not just when a deliverable is complete.
Two methods generally used to monitor and control quality are:
Reviews
◼ Design Reviews are used to evaluate the content and correctness of the
deliverables, ensure consistency among project components; and, verify
deliverables conform to specified standards and guidelines. The following are
examples of types of reviews:
◼ Self-Review-The person producing the deliverable compares attributes of the
deliverable against predefined criteria or checklist
◼ Informal Review - Peers review manageable units of work in brief review
sessions; peers offer insights based on their own work assignments and
experience. Common during program development and testing.
◼ Formal Team Review - Project team members familiar with the overall system
review major task deliverables. Appropriate when: interaction is required to co-
ordinate work. The deliverable produced becomes the foundation for future work;
and/or consistency of subsystems and interfaces is affected.
◼ Structured Walkthroughs for reviewing major project deliverables. This often
precedes formal user acceptance review, also useful when: subject material is
critical; diverse participation is necessary to verify accuracy and completeness,
participants are from diverse parts of the organisation.
Managing Risk
Project risks are uncertainties, liabilities or vulnerabilities that may cause the project
to deviate from the defined plan. Every IT project carries some element of risk; it is
probable that progress will deviate from the plan at some point in the project lifecycle.
The objective of a risk management process is to minimise the impact of unplanned
incidents on the project by identifying and addressing potential risks before significant
negative consequences occur.
Risk management incorporates the identification, analysis and management of project
risk. After potential risks are identified, the purpose of risk analysis is to determine
the relative exposure in terms of time and cost. Risk management is therefore
concerned not only with identifying risks, but also with reducing risks to an
acceptable level.
Potential project-level risks should be identified during the Project Planning phase.
An ongoing risk management process should then be carried out formally as part of
the Project Planning process, and thereafter monitored and updated as appropriate.
An effective risk management plan:
◼ Is proactive, focusing on prevention rather than cure
◼ Includes periodic risk assessments throughout the project lifecycle
3
◼ Incorporates a continuous process of risk identification, analysis, management and
review.
Risk Management Process
The project manager is responsible for identifying and managing risks to enhance the
probability of a successful project implementation. The risk management process
focuses on the proactive elements of risk management by introducing early risk
identification mechanisms and risk impact analysis methods. Using this, the project
manager will be better positioned to identify and manage risks, rather than allowing
them to become major problems or result in actual project delays.
Risks change during the course of a project. New risks may be identified, as more
information becomes available, existing risks may be eliminated as a result of internal
or external influences. Therefore, risk management is an ongoing project
management function. As each project phase is initiated, the project manager and
team leaders should review the risk management plan and discuss specific risks
associated with the phase.
Manage Risks
The following diagram demonstrates the steps within a risk review process. A
detailed work plan will not be approved until the risk review process has been
completed. The Director of Systems Integration must approve the risk review
process.
Identify initial
project-level risks
Document specific
risks
Perform risk
impact analysis
Develop and
implement risk
management plans
4
◼ A Change is any activity that alters the scope, deliverable, architecture, cost or
schedule of a project.
◼ An Issue is a situation, action, problem or question arising during the performance
of the project which demands action to resolve it over and above the tasks
identified in the plan. Left unresolved, an issue will impede or prohibit project-
related progress or development by delaying or suspending work effort.
The primary objective of change control and issue resolution is to establish a standard
method to document, analyse, approve, and communicate changes and issue
resolutions.
Effective change control and issue resolution involves the following responsibilities:
◼ Provision of a centralised change request monitoring and communication service.
◼ Co-ordination of all change requests and issue forms to ensure completeness and
consistency and to reduce duplication of effort
◼ Maintenance of current status information for change requests/issues in the review
and approval process
◼ Processing of change requests/issues by referrals to appropriate project
participants for analysis and input
◼ Compilation of summary statistics and reports to reflect the status of all change
requests
◼ Updating of project plans, based on information received from team leaders to
reflect changes directly related to approved change requests
◼ Monitoring the impact of approved change requests on the overall project
◼ Prepare reports to appropriate management personnel and the project steering
committee for review
The change control process is illustrated on the following page:
5
Cosmetic Mandatory
Request Query
Change Change RESPONSIBILITY
Client/Initiator/
5. Decide on Action (if appropriate)
Project Manager
6
A wide range of statistical and summary reports are available which benefit both the
BearingPoint project team and the client in ensuring that all change requests are
managed in a controlled environment and issues raised are being resolved effectively.
The reports available include the following:
◼ Detailed reports on specific types of change requests/issues raised i.e. (Open,
Closed, Deferred, In Test, Pending fix etc)
◼ Report on the time taken to re-test
◼ Report on time taken to resolve
◼ Report detailing all issues that have re-occurred
◼ Summary reports by status, area, grade
An archive facility is also available to enable project records (and the issues
associated with them) to be archived when no longer in use. These records can
however be re-imported at a later date if required.
Configuration management
Controlling project deliverables is a crucial element of project management. Current
information technology projects are often performed by a diverse project team,
working in a distributed environment. Therefore, maintaining control over key project
deliverables is a challenging process. Configuration management is the collective
term used for the control of tangible project property—primarily project
deliverables—throughout the project lifecycle. Configuration management
encompasses a major project management area previously referred to as version
control, but includes additional areas of control over all project property.
Configuration management processes and procedures are required for all projects.
System integration and implementation projects have more complicated configuration
control requirements, but all projects require that documentation, procedures and files
be controlled. Configurable project property may include a wide variety of items, such
as source code modules, test data, directory structures for LANs (local area networks)
and personal computers, installation procedures, word processing/ spreadsheet files,
training materials, and data files.
Ongoing configuration management processes should use an automated configuration
management tool to reduce the labour intensity of manual control, and to produce
required control reports.