Professional Documents
Culture Documents
a r t i c l e i n f o a b s t r a c t
Article history: It is a commonly asked question: how big should the longwall shields be? The answer is a key aspect of a
Received 15 January 2015 longwall mining feasibility study when the consequences of inadequately rated shields are considered.
Received in revised form 11 March 2015 This paper addresses this question based on the measured nature of the loading environment in which
Accepted 16 June 2015
shields are required to operate, the various geological and geometrical controls of that environment
Available online 24 August 2015
and the various links between their load rating, a range of other relevant shield design factors and the
loss event they are required to prevent a major roof collapse on the longwall face. The paper concludes
Keywords:
that despite the tremendous advances that have been made in shield design and load rating over the past
Longwall geomechanics
Longwall face instability
50 years, the same drivers that caused longwall miners of the past to seek improved roof control on the
Longwall shield design longwall face via the use of ever-higher rated shields, are still as relevant today. However at the current
Periodic weighting of massive strata time, the limits of the largest available longwall shields have yet to be tested, therefore industry focus for
Longwall panel geometry the foreseeable future should possibly be in achieving the maximum level of roof control on the face via
their optimum operational use rather than considering further shield rating increases and incurring the
inevitable downsides in terms of capital cost and shield weight.
Ó 2015 Published by Elsevier B.V. on behalf of China University of Mining & Technology.
http://dx.doi.org/10.1016/j.ijmst.2015.07.001
2095-2686/Ó 2015 Published by Elsevier B.V. on behalf of China University of Mining & Technology.
688 R.C. Frith / International Journal of Mining Science and Technology 25 (2015) 687–706
Cantilever driven
bending moment
Fulcrum point W
Wshield Horizontally
bedded roof
σh x l strata
l
du/dt
Fig. 4. Longwall face roof cavity containing a proliferation of sub-vertical mining t P
induced fractures.
Less than full depth of cover These three influences can be analyzed within the conceptual
loading impacts face
model shown in Fig. 5 by applying Euler Buckling concepts (which
Face width W represent inevitable beam or column instability), in particular that
of critical buckling stress (for both the coal face in a vertical sense
Fig. 8. Sub-critical overburden conditions and likely abutment load distribution
and the roof horizontally within the tip to face distance) so that a
between the face and surrounding coal pillars.
relative measure of roof fall potential (RFP) via stress-driven gut-
tering can be gained according to both face width and extraction
height.
14
Fig. 5 shows the conceptual model for both the coal face and the
roof above the longwall face and as the model is only being used
Average convergence rate (mm/h)
12
for relative comparison purposes, there is no need to factor in such
10
issues as the nature of the coal, nature of the roof or shield rating
8 and location, etc. These will all be considered as constants for the
6
purposes of this illustration but considered individually later.
In terms of coal face spalling (i.e. causing an increase in tip to
4 face distance or x as shown in Fig. 5), the exceeding of the critical
2 buckling stress for a well-cleated coal in a vertical sense is a func-
tion of both rv (i.e. the vertical stress acting in the coal at any given
0 100 200 300 400 500 600 time) and t (the height of extraction) squared. As such it can be sta-
Depth of working (m) ted that:
Fig. 9. Plot of average shield convergence rate against depth of cover [8]. x ¼ f ðrv ; t 2 Þ ð1Þ
For isolated sub-critical panel conditions, panel width w is
These statements allow the three main controls for guttering taken to be the overriding determining factor for rv so that the fol-
type roof cavity development to be identified (other than the long- lowing is also true:
wall shields themselves), namely (a) amount of roof convergence
x ¼ f ðw; t 2 Þ ð2Þ
above the longwall shields, (b) effective tip to face distance and
(c) nature of the immediate roof strata and its susceptibility to It is noted that mechanistically the use of coal buckling in a ver-
undergo horizontal stress driven buckling (i.e. guttering/cutter roof tical column as the conceptual model for face spall is fully consis-
development) when end-loaded. tent with the primary coal rib failure mechanism for roadways
Frith proposed a basic model for the relative influence of differ- reported by Colwell [7].
ent longwall mining geometry (i.e. face width, extraction height However, face spall on its own is not a direct reason for a long-
and cover depth) on the general face loading environment W and wall face to be unable to produce coal and is therefore only an
therefore as a direct consequence, the general propensity for gut- input into the potential for guttering type roof instability ahead
tering type roof cavity development due to roof convergence above of the shields in the tip to face distance as will now be discussed.
the shield and associated strata bending about the face [1]. This In terms of the roof material just ahead of the shields, exceeding
was termed Roof Fall Potential (RFP) at that time remembering that the critical buckling stress for the bedded roof and so becoming
the development of small guttering type cavities can be the critically unstable is a direct function of both the horizontal stress
pre-cursor to larger collapses due to the potential corrupting of rh acting and the tip to face distance (l + x) squared, so that:
shield effectiveness, as previously described.
2
For demonstration purposes herein, the potential for guttering Roof fall potential ðgutteringÞ ¼ f ðrh ; ½l þ x Þ ð3Þ
type roof instability along a single longwall face in sub-critical over-
For a compressive horizontal stress that is generated in the
burden conditions (i.e. typically the higher depths of cover) with
immediate roof as a result of cantilever bending about the face, it
stable surrounding chain pillars (see Fig. 8) will be analyzed in detail.
can also be shown that rh is a direct function of the vertical dis-
As a general concept for sub-critical overburden conditions as
placement of the free end of the cantilever (u), which in turn is a
defined herein, the maximum possible abutment load affecting
direct function of both the rate of roof displacement above the
the center of the longwall face itself will be assumed to be defined
shields (du/dt) and the rate of longwall retreat during production
by a section of overburden equivalent in height to the panel width.
(R).
Note that this assumption also infers an equivalent caving angle of
The rate of shield convergence (du/dt) was generally linked to
around 26° which is at the upper end of measured abutment angles
depth of cover by Frith and Stewart (see Fig. 9 whereby all deep
in both Australia and the USA [5,6].
monitoring sites contained yielding chain pillars under double goaf
In terms of the driving potential for a guttering type roof cavity
loading), but it logically is more a function of panel width w in iso-
ahead of the shields, the following three factors are logically of
lated sub-critical longwall extraction environments as being con-
some direct relevance:
sidered herein [8].
Similarly the rate of longwall retreat R is also to some degree a
Face spall and the associated increase in the tip to face distance
function of panel width w (assuming similar cutting and flitting
(x in Fig. 5).
speeds for the shearer) so that Eq. (3) can be re-written as:
692 R.C. Frith / International Journal of Mining Science and Technology 25 (2015) 687–706
2
Roof fall potential ðgutteringÞ ¼ f ðw2 ; ½l þ x Þ ð4Þ Composite super-critical subsidence trough across
both sub-critical longwall panels and chain pillar
2
When it is also remembered that x = f(w, t ) as given in Eqs. (2)
and (4) can be re-written as: Fully collapsing
upper overburden
2
Roof fall potential ðgutteringÞ ¼ f ðw2 ; ½l þ f ðw; t2 Þ Þ ð5Þ
In order to use Eq. (5) for comparative purposes, the absolute Face loading
term l (i.e. the geometrical tip to face distance without spall) needs Highly exposed to full
First compressed depth of cover
to be removed and this is justified on the basis of the overwhelm- longwall chain pillar
Second longwall
ing experience of the author being that major roof instability
almost always occurs in conjunction with significant face spall sig- Fig. 11. Super-critical overburden conditions across two sub-critical longwall
nificantly greater than the geometrical minimum tip to face dis- panels and a yielding chain pillar.
120 1800-2000
110 1600-1800
100 1400-1600
90 1200-1400
1000-1200
Chock #
80
70 800-1000
600-800
60
400-600
50 200-400
40 0-200
30 -200-0
251 253 255 257 259 261 263 265 267 269 271 273 275 -400--200
Shear #
Fig. 12. Isopachs of measured leg pressure rises in 5 min period after set (in psi)-longwall 5 at Newstan [9].
300
Rapid
convergence
Uncontrollable
250 longwall Caving
Readily Operationally weighting shortwall
controllable controllable
longwall
Panel width (m)
longwall
200 weighting weighting
?
Bridging
shortwall
150
50
0 5 10 15 20 25 30 35 40 45 50
Equivalent conglomerate unit thickness ECT (m)
Fig. 13. Near-Seam, massive strata weighting classification-data points omitted for the sake of clarity [3].
Protection Protection
In direct contrast, if a massive unit cannot span the panel at the
zone zone face, it will naturally become unstable and so cantilever from a
position ahead of the face, this setting up the potential for as
one block rotation about the face (see Fig. 6). This effect will
Overburden weighting zone
be generally confined to the central portion of the face, with
the two face ends being protected due to the presence of stable
Goaf
flanking coal pillars (see Fig. 14).
The periodic weighting cycle length appears to increase in
(a) Hypothetical near-overburden fracturing arc- direct proportion to the thickness of the massive unit (which
longwall geomechanics (Frith and Stewart 1993) makes perfect sense). Similarly increasing roof fall propensity
50 can also be anecdotally directly linked to an increasing thick-
45 ness of massive strata as was clearly evident during the extrac-
40 tion of LW5 at Newstan Colliery in the mid 1990s. This can be
Leg pressure (MPa)
35 seen in Fig. 15 which shows the roof fall plan for LW5, the vari-
30
ations in roof fall frequency being almost entirely linked to dif-
25
20
ferences in conglomerate channel thickness above the
15 extraction horizon-this being known from detailed up-hole dril-
10 ling studies in the adjacent gate roads and surface borehole
Av. Back press.
5 Av. Front press. information.
0 20 40 60 80 100 120 140
Mechanistically it can be argued that the potential for a block
Support # delineation type roof fall on the longwall face is a function of
(b) Measured powered support loading distribution the cube of the thickness of massive strata (i.e. RFP = f[thick-
across a longwall face (Frith and Stewart 1993) ness3]). The associated logic behind this statement is that the
Fig. 14. Typical support load and overburden fracturing distribution across a
rate of block rotation increases as function of thickness2 (both
longwall face. the moment arm and load acting through the center of gravity
are a direct function of thickness), with the distance that the
face has to retreat in order to progress beyond the extent of
the weighting cycle which also increases in relation to thickness
If a massive unit is sufficiently thick to span the extraction panel
[9]. Combining these independent factors allows the thickness3
at the face, even temporarily, the longwall face is not exposed to
relationship to be derived.
block rotation effects as instability of the massive unit is initi-
ated behind rather than ahead of the face (termed ‘‘shortwall’’
Without doubt, longwall roof control experiences that relate
overburden fracturing).
back to the periodic weighting of thick, near-seam massive strata
694 R.C. Frith / International Journal of Mining Science and Technology 25 (2015) 687–706
e
strata as just described.
ra e bl
m enc ure
)
ct
80 ld es
Rises and falls in energy index were plotted on the panel layout
tra
(1 ubs st m
a ir
as shown in Fig. 16, it was apparent that each rise corresponded
F
with the longwall face approaching a maingate (MG)
cut-through (C/T). Similarly the finish of the falling energy
index corresponded with the face crossing the line of a tailgate
Zone 1
(13) (TG) C/T (the MG and TG C/T’s are only slightly offset as can be
seen in Fig. 16).
A
Zone 3
This result suggested that both the anecdotal mining evidence
(79) (i.e. the reported large goaf falls) and the measured
micro-seismic overburden behavior were somehow linked and
Zone 4 the presence of chain pillars C/T’s might be the trigger for such
(29)
behavior. Whilst this one example did not conclusively makes
the link between chain pillar cut-throughs and the measured over-
Zone 5
Roof fall location (29) burden behavior, it resulted in a search for other evidence in sup-
(29) Days of lost production per port of the theory, as will now be detailed.
zone total=157 or 22.5 weeks
CSIRO/SCT reported the outcomes of micro-seismic monitoring
Fig. 15. Major roof falls and other weighting related events, LW5, Newstan [9]. during part of LW28A extraction at Appin Colliery which was
aimed at investigating overburden geomechanics associated with
gas liberation from beneath the Bulli Seam [10]. Fig. 17 is copied
from that report and the following comments are made:
units shows quite clearly that RFP increases disproportionately
with increasing strata unit thickness. Similarly though, highly Luo and Hatherly first reported this Appin Colliery data and
aggressive periodic weighting effects can be largely eliminated made the comments to the effect that surges in micro-seismic
through relatively minor changes in longwall panel width so as activity were directly associated with increased gas makes from
to induce strata bridging or spanning at the face line (shortwall the floor measures [11].
geomechanics). They also stated that ‘‘the fractures occur in zones which are
spaced at approximately 100 m intervals’’.
1.4.2.2. (2) Overburden weighting in proximity to chain pillar cut- It is understood that the longwall chain pillars were in fact
throughs. During research studies into both periodic weighting and 100 m in length and it is clearly evident in Fig. 17 that each of
windblasts and longwall extraction, a significant amount of evi- these ‘‘fracture zones’’ or ‘‘clusters’’ are situated almost exactly
dence was unexpectedly gathered in support of the view that chain above or in close proximity to TG chain pillar cut-throughs.
pillar cut-throughs have a major influence on overburden fractur-
ing, and consequently, face loading condition [3]. This was not a From this evidence it is difficult to arrive at any conclusions
focus of the research work at the outset, and to the best of the other than that the C/T’s in the TG chain pillar are having a funda-
authors’ knowledge had never even been postulated as a hypothe- mental controlling influence on the occurrence of surges in over-
sis. However, over time the data set became such that the existence
of a real and significant overburden weighting mechanism could
no longer be ignored or dismissed. A brief summary of some of
the supporting data is given herein for reference purposes.
The outbye end of LW19 at West Wallsend Colliery was overlain Solid
by a thick conglomerate channel that was thought to be
non-windblast prone but would nonetheless result in large goaf
falls. As such the mine decided to install a full micro-seismic mon-
itoring system and track overburden behavior during extraction
through this area. As expected the area proved to be
non-windblast prone, but the results of the micro-seismic data
analysis combined with reported large goaf falls showed a result
that was totally unexpected. Solid
Fig. 16 shows the overall outcome of the micro-seismic data
analysis plotted on the mine plan in conjunction with reported
large or abnormal goaf falls. The following comments are made:
Rising enargy index
Falling enargy index
Micro-seismic data indicated that the ‘‘energy index’’ of over- Locelion of reported
burden fracturing exhibited periodic rises and falls in a manner abnormal goaf falls
that suggested the occurrence of periodic weighting of some
form. However, surface subsidence indicated that the
near-seam conglomerate channel in its entirety had not in fact
caved and was almost certainly still spanning the longwall
Fig. 16. Results of micro-seismic monitoring linking large goaf falls with enhanced
panel following extraction. It was also the case that the energy overburden fracturing and chain pillar cut-throughs [3].
R.C. Frith / International Journal of Mining Science and Technology 25 (2015) 687–706 695
1400
Drainage holes
Borehole
1300 Station
27
Longwall face
LW
1200
1100
28
LW
1000
Northing (m)
900 Depth: 80 m
SS thick: 14 m
800
Longwall face position
700 Sep6-13 Monltoring
Longwall face position test zone
600 Sep 21-Oct 1
500
Longwall face position
Approximately
Oct 23-Nov 14 uniform increase in
400
cover depth and
200 300 400 500 600 700 800 900 1000 1100 1200 sondstone thickness
Easting (m)
Fig. 17. Micro-seismic monitoring outcomes from LW28 at app in colliery showing N
event clusters on 100 m cycles and TG cut-through lines [3].
Depth: 160 m
l3
SS thick: 36 m
l2
burden fracturing, which in turn are linked to periods of increased
Pane
l1
Pane
l6
Pane
gas make from the floor measures. Anecdotally, later communica-
Pane
l4
l5
tions with mine site staff indicated that during the extraction of
Pane
Pane
subsequent longwall panels it was very common for gas ‘‘blowers’’
to occur along the face as it was crossing a C/T. In between C/T’s Fig. 18. South Bulga mine-location of face weightings from deputies reports [3].
such occurrences were far less frequently.
Early longwall faces at South Bulga were overlain by massive
sandstone (SS) units with various thicknesses. When deputies As the longwall face retreats, abutment loading of the
reports of discernible face weightings were plotted onto a mine super-incumbent strata is ‘‘thrown’’ onto the flanking chain pil-
plan (see Fig. 18), it was immediately obvious that all of those lars incrementally shear by shear.
weightings that were designated as being [M] ‘‘major events’’ However, each C/T and the extreme ends of the chain pillar rep-
(i.e. those that stopped face production for an extended period) resent an area that cannot readily accept abutment load (as
aligned almost exactly with MG and TG cut-throughs (at 100 m there is either no coal there or the coal is of significantly
spacing) being at each end of the longwall face. No major weight- reduced load bearing capacity).
ings were ever experienced outside of a few meters from a chain Therefore, as the face approaches a C/T, vertical abutment load
pillar cut-through. must logically concentrate inbye of the C/T.
Furthermore later longwall panels in the same area of the mine If the chain pillar is highly loaded just inbye the C/T, but imme-
that were formed up using MG cut-throughs spacing of only 50 m diately outbye the C/T, the next pillar has a significantly lower
(for development productivity reasons) as opposed to the previ- load acting upon it, vertical shear movement must occur within
ously used 100 m, never experienced similar major face weight- the overburden above the longwall face due to what may be ter-
ings, despite the overburden lithology, depths of cover and panel med as ‘‘differential chain pillar compression’’ either side of the
geometry being almost identical. C/T.
The South Bulga data set provides a further credible ‘‘cause and It is hypothesized that this ‘‘differential chain pillar compres-
effect’’ relationship between chain pillar cut-through layout and sion’’ acts to form a vertical discontinuity in the overburden
the occurrence of major weightings on the longwall face with the aligned sub-parallel with the longwall face (this then explains
ability to stop face production for a period. the measured micro-seismic behavior discussed previously),
It is finally noted that the same basic link with chain pillar hence the observed surges in vertical abutment stress acting
cut-throughs can also be found in such phenomena as surface sub- in and around the longwall face itself.
sidence cracking (including the varying location of transverse
cracks parallel with the face) and the occurrence of windblasts dur-
ing extraction. They are not described in detail herein due to space
restrictions, but are discussed in detail by Frith and McKavanagh C/T's cannot accept overburden loading
[3].
From the small body of evidence presented herein, the presence Pillar loading area
of chain pillar C/T’s demonstrably has a significant impact upon High pillar Low pillar
overburden behavior, which in turn is influencing longwall face loading loading
conditions in a number of different ways. Other examples of this Vertical fracturing
link have been found as part of consulting studies which are not Retreat due to differential
direction pillar compression
discussed; herein it is suffice to say that the same basic relation- across the C/T
1.6. Summary
Further apart chain pillar C/T’s are, the higher the surge in abut- The various conceptual and mechanistic models described
ment stress as the face crosses each C/T line appear to be (the herein in combination could possibly be viewed as a ‘‘unified the-
formation of significantly more chain pillar cut-throughs in US ory’’ linking a whole range of geometrical and geological parame-
longwall panels as compared to Australian counterparts is ters to the potential for significant roof instability on the
intriguing in this regard). longwall face via two distinctly different fall mechanisms. When
Other evidence also strongly suggests that staggering C/T’s on combined with the uncertainties inherent in any rock mass, they
the MG and TG side increases the frequency of weighting events provide a credible explanation for many major loss events on long-
and so reduces their severity. wall faces as well as an insight into the characteristics of measured
variations in either shield convergence rate or leg pressure rise rate
It is not clear as to why a measured or inferred overburden on a shear by shear basis, an example of which was previously
weighting does not occur at every C/T line. However, based on both shown in Fig. 12 with two further examples being provided in
measured data and anecdotal outcomes, the effect is demonstrably Figs. 22 and 23 [8].
real and often significant in terms of the occurrence of unwanted However, the term ‘‘unified theory’’ cannot in reality be applied
events that detract from face production. It is also the case that as to the best of the authors’ knowledge, there is no realistic way of
even though the phenomenon was first identified through research bringing them all together into a single methodology whereby
studies relating to longwall extraction under massive immediate shear by shear behavior in terms of key roof stability controls
roof conditions, it has been observed and identified under a much issues, such as level of face spall, shield convergence rate, overbur-
wider range of overburden conditions including lithologies that den rotation effects and rate of longwall retreat can even be esti-
contain no discernible massive strata units. mated, let alone credibly predicted. Therefore they stand as
individual explanatory conceptual empirical models that may
1.5. Retreating out from under high vertical cliffs at low cover depth never be combined into an all-encompassing predictive
methodology.
Although never formally published, the author is aware of at The best that can be achieved with the various models is to
least one shallow longwall mine whereby face line roof control dif- allow longwall mining environments and longwall layout to be
ficulties commonly occurred when the face was retreating out evaluated for both mining geometry and geological/geotechnical
from under a high steep cliff line at surface (see Fig. 20), whereas risk, this then potentially allowing:
such difficulties never occurred when the face retreated under sim-
ilar cliff lines from the shallow depth side. (a) Objective comparisons to be made between different long-
The likely technical reasons behind this observation are rela- wall mines-which to the knowledge of the author has never
tively obvious having described in detail both general face loading been done on an industry-wide scale similar to other strata
and overburden rotation mechanisms, as the presence of such a control aspects such as coal pillar stability and roadway
significant vertical discontinuity as a cliff line would inevitably ground control, and more relevantly to this paper.
both (a) increase vertical face loading beneath the cliff line (see (b) Providing input into the selection of shield load-rating based
Fig. 20) and (b) result in a natural rotation of the significant over- on an informed opinion on the likely propensity for major
burden ‘‘block’’ immediately behind the cliff line. roof instability at any given longwall mine or area of a long-
wall mine.
1.5.1. Impact of major geological discontinuities This then represents the authors’ opinion as to the current
The previous two sections of the paper have described in detail ‘‘state of the art’’ in terms of predicting longwall face conditions
some of the more general geometrical and geotechnical drivers for and instability risk according to defined characteristics of the geo-
known longwall roof instability mechanisms in close proximity to logical environment and mining geometries. It therefore becomes a
the longwall face. The final issue that needs to be briefly addressed key factor or indeed limitation when considering how the load rat-
before considering the load-rating design of longwall shields (i.e. ing of longwall shields is assessed and determined.
the main subject of the paper) is the potential influence of signifi-
cant localized geological discontinuities such as major faults. 2. General shield design comments
Fig. 21 shows the actual impact of a mid-angled fault plane hid-
ing outbye of a longwall face in terms of the exacerbation of roof Having provided a detailed description of both roof instability
instability ahead of the shields. Of particular note are (a) significant mechanisms on the longwall face and the various geometrical,
increase in tip to face distance due to the hade of the fault, (b) geotechnical and geological drivers involved, the reader will hope-
R.C. Frith / International Journal of Mining Science and Technology 25 (2015) 687–706 697
(a) Mining towards fault (b) Face fails on fault plane (c) Cavity develops (d) Large cavity remains (e) Rocsil is used
leaving rubble sitting on further while clearing once chain is cleared to fill the cavity
chain and large tip to chain more material falls
face/exposed roof as chain is cleared
Fig. 21. Schematic illustration of the substantial roof instability mechanism caused by a mid-angled fault hiding outbye the face.
35 (6) Leg hydraulics are not impaired by fluid leaks that would
Convergence rate (mm/h)
R
r Support E
loading
B D
C Support
D E lowering
W Support
h1
Shield load
W B C setting
F A
Gob Support
F advance Adjacent shield
A advance GRC
curve
Face P P Shearer cut
GRC curve
After wilson Condition
at setting Adjacent shield
advance GRC curve
Fig. 24. Detached block model of longwall roof behavior and shield rating design
[15]. Convergence
Fig. 27. Cyclic loading pattern on ground reaction curve for individual or a small
group of shields [13].
Theoretical
Effect of hydraulic
leakage can result in
(a) Ground and shield curves are preferably brought together at
set-to-yield lower set pressures and a common point so that presumably a state of ‘‘equilibrium’’
reduced support stiffness
800 t is achieved, this making logical sense when designing
ground support for civil tunnels which was the original
A Working
640 t range intent of the method.
Degradati
B on of roof (b) Effect of time, which as any longwall operator knows can be
Support setting line with time
Setting supports later critical to strata stability via the face being stood for an
C Roof failure
increases convergence
and results in poorer
extended period, is not included.
roof conditions (c) As more face convergence occurs, the necessary shield load
to reach equilibrium seemingly reduces, at least initially.
Convergence
Initial roof Set-to-yield (d) Neither paper provides any guidance or assistance to how
convergence leg closure
the necessary ground reaction curves are developed on a
Fig. 26. Strata-support interaction diagram for longwall support [12]. site-specific basis.
(e) Neither technical paper considers any direct link between
3.1. Matching the shield rating to the expected geotechnical conditions the analyses undertaken and the potential for major roof
and mining geometry falls to occur on the longwall face, either in general or
site-specific terms.
The most recent and commonly cited approaches to longwall
shield rating design relate to either: Frith and Stewart undertook shield monitoring, including shield
convergence monitoring, on various longwall faces at some 12 dif-
(1) Use of the ‘‘ground reaction curve’’ concept which was orig- ferent Australian longwall mines, this being thought to be the most
inally developed for use as part of the ‘‘New Austrian Tun- comprehensive longwall shield convergence study ever under-
nelling Method’’ in the early 1960s [12,13]. taken and reported [18]. They noted that in almost all cases long-
(2) Numerical modeling [14]. wall shields never came to equilibrium during the shear cycle or
even over 2 day longwall stoppages (as was common practice dur-
However before these two recent design methods are critiqued, ing weekends in the early 1990s) and that in instances of very high
the historical shield design methods of Wilson and Smart will be initial shield convergence rates after shield set, only minimal slow-
briefly commented upon [15,16]. ing down of the convergence rate over time. (see Fig. 28
The basic arrangements used by Wilson and Smart are provided re-produced from Frith and Stewart) [18].
in Figs. 24 and 25 respectively. Furthermore, Figs. 22 and 23 show measured examples of aver-
Without even considering details of the analysis conducted, age convergence rate on a shear by shear basis, this indicating the
both methods can be eliminated from current use, as neither caters degree of variation in face loading that can occur as a longwall
for the loss event that the shield should be designed to either pre- retreats in shear cycle increments. Whilst the lowest convergence
vent or reduce the potential for, namely the occurrence of major rate measured in these two examples is zero, typical low-end val-
roof cavities ahead of the shields. With the required outcome not ues are less than 5 mm/h with occasional high values in excess of
R.C. Frith / International Journal of Mining Science and Technology 25 (2015) 687–706 699
15 mm/h peaking at 35 mm/h (i.e. at least 7 times the typical (3) The tip to face distance to maximize roof integrity and limit
low-end values). This reality of measured shear by shear shield dilation should be less than approximately 0.6 m. The smal-
convergence rate on two different longwall faces during retreat ler the distance, the better the result is.
distances of less than 70 m is not effectively captured in the speci-
fic discussions or examples given regarding the use of the ground If these key requirements are met, then the ground about the
reaction curve concept for longwall shield rating design. face and above the supports should be controlled under most geo-
The ground reaction curve was originally developed for and logical circumstances.
applied to a ground stability problem whereby long-term stability In other words, it appears that an almost universally applicable
(i.e. equilibrium) was a necessary outcome, a primary focus being longwall shield design is being presented as one of 100–
in determining a suitable timing for the emplacement of a perma- 110 ton/m2 at yield, a set-yield ratio of 80%, a canopy ratio of
nent concrete tunnel lining which must not be fractured and <2.4 and preferably less than 2 and a tip to face distance of
cracked by excessive ground movements. In complete contrast, <0.6 m. The following comments are made in response to this
monitoring data indicates that longwall faces are more typically research finding:
in a state of non-equilibrium during the vast majority of
short-term shear cycles, such that achieving equilibrium between (1) Numerical model used is presumably only two-dimensional
the strata and the shields is neither necessary or indeed practical although this is never stated in the report, whereas the prob-
given the obvious disparity between the magnitude of possible lem is one of at least three dimensions.
strata loads acting on the shields (Wshield) and available shield load (2) In the opinion of the author, the term ‘‘weak’’ strata is too
ratings (P), which even in the extreme are limited to no more than generic and the research does not include consideration of
approximately 120 ton/m2 or 1.2 MPa of vertical pressure. varying extraction height, periodic weighting, cover depth,
The above disparities between measured shield convergence panel width, chain pillar stability, etc. as design variables
behavior with time, the non-inclusion of elapsed time in the anal- that are either known via other industry research publica-
ysis, the non-inclusion of a major roof fall within the assessment tions that are not considered or referenced in the project
process and the lack of any useable guidance about how a ground report or can be logically concluded as having some level
reaction curve may be developed for any given longwall panel or of influence over the face loading environment during long-
area of a given longwall panel, means that despite the apparent wall extraction, weak strata or otherwise.
link to what is undoubtedly a seminal concept in civil tunneling, (3) Whilst the comments on canopy balance are sensible as they
it is judged that the ground reaction curve concept offers little to can be engineered into the shield at the design stage, the
the problem of determining suitable shield ratings in varying long- suggestion that tip to face distance should be less than some
wall settings on a prudent investment risk basis. pre-determined amount for the shields to be effective is
problematical. Firstly significant face spall can occur (which
3.1.2. Numerical modeling approach is controlled by other factors not least of which is extraction
Others have utilized a numerical modeling approach in longwall height) to significantly increase the effective tip to face dis-
shield design (e.g. Gale who addresses shield design in ‘‘weak’’ tance and secondly, variations in the as-cut roof horizon and
ground or strata) and it is worth briefly reviewing the outcomes of also small scale gutters in the roof ahead of the shields will
this most recent industry funded research into the shield design change the location along the canopy where it first touches
topic [14]. the roof, again increasing the effective tip to face distance.
The research project’s aims are to: (a) better understand frac- Therefore defining an optimum tip to face distance, credible
ture mechanics and geotechnical requirements for face support or otherwise, has no practical value.
in ‘‘weak’’ strata, (b) investigate factors which optimize face sup- (4) The findings from Gale are simply a confirmation of what was
port and (c) review operational factors to optimize support perfor- almost certainly the state of the art in longwall shield ratings
mance within a weak strata section. before the advent of the Moranbah North Mine 2 leg, 1750
The stated findings of the research project are as follows: tons replacement shields in 2009, with two supporting state-
ments to improve their overall effectiveness, one being able to
(1) Yield capacity to control the caving line and provide confine- implemented in the design of the shields with the other out-
ment to the fractured material is recommended to be in the side the control of the shield designer [14,17].
100–110 ton/m2 range with a set of approximately (5) Research confirmed that the specified longwall shields will be
80 ton/m2. effective under ‘‘most geological circumstances’’. The author
(2) The canopy balance is recommended to be less than 2.4 has no major disagreement that this outcome is generally cor-
preferably less than 2. In most instances this relates to a rect. As stated in the first sentence of the paper ‘‘few in the coal
tip to leg distance in the range 3–3.5 m. industry would argue that most longwall faces were not ade-
quately stable for the majority of their operating time’’.
Gale effectively confirms the industry status quo as of the end of
A
2009 whereby longwall shields at that time were effective in the
Roof convergence (mm)
Time (h) (1) Whether the bigger is better approach has any future merit,
including the post-2009 advent of the 2 leg 1750 tons
Fig. 28. Various forms of time-dependent shield convergence behavior during an
individual shear [18]. shields at Moranbah North?
700 R.C. Frith / International Journal of Mining Science and Technology 25 (2015) 687–706
1000
(ton)
900
The design and procurement of the 1750 tons MNC shields was
800
demonstrably driven by both factors (1) and (2) above, hence the
700
drivers for ‘‘bigger is better’’ were alive and well as recently as just
600
500
prior to 2009. Furthermore, ACARP commissioned a concept study
1984 1988 1992 1996 2000 2004 2008 to examine the feasibility of producing 15MTPA from a single long-
Year wall face, one of the major findings being that further research was
required in specifying shield capacity, this concern emanating from
Fig. 29. Historical overview showing trend of increasing shield capacities from
1985 to 2006 [13]. the recognition that the higher the required face production, the
less tolerable are major strata control events and the associated
losses [19].
Two published anecdotes will be used to justify point (3),
(2) Application of the models presented earlier in regards to namely that geotechnical engineering has been following rather
geotechnical and mining layout drivers for longwall instabil- than leading the development of ever-higher shield ratings.
ity to provide guidance on which longwall environments are McDonald states that ‘‘ACIRL suggested that Westcliff should
most prone to face instability? Is bigger better? seek hydraulic supports with a capacity of 800 tons after conduct-
ing exhaustive tests on physical scale models of the strata above
3.2. Bigger is better? the Westcliff/Bulli Seam area [18]. Westcliff increased this to
900 tons and chose Gullick Dobson 4 leg chock shields from the
The bigger is better approach to shield design has been several manufacturers who were able to meet the specification.
on-going in industry since the advent of mechanized longwall min- During the presentation of Klenowksi, it was stated that as a
ing over 50 years ago. result of the numerical modeling study to assess the powered sup-
McDonald made the following statement in regards to the port requirements at Central Colliery, it was concluded that a rat-
development of shield load ratings in Australia following the intro- ing of around 650 tons would suffice [20]. However, the final
duction of longwall mining in 1963: ‘‘every Australian longwall has support rating of 800 tons was selected for Central by a partner
been subject to home-made modifications. These modifications in the project which was more comfortable using a higher rated
were undertaken because of improved roof conditions allowed support.
greater face cutting rates. Improved roof conditions were achieved With the recent procurement of 2 leg 1750 tons longwall
using heavier supports; the area of greatest concern for early long- shields at Moranbah North and the coal industry asking the ques-
wall miners’’ [18]. tion as to the various barriers to producing 15MTPA from a single
The same basic trend of ever-increasing shield ratings over time longwall, it is hard to conclude that the ‘‘bigger is better’’ approach
is also evident in the USA, and Fig. 29 is provided by Barczak and is necessarily at an end at the current time.
Tadolini [13]. However, 2015 is not 1986 and as stated previously; most long-
Finally, the procurement in 2009 by Moranbah North Mine in walls remain adequately stable for most of the time. Therefore,
Australia of the highest rated longwall shields ever manufactured accepting that there may still be a demand for ever-increasing
(2 leg 1750 tons shields) was driven solely by the need for improved shield load ratings in extreme mining circumstances or in conjunc-
roof control on the longwall face, the cost and operational disadvan- tion with abnormally high production expectations, perhaps what
tages of shields weighing more than 60 ton each being set-aside for is really needed is some form of rationale, even if only judgment
improved roof control and longwall production rates [17]. based, as to what shield rating may be appropriate for any given
Therefore, at face value it would seem that the mining industry set of circumstances. This will be considered in the final section
has been informally applying the ‘‘bigger is better’’ approach to long- of the paper after a number of other key shield design issues relat-
wall shield rating design for some time now, in fact since the first ing to strata control are briefly mentioned.
mechanized longwall supports were first used. This raises one sim-
ple question: why has this continued to be necessary, to as recently
as 2009, in spite of the claimed advances in geotechnical modeling 4. Other shield design aspects relating to strata control
and longwall shield rating design by the geotechnical profession?
There are three distinct answers to this question which provides 4.1. Shield width
full context and may pre-empt that the increasing of longwall
shield load ratings is perhaps not at an end, even only a few years Shield widths have increased during the past 20 years from 1.5
after the ‘‘quantum leap’’ associated with the 1750 tons Moranbah to 1.75 m, and currently 2 m wide shields are becoming more com-
North shields: mon. This evolution has been driven largely by operational effi-
ciency considerations, such as reducing the face production
(1) Industry is still seemingly driven by the statement of constraint due to shield lower-advance-reset (LAR) cycle times,
McDonald, the only change being that acceptable levels of reducing the number of shields and AFC pans to be moved during
face production in the past were much lower than they are face relocations (the move to wider longwall faces has simply exac-
now, hence the need for even fewer roof control problems erbated this requirement), and less components on the longwall
during longwall extraction and therefore higher rated face requiring maintenance or that can fail.
shields [18]. However, it is also true to say that as individual shields get
(2) Longwall faces are wider, higher, deeper and in more aggres- wider, higher load capacities can be achieved (without increasing
sive strata conditions than was commonly the case leg pressures markedly) as increased leg diameters that are
pre-1986. This has undoubtedly made faces less stable over- directly proportional to the increased shield width, act to increase
all and so driven the need for higher rated shields. the shield load rating by the leg diameter squared. The load rating
R.C. Frith / International Journal of Mining Science and Technology 25 (2015) 687–706 701
of the current 2 m wide Moranbah North longwall shields 4.3. Canopy ratio
(875 ton/m of face) could not have been achieved within a
1.75 m wide shield without significantly increased leg pressures. Canopy ratio is basically the ratio between the canopy length
ahead of the legs and the canopy length behind the legs (A/B in
4.2. Tip to face distance Fig. 32). The importance of the canopy ratio is to provide a bal-
anced canopy whereby its center of mass is reasonably close to
Tip to face distance is undoubtedly the simplest concept in rela- the location of the legs. This ensures that the Canopy tip does
tion to roof stability on the longwall face, and it is being directly not have a significant tendency to drop away from the roof during
analogous to roadway width. It represents the unsupported span shield lower, advance and re-setting (LAR), which will either tend
between the face and the tip of the shields where roof instability to reduce tip loading of the shield if it stays in contact with the roof
emanates from. Few longwall operators would disagree that main- or increase the tip to face distance if it does not, neither of these
taining the tip to face distance as low as possible, which has a pos- outcomes are beneficial in terms of roof control.
itive impact on roof stability on the longwall face. Whilst the author is not aware of any rigid design values for
The actual tip to face distance at any points within the mining canopy ratio that is backed by fundamental shield design research,
process will be governed by a number of independent factors: optimum values commonly used are between 2 and 2.5, with val-
ues closer to 2 being preferred. Obviously, a better canopy balance
(1) Minimum tip to face distance as determined by the face could be achieved by making the length of the canopy behind the
equipment and method of working (see ‘‘l’’ in Fig. 5) which legs (B) longer, although this simply adds weight and hence cost to
is commonly found to be in the order of 500 mm. the shields. It also tends to reduce the shield Support Load Density
(2) An increased tip to face distance due to face spall effects (see (SLD) (ton/m2), which whilst being a commonly used parameter is
‘‘x’’ in Fig. 5). not a particularly useful means of assessing shield design. This is
(3) An increased tip to face distance caused by the tip of the because maximizing SLD (by reducing the distance B behind the
shields not being set to the roof. This can have a number legs) will almost certainly lead to the canopy becoming less bal-
of different causes, such as the cutting of steps in the roof anced via an increased canopy ratio, which is counter-productive
(Fig. 30), small gutter type roof cavity development ahead in terms of roof control ahead of the canopy tip.
of the shields (Fig. 7) or whether two or four leg shields The other obvious outcome when considering canopy ratio is
are being used (Fig. 31). that lengthening the canopy to reduce tip to face distance for strata
control reasons is also potentially counter-productive, as it will
It is usual for the tip to face distance to be analyzed and opti- tend to increase the canopy ratio thus making the canopy less bal-
mized by reference to the position of the shields and face before anced and so pulling the tip away from the roof.
the cut is taken. The tip location in relation to the face relates to Certainly a combination of reducing tip to face distance by mak-
the shields being back from the AFC and the cut yet to be taken. A ing the canopy longer ahead of the legs (A) and also increasing the
theoretical tip to face of approximately 500 mm is consistent with shield SLD by reducing the canopy length behind the legs (B) is a
current well-designed longwall shields operating in the Australian recipe for disaster in terms of canopy ratio and shield effectiveness.
coal industry and cannot be reduced further, primarily due to It is noted that the author is aware of at least one set of relatively
shearer collision concerns. In other words, operational rather than recently procured shields in the Australian coal industry that have
geotechnical considerations are the limiting factors in this regard. seemingly been designed with exactly this concept in mind.
In reality, the geometrical tip to face distance is a minimum
value and will only fleetingly if ever be as low as 500 mm. The influ-
ence of face spall can be very significant at times (e.g. under peak 4.4. Planned operating height range in relation to the maximum
face loading conditions or in proximity to a major geological struc- operating height
ture) and the author has observed face spall of several meters in
conjunction with major instability on the face, rendering any argu- It is important that when a shield is working at the upper end of
ments about whether the geometrical tip to face distance should be its designated operating height range, and there is still an amount
450 or 500 mm for roof control reasons as essentially meaningless. of leg travel to allow the shield to be correctly set to the roof
Even though the method of face working can be changed to should either the cut inadvertently be taken too high or a small
reduce the tip to face figure under extreme face loading conditions roof cavity forms ahead of the shields. Having the ability to set
by an amount determined by the web depth (e.g. double chocking the shield to the roof for a distance above the designated planned
when working Uni Di IFS which can only be used when significant maximum working height is a prudent shield design consideration,
face spall is occurring anyway), tip to face distances of 1–2 m with as once the shield cannot be correctly set to the roof, the threat of
the shields behind the AFC waiting for the AFC to be advanced (so major roof instability occurring increases significantly.
that double-chocking can again take place) are an inevitable out- Again there are no industry accepted design guidelines in this
come during mining under high face loading conditions, particu- regard, the amount of extra operating height above the planned
larly in thick seam environments. maximum working height being a risk mitigation measure to be
The designed tip to face distance, as is shown on OEM face decided upon by the mine itself. However, as a general rule, the
cross-sections, is no more than a practical minimum value rather author is of the view that two criteria should be applied:
than what is likely to be the case during mining. Accepting that
the tip to face distance prior to the cut should be minimized, it (1) The higher the general likelihood of roof instability occur-
should not be done at the expense of front walkway utility, AFC ring on the longwall face for geotechnical reasons, the
width or canopy ratio (see next section) due to the potentially greater the additional operating height, over and above the
overriding influence of face spall. It is assessed to be of little overall planned maximum working height, should be; and
value to minimize the tip to face before the cut by compromising (2) The higher the maximum planned working height, the
the overall shield geometry, only to eventually realize that it makes greater the additional operating height should be. This
little or no difference to the maximum tip to face values that inevi- relates to the argument that the severity of major roof
tably occur during mining when the potential for roof instability is alls on the face increases in line with the face operating
logically also at a maximum. height.
702 R.C. Frith / International Journal of Mining Science and Technology 25 (2015) 687–706
Fig. 30. Illustration of the impact of ‘‘steps’’ in the roof on effective tip to face distance.
Fig. 31. Illustration of different setting characteristics of two and four leg shields on tip to face distance and load center.
(a) Goaf load slides off the top caving shield-leg (b) Goaf load direct loads top caving shield-
load applied to roof leg load applied to goaf
Fig. 33. Schematic illustrations of how the inclination of the top caving shield influences leg load distribution.
where W is the pillar width; and h the unit thickness with an immediately above the canopy, this directly acts to reduce the
unconfined compressive strength (UCS). effective tip to face distance whereby unsupported roof strata
Using this equation with a peak applied stress of say 8 MPa, a may have the ability to buckle and so form a gutter type cavity.
UCS can be determined that would represent the limiting equilib- Trueman made the suggestion that under certain face loading
rium condition for the first 1 m of floor beneath the shields in conditions, it may be preferable to set the shields to only 60%
terms of whether a bearing failure would occur or not. On the rather than say 90% of their yield loading. The following quote is
assumption that a pontoon is in the order of 700 mm wide (this taken from that paper: ‘‘Where periodic weighting is high enough
representing the minimum footing dimension expected for a to result in periodic shield overload, it may be better for set pres-
1.75 m shield), it is found that for the first 1 m of floor beneath sures to be nearer 60% of yield than 90% (with shields of support
the base, the limiting equilibrium UCS is 3.6 MPa. For values lower density of 100 ton/m2 or greater before the cut). This relates to
than this floor failure is likely, for values above this, floor failure the effect of time. If the support is set to 60% of yield then it will
becomes less likely. take much longer to the first yield event and for the same cycle
The above equation can be used to consider floor stability for time, there will be fewer yields. Fewer yields will result in less con-
different sections of strata beneath the shields, different maximum vergence and subsequent roof degradation and it will be easier to
floor pressures and different pontoon widths. However, the analy- mine through the periods of support overload. If a shield periodi-
sis present indicates that the typical UCS of the first 1 m of floor cally has an inadequate capacity for the conditions, the authors
needs to be below 4 MPa before the issue of floor failure compro- have seen no evidence that very high setting loads will stabilize
mising shield effectiveness becomes a significant possibility. the roof. The belief that very high set pressures are beneficial
It is noted that this analysis has not considered the extent by may have arisen when support capacities were less and set pres-
which the shields may tend to ‘‘plough’’ the floor material ahead sures close to the yield value were necessary for the set pressure
of the pontoons as they are advanced. This relates to such consid- to be adequate’’ [22].
erations as the effectiveness of base lifting rams to lift the toe of The underlying logic behind this statement seems to be that leg
the base clear of the floor and also whether the shields are being yield events allow increased rates of roof convergence, in which
advanced up-dip or down-dip, the specifics of which are outside case the statement potentially makes sense. However in all of the
the scope of this report and the expertise of the author. shield convergence monitoring studies across the coal industry
reported by Frith and Stewart, not once was the rate of shield clo-
4.7. Set: yield ratio sure seen to increase due to the legs going into yield [8]. The rate
may have remained constant after going into yield (which makes
The history of shield development over the past 50–60 years, all sense) but certainly it never accelerated. Therefore the idea that
points to the concept that as well as the yield load rating being ‘‘the reducing the set pressures (assuming it could be done on an
bigger the better’’, the set: yield ratio should be ‘‘the higher the as-needs basis), thus allowing greater shield convergence to simply
better’’. reduce the number of subsequent yield cycles, may not be
It has been argued that the external driver for guttering type well-founded and certainly goes against the entire history of the
failure of the immediate roof ahead of the shields is bending of development of longwall shields.
the immediate roof strata around the face (see Figs. 5 and 7). Fortunately, Trueman made the following statement: ‘‘opera-
Whilst the shield is rarely ever able to prevent such bending due tional controls can nevertheless be effective in minimizing roof
to the inevitable common disparity between Wshield and P, it can control issues in the presence of high level periodic weighting lead-
surely act to minimize it. Therefore it makes no sense to simply ing to support overload. Specific attention to achieving the highest
allow such bending of the roof to compress the shield and so set pressure practicable without compromising the attitude of the
develop load in the legs. It is far better to apply such load actively support canopy can reduce the extent of cavities and associated
back to the roof as early as possible and so limit the overall level of delays in many instances’’ [23].
shield closure and hence roof bending about the face, this then The author fully agrees with this later statement such that it
contributing positively to roof stability ahead of the shields. It appears that there is no obvious dissention to the universal con-
may also be the case that by setting the shields to the highest pos- cept of maximizing the set: yield ratio of shields in order to
sible or practical level and so reducing roof to floor closure, this increase their supporting effectiveness
acts to reduce face spall, which is again a positive aspect in terms
of roof stability ahead of the shields. 4.8. Flipper arrangement
The other justification for a high set: yield ratio is that the long-
wall shield can also be viewed as a reinforcing device for the The flipper at the tip of a shield serves two distinct purposes:
immediate roof of the longwall face and in the same way that roof
bolts and tendons reinforce the roof of a mine roadway, it acts to (1) It allows some measure of direct support to the upper coal
‘‘clamp together’’ what is typically a stratified strata sequence face which has both roof stability and also safety benefits,
immediately above the canopy. By reinforcing the roof strata and
704 R.C. Frith / International Journal of Mining Science and Technology 25 (2015) 687–706
(2) In the event that significant amounts of face spall occur, it The author has the view that the active horizontal force concept
can be used to offer confinement to the exposed roof ahead has a minimal impact on shield effectiveness as a result of the
of the tips. following:
Both are legitimate functions although as discussed by Payne, in (1) Active horizontal force applied to the roof strata is limited by
order to function as a roof support ahead of the tips, the flipper friction between the canopy and roof (which is why Frith
needs to be double-articulated [24]. Otherwise, the situation and Stewart undertook shear tests between steel and rock
shown in Fig. 34 will eventuate whereby the flipper can only act as mentioned earlier in the paper). A friction angle of 26°
to control the face and not the roof when the face has spalled. results in a coefficient of friction is only 0.5 [8].
The available load capacity of a flipper arrangement is generally (2) Accepting that the potential for roof instability on a longwall
small, however in terms of acting to control a buckling/guttering face increases as the face height increases, an increasing face
type failure mechanism in the tip to face area, roadway roof sup- height also results in the legs becoming more vertical. There-
port knowledge shows that relatively small vertical loads can pre- fore any active horizontal force that may be generated
vent buckling under much higher levels of horizontal stress [25]. decreases as a direct consequence. In other words, when it
Therefore despite a low load rating, a flipper that can be positively would be most required it is least able to be generated.
set to the roof offers potential roof control advantages. (3) Model shown in Fig. 5 has the immediate roof ahead of the
However, the limitations of a flipper are two-fold, namely: shields initially failing due to horizontal stress driven buck-
ling and guttering, the horizontal stress being generated due
(1) That like a shield, at some point it needs to be retracted from to bending of the roof strata. Therefore adding an additional
the roof during which time if it were preventing roof buck- active horizontal force into this area due to the design of the
ling, such failure could then occur resulting in a small roof shields cannot be beneficial to roof stability in the tip to face
cavity which immediately then acts to reduce shield sup- distance.
porting effectiveness.
(2) Its reach is limited ahead of the tip, therefore as the amount As shown in Fig. 31, an alternative logic as to why 2 leg shields
of face spall increases, its overall effectiveness in terms of demonstrably result in improved roof control than 4 leg shields
roof control decreases. (which was the context behind the development of the active hor-
izontal force concept) is that they are more amenable to set the
Overall, a double-articulated flipper is a useful addition to a canopy tip to the roof and keep the total leg load as close to the
longwall shield, particularly in high seams with friable roof. How- face as possible.
ever it only assists roof control and will not usually prevent large The primary concern with leg inclination is assessed to be to
scale roof collapses that are driven by excessive face loading and ensure that it does not result in a significant reduction in vertical
associated face spall. It is certainly not a substitute for a force being applied to the roof. On the basis that the vertical force
well-designed and proportioned longwall panel layout and highly applied is equivalent to the leg load multiplied by the cosine of the
rated and well-designed longwall shield. leg inclination angle (to the vertical), a leg inclination of 20° only
results in a 6% reduction in the vertical component as compared
4.9. Inclination of legs toward the face to the absolute leg loading. When it is remembered that the max-
imum leg inclination occurs with the shield at the lower end of its
The inclination of the shield legs has been a general shield operating range, such a reduction is judged to be insignificant in
design consideration since Peng first published the concept of an terms of the overall roof instability threat.
‘‘active horizontal force’’ assisting roof stability ahead of the shield As a general shield design concept, it is suggested that leg incli-
tips (see Fig. 35) [26]. nation should be maintained at no more than 20° to the vertical
throughout the defined operating height range.
Fahf
Fig. 34. Inability of single articulated flippers to secure the face or roof due to
previous face spall [24]. Fig. 35. Active horizontal force (Fahf) concept [26].
R.C. Frith / International Journal of Mining Science and Technology 25 (2015) 687–706 705
(10) Even the highest rated longwall shields can have their effec-
tiveness significantly reduced by overlooking a whole range
of other shield design factors or less than adequate opera-
tional practices.
basis for longwall shield load rating design using strata loading as a [2] Frith R, Creech M. Face width optimisation in both longwall and shortwall
caving environments. Final Report, ACARP Project C5015; 1997.
design input.
[3] Frith R, McKavanagh B. Optimisation of Longwall mining layouts under
Another key aspect is the recognition from numerous shield massive strata conditions and management of the associated safety and
monitoring studies that they rarely, if ever, reach static equilibrium ground control problems. End of Grant Report, ACARP Project C7019; 2000.
during mining, the point being that the design problem is one of [4] Colwell M, Frith R. A roof support design methodology for longwall installation
roadways. Final Project Report, ACARP Project C19008; 2012.
non-equilibrium and the associated increasing of roof fall propen- [5] Mark C. Pillar design methods for longwall mining. United States Bureau of
sity with time during each shear cycle. Again, this does not obvi- Mines Information Circular 9247; 1990.
ously lend itself to a simplistic analysis to determine the [6] Colwell M. Chain pillar design-calibration of ALPS. End of Grant Report, ACARP
Project C6036; 1998.
necessary load-rating of longwall shields. [7] Colwell M. Rib support design methodology for Australian collieries. Final
The fundamental barrier in terms of attempting to understand Report, ACARP Project C11027; 2004.
and numerically analyze the link between longwall shield rating [8] Frith RC, Stewart AM. Optimisation of powered support performance in
relation to strata loading and engineering criteria. End of Grant Report,
and roof fall propensity ahead of the shields, is that the problem NERDDC Project 1445; 1993.
contains too many indefinable variables. Furthermore, the rating [9] Frith R. Development and demonstration of a longwall monitoring system for
of the longwall shield does not directly control roof fall propensity, operational decision-making. End of Grant Report, ACARP Project C4017; 1996.
[10] CSIRO/SCT. Ground behaviour about longwall faces and its effect on mining.
as they are separated by several other controls, including overbur- End of Grant Report, ACARP Project C5017; 1999.
den weighting, the nature of the immediate roof strata, the amount [11] Luo X, Hatherly P. Pre-cursors and new understanding of high gas emissions at
of face spall and any number of operational variables which may Appin colliery through micro-seismic monitoring. End of Grant Report, ACARP
Project C6025; 1998.
not be consistent on a shear by shear basis. With this being the
[12] Medhurst TP. Practical considerations in longwall support behaviour and
case, the inevitable conclusion reached is that credible and mean- ground response. In: Proceedings of coal. australasian institute for mining and
ingful load-rating design for longwall shields still remains beyond metallurgy. Melbourne; 2005.
the reach of the geotechnical fraternity. [13] Barczak T, Tadolini S. Longwall shield and standing gateroad support designs-
is bigger better? NIOSH Publication; 2007.
The paper has concluded that the same basic operational drivers [14] Gale WG. Matching longwall support design to industry requirements in weak
for increasing shield ratings in the past are still as relevant today, ground. End of Grant Report, ACARP Project C14030; 2009.
albeit that the trend may plateau for a period following the quan- [15] Wilson A. Support load requirements on longwall faces. Min Eng
1975;134:479–91.
tum leap associated with the development of the 2 leg 1750 tons [16] Smart B. The evaluation of powered support performance from geological and
shields for Moranbah North Mine which have yet to be tested at mining practice information. In: Proceedings of 27th US rock mechanics
any other mine. With this being the case, the author contends that symposium. Alabama; 1986.
[17] Martin K, Kizil M, Canbulat I. Analysing the effectiveness of the 1750 tonne
the geotechnical focus for the foreseeable future should be in fur- shields at Moranbah North Mine. In: Proceedings of the coal operators
ther defining and proving the key geological and geometrical con- conference. Wollongong: University of Wollongong; 2012.
trols for longwall face stability and therefore longwall production [18] McDonald A. Longwall and shortwall. Australian Coal Mining Practice; 1986. p.
328–63.
risk as well as ensuring that the management and operation of [19] ACARP. High Capacity underground coal mining: scoping study-defining the
longwall faces makes the best possible use of currently available system needs for a 15 MTPA longwall operation. End of Grant Report, ACARP
longwall shields. Only when the highest rated shields that are Project C15008; 2007.
[20] Klenowski G, Ward B, McNabb K, Dyer G. Prediction of longwall support
available are demonstrably being used to their absolute best per-
loading at southern colliery Queensland. In: Proceedings of 11th international
formance limit, should industry consider whether a further signif- conference on ground control in mining. Wollongong; 1992. p. 155–9.
icant increase in shield load rating is required. Industry is far from [21] Seedsman R. The strength of the pillar–floor system. In: Proceedings of the coal
this point at the current time. operators conference. Wollongong: University of Wollongong; 2012. p. 24–31.
[22] Trueman R, Lyman G, Cocker A. Managing roof control problems on a longwall
The final comment made is one of an historical perspective and face. In: Proceedings of the coal operators conference. Wollongong: University
how it may guide our current day thinking as to the future. In 1986 of Wollongong; 2008. p. 10–21.
when McDonald provided their historical perspective on shield [23] Trueman R, Thomas R, Hoyer D. Understanding the causes of roof control
problems on a longwall face from shield monitoring data – a case study. In:
load rating development over time, it would have been inconceiv- Proceedings of the coal operators conference. Wollongong: University of
able to them that in 2015 a single longwall face would have the Wollongong; 2011. p. 40–7.
ability to produce in the order of 10 MTPA and 2 leg 1750 tons [24] Payne D. Crinum mine, 15 years, 40 million tonnes, 45 roof falls-what did we
learn? In: Proceedings of coal. University of Wollongong, Melbourne,
shields would be available for use [18]. This was less than 30 years Wollongong: Australasian Institute for Mining and Metallurgy; 2008. p. 22–43.
ago, therefore it would perhaps be unwise for any of us to close our [25] Colwell M, Frith R. AMCMRR – an analytical model for coal mine roof
minds as to what new technologies in the future may allow in reinforcement. In: Proceedings of the coal operators conference. Wollongong:
University of Wollongong; 2010. p. 73–83.
terms of longwall shield design, If our predecessors had done this [26] Peng SS. Design of active horizontal force for shield supports for controlling
in 1986, the mining industry today would be little different from roof falls. Min Eng 1990;149(345):457–61.
that time. [27] Hebblewhite B. Status and prospects of underground thick coal seam mining
methods. In: Proceedings of 19th international mining congress and fair of
As Orville Wright stated shortly after the first powered flight
turkey. IMCET; 2005. p. 169–78.
‘‘no flying machine will ever fly from New York to Paris. . .’’ And
then a guy called Lindbergh came along.
References
[1] Frith RC. Half a career trying to understand why the roof along the longwall
face falls in from time to time? In: Proceeding of 24th international conference
on ground control in mining. West Virginia; 2005.