Professional Documents
Culture Documents
Cadena de Suministro Trazabilidad 5
Cadena de Suministro Trazabilidad 5
Abstract
Successful, large scale field trials were conducted on two sites in Texas and
Toronto using an integrated system of RFID tags, GPS technology, map software,
and hand held computing to automatically track materials in the projects’ respective
lay down yards. This paper addressed the unresolved research question, that how will
this technology impact projects if it is implemented upstream in the supply chain in
an integrated and automated materials management system? This question is
addressed by modeling the impact of automated materials tracking technology on
increasing visibility within the construction supply chain. It is concluded that
automated materials tracking has the potential to improve construction productivity,
cost, and schedule performance.
Introduction
The Construction industry is characterized by the fact that every project is
different from others in terms of planning, design, and execution. Likewise, the
supply networks that fuel these projects with labour, equipment, and highly
engineered materials are complex entities onto themselves. Improving the materials
management process, particularly at the site level on large construction projects, has
been identified as one area that can have a beneficial impact on the construction
supply network and the construction process as a whole (Construction Industry
Institute 1999; Kini 1999). The integration of Automated Materials Locating and
41
management process have been proposed and shown to be a viable means of process
improvement. These technologies have thus far been shown to be well suited for
application in the construction industry, especially with regards to accurately
identifying, locating, and tracking material and equipment in a construction
environment (Song et al. 2006; Ergen et al. 2007; Razavi et al. 2008).
However, what is currently lacking from the body of knowledge, on the
application of AMLTT in construction, is an understanding of the impact that this
technology could have on a project if implemented on a larger scale. Specifically,
what impact(s) could AMLTT have if it were implemented within the construction
supply network? The objective of the research presented in this paper is to
investigate the theoretical impact that the application of AMLTT could have on the
construction materials management process if implemented within different segments
of the supply network. The specific area of the construction supply network that was
chosen for investigation was the use of AMLTT to increase the level of visibility
within the greater supply network. To examine the impact of AMLTT to increase the
level of visibility within the supply chain, the process piping supply chain was
modeled using EZStrobe, a commercially available modeling and simulation software
package.
Background/Literature Review
The success of Supply Chain Management (SCM) in the manufacturing sector has
lead to interest in its application in other industries, including the construction
industry. The application of SCM principles, such as Just-In-Time (JIT) delivery, has
seen some success in the construction industry. Tommelein (1998) was successful in
demonstrating the theoretical ability of pull-driven scheduling to improve the
performance of the pipe spool installation process by reducing on-site material
buffers, decreasing the project duration, and identifying a means in which to increase
crew productivity by altering their start date. Al-Sudairi et al (1999) simulated a steel
erection process and concluded that a moderate material buffer on site could balance
the impact of uncertainty in material delivery and productivity. Vrijhoef & Koskela
(2000) went on to examine the supply chains of three construction projects (two
residential projects and one office building). From their research it was determined
that there exist significant problems (from a Lean perspective) in a typical
construction supply chain, such as the inclusion of extra time in schedules to
counteract uncertainties and the overall nearsighted management of the supply chain
in general.
The difficulty in applying SCM to construction in all of the studies mentioned
above can be recognized to originate from the fundamental differences between
manufacturing and construction. The construction industry is dominated by ‘one-off’
projects; where ‘one-off’ refers to the lack of repetition in the construction of like
facilities (Vrijhoef & Koskela 2000). Construction schedules vary considerably
between projects, some schedules span years, while others span only a few months.
Other constraints imposed on construction projects, such as weather, site conditions,
site fabrication, availability of resources (e.g. skilled and unskilled labour), and local
laws and regulations can also be highly unpredictable and variable (Koskela 1992;
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 10/03/15. Copyright ASCE. For personal use only; all rights reserved.
Field Trials
Extensive field trials were conducted to investigate the possible impacts of
AMLTT on construction productivity. The field trials were conducted at power plant
construction projects in Rockdale, Texas and Toronto, Ontario, respectively. The
Rockdale field trial was conducted at the Sandow Steam Electric Station Unit 5
project. The second field trial was conducted at the Portlands Energy Center (PEC)
project, located in the port area of Toronto, Ontario.
RFID tags were attached to the construction materials. At the PEC, 224 pipe
spools, 22 safety valves, and 100 globe valves were initially tagged with RFID
transponders. In Rockdale, Texas, 400 structural steel components were tagged for
one boiler. On both sites, data was collected on a daily basis to update and generate
the positions of the tagged components. An individual carried a kit consisting of an
integrated GPS unit, RFID reader, and a handheld computer. As the individual moved
around the site, the GPS receiver determined its own position while the RFID reader
identified the presence of the tagged components around that position at a rate of
several thousand reads per second. The localization algorithms then processed the
collected data to provide a more accurate estimate of the location of each tagged
component. Details about these field trials and their results can be found in CII
(2008).
Formulated Simulation Models
Simulation models were formulated for investigating the increase in visibility
within the construction supply network due to the use of AMLTT. Models of the
process piping supply chain, a typical component of industrial construction projects,
were developed as the primary investigative tool for this research. Process piping,
specifically the fabrication and installation of pipe spools, was chosen as the basis of
the completed investigation due to the availability of literature which provided an
understanding of its supply chain network and due to the authors’ own field
experience with this construction activity (Howell & Ballard 1996; Tommelein 1998;
Razavi et al. 2008). Two simulation models were developed. The first simulation
model represents the existing process or situation as it typically exists in the
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 10/03/15. Copyright ASCE. For personal use only; all rights reserved.
model include the material receiving process, the completion of install area
preparation, pre-installation work, and final installation. There is little to no supply
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 10/03/15. Copyright ASCE. For personal use only; all rights reserved.
include the design of pipe spools, the overall fabrication of pipe spools, and the
delivery of pipe spools to the site. The installation based activities include the install
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 10/03/15. Copyright ASCE. For personal use only; all rights reserved.
Figure 2: Percent Complete vs. Time Figure 3: Percent Complete vs. Time
(Existing Model) Modified Model (Work Opportunities)
immediately following the delivery of the first load of pipe spools on day 20. This
activity reached 100% completion 190 days later on day 210. This corresponds to an
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 10/03/15. Copyright ASCE. For personal use only; all rights reserved.
overall rate of production of 2.1 pipe spools per day. Sufficient work opportunities
were also generated to allow the preparation of install areas to commence
immediately after the 50 day delay period to account for site work. This activity
reached 100% completion on day 139. This translates into a rate of production of 1.1
areas every 10 days. Finally, installation was able to begin on day 58 and was
subsequently completed on day 219. The resulting rate of production for this activity
was calculated to be 0.6 areas completed every 10 days.
can be compensated for by reducing the crew size by a half as indicated by the
corresponding resource allocation profile. While the overall activity duration is
Downloaded from ascelibrary.org by UNIVERSITE LAVAL on 10/03/15. Copyright ASCE. For personal use only; all rights reserved.
increased, most project managers should appreciate the greater flexibility that this
alternative provides and improved productivity.
Conclusions
Based on the completed comparison it is evident that the integration of AMLTT
into the construction supply chain has the potential to improve or at least maintain
construction schedule performance, while reducing the dependency on costly material
stockpiles. It is recognized that under the AMLTT based model the rate of
production of two thirds of the site based activities was reduced significantly and
crew idle time increased. However, as was shown, this can be compensated for by
reducing the applicable crew size. The ability to start work tasks earlier in the
construction schedule as a result of an increased state of knowledge of the supply
situation should also provide project managers with a greater flexibility to account for
other unexpected events that may hinder project performance. In addition, the overall
duration of the theoretical piping operation was reduced from 246 to 219 days in
favor of the AMLTT based model; a reduction in schedule duration of approximately
References
Al-Sudairi, A. A., Diekmann, J. E., Songer, A. D., & Brown, H. M. (1999).
Simulation of Construction Processes: Traditional Practices Versus Lean
Principles. IGLC-7 (pp. 39-50). Berkeley, CA: International Group for Lean
Construction.
Construction Industry Institute. (1999). Procurement and Materials Management: A
Guide to Effective Project Execution. University of Texas at Austin. Austin,
Texas: Construction Industry Institue.
Construction Industry Institute. (2008). RT-240 Leveraging Technology to Improve
Construction Productivity,Publication No. 240-11, University of Texas at Austin.
Austin, Texas: Construction Industry Institute.
Cox, A., Ireland, P., & Townsend, M. (2006). Managing in Construction Supply
Chains and Markets. London, United Kingdom: Thomas Telford Publishing.
Ergen, E., Akinci, B., & Sacks, R. (2007). Tracking and locating components in a
precast storage yard utilizing radio frequency identification technology and GPS.
Automation in Construction , 16 (3), 354-367.
Howell, G. A., & Ballard, H. G. (1996). RR 47-13 Managing Uncertainty in the
Piping Function. The University of Texas at Austin. Austin, Texas: Construction
Industry Institute.
Kini, D. (1999). Materials Management: The Key to Successful Project Management.
Journal of Managment in Engineering , 30-34.
Koskela, L. (1992). Application of the New Production Philosophy to Construction.
Stanford: Stanford University.
Plemmons, J. K., & Bell, L. C. (1995). Measuring Effectiveness of Materials
Management Process. Journal of Management in Engineering , 11, 26-32.
Razavi, S. N., Young, D. A., Nasir, H., Haas, C. T., Caldas, C., Goodrum, P., et al.
(2008). Field Trial of Automated Material Tracking in Construction. CSCE 2008
Annual Conference. Quebec City.
Song, J., Haas, C. T., & Caldas, C. (2006). Tracking the Location of Materials on
Construction Job Sites. Journal of Construction Engineering and Management ,
132 (9), 911-918.
Thomas, H. R., Riley, D. R., & Messner, J. I. (2005). Fundamental Principles of Site
Material Management. Journal of Construction Engineering and Management ,
131 (7), 808-815.
Tommelein, I. D. (1998). Pull-Driven Scheduling for Pipe Spool Installation:
Simulation of Lean Construction Technique. Journal of Construction Engineering
and Managment , 124 (4), 279-288.
Vrijhoef, R., & Koskela, L. (2000). The Four Roles of Supply Chain Management in
Construction. European Journal of Purchasing & Supply Management , 6, 169-
178.