Professional Documents
Culture Documents
CE 509 CE Projects 2
2nd Semester, SY 2018-2019
Aguillon, Edralyn V.
Student/Team
Barreda, Maria Claudette M.
Group
Magboo, James Matthew F.
DESIGN OF STORM WATER DRAINAGE AT BARANGAY
Project Title
BAMBANG, PASIG CITY
Program Concentration Area Water, Structural
Constraints 1
Economic constraint of the project deals with the fact that in
construction, it is required to create a project that will sufficiently meet
the required strength and durability while minimizing the costs. This
constraint also takes into consideration the relationship of the design
Economic
life of the project with the cost, having greater design life will result to
higher cost of the project. For this, the designers will assess the total
costs (that which includes the initial costs and maintenance costs) of
alternatives to come up with the best design
Sustainability constraint takes into account the problem on how long
the design life of a project is with respect to its design strength. One of
the basic ideas in engineering design is that with greater design
Sustainability strength, there is an equivalent increase in cost due to the need of higher
quality material. However, choosing the cheapest materials and leaving
the structure without timely maintenance treatment can have expensive
maintenance requirements.
Time is a very significant factor that should be considered in any
construction project. The longer the time to finish the project could
mean a larger cost. The project schedule should be followed correctly
Constructability so the actual money being spent will not exceed the allocated money
for the entire project. The designers will estimate the man-hour and
time needed for the equipment to be rented for each trade-off for a
better judgment of the trade-off that will govern in the project.
The size and the materials to be used for the drainage system plays a
big part especially in serving the drainage’s primary function which is
to collect surface water and/or ground water and direct it away, thereby
keeping the ballast bed drained. The storm water drainage must also
protect the substructure from erosion, from becoming sodden, and from
losing its load-bearing capacity and stability. The amount of water and
Serviceability the amount of force it can hold are one of the most critical factors to be
considered. The amount of rainfall is not consistent and it always
changes that is why the stability and the capacity to hold large amount
of discharge must be considered. The storm water drainage to be built
expects to hold a huge amount of water as well as great discharge to be
produced especially during rainy seasons. The material to be used
should determine the most efficient and stable to hold such great
discharge which will be determined using the trade-offs considered by
the designers.
Risk assessment is the process of evaluating risks to worker’s safety
and health from workplace hazards. It is a systematic examination of
all aspects of work that considers: hazards identification, risk analysis,
and risk control. In designing flood control structures, the designers
should be aware of, and assess the risks from, the following principal
hazards, all the sources of flooding are need to be consider in order to
mitigate the impact of flooding in the area. Flood risk is the
Risk Assessment combination of flood damage potential and the probability of its
occurrence. Flood control measures have its design capacity, but if
poorly designed or constructed or when it exceeds its capacity the flood
control measures could fail and the damage can have devastating
consequences. The process of flood risk assessment is to evaluate the
actual usage of the designed drainage system and how much more can
it hold on if a certain storm exceeded the designed rainfall data used in
the designed stormwater drainage
Tradeoff 1
Reinforced concrete pipes have been available since the eighties of the 19th
Century. The relatively thin wall thickness and resulting weight reduction
brought about by this was the reason that, already at the start of the 20th
Century, reinforced concrete pipes with circular cross sections were
produced in the factory in sizes up to DN 2500.
Reinforced Concrete Pipe Reinforced concrete pipes for gravity system sewers can be dimensioned for
any load cases; they are especially suited for high loads and for dynamic
stresses caused by heavy traffic with small cover depth. Pipes with smaller
nominal sizes were often reinforced in only one direction, larger ones
received spiral reinforcement, very large ones, double and triple layers
depending on the loading
HDPE is a hydrocarbon polymer prepared from ethylene/petroleum by a
catalytic process. It is a kind of thermoplastic which is famous for its tensile
strength. Its unique properties can stand high temperatures. HDPE is a boon
to developing countries like India where it is used to prevent groundwater
High-Density Polyethylene
pollution. It can be easily molded and welded together. Due to its high
Pipe (HDPE)
chemical resistance property, it is used in piping systems. HDPE pipes are
used to both carry potable water and hazardous waste. It has other
applications also like in making backpacking frames, bottle caps, food
storage containers, vehicles fuel tanks, folding chairs.
Ductile iron pipe, made from ductile cast iron, is a graphite-rich cast iron in
which the graphite has a spheroidal shaped molecular structure. This
Ductile Iron Pipe molecular structure makes the cast iron less brittle and more resistant to
impact than the other varieties, which have a flaky structure. The ductile iron
pipe is used in trenchless technology for water and sewer lines.
Constraint 2
Economic Economic constraint of the project deals with the fact that in construction, it
is required to create a project that will sufficiently meet the required strength
and durability while minimizing the costs. This constraint also takes into
consideration the relationship of the design life of the project with the cost,
having greater design life will result to higher cost of the project. For this,
the designers will assess the total costs (that which includes the initial costs
and maintenance costs) of alternatives to come up with the best design
Time is a very significant factor that should be considered in any construction
project. The longer the time to finish the project could mean a larger cost.
The project schedule should be followed correctly so the actual money being
Constructability spent will not exceed the allocated money for the entire project. The
designers will estimate the man-hour and time needed for the equipment to
be rented for each trade-off for a better judgment of the trade-off that will
govern in the project.
The size and the materials to be used for the drainage system plays a big
part especially in serving the drainage’s primary function which is to collect
surface water and/or ground water and direct it away, thereby keeping the
ballast bed drained. The storm water drainage must also protect the
substructure from erosion, from becoming sodden, and from losing its load-
bearing capacity and stability. The amount of water and the amount of force
it can hold are one of the most critical factors to be considered. The amount
Serviceability of rainfall is not consistent and it always changes that is why the stability
and the capacity to hold large amount of discharge must be considered. The
storm water drainage to be built expects to hold a huge amount of water as
well as great discharge to be produced especially during rainy seasons. The
material to be used should determine the most efficient and stable to hold
such great discharge which will be determined using the trade-offs
considered by the designers.
Sustainability constraint takes into account the problem on how long the
design life of a project is with respect to its design strength. One of the
basic ideas in engineering design is that with greater design strength, there
Sustainability is an equivalent increase in cost due to the need of higher quality material.
However, choosing the cheapest materials and leaving the structure without
timely maintenance treatment can have expensive maintenance
requirements.
Risk assessment is the process of evaluating risks to worker’s safety and
health from workplace hazards. It is a systematic examination of all aspects
of work that considers: hazards identification, risk analysis, and risk control
Risk Assessment resistant to pressure and surges of water. Due to this said pressure the
material can decay and later become weak and have a tendency to broke
down. The designers estimated the strength of the material in terms of
material properties of each trade-off.
Tradeoff 2
Detention tank are used to reduce the peak outflow from a certain location.
Urban development results in increase impervious areas which causes faster
catchment responses and higher peak flow rates. It is often employed to
Detention Tank return peak flow rates and volumes to the pre-developed condition to prevent
the development resulting in adverse flood impacts downstream. It performs
this through intercepting storm water flows and releasing storm water
volumes in a controlled manner over a period of time.
According to Jana Napoli Floodwall is a primarily vertical artificial barrier
designed to temporarily contain the waters of a river or other waterway
which may rise to unusual levels during seasonal or extreme weather
Flood Wall events. Flood walls are mainly used on locations where space is scarce,
such as cities or where building levees or dikes would interfere with other
interests, such as existing buildings, historical architecture or commercial
use of embankments.
It is the removal of sediments and debris from the bottom of lakes, rivers,
harbors, and other water bodies. Dredging is often focused on maintaining
or increasing the depth of navigation channels, anchorages, or berthing
Dredging areas to ensure the safe passage of boats and ships. Vessels require a certain
amount of water in order to float and not touch bottom. It is also performed
to reduce the exposure of fish, wildlife, and people to contaminants and to
prevent the spread of contaminants to other areas of the water body.
Standards
National Plumbing Code of The basic goal of the National Plumbing Code of the Philippines is to ensure
the Philippines the qualified observance of the latest provision of the plumbing and
environmental laws.
National Building Code of The National Building Code of the Philippines (PD 1096).
the Philippines (Presidential
Decree No. 1096) The National Building Code of the Philippines, also known as Presidential
Decree No. 1096 was formulated and adopted as a uniform building code to
embody up-to-date and modern technical knowledge on building design,
construction, use, occupancy and maintenance. The Code provides for all
buildings and structures, a framework of minimum standards and
requirements to regulate and control location, site, design, and quality of
materials, construction, use, occupancy, and maintenance This code also
provides guidelines for the design of wastewater disposal system and storm
drainage system. It consist wastewater and drainage provisions.
DPWH -Technical Standards This volume of the Technical Guidelines was formulated in order to establish
and Guidelines for Planning uniformity in planning and designing of flood control projects. It aims to
and Design -Flood Control provide the engineers of DPWH involved in flood control planning and
Volume I design, the essential tools to formulate effective and efficient
countermeasures against floods.
Indian Standard 3370 This provide some of the equations needed to do find the allowable stresses
and design requirements for concrete storage structure.
CONCRETE STRUC'TURES FOR STORAGE OF LIQUIDS - CODE OF
PRACTICE
Modern Tools/Techniques
(For SO e)
StormCAD STAAD Pro is one of the most widely used stormwater drainage analysis and
design software worldwide. Basically StormCAD helps civil and sanitary
engineers automate tasks by removing the tedious and long procedures of the
manual methods. StormCAD can also be used to analyze catchment,
conduits, manholes, rainfall data and apply design constraints based on the
codes and provisions from the design standards. The designers used the
software to create an analytical model to analyze and measure the initial
deflection of each trade-offs.
RUBRIC FOR STUDENT DESIGN PROJECT REPORT
Intended Learning Outcome: Ability to write a design project report that illustrates effective writing in English.
Evaluated by:
Student Outcome (b): Identify, formulate and solve complex engineering problems.
Program: BS in Civil Engineering Course: CE 509 – CE Design Projects 2 Section: CE52FA1 2ND Semester School Year: 2018-2019
Evaluated by:
Program: BS in Civil Engineering Course: CE 509 – CE Design Projects 2 Section: CE52FA1 2ND Semester School Year: 2018-2019
Evaluated by:
Program: BS in Civil Engineering Course: CE 509 – CE Design Projects 2 Section: CE52FA1 2ND Semester School Year: 2018-2019
Evaluated by:
Student Outcome (h): Apply principles of ethics and commit to professional ethics and responsibilities.
Program: BS in Civil Engineering Course: CE 509 – CE Design Projects 2 Section: CE52FA1 2ND Semester School Year: 2018-2019
Evaluated by:
Student Outcome (i): Function effectively as an individual and as a member or leader in diverse teams and in multidisciplinary setting.
Program: BS in Civil Engineering Course: CE 509 – CE Design Projects 2 Section: CE52FA1 2ND Semester School Year: 2018-2019
Evaluated by:
Student Outcome (j): Communicate effectively on complex engineering activities with various communities including engineering experts and society at large using
appropriate levels of discourse.
Program:BS in Civil Engineering Course: CE 509 – CE Design Projects 2 Section: CE52FA1 2ND Semester School Year: 2018-2019
Performance Unsatisfactory Developing Satisfactory Very Satisfactory Exemplary
Indicators 1 2 3 4 5
Score
10. Express ideas Does not communicate his Communicates Communicates important Clearly communicates the Clearly and effectively
clearly ideas clearly information as isolated information but not a clear main idea or theme and communicates the main
ideas in a random fashion theme or over all structure provides suitable support idea or theme and
and detail provides support that
contains rich, vivid, and
powerful detail
11. Effectively Does not demonstrate the Presents information in a Presents information in a Presents information in a Presents information in a
communicate with ability to adjust tone or style and tone style and tone inappropriate style and tone consistent style and tone that
diverse audiences style for different inappropriate for both for the audience’s level of with the audience’s level effectively capitalized on
audiences audience’s level of interest interest or the audience’s of interest and level of the audience’s level of
and level of knowledge level of knowledge knowledge or interest and level of
understanding knowledge or
understanding
12. Effectively Uses only one method of Uses one method and Attempts to use two Uses of two different Uses multiple methods of
communicate in a communication when correctly applies the methods of communication, methods of communication, applying
variety of ways more than one method is conventions and rules of but does not apply the communication, applying the conventions and rules
clearly needed or that method conventions and rules of the conventions and rules of those methods in highly
requested and does not those methods of those methods in creative and imaginative
correctly apply the customary ways ways
conventions and rules of
that method
Total Score
Mean Score = (Total Score / 3)
Percentage Rating = (Total Score / 15) x 100%
Evaluated by:
Program: BS in Civil Engineering Course: CE – 509 CE Design Projects 2 Section: CE52FA1 2nd Semester School Year: 2018 - 2019
Scale
SOs Addressed by the
Performance Indicators Unsatisfactory Satisfactory Exemplary Score
Course
1 2 3
Identify, formulate, and solve Identify an engineering The engineering problem The engineering problem The engineering problem
complex engineering problems problem and/or satisfy a and/or need is unidentified and/or need is identified and/or need is clearly and
(student outcome b) need specifically identified
Formulate engineering The engineering solution to a The engineering solution to The engineering solution to
solutions to a given problem given problem and/or need is a given problem and/or a given problem and/or
and/or need not formulated need is partly formulated need is correctly and
completely formulated
Solve the engineering The engineering problem The engineering problem The engineering problem
problem and/or satisfy the and/or need is unsolved and/or need is solved by and/or need is innovatively
need adopting existing solved by adopting new
technologies, systems, technologies, systems,
components, or processes components, or processes
and methods and methods
Solve complex engineering Apply appropriate constraints Less than three constraints Three constraints are More than three
problems by designing in the design process are applied in the design applied in the design appropriate constraints are
systems, components, or process process applied in the design
processes to meet process
specifications within realistic Apply appropriate standards Appropriate standards and Appropriate local Appropriate local and
constraints such as economic, and codes in the design codes are not applied in the standards and codes are international standards and
environmental, cultural, social, process design process applied in the design codes are applied in the
societal, political, ethical, process design process
health and safety, Use trade-offs to determine Less than three options were Three options were used in More than three options
manufacturability, and final design choice used in the trade-offs to the trade-offs to determine were used in the trade-offs
sustainability in accordance determine the final design the final design choice to determine the final
with standards choice design choice
(student outcome c)
Scale
SOs Addressed by the
Performance Indicators Unsatisfactory Satisfactory Exemplary Score
Course
1 2 3
Use the techniques, skills, and Identify appropriate Techniques, skills, and Techniques, skills, and Techniques, skills, and
modern engineering tools techniques, skills, and modern engineering tools modern engineering tools modern engineering tools
necessary for engineering modern engineering tools are not clearly identified in are well identified in the are appropriately identified
practice in complex necessary in the design the design process design process in the design process
engineering activities process
(student outcome e) Use appropriate techniques, Techniques, skills, and Techniques, skills, and Appropriate techniques,
skills, and modern modern engineering tools modern engineering tools skills, and modern
engineering tools in the are not appropriately used in are appropriately used in engineering tools are
design process the design process the design process accurately used in the
design process
Apply principles of ethics and Demonstrate ethics by Design project submitted or Design project submitted Design project submitted or
commit to professional ethics submitting or presenting a presented does not cite or presented partly cited presented completely cited
and responsibilities design project that cites references references based on references based on
(student outcome h) references Turnitin results Turnitin results
Demonstrate professionalism Design project is not Design project is submitted Design project is submitted
by submitting or presenting submitted or presented on or presented on schedule or presented ahead of
the design projects on schedule as planned as planned schedule as planned
schedule as planned
Communicate effectively on Deliver effective oral
complex engineering activities presentations Use the mean score from the rubric for oral presentation of design projects
with various communities
including engineering experts Write a design project report
and society at large using that illustrates effective
appropriate levels of discourse Use the mean score from the rubric for design project report
writing in English
(student outcome j)
Total Score
Total Score
Percentage Rating= ( ) x 100
12
Evaluated by:
CE 509
CE Design Projects 2
PREPARED BY:
AGUILLON, EDRALYN V.
CE52FA1
SUBMITTED TO:
Adviser
ii
Approval Sheet
The design project entitled “Design of Storm-Water Drainage in Barangay Bambang, Pasig City”
prepared by Edralyn V. Aguillon, Maria Claudette M. Barreda, Leonard SJ. Marcelino, and Vernon Royce O.
Mendoza, James Matthew Magboo of the Civil Engineering Department was examined and evaluated by the
members of the Students Design Evaluation Panel, and is hereby recommended for approval.
iii
ABSTRACT
Storm-water is collected by drains and catch basins which then convey it underground through sewers. Its
discharge to a natural water system such as a creek, river or lake. If not be discharged properly, problems
The project design includes the lay-out of both water engineering and structural engineering context of the
storm-water drainage. The results of the design were based on the constraints provided by the client and
stated by the designers. Economic, Constructability, Sustainability and Serviceability are the derived
constraints for this project. These are the limiting factor that the designers considered and this serves as the
basis in deciding what possible alternative that may use in the project. The three trade-offs that the designers
chose for the storm-water drainage are pipe materials. The constraints are ranked based on the client and
designers’ perspective of what is the most important factor that needs to consider in the design. This was
evaluated based on the equations formulated by (Otto & Antonsson, 1991). In the initial design and raw
ranking of the trade-offs, Reinforced Concrete Pipe governed among the three trade-offs provided.
The resulting values are provided by a software which is the StormCAD it provided the designers the value
of the discharge needed to get the adequacy of the pipe. Then, the designers estimated and ranked the
trade-offs for the validation of the winning trade-off. As assessed by the designers, Reinforced Concrete Pipe
governed as the trade-off which satisfied the constraints of the design project.
iv
Table of Contents
i
2.7.4 Distribution Factor, DF ................................................................................................................ 26
2.7.5 Computation for Flood Wall ........................................................................................................ 26
2.7.6 Computation for Dredging ........................................................................................................... 30
2.8 Related Literature and Studies .......................................................................................................... 32
CHAPTER 3: CONSTRAINTS, TRADE-OFFS, AND STANDARDS............................................................ 35
3.1 Design Constraints ............................................................................................................................ 36
3.1.1 Quantitative Constraints ............................................................................................................. 36
3.1.2 Qualitative Constraints ................................................................................................................ 37
3.2. Trade-offs for Water Context ............................................................................................................ 37
3.2.1. Material Trade-offs..................................................................................................................... 38
3.3. Designer’s Raw Ranking .................................................................................................................. 41
3.3.1 Initial Estimated Values for Economic (Cost of the Project) ........................................................ 41
3.3.2 Initial Estimated Values for Sustainability (Maintenance Cost) ................................................... 43
3.3.3 Initial Estimated Values for Constructability (Labor and Equipment) .......................................... 44
3.3.4 Initial Estimated Values for Serviceability (Efficiency) ................................................................. 46
3.3.4 Initial Estimated Values for Risk Assessment ............................................................................. 47
3.4. Trade-off Assessment....................................................................................................................... 49
3.4.1. Economic Assessment............................................................................................................... 49
3.4.2. Sustainability Assessment ......................................................................................................... 49
3.4.3. Constructability Assessment ...................................................................................................... 49
3.4.4. Serviceability Assessment ......................................................................................................... 49
3.4.5. Risk Assessment ....................................................................................................................... 50
3.5. Trade-offs for Structural Context....................................................................................................... 50
3.5.1. Process Trade-offs .................................................................................................................... 50
3.5.2 Flood Control System Tradeoffs ................................................................................................. 53
3.6 Designer’s Raw Ranking ................................................................................................................... 54
3.6.4 Initial Estimated Values for Serviceability ................................................................................... 58
3.6.5 Initial Estimated Values for Risk Assessment ............................................................................. 59
3.6.2. Initial Estimated Values ............................................................................................................. 60
3.7 Trade-offs Assessment: ..................................................................................................................... 61
3.7.4 Serviceability Assessment .......................................................................................................... 61
ii
3.7.5 Risk Assessment ........................................................................................................................ 62
3.8 Design Standards .............................................................................................................................. 62
3.8.1 National Plumbing Code of the Philippines ................................................................................. 62
3.8.2 National Building Code of the Philippines (Presidential Decree No. 1096) ................................. 62
3.8.3 Indian Standard 3370 ................................................................................................................. 62
3.8.4 DPWH -Technical Standards and Guidelines for Planning and Design -Flood Control Volume I 62
CHAPTER 4: DESIGN OF STRUCTURE ................................................................................................... 62
4.1 Water Context ........................................................................................................................................ 62
4.1.1 Methodology ................................................................................................................................... 62
4.1.2 Design Process............................................................................................................................... 63
4.1.3. Design Process for Drainage System ............................................................................................ 64
4.1.4 Reinforced Concrete Pipe ............................................................................................................... 65
4.1.5 HDPE.............................................................................................................................................. 70
4.1.6 Ductile Iron Pipe ............................................................................................................................. 75
4.1.7 Designer’s Final Raw Ranking ........................................................................................................ 80
4.1.7.1 Computation of Final Rankings ................................................................................................ 81
4.1.8 Trade-off Assessment..................................................................................................................... 85
4.1.8.1 Economic Assessment............................................................................................................. 85
4.1.8.2 Sustainability Assessment ....................................................................................................... 85
4.1.8.3 Constructability Assessment .................................................................................................... 85
4.1.8.4 Serviceability Assessment ....................................................................................................... 85
4.1.9 Influence of Multiple Constraints, Trade-offs, and Standards ......................................................... 85
4.1.9.1 Economic Alternatives ............................................................................................................. 86
4.1.9.2 Sustainability Alternatives ........................................................................................................ 87
4.1.9.3 Constructability Alternatives..................................................................................................... 88
4.1.9.4 Serviceability Alternatives ........................................................................................................ 89
4.1.10 Sensitivity Analysis for Constraints ............................................................................................... 89
4.1.10.1 Sensitivity Analysis for Economic and Sustainability Constraint ............................................ 90
4.1.10.2 Sensitivity Analysis for Economic and Constructability Constraint ......................................... 93
4.1.10.3 Sensitivity Analysis for Economic and Serviceability Constraint ............................................ 96
4.1.11. Summary of Comparison of Trade-Offs ....................................................................................... 98
iii
4.2 Structural Context .................................................................................................................................. 99
4.2.1 Design Methodology ....................................................................................................................... 99
4.2.2 Design Process............................................................................................................................... 99
4.2.3. Design Process for Underground Detention Tank ....................................................................... 101
4.2.4 Design Process for Flood Wall...................................................................................................... 101
4.2.5 Design Process for Dredging ........................................................................................................ 103
4.2.4 Designers Raw Ranking ............................................................................................................... 103
4.2.4.1 Computation of Final Rankings .............................................................................................. 104
4.2.5 Trade-offs Assessment: ................................................................................................................ 108
4.2.5.4 Serviceability Assessment ..................................................................................................... 109
4.2.6 Influence of Multiple Constraints, Trade-offs, and Standards ....................................................... 109
4.2.6.1 Economic Alternatives ........................................................................................................... 109
4.2.6.3 Serviceability Alternatives ...................................................................................................... 110
4.2.6.4 Sustainability Alternatives ...................................................................................................... 110
4.2.7 Sensitivity Analysis for Constraints ............................................................................................... 111
4.2.7.1 Sensitivity Analysis for Economic and Constructability Constraint ......................................... 111
4.2.7.2 Sensitivity Analysis for Economic and Sustainability Constraint ............................................ 113
4.2.7.3 Sensitivity Analysis for Economic and Serviceability Constraint ............................................ 115
CHAPTER 5: FINAL DESIGN .................................................................................................................... 118
5.1. Final Design Scheduling of Reinforced Concrete ........................................................................... 118
5.2. Final Design Scheduling of Detention Tank .................................................................................... 121
APPEDIX A- Summary of Design Computation for Stormwater Drainage ................................................. 128
APPENDIX B-Summary of Design Computation Using HDPE .................................................................. 131
APPENDIX C-Summary of Design Computation Using DIP ...................................................................... 135
APPENDIX D-Street Elevation .................................................................................................................. 140
APPENDIX E- Computation for Backfill and Excavated Area of RCP ........................................................ 144
APPENDIX F- Computation for Backfill and Excavated Area of HDPE ..................................................... 149
APPENDIX G- Computation for Backfill and Excavated Area of DIP ......................................................... 154
APPENDIX H: DETENTION TANK ............................................................................................................ 159
APPENDIX I: DETENTION TANK (STRUCTURAL) .................................................................................. 162
APPENDIX J: FLOOD WALL (STRUCTURAL) ......................................................................................... 163
iv
APPENDIX K: DREDGING (STRUCTURAL)............................................................................................. 170
Appendix L (Final Estimates for Stormwater Drainage) ............................................................................. 172
Appendix M (Final Estimates for Stormwater Drainage) ............................................................................ 172
Appendix N (Final Estimates for Stormwater Drainage) ............................................................................ 173
Appendix O (Initial Estimates for Floodwall) .............................................................................................. 174
Appendix P (Initial Estimates for Dredging) ............................................................................................... 175
Appendix Q (Initial Estimates for Detention Tank) ..................................................................................... 176
Appendix R (Final Estimates for Floodwall) ............................................................................................... 177
Appendix S (Final Estimates for Dredging) ................................................................................................ 178
Appendix T (Final Estimates for Detention Tank) ...................................................................................... 179
MINUTES OF THE MEETING ................................................................................................................... 181
MINUTES OF THE MEETING ................................................................................................................... 182
MINUTES OF THE MEETING ................................................................................................................... 183
MINUTES OF THE MEETING ................................................................................................................... 184
MINUTES OF THE MEETING ................................................................................................................... 185
MINUTES OF THE MEETING ................................................................................................................... 186
CURRICULUM VITAE ............................................................................................................................... 187
EDRALYN AGUILLON............................................................................................................................... 188
v
List of Figures:
Figure 1.1 Project Location ............................................................................................................ 1
Figure 2-1 Topographic Map of Barangay Bambang, Pasig City ................................................... 4
Figure 2-2 5 Year Flood Hazard Map of Bambang, Pasig City ...................................................... 5
Table 2-1 Precipitation Data of Pasig City ..................................................................................... 5
Figure 2-3 Average Annual Precipitation Data of Pasig City .......................................................... 6
Figure 2-4 Elevation of Luna Street .............................................................................................. 6
Figure 2-5 Elevation of CM- Cruz Street ........................................................................................ 7
Figure 2-6 Elevation of V. Porzon Street ....................................................................................... 7
Figure 2-7 Elevation of F. Manalo Street ....................................................................................... 8
Figure 2-8 Elevation of G Valderama Street .................................................................................. 8
Figure 2-9 Elevation of M. Santos Street ....................................................................................... 9
Figure 2-10 Elevation of Villarosa Street ....................................................................................... 9
Figure 2-11 Elevation of Jose Pueblo Street................................................................................ 10
Figure 2-12 Pasig River near Barangay Bambang ...................................................................... 11
Figure 2-13 Drainage map of the Pasig-Marikina River system ................................................... 12
Figure 2-22 Forces Acting on the Floodwall ................................................................................ 29
Table 2-5 Soil Factors for Floodwall Design ................................................................................ 30
Figure 2-23 Calculated Maximum and Minimum Diameter of Storm Sewer Pipes ....................... 34
Figure 3-1 Reinforced Concrete Pipe .......................................................................................... 38
Figure 3-2 High-Density Polyethylene Pipe (HDPE) .................................................................... 39
Figure 3-3 Ductile Iron Pipe ...................................................................................................... 40
Figure 3-4 Ranking Scale for Percentage Difference ................................................................... 41
Table 3-1 Initial Estimated Values for Economic (Cost of the Project) ......................................... 42
Figure 3-5 Ranking Scale for Percentage Difference of RC Pipe and HDPE Pipe ...................... 42
Figure 3-6 Ranking Scale for Percentage Difference of RC Pipe and DI Pipe ............................. 43
Table 3-2 Initial Estimated Values for Sustainability (Maintenance Cost) .................................... 43
Figure 3-7 Ranking Scale for Percentage Difference of RC Pipe and HDPE Pipe ...................... 44
Figure 3-8 Ranking Scale for Percentage Difference of RC Pipe and DI Pipe ...................... 44
Table 3-3 Initial Estimated Values for Constructability (Labor and Equipment) ........................... 44
Figure 3-9 Ranking Scale for Percentage Difference of RC Pipe and HDPE Pipe ...................... 45
ii
Figure 3-10 Ranking Scale for Percentage Difference of RC Pipe and DI Pipe ........................... 46
Table 3-4 Initial Estimated Values for Serviceability (Efficiency Cost) ......................................... 46
Figure 3-11 Ranking Scale for Percentage Difference of DIP and HDPE Pipe ............................ 46
Figure 3-12 Ranking Scale for Percentage Difference of RC Pipe and DIP................................. 47
Table 3-4 Initial Estimated Values for Serviceability (Efficiency Cost) ......................................... 47
Figure 3-11 Ranking Scale for Percentage Difference of DIP and HDPE Pipe ............................ 48
Figure 3-12 Ranking Scale for Percentage Difference of RC Pipe and DIP................................. 48
Table 3-5 Initial Designers Ranking ............................................................................................. 49
Figure 3-13 Detention Tank ......................................................................................................... 50
Figure 3-14 Floodwall .................................................................................................................. 51
Figure 3-15 Dredging ................................................................................................................... 52
Figure 3-16 Structural Context Area ............................................................................................ 54
Table 3-6 Initial Economical Cost Estimate.................................................................................. 54
Figure 3-17 Initial Ranking Scale for Economic Constraint (1)..................................................... 55
Figure 3-18 Initial Ranking Scale for Economic Constraint (2)..................................................... 55
Table 3-7 Initial Labor and Equipment Cost Estimate .................................................................. 55
Figure 3-19 Initial Ranking Scale for Constructability Constraint (1) ............................................ 56
Figure 3-20 Initial Ranking Scale for Constructability Constraint (2) ............................................ 56
Table 3-8 Initial Sustainability Factor Estimate ............................................................................ 57
Figure 3-21 Initial Ranking Scale for Sustainability Constraint (1) ............................................... 57
Figure 3-22 Initial Ranking Scale for Sustainability Constraint (2) ............................................... 58
Table 3-8 Initial Estimated Values for Serviceability (Efficiency Cost) ......................................... 58
Figure 3-22 Ranking Scale for Percentage Difference of Detention Tank and Flood Wall ........... 58
Figure 3-23 Ranking Scale for Percentage Difference of RC Pipe and DIP................................. 59
Table 3-9 Initial Estimated Values for Risk Assessment .............................................................. 59
Figure 3-24 Ranking Scale for Percentage Difference of Detention Tank and Dredging ............. 60
Figure 3-25 Ranking Scale for Percentage Difference of Flood Wall and Dredging .................... 60
Table 3-10 Summary of Initial Estimated Values ......................................................................... 60
Figure 4-1 General Design Process............................................................................................. 63
Figure 4-2 Design Process for Storm Water Drainage ................................................................. 64
Figure 4-3 Flow chat for Reinforced Concrete Pipe ..................................................................... 65
iii
Table 4-1 Design Result of Storm Water Drainage using Reinforced Concrete Pipe .................. 66
Figure 4-4 Flow chat for HDPE ................................................................................................. 70
Table 4-2 Design Result of Stormwater Drainage using HDPE .............................................. 71
Figure 4-5 Flow chat for DIP ..................................................................................................... 75
Table 4-3 Design Result of Stormwater Drainage Using Ductile Iron Pipe ........................... 76
Table 4-4 Summary of Final Estimated Values for Water Context ............................................... 80
Figure 4-6 Cost Difference ........................................................................................................... 81
Figure 4-7 Cost Difference ........................................................................................................... 81
Figure 4-8 Labor Cost Difference................................................................................................. 82
Figure 4-9 Labor Cost Difference................................................................................................ 82
Figure 4-10 Maintenance Cost Difference ................................................................................... 82
Figure 4-11 Maintenance Cost Difference .................................................................................. 83
Figure 4-12 Service Discharge Efficiency Difference ................................................................... 83
Figure 4-13 Service Discharge Efficiency Difference .................................................................. 83
Table 4-5 Water Context Final Designer’s Ranking ................................................................ 84
Figure 4-14 Economic Comparison ............................................................................................. 86
Figure 4-15 Sustainability Comparison ........................................................................................ 87
Figure 4-16 Constructability Comparison ..................................................................................... 88
Figure 4-17 Serviceability Comparison ........................................................................................ 89
Table 4-6 Results of Sensitivity Analysis for Economic vs. Sustainability Constraint ................... 90
Figure 4-18 Variation Between Economic and Sustainability Constraint (RC Pipe) ..................... 91
Figure 4-19 Variation Between Economic and Sustainability Constraint (HDPE Pipe) ....... 91
Figure 4-20 Variation Between Economic and Sustainability Constraint (DIP Pipe) .................... 92
Figure 4-21 Summary of Variation between Economic and Sustainability Constraint .................. 92
Table 4-7 Results of Sensitivity Analysis for Economic and Constructability Constraint .............. 93
Figure 4-22 Variation Between Economic and Constructability Constraint (RC Pipe) ................. 94
Figure 4-23 Variation Between Economic and Constructability Constraint (HDPE Pipe) ............. 94
Figure 4-24 Variation Between Economic and Constructability Constraint (DIP Pipe) ................. 95
Figure 4-25 Summary of Variation Between Economic and Sustainability Constraint ................. 95
Table 4-8 Results of Sensitivity Analysis for Economic and Serviceability Constraint ................. 96
Figure 4-26 Variation Between Economic and Serviceability Constraint (RC Pipe) ..................... 97
iv
Figure 4-27 Variation Between Economic and Serviceability Constraint (HDPE Pipe) ................ 97
Figure 4-28 Variation Between Economic and Serviceability Constraint (DIP Pipe) .................... 98
Figure 4-29 Summary of Variation between Economic and Serviceability Constrain ................... 98
Table4-9 Summary of Initial Estimated Values ............................................................................ 98
Figure 4-30 General Design Process......................................................................................... 100
Figure 4-31 Design Process for Detention Pipes ....................................................................... 101
Figure 4-32 Design Process for Flood Wall ............................................................................... 103
Figure 4-33 Design Process for Dredging .................................................................................. 103
Table 4-10 Summary of Final Estimated Values for Structural Context ..................................... 103
Figure 4-32 Cost Difference ....................................................................................................... 104
Figure 4-33 Cost Difference ....................................................................................................... 104
Figure 4-34 Labor Cost Difference............................................................................................. 105
Figure 4-35 Labor Cost Difference............................................................................................. 105
Figure 4-36 Serviceability Cost Difference ................................................................................ 106
Figure 4-37 Serviceability Cost Difference ................................................................................. 106
Figure 4-38 Maintenance Cost Difference ................................................................................. 107
Figure 4-39 Maintenance Cost Difference ................................................................................. 107
Table 4-5 Structural Context Final Designer’s Ranking ....................................................... 108
Figure 4-40 Economic Comparison ........................................................................................... 109
Figure 4-42 Serviceability Comparison ...................................................................................... 110
Figure 4-43 Sustainability Comparison ...................................................................................... 110
Figure 4-51 Summary of Variation Between Economic and Sustainability Constraint ............... 115
Figure 4-52 Variation Between Economic and Serviceability Constraint ................................... 116
Figure 4-53 Variation Between Economic and Serviceability Constraint ................................... 117
Figure 4-54 Variation Between Economic and Serviceability Constraint ................................... 117
Figure 4-55 Summary of Variation between Economic and Serviceability Constrain ................. 118
Figure 5-1 Manhole Cover Detail ............................................................................................... 119
Figure 5-2 Manhole Plan (Top View) ......................................................................................... 119
Figure 5-3 Cross Section of Storm-water Drainage ................................................................... 120
Figure 5-4 Manhole Plan (Section A-A) ..................................................................................... 120
Figure 5-5 Cylindrical Detention Tank Plan................................................................................ 121
v
Figure 5-6 Cylindrical Detention Tank Top View ........................................................................ 123
Figure 5-7 Cylindrical Detention Left Side ................................................................................. 124
Figure 5-8 Cylindrical Detention Tank Right Side ...................................................................... 125
Figure 5-9 Stormwater Drainage Design Layout ........................................................................ 126
Figure 5-10 Storm Water Drainage Flow Network ..................................................................... 127
vi
ABBREVIATION
HDPE – High-Density Polyethylene Pipe
DIP – Ductile Iron Pipe
RCP – Reinforced Concrete Pipe
𝑄– flow rate (𝑚3/𝑠)
𝐴– Cross sectional area of flow (𝑚2)
𝑉 – Mean Velocity across a cross section (𝑚/𝑠)
𝑛 – Manning’s Coefficient of roughness (S.I. unit)
𝑅 – Hydraulic Radius (cross sectional area divided by the wetted perimeter) (𝑚)
𝑆 – Slope of the hydraulic gradient (non-dimensional)
𝑡𝑐 – time of concentration, in minutes
𝐾 – unit’s conversion coefficient, in which K = 0.0078 for traditional units, and K = 0.00195 for SI Units
𝐿 – the channel flow length, in feet or meters as
𝑆 – the dimensionless main-channel slope
fbuoy – total force due to buoyancy (KN/m)
fbuoy1 – buoyancy force due to hydrostatic pressure at the floodwall heel acting at an approximate
distance of B/3 from the heel (KN/m)
fbuoy2 – buoyancy force due to hydrostatic pressure at the floodwall toe, acting at an approximate distance
of B/3 from the toe (KN/m)
yw – specific weight of water (9.81 KN/m for fresh water and 10.05 KN/m for saltwater)
Ah – width of the footing above the heel (m)
C – width of the footing above the toe (m)
H – floodproofing design depth (m)
Dt – depth of soil above the floodwall toe (m)
tftg –thickness of the floodwall footing (m)
twall –thickness of the floodwall (m)
wftg – weight of the footing (KN/m)
B – width of the footing (m)
Sg – unit weight of wall material (concrete is 23.56 𝐾𝑁/𝑚3 )
vii
wst – weight of the soil over the toe (KN/m)
C – width of the footing toe (m)
Dt –depth of the soil above the floodwall toe (m)
ysoil – unit weight of soil (KN/m)
wwh – weight of the water above the heel (KN/m)
wG – total gravity forces acting downward (KN/m)
V – Volume
SEMSWA – Storm water Management Manual
viii
CHAPTER 1: INTRODUCTION
1.1 The Project
According to 2015 census, Pasig City has a population of 755,300 people. Although it has this large
number of population, the city is considered as a first class highly urbanized city in Metro Manila. The city has a
total land area of 31 km2. It is composed of 30 barangays including the Barangay Bambang which has a total
population of 20,657 people and has an area of 38.41 ha.
Based on research, the barangay has an existing drainage system but it has a substandard material used in
constructing the lines. It is considered to be the primary cause of flooding in the area. Last August 12, 2018, a
southwest monsoon hit Bambang that results in traffic congestions and evacuating families near the Marikina
River caused by an immediate uplift of water. Therefore, an effective drainage system should be design and
implement.
The project is the design of storm water drainage in Barangay Bambang, Pasig City. This will be design in
order to lessen the flooding on the area by collecting the rainwater using a standard drainage system that is based
on the Water Code of the Philippines.
1
1.3 The Client
The client is the head of Flood Control Department of Pasig Municipal Hall, Engr. Minwena P.Gamilla.
The project, if implemented, will be funded by the Pasig Municipal Budget Department. The client demands
to have an economical project cost, quality of the drainage system, and to have a short duration of project to
avoid traffic congestions.
1.4 Project Objectives
1. The design study includes the area bounded in Barangay Bambang only.
2. The design study does not include actual execution and construction of proposed design.
3. The design study does not include the analysis, maintenance and alterations of the system after the
proposal.
1.6 Project Development Plan
For the project’s completion, the designers developed a plan in order to design an effective storm-water
drainage in Barangay Sta. Lucia, Pasig City. The designers must begin by identifying the problem. And as the
problem was identified, which is the inadequacy of the existing drainage, the conceptualization of the project
should be analyzed. The designers should apply various methods for gathering data.
Then, the project’s constraints must be classified. It is the scope and the expected accomplishment of the
project. After considering the constraints, the designers will provide possible trade-offs that may solve the problem
and proceed in designing of each given trade-offs. The designers will estimate each designs and will view the
results then evaluate the most economic and effective design. The diagram shown is the detailed process of the
plan.
2
START
IDENTIFYING
THE PROBLEMS
CONCEPTUALIZATION
DATA GATHERING
PROJECT CONSTRAINTS
AND STANDARDS
EVALUATION OF
RESULT
FINAL DESIGN
END
3
CHAPTER 2: DESIGN INPUTS
2.1. Topography
Figure 2.1 shows the topographic map of Barangay Bambang, Pasig City. Bambang is situated at approximately
14.5554° N, 121.0801° E, these coordinates is estimated at 12 meters above mean sea level.
(Source: http://en-ph.topographic-map.com)
2.1.2 Geography
According to Geographical and Demographic Profile of Pasig City, it lays approximately 12 km. East of Manila
sprawled along the banks of Marikina and Pasig Rivers, on the southeastern end of Pasig River, bounded by
Quezon City and Marikina City on the North, Mandaluyong City on the West, Makati City, Pateros and Taguig on
the South, Cainta and Taytay (Province of rizal) on the East.
4
Figure 2-2 5 Year Flood Hazard Map of Bambang, Pasig City
(Source: https://lipad-fmc.dream.upd.edu.ph )
2.3 Rainfall Data
Figure 2.3 shows that Pasig City is provided with the highest annual average precipitation of 2586.7mmin the year
of 2012. Table 2.3 shows that April is the driest weather with an average precipitation of 16.67mm and September
is the wettest weather with an average of 393.17mm.
Table 2-1 Precipitation Data of Pasig City
MONTHLY TOTAL AND ANNUAL CLIMATIC
DATA RAINFALL DATA RAINFALL AMOUNT (mm)
YEAR JAN FEB MARCH APRIL MAY JUNE JULY AUG SEPT OCT NOV DEC ANNUAL
2012 29.5 87.5 55.5 4.5 125 -2 -2 -2 472 278.5 7 14.5 1074
2013 53.5 76 27 34.5 68 257 -2 921.9 734.5 277.8 99 37.5 2586.7
2014 T 3 7 0 64.5 193.5 380.5 244 424 227 34 120.5 1698
2015 25 0.5 7 T 32.5 91 294.5 241 268 221 14 294.5 1492
2016 0.5 20.5 T 12 47 124.5 268 348.5 136.5 266.5 98 70 1292
2017 39 31.5 3.5 38 70 169 272.5 298.5 324 194.5 114.5 61.5 1616.5
(Source PAG-ASA Science Garden, Quezon City)
5
450
400
384.32 393.17
350
300
250
227.55
200 203.08
150 139.08
100 100.25
67.83 61.08
50
24.58 36.5 16.67 14.83
0
16
14
12
10
Elevation
6
14
12
10
Elevation
12
10
8
Elevation
7
14
12
10
Elevation
12
10
8
Elevation
8
14
12
10
Elevation
14
12
10
Elevation
0
0+000 0+020 0+040 0+060
Villarosa Street 81.81m
9
14
12
10
Elevation
10
2.5 Outfall
The designer consider the Pasig River to be the outfall of the design Stormwater Drainage. Pasig river flows north-
northwest through the market town of Pasig and bisects Manila, then enters the bay between the North and South
harbours. Its length is 14 mi (23 km) and it has an average of 50 meters in width. It can carrya maximum discharge
of 56 𝑚3 /𝑠.
11
Figure 2-13 Drainage map of the Pasig-Marikina River system
(SOURCE: https://en.wikipedia.org/wiki/Pasig_River )
12
2.5 Existing Drainage Data
13
14
15
16
17
18
19
2.6 Design Inputs for Water Context
𝑄 = 𝐴𝑉
1 2 1
𝑉 = ( ) 𝑅3𝑆 2
𝑛
In practice, when designing the storm drains, the slope of the invert is used for S according to the supposition that
the condition of the flow in the pipes is uniform. Manning’s roughness coefficient is basically an index of the
frictional resistance to flow. Value for the coefficient is usually determined from the tabulated data shown below:
20
Table 2-2 typical Values of Roughness Coefficient
21
Table 2-3 Runoff Coefficient
22
2.6.3 Design Depth of Flow
2.6.3.1 Closed Conduit
Circular conduit is to be assumed to flow full as the design flow by means of Manning
formula. Although it is theoretically possible for a pipe flowing less than full to carry more
than when it is full, it is impractical to assume that this large conveyance will be available.
On the other hand, in case of rectangular conduit (culvert), design depth of flow should be
set 90% of full as the design flow. The ratios 𝑄/𝑄𝑓𝑢𝑙𝑙 and 𝑉/𝑉𝑓𝑢𝑙𝑙 are called the hydraulic
elements. A symbol without subscript represents the value of a variable when conduit is
flowing partially full.
23
Where:
𝑡𝑐 – time of concentration, in minutes
𝐾 – unit’s conversion coefficient, in which K = 0.0078 for traditional units, and K = 0.00195 for SI Units
𝐿 – the channel flow length, in feet or meters as
𝑆 – the dimensionless main-channel slope
4.4.5. Rainfall Intensity
The rainfall intensity (I) is the average rainfall rate in 𝑚𝑚ℎ𝑟 with the safety level indicated in the form of
return period for a catchment area during the concentration time. The rainfall intensity is obtained from
the rainfall intensity duration frequency (RIDF) curve.
The rainfall intensity can be expressed as follows:
1726.23
𝐼 = 0.66
𝑡𝑐 + 0.45
24
2.6.6 Velocity Limits
The minimum velocity for culverts is 0.6 𝑚/𝑠. Maintaining velocity may become difficult during dry
seasons. In this kind of situations, introducing smaller channel in the bottom of the culvert is possible to
confine the smaller flows to a smaller cross section to possibly achieve the minimum velocity. On the other
hand, the maximum velocity that the culverts can accumulate is limited to 5.0 𝑚/𝑠., to prevent damages
to the culvert.
25
Figure 2-20 Fixed End Moment Formula
Note:
DF = 0 for fixed end.
26
1
❖ 𝑓𝑠𝑡𝑎 = 𝑦𝑤𝐻 2
2
1
❖ 𝑓𝑑𝑖𝑓 = (𝑆 − 𝑦w)𝐷2
2
𝐶𝑑 𝑉 2
❖ 𝑑ℎ = 2𝑔
❖ 𝑓𝑑ℎ = 𝑦𝑤(𝑑ℎ)𝐻
❖ 𝐹𝑛 = 𝑊𝑉𝐶𝐷𝐶𝐵𝐶𝑆𝑡𝑟
❖ 𝐹𝑆𝑡𝑎 = 𝑓𝑠𝑡𝑎 + 𝑓𝑑𝑖𝑓 + 𝑓𝑑ℎ
Since Fn acts only at a single point, we will not include loading into the uniform lateral floodwall loading. Once the
floodwall is sized, we will evaluate the wall perpendicular to flow to determine ability to resist the impact loading. If
necessary this wall will be redesigned to resist impact loads. This process will avoid overdesigning of the entire
floodwall.
1
❖ 𝐹𝑝 = 2 [𝑘𝑝(𝑦𝑠𝑜𝑖𝑙 − 𝑦𝑤) + 𝑦𝑤 ]𝐷𝑡 2
27
Step 5: Check overturning.
𝐻 𝐷 2𝐵 𝐻 𝐵
❖ 𝑀𝑜 = 𝐹𝑆𝑡𝑎 3 + 𝑓𝑑𝑖𝑓 3 + 𝑓𝑏𝑢𝑜𝑦1 + 𝑓𝑑ℎ 2 + 𝑓𝑏𝑢𝑜𝑦2 3 =
3
𝑡𝑤𝑎𝑙𝑙 𝐶 𝐵 𝐴ℎ 𝐴ℎ 𝐷𝑡
❖ 𝑀𝑅 = 𝑤𝑤𝑎𝑙𝑙 (𝐶 + ) + 𝑤𝑓𝑡𝑔 (2) + 𝑤𝑠𝑡 ( 2 ) + 𝑤𝑠ℎ (𝐵 − ) + 𝑤𝑤ℎ (𝐵 − ) + 𝐹𝑝( 3 ) =
2 2 2
𝑀𝑅
❖ 𝐹𝑆𝑂𝑇 = 𝑀𝑂 > 1.5
𝐹𝑣 6𝑒
❖ 𝑞𝑚𝑎𝑥 = ( 𝐵 ) (1 + )
𝐵
𝐹𝑣 6𝑒
❖ 𝑞𝑚𝑖𝑛 = ( 𝐵 ) (1 − )
𝐵
❖ 𝐴𝑠 = ( 7.5𝑑𝑓
1000
)=
4𝐴𝑠
❖ 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 = √ 𝜋
4𝐴𝑠
❖ 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 = √ 𝜋
28
For bottom steel in the footing section:
1.5
❖ 𝑞 = 𝑞𝑚𝑎𝑥 + (𝑞𝑚𝑎𝑥 − 𝑞𝑚𝑖𝑛)
8
𝐶2
❖ 𝑀𝑏 = (𝑞 + 2𝑞𝑚𝑎𝑥) ( 6 ) =
𝑀𝑏
❖ 𝐴𝑠 = ( 7.5𝑑𝑓 )
1000
4𝐴𝑠
❖ 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 = √ 𝜋
29
Table 2-5 Soil Factors for Floodwall Design
Duration of Dredging
𝑉𝑜𝑙𝑢𝑚𝑒
𝑇𝑑 =
2 ∗ 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝑏𝑎𝑐𝑘ℎ𝑜𝑒
Unloading
30
𝑉𝑜𝑙𝑢𝑚𝑒
𝑇𝑢 =
2 ∗ 74
Return trip
𝐿
𝑇𝑟 =
𝐶𝑠𝑝𝑒𝑒𝑑
Number of trucks needed
148
𝑁=
𝑄ℎ
Dredging
❖ Basic Conditions
Study of the backfill site was made according to following items as basic condition.
31
2.8 Related Literature and Studies
According to Linsley(1942), "From a strict hydrological sense, flood is defined as a rise, usually brief, in the water
level in a stream to a peak from which the water level recedes at a slower rate. The episodic behavior of a river
that may be considered flood is then termed "flood event" which is described as a flow of water in a stream
constituting a distinct progressive rise, culminating in a crest, together with the recession that follows the crest.”
“A storm water detention tank is an artificial flow-control structure that is used to “detained” storm water for a short
period of time. Storm water stored in the detention tank will then be filtered to be reuse. The concept of the storm
water detention tank is to temporarily store excess storm water runoff. This is to avoid hydraulic overload of the
sewer system, which could result in the flooding if roads and building with untreated wastewater or its release
directly into the environment, causing pollution. When space is available in the sewer system, the detained water
is released at a rate not exceeding the capacities of the sewer system, and the tank should be cleaned ready for
the next flush.” (Mays, Lary W, 2010)
As stated by the IJDRBC Vol. 6(November 2015), the existing drainage system in Manila and suburbs are is
composed of closed principal channels called “drainage mains” or the “outfalls”, and open channels called “creeks”
or the “estuary”, secondary or the tertiary drainage channels called “drainage laterals”, and pumping stations. The
initial drainage construction works were based on the plan for the drainage of Manila and suburbs areas. A master
plan prepared in 1952 by the former Bureau of Public Works (BPW), subsequent system improvements were
based on lateral revisions of the 1952 master plan. One of such revisions was made in 1978 under the “Manila
and suburbs flood control projects”, another was made in 1984 under” Metro Manila integrated urban drainage
and flood control master plan” of the Ministry of Public Works and Highways now it is called the Department Public
Works and Highways (DPWH).
The DPWH today is in charge of the installation and maintenance of drainage facilities located along national
roads. The Local Government Units (LGU), on the other hand, are responsible for the construction and
maintenance of drainage facilities located along cities or municipal roads. The DPWH has installed 35 drainage
mains (outfalls) along the national roads of Metro Manila, which all together have a total length of 34 kilometers.
There is no consolidated data on drainage facilities constructed by the various LGU but most of the roads within
Manila and suburbs have drainage laterals installed. Manila suburbs which are being serviced by 15 pumping
stations for draining the storm water to the Pasig River or Manila bay. All these stations are operated and
maintained by the DPWH and were designed for draining storm water of a 10 years return period of these pumping
stations. Seven (7) were composed and become operational between 1976 and 1977 through financial assistance
by the Overseas Economic Cooperation Fund (OECF). These seven stations shown in Figure 1 are Valencia,
Quiapo, Pandacan, Aviles-Sampaloc, Paco, Sta. Clara, and Tripa De Gallina. Procurements of the required
equipment for three (3) of the 15 stations for draining the storm water namely: Libertad, Binondo and Makati
pumping stations, was individually undertaken during 1979 to 1985. The export-import bank (EXIM bank) of Japan
financed the equipment procurement. The construction of 5 remaining stations namely: Vitas, Balut, Escolta, san
Andres and Balete were made possible through the financial loan assistance from OECF Japan. The said
construction started in 1994 and it was completed in 1998. To address the increasing accumulation of sediments
and garbage in drainage channels, The DPWH carried out the project for retrieval of flood prone areas in Metro
Manila. The Phase 1 of the project was implemented in 1990 and the Phase 2 is in 1994 for this project, which
was also meant to complement the gains made in other flood control projects.
Based from “An Analysis of the Public Perception of Floods in Manila City” (Tomas Ganiron Jr.), In Manggahan
Floodway, the main purpose of its construction was to divert a portion of the Marikina flood flow towards to Laguna
32
Lake in order to minimize the flooding hazard and damage of low-lying areas located along the Marikina and Pasig
Rivers. Flood volumes diverted from. Marikina a River as well as sustained direct rainfall and tributary inflows from
surrounding lakeshore watersheds may cause the significant rise of the Laguna Lake level. Its slow recession is
due to the low discharge capacity of the single outlet, the Napindan Pasig River channel.
Pump station is one of the factors in solving the flood problem in our country. This is very important factor in the
clean-up of the river. They are very complex but can be simplified in a simple tour but once know how they work,
they seen a lot easier to understand. First, a number of pumps are opened. When the river got to a certain point,
those pumps would open. From there the water goes into a bar screen. This filtered the river water, cleaning out
the debris. After being filtered, the water flows through the gates and into the river. When the water goes through
the pump, it pushes open a check valve, or a flap, that keeps the river water out. These are the depths when the
pumping stations kick in. The pump station at the Lagusnilad Underpass plays an important role in flood control
such as (a) It removes storm water from the streets and permits the transportation arteries to function during bad
weather-when this is done efficiently, the life expectancy of street pavement is extended. (b) The pump station
controls the rate and velocity of runoff along gutters and other surfaces in a manner that reduces the hazard to
local residents and potential for damage to pavement. (c) The pump conveys runoff to natural or manmade
drainage ways. (d) The system was designed to control the mass of pollutants arriving at receiving waterways. (e)
Major open drainage ways and detention facilities offer opportunities for multiple uses such as recreation, parts,
and wildlife preserves.
According to a study made by Zairon Delos Santos, Mikhail Dimitri Paulino and Fiina Kamille Pel, Quezon City is
one of the Local Government Units that adopts the Green Building Standards to strictly adhere to energy efficiency,
cost effectiveness and mitigate adverse impacts on environmental degradation and the city government also plans
to develop an eco-village that will house the informal settlers. In line with this matter, they will also need to invest
in drainage works. But, the city government may also face floods especially on the low areas. For this reason,
investigation has been made for the possibilities of constructing a storm sewer system. The infrastructure would
manage the storm water and to have a potential source of water for the village.
Based from the calculations for the design of the storm sewer system, the pipe diameters to be laid are 0.30, 0.36
and 0.53 mm. These sizes are capable of withstanding the volume of rain with 41.2 mm of precipitation. It is
showed that the storm water volume for a day during the rainy season of the Philippines with the assumed rate of
precipitation which is 41.2 mm., is 3,014,887 cubic meters. During also that season, the water requirement of the
tenants of the village is 320427.9 cubic meters. Therefore, comparing the two values, it shows that the storm water
is higher than the water requirements and is capable of supplying these requirements if the local government will
subject this water to treatment.
“In the 1950's, the Shanghai government completed development of new residential areas, suburban industrial
areas and satellite towns, and the separated drainage system was implemented for those areas. After ten years,
six drainage systems were built in new residential areas, and six small sewage treatment plants and three sewage
systems were established in the new industrial areas. Meanwhile, technological transformation was done for the
original three sewage treatment plants (Wang, 2007). In 1983, the municipal government proposed the policy of
―comprehensive and simultaneous management and governance‖ and adopted the combined co-existence with
separated drainage system in Shanghai. A combined drainage system was constructed as the main style. In order
to serve new residential areas, four medium-sized sewage treatment plants were built or rebuilt and another four
small sewage treatment plants were constructed (Li, 2008).
According to this case study by Renato T. Cruz, “Water Pollution Control - A Guide to the Use of Water Quality
Management Principles,” factories and squatter colonies situated in the banks of Pasig River contributes to the
33
extensive pollution along the river. Industrial pollution accounts for 45 per cent of the total pollution in the Pasig
River. About 315 of the 2,000 or more factories situated in the river basin have been determined as principal
polluters of the river. Domestic liquid waste contributes another 45 per cent of the pollution load in the Pasig River.
There were approximately 4.4 million people living in the Pasig River catchment area during the study period and
only 0.6 million, or 12 per cent, were serviced by the sewerage system which treats domestic wastewaters before
discharging them into Manila Bay. Untreated waste-waters from the remaining 88 per cent of the population flow
through canals and esteros into viaducts leading into the Pasig River. Lastly, the 10 per cent of the pollution in the
Pasig River are from solid wastes.
As a further matter, “For the flashfloods experienced in the urban area of New Delhi, India, the author proposed
the idea of pre-fabricated drain design. Oarno and Cairncross (1991) formulated low cost drainage system design
used in informal urban settlements implemented in San Salvador, Brazil. Furthermore, they stated that the smallest
channel which is less than 300 mm deep conveniently lined with brick or with pre-cast concrete elements. The
elements weigh less than 50 kg carried by two persons. These pre-cast channels laid on a bed of compacted
sand, 50mm thick. The advantage of the pre-fabricated elements over masonry/ in situ concrete lining is they can
be laid quickly. There are difficulties concerning the masonry drains. It requires several days to set and if drains
constructed during dry season, the shortage of water for curing process of concrete takes place. The used of pre-
cast elements can overcome the said difficulties and the firm quality control can be enforce in the preparation of
the product.” (Pre-Cast Drainage Design in New Delhi, India)
Moreover, S. Needhidasan and M. Nallanathel of Saveetha School of Engineering, Saveetha University Chennai
conducted a case study for drainage design of Palayam Area, Calicut City in Kerala, India. The case study is an
approach to Storm Water Management for Environmental Protection. According to them, they said area is
experiencing excess runoff that is considered as a threat to the environment due to dense population. The
urbanization increases the surface runoff, by creating more impervious surfaces such as pavement and buildings
that prevents percolation of the water down through the soil to the aquifer. Excessive runoff reduces groundwater
recharge, thus lowering the water table and making droughts worse who depend on water wells. Thus,
urbanization and runoff quality create big impact to the environment and causes a general degradation of water
quality in the receiving waters. (Storm Water Drainage by Rational Method in Calicut, India)
Figure 2-23 Calculated Maximum and Minimum Diameter of Storm Sewer Pipes
Lastly, “In the Zambian city of Ndola, the capital of the Copperbelt Province, flooding occurs in some parts of the
city. The city is among the cleanest, well-planned and most-organized cities in Zambia with an approximate
34
population of 455,194 in 2010 as compared to 374,757 in 2000. Lately, Ndola has been facing challenges with
pluvial floods and flash floods caused by short lived intense convective rainfall and/ or prolonged frontal rainfall
events, where the proximity to the equator influences the climatology.
According to the study, the major problem with the system is blockages resulting from mainly garbage being
thrown into the systems as well as silt build-up overtime if no adequate maintenance is done. From the modelling
and simulations, it can also be concluded that changing the size of the pipe (P27=600mm) draining water from
the under bridge would improve the drainage systems’ rainfall events’ handling capacity to more than 10yrs return
period without flooding. The pipe to be changed lies on a 200m length stretch which may not be too costly as it
lies outside the CBA on the downstream part of the catchment.” - David Titus Banda, “Drainage System and Storm
Water Management for Ndola Central Business Area, Zambia.
35
3.1 Design Constraints
Design Constraints are necessary action to determine the limiting factors that will affect the construction of the
project. These constraints will give a better understanding about the factors that needs to be assessed before,
during and after the project. Constraints may be in form of health, safety, political, environmental, constructability,
sustainability and financial. A design constraint is normally imposed externally, either by the organization or by
some external regulation. During system design, it is important to identify each design constraint as it is to elicit
requirements since the design constraints place an overall boundary around the system design process.
The following constraints were considered by the designer because it has a substantial impact on the storm water
drainage to be built at Barangay Bambang, Pasig City for flood mitigation measures:
3.1.1 Quantitative Constraints
3.1.1.1 Economic Constraint (Total Cost of the Project)
Economic constraint of the project deals with the fact that in construction, it is required to create a project
that will sufficiently meet the required strength and durability while minimizing the costs. This constraint
also takes into consideration the relationship of the design life of the project with the cost, having greater
design life will result to higher cost of the project. For this, the designers will assess the total costs (that
which includes the initial costs and maintenance costs) of alternatives to come up with the best design
3.1.1.2. Sustainability Constraint (Maintenance Cost)
Sustainability constraint takes into account the problem on how long the design life of a project is with
respect to its design strength. One of the basic ideas in engineering design is that with greater design
strength, there is an equivalent increase in cost due to the need of higher quality material. However,
choosing the cheapest materials and leaving the structure without timely maintenance treatment can have
expensive maintenance requirements.
3.1.1.3. Constructability Constraint (Labor and Equipment Cost)
Time is a very significant factor that should be considered in any construction project. The longer the time
to finish the project could mean a larger cost. The project schedule should be followed correctly so the
actual money being spent will not exceed the allocated money for the entire project. The designers will
estimate the man-hour and time needed for the equipment to be rented for each trade-off for a better
judgment of the trade-off that will govern in the project.
3.1.1.4. Serviceability Constraint (Efficiency)
The size and the materials to be used for the drainage system plays a big part especially in serving the
drainage’s primary function which is to collect surface water and/or ground water and direct it away,
thereby keeping the ballast bed drained. The storm water drainage must also protect the substructure
from erosion, from becoming sodden, and from losing its load-bearing capacity and stability. The amount
of water and the amount of force it can hold are one of the most critical factors to be considered. The
amount of rainfall is not consistent and it always changes that is why the stability and the capacity to hold
large amount of discharge must be considered. The storm water drainage to be built expects to hold a
huge amount of water as well as great discharge to be produced especially during rainy seasons. The
material to be used should determine the most efficient and stable to hold such great discharge which will
be determined using the trade-offs considered by the designers.
36
3.1.1.5 Risk Assessment (Room for Exceeding Actual Discharge)
Risk assessment is the process of evaluating risks to worker’s safety and health from workplace hazards. It is
a systematic examination of all aspects of work that considers: hazards identification, risk analysis, and risk
control. In designing flood control structures, the designers should be aware of, and assess the risks from, the
following principal hazards, all the sources of flooding are need to be consider in order to mitigate the impact of
flooding in the area. Flood risk is the combination of flood damage potential and the probability of its
occurrence. Flood control measures have its design capacity, but if poorly designed or constructed or when it
exceeds its capacity the flood control measures could fail and the damage can have devastating
consequences. The process of flood risk assessment is to evaluate the actual usage of the designed drainage
system and how much more can it hold on if a certain storm exceeded the designed rainfall data used in the
designed stormwater drainage
3.1.2.2 Environmental
This constraint discuss the overall impact of the designed stormwater drainage to the environment of the project
location. The impact of the materials that will be used in the project is needed to be considered as it can affect
the strength of the soil, which can cause problems since the project location is a residential site. This constraint
determines the fit of a certain material, or process to the design and assess whether it is appropriate to be
implemented or not.
37
3.2.1. Material Trade-offs
3.2.1.1. Reinforced Concrete Pipe
Reinforced concrete pipes have been available since the eighties of the 19th Century. The relatively thin
wall thickness and resulting weight reduction brought about by this was the reason that, already at the
start of the 20th Century, reinforced concrete pipes with circular cross sections were produced in the
factory in sizes up to DN 2500.
Reinforced concrete pipes for gravity system sewers can be dimensioned for any load cases; they are
especially suited for high loads and for dynamic stresses caused by heavy traffic with small cover
depth.Pipes with smaller nominal sizes were often reinforced in only one direction, larger ones received
spiral reinforcement, very large ones, double and triple layers depending on the loading
38
can be easily molded and welded together. Due to its high chemical resistance property, it is used in
piping systems. HDPE pipes are used to both carry potable water and hazardous waste. It has other
applications also like in making backpacking frames, bottle caps, food storage containers, vehicles fuel
tanks, folding chairs.
39
3.2.1.3 Ductile Iron Pipe
Ductile iron pipe, made from ductile cast iron, is a graphite-rich cast iron in which the graphite has a
spheroidal shaped molecular structure. This molecular structure makes the cast iron less brittle and more
resistant to impact than the other varieties, which have a flaky structure. The ductile iron pipe is used in
trenchless technology for water and sewer lines.
40
❖ Over the last 100 years, the average thickness of iron pipes has decreased due to increased metal
strength, through metallurgical advancements as well as improved casting technique.
41
Table 3.1 shows the initial cost of the three trade-offs. By means of this initial result, the designers may
find out what trade-off governs in terms of economical cost whichever has the lower price for material
cost.
Table 3-1 Initial Estimated Values for Economic (Cost of the Project)
Description RCP HDPE DIP
Economical Cost 2,105,337.52 2,621,840 7,563,000
(Php)
SUBORDINATE 10 8.03 2.78
RANK
3.3.1.1 Computation of Ranking for Economic Constraint
2,621,840−2,105,337.52
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
2,621,840
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟏. 𝟗𝟕
Figure 3-5 Ranking Scale for Percentage Difference of RC Pipe and HDPE Pipe
7,563,000−2,105,337.52
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
7,563,000
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟕. 𝟐𝟐
42
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘=𝐺𝑜𝑣𝑒𝑟𝑛𝑖𝑛𝑔 𝑅𝑎𝑛𝑘−(% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒)
Figure 3-6 Ranking Scale for Percentage Difference of RC Pipe and DI Pipe
105,226.88−104,873.6
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
105,226.88
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟎. 𝟎𝟑
43
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘 =9.97
Figure 3-7 Ranking Scale for Percentage Difference of RC Pipe and HDPE Pipe
❖ HDPE Vs. DIP
𝐻𝑖𝑔ℎ𝑒𝑟 𝑉𝑎𝑙𝑢𝑒−𝐿𝑜𝑤𝑒𝑟 𝑉𝑎𝑙𝑢𝑒
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
𝐻𝑖𝑔ℎ𝑒𝑟 𝑉𝑎𝑙𝑢𝑒
226,890−104,873.6
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
226,890
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟓. 𝟑𝟖
Figure 3-8 Ranking Scale for Percentage Difference of RC Pipe and DI Pipe
44
SUBORDINATE 10 8.03 2.58
RANK
3.3.3.1 Computation of Ranking for Constructability
Governing Rank : 10 (Reinforced Concrete Pipe)
❖ RCP Vs. HDPE
𝐻𝑖𝑔ℎ𝑒𝑟 𝑉𝑎𝑙𝑢𝑒−𝐿𝑜𝑤𝑒𝑟 𝑉𝑎𝑙𝑢𝑒
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
𝐻𝑖𝑔ℎ𝑒𝑟 𝑉𝑎𝑙𝑢𝑒
786,552−631,601.26
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
786,552
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟏. 𝟗𝟕
Figure 3-9 Ranking Scale for Percentage Difference of RC Pipe and HDPE Pipe
2,268,900−631,601.26
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
2,268,900
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟕. 𝟐𝟐
45
Figure 3-10 Ranking Scale for Percentage Difference of RC Pipe and DI Pipe
3.3.4 Initial Estimated Values for Serviceability (Efficiency)
According to Ductile Iron Pipe Research Association Ductile Iron Pipe is more efficient than other pipe
material due to its nominal inside diameter which results in a lower head loss and lowering Pumping cost
of 21%, second is HDPE 19%, and lastly is RCP 16%. In this case the designers considered the average
efficiency cost of each material trade-off.
Table 3-4 Initial Estimated Values for Serviceability (Efficiency Cost)
Description RCP HDPE DIP
Economical 336,854.00 498,149.6 1,588,230
Cost (Php)
SUBORDINATE 2.12 3.14 10
RANK
1,588,230−498,149.6
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
1,588,230
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟔. 𝟖𝟔
Figure 3-11 Ranking Scale for Percentage Difference of DIP and HDPE Pipe
46
1,588,230−336,854.00
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
1,588,230
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟕. 𝟖𝟖
Figure 3-12 Ranking Scale for Percentage Difference of RC Pipe and DIP
3.3.4 Initial Estimated Values for Risk Assessment
According to Ductile Iron Pipe Research Association Ductile Iron Pipe is more resistant to high pressure,
and surges than other pipe material due to its nominal inside diameter which results in a lower head loss
and lowering Pumping cost of 11%, second is HDPE 9%, and lastly is RCP 6%. In this case the designers
considered the average efficiency cost of each material trade-off.
Table 3-4 Initial Estimated Values for Serviceability (Efficiency Cost)
Description RCP HDPE DIP
Economical 1,263,202.5 2,359,656 831,930
Cost (Php)
SUBORDINATE 2.12 3.14 10
RANK
1,263,202.5−831,930
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
1,263,202.5
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟑. 𝟒𝟏
47
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘 =6.59
Figure 3-11 Ranking Scale for Percentage Difference of DIP and HDPE Pipe
2,359,656−831,930
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
2,359,656
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟔. 𝟒𝟕
Figure 3-12 Ranking Scale for Percentage Difference of RC Pipe and DIP
48
Table 3-5 Initial Designers Ranking
Importance Design Of Stormwater Drainage
Design Criteria (Scale 0-10) RCP HDPE DIP
49
Manning’s Formula. The results show that the HDPE which has the largest discharge capacity of 0.64767
m3/s is the most efficient.
3.4.5. Risk Assessment
The Risk Assessment Constraint has given an importance factor of 8 in terms of resistant to pressure and
surges of water. Due to this said pressure the material can decay and later become weak and have a
tendency to broke down. The designers estimated the strength of the material in terms of material
properties of each trade-off. The results show that the DIP which has the largest pressure resistance
among the three tradeoffs.
50
building levees or dikes would interfere with other interests, such as existing buildings, historical
architecture or commercial use of embankments.
51
❖ Local drainage can be affected, possibly creating water problems for others. ü Interior drainage
must be provided.
❖ Require periodic maintenance.
❖ No reduction in flood insurance premiums.
❖ Do not eliminate the need to evacuate during floods.
3.5.1.3 Dredging
It is the removal of sediments and debris from the bottom of lakes, rivers, harbors, and other water bodies.
Dredging is often focused on maintaining or increasing the depth of navigation channels, anchorages, or
berthing areas to ensure the safe passage of boats and ships. Vessels require a certain amount of water in
order to float and not touch bottom. It is also performed to reduce the exposure of fish, wildlife, and people to
contaminants and to prevent the spread of contaminants to other areas of the water body.
52
Disadvantages of Dredging:
1.) Disturbing the natural water flow may have unintended and unknown effects. Changing the water flow often
destroys habitats.
2.) Dredging causes harmful to wildlife in a variety of ways such as the mechanical act of dredging destroys
habitats and may kill fish and other animal life.
3.) It can crush and kill marine flora, smooth bedforms so plant life has a harder time gaining a foothold and
reduce biodiversity.
53
Figure 3-16 Structural Context Area
The designers presented prices for different systems using the site “All Cost Data Info” to come up with the
project’s initial material cost which are as follows:
❖ A Precast Concrete Pipe with a minimum of 46 cm diameter pipe will cost a converted amount of 572 php
per unit length..
❖ A Flood Wall with a minimum height of 3m will cost a converted amount of 5500php per unit length.
❖ A Dredging process with a minimum height of 3m will cost a converted amount of 430php per unit volume.
By means of this initial result, the designers may find out what trade-off governs in terms of economic cost
whichever has the lower price for material cost.
Description System 3
System 1 System 2
The computation for the ranking of the three trade-offs is illustrated below using the formula stated above.
• Computation of ranking for Economic Constraint
➢ GOVERNING RANK
System 1: 10
▪ System 1 vs System 2
ℎ𝑖𝑔ℎ𝑒𝑟 𝑣𝑎𝑙𝑢𝑒 − 𝑙𝑜𝑤𝑒𝑟 𝑣𝑎𝑙𝑢𝑒
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
ℎ𝑖𝑔ℎ𝑒𝑟 𝑣𝑎𝑙𝑢𝑒
11638779.35 −1213785
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
11638779.35
%𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = 8.96
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 𝐺𝑜𝑣𝑒𝑟𝑛𝑖𝑛𝑔 𝑟𝑎𝑛𝑘 − %𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 10 – 8.96
𝑺𝒖𝒃𝒐𝒓𝒅𝒊𝒏𝒂𝒕𝒆 𝒓𝒂𝒏𝒌 = 1.04
54
Figure 3-17 Initial Ranking Scale for Economic Constraint (1)
▪ System 1 vs System 3
ℎ𝑖𝑔ℎ𝑒𝑟 𝑣𝑎𝑙𝑢𝑒 − 𝑙𝑜𝑤𝑒𝑟 𝑣𝑎𝑙𝑢𝑒
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
ℎ𝑖𝑔ℎ𝑒𝑟 𝑣𝑎𝑙𝑢𝑒
1500000 −1213785
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
1500000
%𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = 1.91
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 𝐺𝑜𝑣𝑒𝑟𝑛𝑖𝑛𝑔 𝑟𝑎𝑛𝑘 − %𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 10 – 1.91
𝑺𝒖𝒃𝒐𝒓𝒅𝒊𝒏𝒂𝒕𝒆 𝒓𝒂𝒏𝒌 = 8.09
The computation for the ranking of the three trade-offs is illustrated below using the formula stated above.
55
➢ GOVERNING RANK
System 1 :10
▪ System 1 vs System 2
ℎ𝑖𝑔ℎ𝑒𝑟 𝑣𝑎𝑙𝑢𝑒 − 𝑙𝑜𝑤𝑒𝑟 𝑣𝑎𝑙𝑢𝑒
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
ℎ𝑖𝑔ℎ𝑒𝑟 𝑣𝑎𝑙𝑢𝑒
3491633.805 −364135.5
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
3491633.805
%𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = 8.96
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 𝐺𝑜𝑣𝑒𝑟𝑛𝑖𝑛𝑔 𝑟𝑎𝑛𝑘 − %𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 10 – 8.96
𝑺𝒖𝒃𝒐𝒓𝒅𝒊𝒏𝒂𝒕𝒆 𝒓𝒂𝒏𝒌 = 1.04
▪ System 1 vs System 3
ℎ𝑖𝑔ℎ𝑒𝑟 𝑣𝑎𝑙𝑢𝑒 − 𝑙𝑜𝑤𝑒𝑟 𝑣𝑎𝑙𝑢𝑒
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
ℎ𝑖𝑔ℎ𝑒𝑟 𝑣𝑎𝑙𝑢𝑒
450000 −364135.5
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
450000
%𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = 1.91
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 𝐺𝑜𝑣𝑒𝑟𝑛𝑖𝑛𝑔 𝑟𝑎𝑛𝑘 − %𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 10 – 1.91
𝑺𝒖𝒃𝒐𝒓𝒅𝒊𝒏𝒂𝒕𝒆 𝒓𝒂𝒏𝒌 = 8.09
56
❖ A Dredging will have a maintenance cost of 5% because of its life expectancy which last for 5-10 years
(Php)
The computation for the ranking of the three trade-offs is illustrated below using the formula stated above.
• Computation of ranking for Constructability
Constraint
➢ GOVERNING RANK
System 1: 10
▪ System 1 vs System 2
ℎ𝑖𝑔ℎ𝑒𝑟 𝑣𝑎𝑙𝑢𝑒 − 𝑙𝑜𝑤𝑒𝑟 𝑣𝑎𝑙𝑢𝑒
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
ℎ𝑖𝑔ℎ𝑒𝑟 𝑣𝑎𝑙𝑢𝑒
465551.174 −36413.55
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
465551.174
%𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = 9.22
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 𝐺𝑜𝑣𝑒𝑟𝑛𝑖𝑛𝑔 𝑟𝑎𝑛𝑘 − %𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 10 – 9.22
𝑺𝒖𝒃𝒐𝒓𝒅𝒊𝒏𝒂𝒕𝒆 𝒓𝒂𝒏𝒌 = 0.78
75000−36,413.55
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
75000
57
%𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = 5.14
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 𝐺𝑜𝑣𝑒𝑟𝑛𝑖𝑛𝑔 𝑟𝑎𝑛𝑘 − %𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑟𝑎𝑛𝑘 = 10 – 5.14
𝑺𝒖𝒃𝒐𝒓𝒅𝒊𝒏𝒂𝒕𝒆 𝒓𝒂𝒏𝒌 = 4.86
1498149.6−336854
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
1498149.6
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟕. 𝟕𝟓
Figure 3-22 Ranking Scale for Percentage Difference of Detention Tank and Flood Wall
58
❖ Flood Wall Vs Dredging
𝐻𝑖𝑔ℎ𝑒𝑟 𝑉𝑎𝑙𝑢𝑒−𝐿𝑜𝑤𝑒𝑟 𝑉𝑎𝑙𝑢𝑒
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
𝐻𝑖𝑔ℎ𝑒𝑟 𝑉𝑎𝑙𝑢𝑒
1,498149.6−588230
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
1498149.6
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟔. 𝟎𝟕
Figure 3-23 Ranking Scale for Percentage Difference of RC Pipe and DIP
3.6.5 Initial Estimated Values for Risk Assessment
Table 3-9 Initial Estimated Values for Risk Assessment
Description Detention Tank Flood Wall Dredging
Economical 1,263,202.5 2,359,656 831,930
Cost (Php)
SUBORDINATE 2.12 3.14 10
RANK
1,263,202.5−831,930
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
1,263,202.5
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟑. 𝟒𝟏
59
𝑆𝑢𝑏𝑜𝑟𝑑𝑖𝑛𝑎𝑡𝑒 𝑅𝑎𝑛𝑘 =6.59
Figure 3-24 Ranking Scale for Percentage Difference of Detention Tank and Dredging
2,359,656−831,930
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝑥10%
2,359,656
% 𝑑𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒= 𝟔. 𝟒𝟕
Figure 3-25 Ranking Scale for Percentage Difference of Flood Wall and Dredging
60
Serviceability 10 2.25 10 3.93
Risk Assessment 8 2.12 3.14 10
Over-all Rank 319.46 129.8 154.21
61
3.7.5 Risk Assessment
The Risk Assessment Constraint has given an importance factor of 8 in terms of resistant to pressure and
surges of water. Due to this said pressure the material can decay and later become weak and have a
tendency to broke down. The designers estimated the strength of the material in terms of material
properties of each trade-off. The results show that the Flood Wall which has the largest pressure
resistance among the three tradeoffs.
3.8.4 DPWH -Technical Standards and Guidelines for Planning and Design -Flood Control Volume I
This volume of the Technical Guidelines was formulated in order to establish uniformity in planning and
designing of flood control projects. It aims to provide the engineers of DPWH involved in flood control planning
and design, the essential tools to formulate effective and efficient countermeasures against floods.
62
4.1.2 Design Process
The following figure will be used by the designers in the design process of the systems. Each trade-off will be
evaluated to come up with the most effective design.
EVALUATION OF TRADE-OFFS
DESIGN
63
4.1.3. Design Process for Drainage System
START
END
64
4.1.4 Reinforced Concrete Pipe
65
Table 4-1 Design Result of Storm Water Drainage using Reinforced Concrete Pipe
Design of Stormwater Drainage
A. Luna Street
Pipe
Highest Lowest Diameter Actual Design Actual/Design Remarks
Conduit
Elevation Elevation Discharge Discharge
(m) (m) (mm) (L/s) (L/s) (%)
A.LUNA P-1 13.4 9.46 675 239.62 325.41 73.6 ADEQUATE
A.LUNA P-2 13.36 13.4 675 220.94 266.89 82.8 ADEQUATE
A.LUNA P-3 13.36 13.27 600 199.69 235.46 84.8 ADEQUATE
A.LUNA P-4 13.3 13.27 600 180.43 226.96 79.5 ADEQUATE
A.LUNA P-5 13.45 13.3 600 159.01 235.75 67.4 ADEQUATE
A.LUNA P-6 13.5 13.12 500 138.78 146.32 94.9 ADEQUATE
A.LUNA P-7 13.5 13.5 500 120.36 143.27 84 ADEQUATE
A.LUNA P-8 13.5 13.5 450 99.14 109.92 90.2 ADEQUATE
A.LUNA P-9 13.51 13.5 400 77.58 78.89 98.3 ADEQUATE
A.LUNA P-10 13.55 13.51 350 54.93 56.55 97.1 ADEQUATE
A.LUNA P-11 13.55 13.54 300 35.33 37.94 93.1 ADEQUATE
A.LUNA P-12 13.55 13.54 225 16.78 19.58 85.7 ADEQUATE
66
Design of Stormwater Drainage
C.M. Cruz Street
Pipe
Highest Lowest Diamter Actual Design Actual/Design Remarks
Conduit
Elevation Elevation Discharge Discharge
(m) (m) (mm) (L/s) (L/s) (%)
CM CRUZ P-1 9.49 9.48 1,000.00 1,069.42 1,645.72 65 ADEQUATE
CM CRUZ P-2 9.52 9.49 1,250.00 1,063.03 1,697.52 62.6 ADEQUATE
CM CRUZ P-3 9.55 9.52 1,250.00 1,055.02 1,702.03 62 ADEQUATE
CM CRUZ P-4 9.58 9.55 900 531.96 699.21 76.1 ADEQUATE
CM CRUZ P-5 9.61 9.58 900 518.91 701.33 74 ADEQUATE
CM CRUZ P-6 12 9.61 900 502.43 703.41 71.4 ADEQUATE
CM CRUZ P-7 12.01 12 900 485.06 702.69 69 ADEQUATE
CM CRUZ P-8 12.1 12.01 900 468.98 715.34 65.6 ADEQUATE
CM CRUZ P-9 12.15 12.1 900 451.75 700.15 64.5 ADEQUATE
CM CRUZ P-10 12.27 12.15 600 172.4 233.29 73.9 ADEQUATE
CM CRUZ P-11 12.3 12.27 600 154.59 234.02 66.1 ADEQUATE
CM CRUZ P-12 12.33 12.3 600 134.34 241.46 55.6 ADEQUATE
CM CRUZ P-13 12.35 12.33 500 116.37 144.2 80.7 ADEQUATE
CM CRUZ P-14 12.4 12.35 500 97.58 146.17 66.8 ADEQUATE
CM CRUZ P-15 12.55 12.4 500 78.83 142.59 55.3 ADEQUATE
CM CRUZ P-16 12.6 12.55 400 62.84 90.5 69.4 ADEQUATE
CM CRUZ P-17 12.95 12.6 400 48.09 73.98 65 ADEQUATE
CM CRUZ P-18 13 12.95 300 28.14 32.17 87.5 ADEQUATE
67
Design of Stormwater Drainage
F. Manalo Street
Pipe
Highest Lowest Diamter Actual Design Actual/Design Remarks
Conduit
Elevation Elevation Discharge Discharge
(m) (m) (mm) (L/s) (L/s) (%)
F.MANALO P-1 12.66 12.64 775 416.46 469.28 88.7 ADEQUATE
F.MANALO P-2 12.64 12.63 775 397.96 490.23 81.2 ADEQUATE
F.MANALO P-3 12.65 12.63 775 379.17 495.38 76.5 ADEQUATE
F.MANALO P-4 12.69 12.65 775 359.05 492.39 72.9 ADEQUATE
F.MANALO P-5 12.69 12.66 775 341.26 495.77 68.8 ADEQUATE
F.MANALO P-6 12.68 12.66 775 324.52 498.8 65.1 ADEQUATE
F.MANALO P-7 12.68 12.65 775 312.61 488.56 64 ADEQUATE
F.MANALO P-8 12.65 12.63 775 301.88 478.76 63.1 ADEQUATE
F.MANALO P-9 12.67 12.63 350 50.05 59.38 84.3 ADEQUATE
F.MANALO P-10 12.71 12.67 350 39.13 58.55 66.8 ADEQUATE
F.MANALO P-11 12.75 12.71 300 28.12 38.93 72.2 ADEQUATE
F.MANALO P-12 12.79 12.75 300 14.92 39.25 38 ADEQUATE
68
Design of Stormwater Drainage
J. Pueblo Street
Pipe
Highest Lowest Diamter Actual Design Actual/Design Remarks
Conduit
Elevation Elevation Discharge Discharge
(m) (m) (mm) (L/s) (L/s) (%)
J.PUEBLO P-1 12.66 12.64 300 29.15 36.46 80 ADEQUATE
J.PUEBLO P-2 12.66 12.63 400 53.59 80.51 66.6 ADEQUATE
J.PUEBLO P-3 12.65 12.63 400 71.74 81.53 88 ADEQUATE
J.PUEBLO P-4 12.68 12.65 450 89.04 124.26 71.7 ADEQUATE
J.PUEBLO P-5 12.69 12.68 600 182.75 233.57 78.2 ADEQUATE
J.PUEBLO P-6 12.69 12.66 675 199.96 311.65 64.2 ADEQUATE
J.PUEBLO P-7 12.68 12.66 675 221.4 315.95 70.1 ADEQUATE
J.PUEBLO P-8 12.68 12.63 675 245.24 305.55 80.3 ADEQUATE
69
4.1.5 HDPE
70
Table 4-2 Design Result of Stormwater Drainage using HDPE
71
Design of Stormwater Drainage
C.M. Cruz Street
Pipe
Highest Lowest Diamter Actual Design Actual/Design Remarks
Conduit
Elevation Elevation Discharge Discharge
(m) (m) (mm) (L/s) (L/s) (%)
CM CRUZ P-1 9.49 9.48 800.00 1,117.90 1,179.97 94.7 ADEQUATE
CM CRUZ P-2 9.52 9.49 1,000.00 1,110.25 1,217.11 91.2 ADEQUATE
CM CRUZ P-3 9.55 9.52 1,000.00 1,100.93 1,220.35 90.2 ADEQUATE
CM CRUZ P-4 9.58 9.55 800 544.68 663.96 82 ADEQUATE
CM CRUZ P-5 9.61 9.58 800 530.8 665.97 79.7 ADEQUATE
CM CRUZ P-6 12 9.61 800 513.44 667.95 76.9 ADEQUATE
CM CRUZ P-7 12.01 12 800 495.19 667.27 74.2 ADEQUATE
CM CRUZ P-8 12.1 12.01 800 478.34 679.28 70.4 ADEQUATE
CM CRUZ P-9 12.15 12.1 800 460.29 664.86 69.2 ADEQUATE
CM CRUZ P-10 12.27 12.15 500 174.85 186.51 93.7 ADEQUATE
CM CRUZ P-11 12.3 12.27 500 156.88 187.09 83.9 ADEQUATE
CM CRUZ P-12 12.33 12.3 500 136.8 193.04 70.9 ADEQUATE
CM CRUZ P-13 12.35 12.33 500 119.43 187.46 63.7 ADEQUATE
CM CRUZ P-14 12.4 12.35 400 99.69 104.8 95.1 ADEQUATE
CM CRUZ P-15 12.55 12.4 400 79.72 102.24 78 ADEQUATE
CM CRUZ P-16 12.6 12.55 350 63.29 82.4 76.8 ADEQUATE
CM CRUZ P-17 12.95 12.6 350 48.09 67.37 71.4 ADEQUATE
CM CRUZ P-18 13 12.95 300 28.14 41.82 67.3 ADEQUATE
Design of Stormwater Drainage
M. Santos Street
Pipe
Highest Lowest Diamter Actual Design Actual/Design Remarks
Conduit
Elevation Elevation Discharge Discharge
(m) (m) (mm) (L/s) (L/s) (%)
M.SANTOS P-1 12.68 12.64 200 13.82 16.3 84.8 ADEQUATE
M.SANTOS P-2 12.73 12.68 400 74.46 102.74 72.5 ADEQUATE
M.SANTOS P-3 12.76 12.73 350 61.08 72.5 84.2 ADEQUATE
M.SANTOS P-4 12.76 12.79 300 44.51 47.5 93.7 ADEQUATE
M.SANTOS P-5 12.79 12.8 250 28.42 29.48 96.4 ADEQUATE
M.SANTOS P-6 12.84 12.8 200 13.12 15.49 84.7 ADEQUATE
72
Pipe
Highest Lowest Diamter Actual Design Actual/Design Remarks
Conduit
Elevation Elevation Discharge Discharge
(m) (m) (mm) (L/s) (L/s) (%)
VILLAROSA P-1 12.15 12.01 600 268.84 304.95 88.2 ADEQUATE
VILLAROSA P-2 12.1 12.01 600 250.8 305.21 82.2 ADEQUATE
VILLAROSA P-3 12.15 12.1 550 230.65 242 95.3 ADEQUATE
VILLAROSA P-4 12.27 12.15 550 209.99 242.45 86.6 ADEQUATE
VILLAROSA P-5 12.33 12.27 550 187.28 238.82 78.4 ADEQUATE
VILLAROSA P-6 12.38 12.33 500 163.52 188.33 86.8 ADEQUATE
VILLAROSA P-7 12.38 12.35 500 143.61 187.04 76.8 ADEQUATE
VILLAROSA P-8 12.38 12.35 450 117.36 140.88 83.3 ADEQUATE
VILLAROSA P-9 12.38 12.34 400 94.32 103 91.6 ADEQUATE
VILLAROSA P-10 12.37 12.34 350 67.67 72.06 93.9 ADEQUATE
VILLAROSA P-11 12.37 12.36 350 40.56 72.7 55.8 ADEQUATE
VILLAROSA P-12 12.38 12.36 200 15.26 16.03 95.2 ADEQUATE
73
Pipe
Highest Lowest Diamter Actual Design Actual/Design Remarks
Conduit
Elevation Elevation Discharge Discharge
(m) (m) (mm) (L/s) (L/s) (%)
G.VALDERAMA P-1 9.46 9.45 600 263.06 282.82 93 ADEQUATE
G.VALDERAMA P-2 9.48 9.45 600 278.58 285.75 97.5 ADEQUATE
G.VALDERAMA P-3 9.53 9.48 500 146.95 186.79 78.7 ADEQUATE
G.VALDERAMA P-4 9.53 9.5 450 130.21 140.5 92.7 ADEQUATE
G.VALDERAMA P-5 9.53 9.5 450 108.68 140.44 77.4 ADEQUATE
G.VALDERAMA P-6 9.53 9.52 400 88.57 101.08 87.6 ADEQUATE
G.VALDERAMA P-7 9.52 9.49 350 69.08 74.53 92.7 ADEQUATE
G.VALDERAMA P-8 9.49 9.48 300 44.8 49.04 91.4 ADEQUATE
G.VALDERAMA P-9 9.5 9.48 250 23.12 29.59 78.1 ADEQUATE
74
4.1.6 Ductile Iron Pipe
75
Table 4-3 Design Result of Stormwater Drainage Using Ductile Iron Pipe
76
Design of Stormwater Drainage
F. Manalo Street
Pipe
Highest Lowest Diamter Actual Design Actual/Design Remarks
Conduit
Elevation Elevation
(m) (m) (mm) Discharge (L/s) Discharge (L/s) (%)
F.MANALO P-1 12.66 12.64 750 424.72 508.17 83.6 ADEQUATE
F.MANALO P-2 12.64 12.63 700 405.61 441.65 91.8 ADEQUATE
F.MANALO P-3 12.65 12.63 675 386.25 405.04 95.4 ADEQUATE
F.MANALO P-4 12.69 12.65 675 365.53 402.59 90.8 ADEQUATE
F.MANALO P-5 12.69 12.66 675 347.22 405.36 85.7 ADEQUATE
F.MANALO P-6 12.68 12.66 675 329.99 407.83 80.9 ADEQUATE
F.MANALO P-7 12.68 12.65 675 317.68 399.46 79.5 ADEQUATE
F.MANALO P-8 12.65 12.63 675 306.57 391.45 78.3 ADEQUATE
F.MANALO P-9 12.67 12.63 350 51.63 70.17 73.6 ADEQUATE
F.MANALO P-10 12.71 12.67 300 40.08 45.87 87.4 ADEQUATE
F.MANALO P-11 12.75 12.71 300 28.77 46.01 62.5 ADEQUATE
F.MANALO P-12 12.79 12.75 200 14.92 15.73 94.8 ADEQUATE
77
Design of Stormwater Drainage
Villarosa Street
Pipe
Highest Lowest Diamter Actual Design Actual/Design Remarks
Conduit
Elevation Elevation
(m) (m) (mm) Discharge (L/s) Discharge (L/s) (%)
VILLAROSA P-1 12.15 12.01 600 264.53 277.23 95.4 ADEQUATE
VILLAROSA P-2 12.1 12.01 600 247.27 277.47 89.1 ADEQUATE
VILLAROSA P-3 12.15 12.1 600 227.7 277.46 82.1 ADEQUATE
VILLAROSA P-4 12.27 12.15 550 207.34 220.41 94.1 ADEQUATE
VILLAROSA P-5 12.33 12.27 550 184.5 217.11 85 ADEQUATE
VILLAROSA P-6 12.38 12.33 500 160.17 171.21 93.6 ADEQUATE
VILLAROSA P-7 12.38 12.35 500 140.43 170.04 82.6 ADEQUATE
VILLAROSA P-8 12.38 12.35 450 114.84 128.07 89.7 ADEQUATE
VILLAROSA P-9 12.38 12.34 450 92.69 128.19 72.3 ADEQUATE
VILLAROSA P-10 12.37 12.34 400 66.83 93.53 71.5 ADEQUATE
VILLAROSA P-11 12.37 12.36 350 40.08 66.09 60.6 ADEQUATE
VILLAROSA P-12 12.38 12.36 250 15.26 26.43 57.8 ADEQUATE
78
Design of Stormwater Drainage
G. Valderama Street
Pipe
Highest Lowest Diamter Actual Design Actual/Design Remarks
Conduit
Elevation Elevation Discharge Discharge
(m) (m) (mm) (L/s) (L/s) (%)
G.VALDERAMA P-1 9.46 9.45 675 263.06 351.98 74.7 ADEQUATE
G.VALDERAMA P-2 9.48 9.45 675 278.02 355.63 78.2 ADEQUATE
G.VALDERAMA P-3 9.53 9.48 500 144.94 169.81 85.4 ADEQUATE
G.VALDERAMA P-4 9.53 9.5 500 128.87 169.17 76.2 ADEQUATE
G.VALDERAMA P-5 9.53 9.5 450 107.59 127.68 84.3 ADEQUATE
G.VALDERAMA P-6 9.53 9.52 400 87.71 91.89 95.5 ADEQUATE
G.VALDERAMA P-7 9.52 9.49 400 68.7 96.73 71 ADEQUATE
G.VALDERAMA P-8 9.49 9.48 350 44.8 67.25 66.6 ADEQUATE
G.VALDERAMA P-9 9.5 9.48 250 23.12 26.9 85.9 ADEQUATE
79
4.1.7 Designer’s Final Raw Ranking
Table 4-4 Summary of Final Estimated Values for Water Context
CONSTRAINTS
HDPE Reinforced Concrete Ductile Iron Pipe
Economic
Constructability
Sustainability
80
4.1.7.1 Computation of Final Rankings
Economic Constraint (Cost)
% difference = 1.50
Subordinate Rank = 10 – 1.50
Subordinate Rank = 8.50
% difference = 5.54
Subordinate Rank = 10 – 5.54
Subordinate Rank = 4.45
% difference = 1.87
Subordinate Rank = 10 – 1.87
Subordinate Rank = 8.13
81
Figure 4-8 Labor Cost Difference
DIP
4,452,583.89−1879010.08
% difference = 𝑥10
1765163.742
% difference = 5.78
Subordinate Rank = 10 – 5.78
Subordinate Rank = 4.22
% difference = 1.87
Subordinate Rank = 10 – 1.87
Subordinate Rank = 8.13
% difference = 5.78
Subordinate Rank = 10 – 5.78
Subordinate Rank = 4.22
82
Figure 4-11 Maintenance Cost Difference
% difference = 1.08
Subordinate Rank = 10 – 1.08
Subordinate Rank = 8.92
% difference = 0.03
Subordinate Rank = 10 – 0.03
Subordinate Rank = 9.97
83
Table 4-5 Water Context Final Designer’s Ranking
IMPORTANCE
DESIGN OF STORM WATER DRAINAGE AND SEWERAGE SYSTEM
(Scale 0-10)
Concrete
OVER-ALL
RANK
320.54 380 221.96
84
4.1.8 Trade-off Assessment
The comprehensive discussion presented below cover’s the designer’s justification in the rating criteria
above:
4.1.8.1 Economic Assessment
In this criterion, RCCP governed. RCCP got the highest point of five (5) since the estimated cost for the
design is PHP 14,360,971.59. The design is the most economical in the sense that, considering the initial
plastic material cost, it is much cheaper than the two other trade-offs.
4.1.8.2 Sustainability Assessment
In terms of sustainability, since the RCCP has the cheapest maintenance cost of PHP 469,752.52, it is
considered as the governing trade-off. Having the cheapest maintenance means longest service life which
results to being the most economical amongst the other trade-offs. Client can also consider that RC Pipe is
made of Reinforced Concrete actually strengthens as the time goes by.
4.1.8.3 Constructability Assessment
In this criterion, the assessment is based on the labor cost of construction and that cover the amount of work
needed. RCCP governed amongst the two other trade-offs having only Php 1,879,010.08 of labor cost based
on estimated total cost. It has the shortest period of installation also compare to two trade offs.
4.1.8.4 Serviceability Assessment
In terms of serviceability, the trade-off with the highest discharge efficiency will be considered as the
governing trade-off. With the amount of discharge of 82.43%, RCCP governed in this criterion, it serves as
an advantage that the pipe chosen has a high discharge efficiency that it maximize the designed stormwater
drainage and has the least excess capacity that the actual discharge it receives.
85
4.1.9.1 Economic Alternatives
Economic Comparison
35000000
30000000
25000000
20000000
15000000
10000000
5000000
86
4.1.9.2 Sustainability Alternatives
Sustainability Comparison
1200000
1000000
800000
600000
400000
200000
87
4.1.9.3 Constructability Alternatives
Constructability Comparison
5000000
4500000
4000000
3500000
3000000
2500000
2000000
1500000
1000000
500000
88
4.1.9.4 Serviceability Alternatives
Serviceability Comparison
84.0%
82.0%
80.0%
78.0%
76.0%
74.0%
72.0%
70.0%
68.0%
89
4.1.10.1 Sensitivity Analysis for Economic and Sustainability Constraint
Table 4-6 Results of Sensitivity Analysis for Economic vs. Sustainability Constraint
The table above shows the result of the alterations made to observe the variation between the Economic (Cost) and
Sustainability (Maintenace Cost) Constraints. There are no changes in the maintenance cost although the cost has
been optimized having an additional 5% to 20% to its total original cost because the cost of the project doesn’t affect
the maintenance to be used of the structure. Based on researches, the service life of the structure mainly depends
on the quality of the construction and the environment in which the structure is located.
90
Figure 4-18 Variation Between Economic and Sustainability Constraint (RC Pipe)
Figure 4-19 Variation Between Economic and Sustainability Constraint (HDPE Pipe)
91
Figure 4-20 Variation Between Economic and Sustainability Constraint (DIP Pipe)
92
4.1.10.2 Sensitivity Analysis for Economic and Constructability Constraint
Table 4-7 Results of Sensitivity Analysis for Economic and Constructability Constraint
The table above shows the result of the alterations made to observe the variation between the
Economic (Cost) and Constructability (Labor Cost) Constraints. We, as the designers chose the labor
cost as the factor to be optimized having an additional 5% to 20% to its total cost because based on
the computations, the manpower varies inversely with the number of working days. Also, based on the
observations made on the actual field, a large quantity of manpower induces lesser number of working
days
93
RC Pipe
3000000
2500000
2000000
1500000
1000000
500000
0
0 5 10 15 20
RC Pipe
Figure 4-22 Variation Between Economic and Constructability Constraint (RC Pipe)
HDPE Pipe
2500000
2000000
1500000
1000000
500000
0
0 5 10 15 20
HDPE Pipe
Figure 4-23 Variation Between Economic and Constructability Constraint (HDPE Pipe)
94
DIP Pipe
6000000
5000000
4000000
3000000
2000000
1000000
0
0 5 10 15 20
DIP Pipe
Figure 4-24 Variation Between Economic and Constructability Constraint (DIP Pipe)
Labor Cost
6000000
5000000
4000000
3000000
2000000
1000000
0
0 5 10 15 20
95
4.1.10.3 Sensitivity Analysis for Economic and Serviceability Constraint
Table 4-8 Results of Sensitivity Analysis for Economic and Serviceability Constraint
The table above shows the result of the alterations made to observe the variation between the Economic (Cost) and
Serviceability (Discharge Efficiency) Constraints. We, as the designers chose the cost of the pipes used as the factor
to be optimized having an additional 5% to 20% to its total cost. Based on the computations, the results, the efficiency
stays the same even if it increases the cost because, design discharge solely based on the designed diameter and
it did not affect the design because discharge varies on rainfall that the drainage receives.
96
RC Pipe
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
0 5 10 15 20
RC Pipe
Figure 4-26 Variation Between Economic and Serviceability Constraint (RC Pipe)
HDPE Pipe
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
0 5 10 15 20
HDPE Pipe
Figure 4-27 Variation Between Economic and Serviceability Constraint (HDPE Pipe)
97
DIP Pipe
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
0 5 10 15 20
DIP Pipe
Figure 4-28 Variation Between Economic and Serviceability Constraint (DIP Pipe)
Efficiency
0.84
0.82
0.8
0.78
0.76
0.74
0.72
0.7
0.68
0 5 10 15 20
Reinforced HDPE
Ductile Iron Pipe
Concrete
The table shows the summary of the comparison of values among the three trade-offs: Reinforced Concrete Pipe, HDPE
Pipe, and Ductile Iron Pipe. The comparison includes the values calculated for the different constraints: Maintenance Cost,
Efficiency of the material used in the designed system, Labor Cost, and the total design budget for each trade off.
99
Figure 4-30 General Design Process
Figure 4-4 shows the flow of the general process in the design of the proposed detention pipes. Identification of the
problem comes up first for the designers need to know the rationale for designing the detention pipe. Considering all
the design aspects (i.e. discharge required, area of catchment, rainfall data, etc.) and the constraints that will limit
the design of the system together with the proposed trade-offs, the designers can now proceed to the detailed design
of the system. The governing trade-off which is most effective one will be chosen as the final design.
100
4.2.3. Design Process for Underground Detention Tank
Start
Determine:
1. Wall height
Prepare plans and
2. Footing depth
Specifications
101
Assume Dimensions:
102
Figure 4-32 Design Process for Flood Wall
103
CONSTRUCTABILITY ₱ 164,562.44 ₱ 476,836.00 ₱ 202,509.21
(Duration)
SERVICEABILITY ₱ 989,774.85 ₱ 12,622,270 ₱ 1,012,546.05
(Efficiency)
SUSTAINABILITY ₱ 30,000 ₱ 20,000 ₱ 50,627.39
(Maintenance)
% difference = 9.11
Subordinate Rank = 10 – 9.11
Subordinate Rank = 0.89
DREDGING TRADE-OFF 3
Php. 1,484,398.22 −Php.1,341,230.00
% difference = 𝑥10
Php 1,484,398.22
% difference =0.67
Subordinate Rank = 10 – 0.67
Subordinate Rank = 9.33
Php.476836.00−Php.164562.44
% difference = 𝑥10
Php.476836.00
% difference = 6.55
104
Subordinate Rank = 10 – 6.55
Subordinate Rank = 3.45
DREDGING TRADE-OFF 3
Php.202509.21−Php.164,562.44
% difference = 𝑥10
Php.245,429.99
% difference = 1.87
Subordinate Rank = 10 – 1.87
Subordinate Rank = 8.13
105
❖ Serviceability Constraint (Cost)
Governing Rank: DETENTION TANK = 10.0
FLOOD WALL TRADE-OFF 2
Php. 12622270.00−Php.989,774.85
% difference = 𝑥10%
Php. 12622270.00
% difference = 9.22
Subordinate Rank = 10 – 9.22
Subordinate Rank = 0.78
DREDGING TRADE-OFF 3
Php. 1012546.05 −Php.989,774.85
% difference = 𝑥10%
Php. 1012546.05
% difference = 0.22
Subordinate Rank = 10 – 0.22
Subordinate Rank = 9.78
106
❖ Sustainability Constraint (Cost)
Governing Rank: FLOOD WALL = 10.0
DETENTION TANK TRADE-OFF 1
Php 30000−Php. 20000
% difference = 𝑥 10%
Php.30000
% difference = 3.33
Subordinate Rank = 10 – 3.33
Subordinate Rank = 6.67
% difference = 6.05
Subordinate Rank = 10 – 6.05
Subordinate Rank = 3.95
107
Table 4-5 Structural Context Final Designer’s Ranking
108
4.2.5.4 Serviceability Assessment
The Serviceability Constraint has given an importance factor of 10 in terms of efficiency of the structure to
repel storm water after it has been acquired by the storm water drainage.. The designers estimated the
serviceability in terms of estimating the maximum discharge capacity of each trade-off. The results show that
the Flood Wall which has the largest discharge capacity that can sustain stormwater drainage
1,500,000.00
1,450,000.00
1,400,000.00
1,350,000.00
1,300,000.00
1,250,000.00
Economic Comparison
109
4.2.6.2 Constructability Alternative
Serviceability Comparison
104000000.0%
103000000.0%
102000000.0%
101000000.0%
100000000.0%
99000000.0%
98000000.0%
97000000.0%
96000000.0%
Sustainability Comparison
25,000
20,000
15,000
10,000
5,000
110
4.2.7 Sensitivity Analysis for Constraints
One of the most important things to do after the validation is the sensitivity analysis of each trade-offs wherein the
designer will optimize the constraints of the design project having an additional 5% to 20% to a certain factor to observe
the variation between two constraints, taking the Economical Constraint as its basis. The results of the alteration will be
an additional choice for the client. The table below will indicate the effects of each case.
Table 4-6 Results of Sensitivity Analysis for Economic vs. Constructability Constraint
111
2,000,000.00
1,800,000.00
1,600,000.00
1,400,000.00
1,200,000.00
1,000,000.00
800,000.00
600,000.00
400,000.00
200,000.00
0.00
1 2 3 4 5
Economic Constructability
Figure 4-
44 Variation
Between Economic and Constructability Constraint
(TRADE-OFF 1)
2,000,000.00
1,800,000.00
1,600,000.00
1,400,000.00
1,200,000.00
1,000,000.00
800,000.00
600,000.00
400,000.00
200,000.00
0.00
1 2 3 4 5
Economic Constructability
112
1,800,000.00 Figure
4-46 Variation
1,600,000.00
Between
1,400,000.00 Economic and
1,200,000.00 Constructability
1,000,000.00 Constraint
(TRADE-OFF 3)
800,000.00
600,000.00
400,000.00
200,000.00
Labor Cost
300,000.00
0.00
1 2 3 4 5
250,000.00
Economic Constructability
200,000.00
150,000.00
100,000.00
50,000.00
0.00
0 5 10 15 20
The table above shows the result of the alterations made to observe the variation between the Economic (Cost)
and Sustainability (Maintenace Cost) Constraints. There are no changes in the maintenance cost although the cost has
been optimized having an additional 5% to 20% to its total original cost because the cost of the project doesn’t affect the
113
maintenance to
2,000,000.00 be used of the
1,800,000.00 structure.
Based on
1,600,000.00
researches, the
1,400,000.00 service life of
1,200,000.00 the structure
1,000,000.00 mainly depends
on the quality of
800,000.00
the construction
600,000.00
and the
400,000.00 environment in
200,000.00 which the
structure is
0.00
0 5 10 15 20 located.
Economic Sustainability
Figure
2,000,000.00
4-49 Variation
1,800,000.00 Between
1,600,000.00 Economic and
1,400,000.00 Sustainability
1,200,000.00
Constraint
(TRADE-OFF
1,000,000.00
1,800,000.00 2)
800,000.00
1,600,000.00
600,000.00
1,400,000.00
400,000.00
1,200,000.00
200,000.00
1,000,000.00
0.00
800,000.00 1 2 3 4 5
400,000.00
200,000.00
0.00
1 2 3 4 5
Economic Sustainability
114
Figure 4-50 Variation Between Economic and Sustainability Constraint
(TRADE-OFF 3)
10,000.00
5,000.00
0.00
0 5 10 15 20
Sustainability Constraint
4.2.7.3 Sensitivity Analysis for Economic and Serviceability Constraint
Table 4-8 Results of Sensitivity Analysis for Economic and Serviceability Constraint
The table above shows the result of the alterations made to observe the variation between the Economic (Cost) and
Serviceability (Discharge Efficiency) Constraints. We, as the designers chose the cost of the pipes used as the factor to be
optimized having an additional 5% to 20% to its total cost. Based on the computations, the results, the efficiency stays the
same even if it increases the cost because, design discharge solely based on the designed diameter and it did not affect
the design because discharge varies on rainfall that the drainage receives.
115
200000000.00%
180000000.00%
160000000.00% Figure 4-
52
140000000.00%
Variation
120000000.00% Between
100000000.00%
80000000.00%
60000000.00%
40000000.00%
20000000.00%
0.00%
0 5 10 15 20
Economic Serviceability
116
200000000.00%
180000000.00%
160000000.00%
140000000.00%
120000000.00%
100000000.00%
80000000.00%
60000000.00%
40000000.00%
20000000.00%
0.00%
0 5 10 15 20
Economic Serviceability
120000000.00%
100000000.00%
80000000.00%
60000000.00%
40000000.00%
20000000.00%
0.00%
0 5 10 15 20
Economic Serviceability
117
Figure Efficiency 4-
55 1,040,000.00
1,030,000.00
1,020,000.00
1,010,000.00
1,000,000.00
990,000.00
980,000.00
970,000.00
960,000.00
0 5 10 15 20
The designers have come up to a design of drainage system that is in line with the code and standards by using
multiple constraints and trade-offs. The design of storm water drainage had undergone analysis, multiple
assessments and design processes in accordance with the general objectives. Therefore, the designers were able
to design a drainage system for storm water that satisfies the criteria and carefully assessed the constraints. The
trade-offs that were given by the designers were analysed with supporting details and computations.
With the aid of software such as storm-cad and Microsoft excel, the designers were able to design a storm-water
drainage system in Barangay Bambang, Pasig City to control and prevent flooding during heavy rainfall. The design
analysis for each trade-off is adequate and the final raw ranking and sensitivity analysis were validated to choose
which trade-off fits in the project in Barangay Bambang, Pasig City.
Concluding up the design of drainage system, the designers will suggest the use of Reinforced Concrete to Engr.
Minwena P.Gamilla, Municipal Engineer in the Engineering Department from Pasig Municipal Hall as the material to
be used in the project because it is more economical with an estimated price of Php 14,360,971.59 compared to the
other trade-offs. The designers can now put up a solution regarding the flooding in Barangay Bambang, Pasig City
due to an inadequate of drainage system in the said area.
118
Figure 5-1 Manhole Cover Detail
119
Figure 5-3 Cross Section of Storm-water Drainage
120
Figure 5-4 Section of Road
5.2. Final Design Scheduling of Detention Tank
121
122
Figure 5-6 Cylindrical Detention Tank Top View
123
Figure 5-7 Cylindrical Detention Left Side
124
Figure 5-8 Cylindrical Detention Tank Right Side
125
Figure 5-9 Stormwater Drainage Design Layout
126
Figure 5-10 Storm Water Drainage Flow Network
127
APPEDIX A- Summary of Design Computation for Stormwater Drainage
Design of Stormwater Drainage
A. Luna Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
A.LUNA P-1 675 239.62 325.41 73.6 ADEQUATE
A.LUNA P-2 675 220.94 266.89 82.8 ADEQUATE
A.LUNA P-3 600 199.69 235.46 84.8 ADEQUATE
A.LUNA P-4 600 180.43 226.96 79.5 ADEQUATE
A.LUNA P-5 600 159.01 235.75 67.4 ADEQUATE
A.LUNA P-6 500 138.78 146.32 94.9 ADEQUATE
A.LUNA P-7 500 120.36 143.27 84 ADEQUATE
A.LUNA P-8 450 99.14 109.92 90.2 ADEQUATE
A.LUNA P-9 400 77.58 78.89 98.3 ADEQUATE
A.LUNA P-10 350 54.93 56.55 97.1 ADEQUATE
A.LUNA P-11 300 35.33 37.94 93.1 ADEQUATE
A.LUNA P-12 225 16.78 19.58 85.7 ADEQUATE
128
Design of Stormwater Drainage
F. Manalo Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
F.MANALO P-1 775 416.46 469.28 88.7 ADEQUATE
F.MANALO P-2 775 397.96 490.23 81.2 ADEQUATE
F.MANALO P-3 775 379.17 495.38 76.5 ADEQUATE
F.MANALO P-4 775 359.05 492.39 72.9 ADEQUATE
F.MANALO P-5 775 341.26 495.77 68.8 ADEQUATE
F.MANALO P-6 775 324.52 498.8 65.1 ADEQUATE
F.MANALO P-7 775 312.61 488.56 64 ADEQUATE
F.MANALO P-8 775 301.88 478.76 63.1 ADEQUATE
F.MANALO P-9 350 50.05 59.38 84.3 ADEQUATE
F.MANALO P-10 350 39.13 58.55 66.8 ADEQUATE
F.MANALO P-11 300 28.12 38.93 72.2 ADEQUATE
F.MANALO P-12 300 14.92 39.25 38 ADEQUATE
129
Design of Stormwater Drainage
Villarosa Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
VILLAROSA P-1 675 263.79 321.14 82.1 ADEQUATE
VILLAROSA P-2 675 246.38 321.42 76.7 ADEQUATE
VILLAROSA P-3 600 226.64 234.77 96.5 ADEQUATE
VILLAROSA P-4 600 206.29 235.21 87.7 ADEQUATE
VILLAROSA P-5 600 183.37 231.68 79.1 ADEQUATE
VILLAROSA P-6 600 159.1 235.58 67.5 ADEQUATE
VILLAROSA P-7 600 138.64 233.96 59.3 ADEQUATE
VILLAROSA P-8 500 112.95 143.53 78.7 ADEQUATE
VILLAROSA P-9 450 91.22 108.46 84.1 ADEQUATE
VILLAROSA P-10 400 65.82 79.14 83.2 ADEQUATE
VILLAROSA P-11 350 39.5 55.92 70.6 ADEQUATE
VILLAROSA P-12 300 15.26 36.37 42 ADEQUATE
130
Design of Stormwater Drainage
G. Valderama Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
G.VALDERAMA P-1 675 259.21 297.83 87 ADEQUATE
G.VALDERAMA P-2 700 273.87 331.56 82.6 ADEQUATE
G.VALDERAMA P-3 600 140.63 233.65 60.2 ADEQUATE
G.VALDERAMA P-4 600 124.66 232.76 53.6 ADEQUATE
G.VALDERAMA P-5 500 104.27 143.08 72.9 ADEQUATE
G.VALDERAMA P-6 500 85.85 140.97 60.9 ADEQUATE
G.VALDERAMA P-7 450 67.61 112.05 60.3 ADEQUATE
G.VALDERAMA P-8 400 44.39 81.25 54.6 ADEQUATE
G.VALDERAMA P-9 300 23.12 37.02 62.4 ADEQUATE
131
Design of Stormwater Drainage
A. Luna Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
A.LUNA P-1 600 242.69 309.01 78.5 ADEQUATE
A.LUNA P-2 600 223.3 253.43 88.1 ADEQUATE
A.LUNA P-3 550 201.53 242.71 83 ADEQUATE
A.LUNA P-4 550 181.78 233.95 77.7 ADEQUATE
A.LUNA P-5 500 160.28 188.47 85 ADEQUATE
A.LUNA P-6 500 139.86 190.21 73.5 ADEQUATE
A.LUNA P-7 450 120.88 140.63 86 ADEQUATE
A.LUNA P-8 450 99.56 142.89 69.7 ADEQUATE
A.LUNA P-9 400 77.9 102.56 76 ADEQUATE
A.LUNA P-10 350 55.14 73.51 75 ADEQUATE
A.LUNA P-11 300 35.46 49.32 71.9 ADEQUATE
A.LUNA P-12 200 16.78 18.59 90.3 ADEQUATE
132
F. Manalo Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
F.MANALO P-1 700 430.04 465.05 92.5 ADEQUATE
F.MANALO P-2 675 410.54 440.91 93.1 ADEQUATE
F.MANALO P-3 675 390.8 445.54 87.7 ADEQUATE
F.MANALO P-4 675 369.7 442.85 83.5 ADEQUATE
F.MANALO P-5 675 351.05 445.89 78.7 ADEQUATE
F.MANALO P-6 675 333.52 448.62 74.3 ADEQUATE
F.MANALO P-7 675 320.96 439.41 73 ADEQUATE
F.MANALO P-8 600 309.65 314.53 98.5 ADEQUATE
F.MANALO P-9 350 52 77.19 67.4 ADEQUATE
F.MANALO P-10 300 40.36 50.46 80 ADEQUATE
F.MANALO P-11 250 28.77 31.12 92.5 ADEQUATE
F.MANALO P-12 200 14.92 17.3 86.2 ADEQUATE
133
Design of Stormwater Drainage
V. Pozon Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
V. POZON P-1 800.00 558.01 639.07 87.3 ADEQUATE
V. POZON P-2 800.00 544.65 664.61 82 ADEQUATE
V. POZON P-3 800.00 530.22 647.52 81.9 ADEQUATE
V. POZON P-4 800.00 516.78 651.08 79.4 ADEQUATE
V. POZON P-5 800.00 504.07 640.04 78.8 ADEQUATE
V. POZON P-6 800.00 488.75 637.72 76.6 ADEQUATE
V. POZON P-7 800.00 475.47 640.38 74.2 ADEQUATE
V. POZON P-8 800.00 460.08 644.83 71.3 ADEQUATE
V. POZON P-9 300 447.37 453.37 98.7 ADEQUATE
134
Design of Stormwater Drainage
G. Valderama Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
G.VALDERAMA P-1 600 263.06 282.82 93 ADEQUATE
G.VALDERAMA P-2 600 278.58 285.75 97.5 ADEQUATE
G.VALDERAMA P-3 500 146.95 186.79 78.7 ADEQUATE
G.VALDERAMA P-4 450 130.21 140.5 92.7 ADEQUATE
G.VALDERAMA P-5 450 108.68 140.44 77.4 ADEQUATE
G.VALDERAMA P-6 400 88.57 101.08 87.6 ADEQUATE
G.VALDERAMA P-7 350 69.08 74.53 92.7 ADEQUATE
G.VALDERAMA P-8 300 44.8 49.04 91.4 ADEQUATE
G.VALDERAMA P-9 250 23.12 29.59 78.1 ADEQUATE
135
Design of Stormwater Drainage
A. Luna Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
A.LUNA P-1 600 242.69 280.92 86.4 ADEQUATE
A.LUNA P-2 600 223.3 230.39 96.9 ADEQUATE
A.LUNA P-3 550 201.53 220.65 91.3 ADEQUATE
A.LUNA P-4 550 181.78 212.68 85.5 ADEQUATE
A.LUNA P-5 500 160.28 171.34 93.5 ADEQUATE
A.LUNA P-6 500 139.86 172.92 80.9 ADEQUATE
A.LUNA P-7 450 120.88 127.85 94.5 ADEQUATE
A.LUNA P-8 450 99.56 129.9 76.6 ADEQUATE
A.LUNA P-9 400 77.9 93.23 83.5 ADEQUATE
A.LUNA P-10 350 55.14 66.83 82.5 ADEQUATE
A.LUNA P-11 300 35.46 44.84 79.1 ADEQUATE
A.LUNA P-12 200 16.78 16.9 99.3 ADEQUATE
136
F. Manalo Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
F.MANALO P-1 750 424.72 508.17 83.6 ADEQUATE
F.MANALO P-2 700 405.61 441.65 91.8 ADEQUATE
F.MANALO P-3 675 386.25 405.04 95.4 ADEQUATE
F.MANALO P-4 675 365.53 402.59 90.8 ADEQUATE
F.MANALO P-5 675 347.22 405.36 85.7 ADEQUATE
F.MANALO P-6 675 329.99 407.83 80.9 ADEQUATE
F.MANALO P-7 675 317.68 399.46 79.5 ADEQUATE
F.MANALO P-8 675 306.57 391.45 78.3 ADEQUATE
F.MANALO P-9 350 51.63 70.17 73.6 ADEQUATE
F.MANALO P-10 300 40.08 45.87 87.4 ADEQUATE
F.MANALO P-11 300 28.77 46.01 62.5 ADEQUATE
F.MANALO P-12 200 14.92 15.73 94.8 ADEQUATE
137
Design of Stormwater Drainage
Villarosa Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
VILLAROSA P-1 600 264.53 277.23 95.4 ADEQUATE
VILLAROSA P-2 600 247.27 277.47 89.1 ADEQUATE
VILLAROSA P-3 600 227.7 277.46 82.1 ADEQUATE
VILLAROSA P-4 550 207.34 220.41 94.1 ADEQUATE
VILLAROSA P-5 550 184.5 217.11 85 ADEQUATE
VILLAROSA P-6 500 160.17 171.21 93.6 ADEQUATE
VILLAROSA P-7 500 140.43 170.04 82.6 ADEQUATE
VILLAROSA P-8 450 114.84 128.07 89.7 ADEQUATE
VILLAROSA P-9 450 92.69 128.19 72.3 ADEQUATE
VILLAROSA P-10 400 66.83 93.53 71.5 ADEQUATE
VILLAROSA P-11 350 40.08 66.09 60.6 ADEQUATE
VILLAROSA P-12 250 15.26 26.43 57.8 ADEQUATE
138
Design of Stormwater Drainage
G. Valderama Street
Conduit Pipe Diamter Actual Discharge Design Discharge Actual/Design (%) Remarks
G.VALDERAMA P-1 675 263.06 351.98 74.7 ADEQUATE
G.VALDERAMA P-2 675 278.02 355.63 78.2 ADEQUATE
G.VALDERAMA P-3 500 144.94 169.81 85.4 ADEQUATE
G.VALDERAMA P-4 500 128.87 169.17 76.2 ADEQUATE
G.VALDERAMA P-5 450 107.59 127.68 84.3 ADEQUATE
G.VALDERAMA P-6 400 87.71 91.89 95.5 ADEQUATE
G.VALDERAMA P-7 400 68.7 96.73 71 ADEQUATE
G.VALDERAMA P-8 350 44.8 67.25 66.6 ADEQUATE
G.VALDERAMA P-9 250 23.12 26.9 85.9 ADEQUATE
139
APPENDIX D-Street Elevation
A. Luna Street 237.24m
Station Elevation (m)
STA 0+000 13.40
STA 0+020 13.36
STA 0+040 13.27
STA 0+060 13.30
STA 0+080 13.45
STA 0+100 13.12
STA 0+120 13.50
STA 0+140 13.51
STA 0+160 13.55
STA 0+180 13.54
STA 0+200 13.53
STA 0+220 13.55
STA 0+237.24 13.56
140
V. Porzon Street 241.36m
Station Elevation (m)
STA 0+000 9.52
STA 0+020 9.50
STA 0+040 9.53
STA 0+060 9.52
STA 0+080 9.51
STA 0+100 9.49
STA 0+120 9.48
STA 0+140 9.53
STA 0+160 9.50
STA 0+180 9.53
STA 0+200 9.52
STA 0+220 9.49
STA 0+240 9.48
STA 0+241.36 9.50
141
G Valderama Street 238.86m
Station Elevation (m)
STA 0+000 9.49
STA 0+020 9.48
STA 0+040 9.53
STA 0+060 9.50
STA 0+080 9.53
STA 0+100 9.52
STA 0+120 9.49
STA 0+140 9.48
STA 0+160 9.50
STA 0+180 9.49
STA 0+200 9.48
STA 0+220 9.50
STA 0+238.36 9.48
142
Jose Puedlo Street 158.81m
Station Elevation (m)
STA 0+000 12.64
STA 0+020 12.66
STA 0+040 12.63
STA 0+060 12.65
STA 0+080 12.69
STA 0+100 12.66
STA 0+120 12.68
STA 0+140 12.65
STA 0+160 12.63
STA 0+180 12.67
STA 0+200 12.71
STA 0+220 12.75
STA 0+240 12.79
STA 0+260 12.83
STA 0+280 12.87
STA 0+300 12.83
STA 0+320 12.85
STA 0+328.81 12.89
143
APPENDIX E- Computation for Backfill and Excavated Area of RCP
Design of Stormwater Drainage
A. Luna Street (237.24m)
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
A.LUNA P-1 0.675 0.86 0.580880482 20 22.472 10.85439037
A.LUNA P-2 0.675 0.86 0.580880482 20 22.472 10.85439037
A.LUNA P-3 0.6 0.75 0.441786467 20 18.05 9.214270662
A.LUNA P-4 0.6 0.75 0.441786467 20 18.05 9.214270662
A.LUNA P-5 0.6 0.75 0.441786467 20 18.05 9.214270662
A.LUNA P-6 0.5 0.67 0.352565236 20 15.138 8.086695289
A.LUNA P-7 0.5 0.67 0.352565236 20 15.138 8.086695289
A.LUNA P-8 0.45 0.6 0.282743339 20 12.8 7.145133224
A.LUNA P-9 0.4 0.54 0.229022104 20 10.952 6.371557911
A.LUNA P-10 0.35 0.48 0.180955737 20 9.248 5.628885263
A.LUNA P-11 0.3 0.4 0.125663706 20 7.2 4.686725877
A.LUNA P-12 0.225 0.34 0.090792028 17.24 5.027184 3.461929443
total 174.597184 92.81921501
144
Design of Stormwater Drainage
A. Luna Street (237.24m)
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
CM CRUZ P-1 1.00 1.23 1.19 20 40.898 17.13342237
CM CRUZ P-2 1.25 1.36 1.45 20 48.672 19.61855114
CM CRUZ P-3 1.25 1.36 1.45 20 48.672 19.61855114
CM CRUZ P-4 0.9 1.12 0.99 20 34.848 15.14393088
CM CRUZ P-5 0.9 1.12 0.99 20 34.848 15.14393088
CM CRUZ P-6 0.9 1.12 0.99 20 34.848 15.14393088
CM CRUZ P-7 0.9 1.12 0.99 20 34.848 15.14393088
CM CRUZ P-8 0.9 1.12 0.99 20 34.848 15.14393088
CM CRUZ P-9 0.9 1.12 0.99 20 34.848 15.14393088
CM CRUZ P-10 0.6 0.75 0.44 20 18.05 9.214270662
CM CRUZ P-11 0.6 0.75 0.44 20 18.05 9.214270662
CM CRUZ P-12 0.6 0.75 0.44 20 18.05 9.214270662
CM CRUZ P-13 0.5 0.67 0.35 20 15.138 8.086695289
CM CRUZ P-14 0.5 0.67 0.35 20 15.138 8.086695289
CM CRUZ P-15 0.5 0.67 0.35 20 15.138 8.086695289
CM CRUZ P-16 0.4 0.54 0.23 20 10.952 6.371557911
CM CRUZ P-17 0.4 0.54 0.23 20 10.952 6.371557911
CM CRUZ P-18 0.3 0.4 0.13 26.82 9.6552 6.284899401
Total 478.4532 218.165023
145
Design of Stormwater Drainage
F.MANALO P-1
F.MANALO P-2 ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
F.MANALO P-1 0.775 0.9 0.636172512 20 24.2 11.47654975
F.MANALO P-2 0.775 0.9 0.636172512 20 24.2 11.47654975
F.MANALO P-3 0.775 0.9 0.636172512 20 24.2 11.47654975
F.MANALO P-4 0.775 0.9 0.636172512 20 24.2 11.47654975
F.MANALO P-5 0.775 0.9 0.636172512 20 24.2 11.47654975
F.MANALO P-6 0.775 0.9 0.636172512 20 24.2 11.47654975
F.MANALO P-7 0.775 0.9 0.636172512 20 24.2 11.47654975
F.MANALO P-8 0.775 0.9 0.636172512 20 24.2 11.47654975
F.MANALO P-9 0.35 0.48 0.180955737 20 9.248 5.628885263
F.MANALO P-10 0.35 0.48 0.180955737 20 9.248 5.628885263
F.MANALO P-11 0.3 0.4 0.125663706 20 7.2 4.686725877
F.MANALO P-12 0.3 0.4 0.125663706 18.09 6.5124 4.239143556
Total 225.8084 111.996038
146
Design of Stormwater Drainage
VILLAROSA)
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
VILLAROSA P-1 0.675 0.755 0.447696588 20 18.2405 9.286568238
VILLAROSA P-2 0.675 0.755 0.447696588 20 18.2405 9.286568238
VILLAROSA P-3 0.6 0.75 0.441786467 20 18.05 9.214270662
VILLAROSA P-4 0.6 0.75 0.441786467 20 18.05 9.214270662
VILLAROSA P-5 0.6 0.75 0.441786467 20 18.05 9.214270662
VILLAROSA P-6 0.6 0.75 0.441786467 20 18.05 9.214270662
VILLAROSA P-7 0.6 0.75 0.441786467 20 18.05 9.214270662
VILLAROSA P-8 0.5 0.67 0.352565236 20 15.138 8.086695289
VILLAROSA P-9 0.45 0.6 0.282743339 20 12.8 7.145133224
VILLAROSA P-10 0.4 0.54 0.229022104 20 10.952 6.371557911
VILLAROSA P-11 0.35 0.48 0.180955737 20 9.248 5.628885263
VILLAROSA P-12 0.3 0.4 0.125663706 11.81 4.2516 2.76751163
Total 179.1206 94.6442731
147
Design of Stormwater Drainage
G.VALDERAMA
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
G.VALDERAMA P-1 0.675 0.755 0.447696588 20 18.2405 9.286568238
G.VALDERAMA P-2 0.7 0.87 0.59446787 20 22.898 11.0086426
G.VALDERAMA P-3 0.6 0.75 0.441786467 20 18.05 9.214270662
G.VALDERAMA P-4 0.6 0.75 0.441786467 20 18.05 9.214270662
G.VALDERAMA P-5 0.5 0.67 0.352565236 20 15.138 8.086695289
G.VALDERAMA P-6 0.5 0.67 0.352565236 20 15.138 8.086695289
G.VALDERAMA P-7 0.45 0.6 0.282743339 20 12.8 7.145133224
G.VALDERAMA P-8 0.4 0.54 0.229022104 20 10.952 6.371557911
G.VALDERAMA P-9 0.3 0.4 0.125663706 18.86 6.7896 4.419582502
Total 138.0561 72.83341638
148
APPENDIX F- Computation for Backfill and Excavated Area of HDPE
Design of Stormwater Drainage
A. Luna Street (237.24m)
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
A.LUNA P-1 0.6 0.657 0.339016332 20 14.68898 7.908653363
A.LUNA P-2 0.6 0.657 0.339016332 20 14.68898 7.908653363
A.LUNA P-3 0.55 0.559 0.245422003 20 11.52162 6.61317993
A.LUNA P-4 0.55 0.559 0.245422003 20 11.52162 6.61317993
A.LUNA P-5 0.5 0.559 0.245422003 20 11.52162 6.61317993
A.LUNA P-6 0.5 0.559 0.245422003 20 11.52162 6.61317993
A.LUNA P-7 0.45 0.457 0.164029621 20 8.63298 5.352387579
A.LUNA P-8 0.45 0.457 0.164029621 20 8.63298 5.352387579
A.LUNA P-9 0.4 0.406 0.129461892 20 7.34472 4.755482167
A.LUNA P-10 0.35 0.356 0.099538222 20 6.18272 4.191955567
A.LUNA P-11 0.3 0.324 0.082447958 20 5.49152 3.842560848
A.LUNA P-12 0.2 0.219 0.037668481 17.24 3.02667164 2.377267022
total 114.7760316 68.14206721
149
Design of Stormwater Drainage
CM CRUZ P
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
CM CRUZ P-1 0.80 0.81 0.519123839 20 20.52338 10.14090323
CM CRUZ P-2 1.00 1.02 0.810731967 20 29.57312 13.35848067
CM CRUZ P-3 1.00 1.02 0.810731967 20 29.57312 13.35848067
CM CRUZ P-4 0.8 0.81 0.515299735 20 20.402 10.0960053
CM CRUZ P-5 0.8 0.81 0.515299735 20 20.402 10.0960053
CM CRUZ P-6 0.8 0.81 0.515299735 20 20.402 10.0960053
CM CRUZ P-7 0.8 0.81 0.515299735 20 20.402 10.0960053
CM CRUZ P-8 0.8 0.81 0.515299735 20 20.402 10.0960053
CM CRUZ P-9 0.8 0.81 0.515299735 20 20.402 10.0960053
CM CRUZ P-10 0.5 0.508 0.202682992 20 10.02528 5.971620167
CM CRUZ P-11 0.5 0.508 0.202682992 20 10.02528 5.971620167
CM CRUZ P-12 0.5 0.508 0.202682992 20 10.02528 5.971620167
CM CRUZ P-13 0.5 0.508 0.202682992 20 10.02528 5.971620167
CM CRUZ P-14 0.4 0.406 0.129461892 20 7.34472 4.755482167
CM CRUZ P-15 0.4 0.406 0.129461892 20 7.34472 4.755482167
CM CRUZ P-16 0.35 0.356 0.099538222 20 6.18272 4.191955567
CM CRUZ P-17 0.35 0.356 0.099538222 20 6.18272 4.191955567
CM CRUZ P-18 0.3 0.305 0.073061664 26.82 6.8397705 4.880256667
Total 276.0773905 144.0955092
150
Design of Stormwater Drainage
M.SANTOS
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
M.SANTOS P-1 0.2 0.203 0.032365473 20 3.24818 2.600870542
M.SANTOS P-2 0.4 0.406 0.129461892 20 7.34472 4.755482167
M.SANTOS P-3 0.35 0.356 0.099538222 20 6.18272 4.191955567
M.SANTOS P-4 0.3 0.305 0.073061664 20 5.1005 3.639266717
M.SANTOS P-5 0.25 0.254 0.050670748 20 4.12232 3.108905042
M.SANTOS P-6 0.2 0.203 0.032365473 13.81 2.24286829 1.795901109
Total 28.24130829 20.09238114
151
Design of Stormwater Drainage
V. POZON
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
V. POZON P-1 0.80 0.81 0.515299735 20 20.402 10.0960053
V. POZON P-2 0.80 0.81 0.515299735 20 20.402 10.0960053
V. POZON P-3 0.80 0.81 0.515299735 20 20.402 10.0960053
V. POZON P-4 0.80 0.81 0.515299735 20 20.402 10.0960053
V. POZON P-5 0.80 0.81 0.515299735 20 20.402 10.0960053
V. POZON P-6 0.80 0.81 0.515299735 20 20.402 10.0960053
V. POZON P-7 0.80 0.81 0.515299735 20 20.402 10.0960053
V. POZON P-8 0.80 0.81 0.515299735 20 20.402 10.0960053
V. POZON P-9 0.3 0.305 0.073061664 11.36 2.897084 2.067103495
Total 166.113084 82.83514589
152
Design of Stormwater Drainage
J.PUEBLO
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
J.PUEBLO P-1 0.3 0.305 0.073061664 20 5.1005 3.639266717
J.PUEBLO P-2 0.35 0.356 0.099538222 20 6.18272 4.191955567
J.PUEBLO P-3 0.35 0.356 0.099538222 20 6.18272 4.191955567
J.PUEBLO P-4 0.4 0.406 0.129461892 20 7.34472 4.755482167
J.PUEBLO P-5 0.55 0.559 0.245422003 20 11.52162 6.61317993
J.PUEBLO P-6 0.55 0.559 0.245422003 20 11.52162 6.61317993
J.PUEBLO P-7 0.55 0.559 0.245422003 20 11.52162 6.61317993
J.PUEBLO P-8 0.6 0.61 0.292246657 18.81 12.341241 6.844081389
Total 71.716761 43.4622812
153
APPENDIX G- Computation for Backfill and Excavated Area of DIP
Design of Stormwater Drainage
A. Luna Street (237.24m)
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
A.LUNA P-1 0.6 0.635 0.316692174 20 13.9445 7.610656511
A.LUNA P-2 0.6 0.635 0.316692174 20 13.9445 7.610656511
A.LUNA P-3 0.55 0.532 0.22228653 20 10.71648 6.270749404
A.LUNA P-4 0.55 0.532 0.22228653 20 10.71648 6.270749404
A.LUNA P-5 0.5 0.532 0.22228653 20 10.71648 6.270749404
A.LUNA P-6 0.5 0.532 0.22228653 20 10.71648 6.270749404
A.LUNA P-7 0.45 0.48 0.180955737 20 9.248 5.628885263
A.LUNA P-8 0.45 0.48 0.180955737 20 9.248 5.628885263
A.LUNA P-9 0.4 0.429 0.144545463 20 7.91282 5.021910732
A.LUNA P-10 0.35 0.378 0.112220831 20 6.68168 4.437263376
A.LUNA P-11 0.3 0.326 0.083468975 20 5.53352 3.864140496
A.LUNA P-12 0.2 0.222 0.038707563 17.24 3.07016816 2.402849772
total 112.4491082 67.28824554
154
Design of Stormwater Drainage
C M Cruz Street 366.82m
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
CM CRUZ P-1 0.90 0.945 0.701380195 20 26.2205 12.1928961
CM CRUZ P-2 1.00 1.048 0.862605944 20 31.15008 13.89796111
CM CRUZ P-3 1.00 1.048 0.862605944 20 31.15008 13.89796111
CM CRUZ P-4 0.8 0.842 0.556819024 20 21.71528 10.57889953
CM CRUZ P-5 0.8 0.842 0.556819024 20 21.71528 10.57889953
CM CRUZ P-6 0.8 0.842 0.556819024 20 21.71528 10.57889953
CM CRUZ P-7 0.8 0.842 0.556819024 20 21.71528 10.57889953
CM CRUZ P-8 0.8 0.842 0.556819024 20 21.71528 10.57889953
CM CRUZ P-9 0.8 0.842 0.556819024 20 21.71528 10.57889953
CM CRUZ P-10 0.6 0.635 0.316692174 20 13.9445 7.610656511
CM CRUZ P-11 0.5 0.532 0.22228653 20 10.71648 6.270749404
CM CRUZ P-12 0.5 0.532 0.22228653 20 10.71648 6.270749404
CM CRUZ P-13 0.5 0.532 0.22228653 20 10.71648 6.270749404
CM CRUZ P-14 0.5 0.532 0.22228653 20 10.71648 6.270749404
CM CRUZ P-15 0.4 0.429 0.144545463 20 7.91282 5.021910732
CM CRUZ P-16 0.35 0.378 0.112220831 20 6.68168 4.437263376
CM CRUZ P-17 0.35 0.378 0.112220831 20 6.68168 4.437263376
CM CRUZ P-18 0.3 0.326 0.083468975 26.82 7.42045032 5.181812405
Total 304.3193903 155.2341195
155
Design of Stormwater Drainage
M Santos Street 113.81m
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
M.SANTOS P-1 0.2 0.222 0.038707563 20 3.56168 2.787528738
M.SANTOS P-2 0.4 0.429 0.144545463 20 7.91282 5.021910732
M.SANTOS P-3 0.35 0.378 0.112220831 20 6.68168 4.437263376
M.SANTOS P-4 0.35 0.378 0.112220831 20 6.68168 4.437263376
M.SANTOS P-5 0.3 0.326 0.083468975 20 5.53352 3.864140496
M.SANTOS P-6 0.2 0.222 0.038707563 13.81 2.45934004 1.924788594
Total 32.83072004 22.47289531
156
Design of Stormwater Drainage
V. Porzon Street 171.36m
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
V. POZON P-1 0.80 0.842 0.556819024 20 21.71528 10.57889953
V. POZON P-2 0.80 0.842 0.556819024 20 21.71528 10.57889953
V. POZON P-3 0.80 0.842 0.556819024 20 21.71528 10.57889953
V. POZON P-4 0.80 0.842 0.556819024 20 21.71528 10.57889953
V. POZON P-5 0.80 0.842 0.556819024 20 21.71528 10.57889953
V. POZON P-6 0.80 0.842 0.556819024 20 21.71528 10.57889953
V. POZON P-7 0.80 0.842 0.556819024 20 21.71528 10.57889953
V. POZON P-8 0.80 0.842 0.556819024 20 21.71528 10.57889953
V. POZON P-9 0.35 0.326 0.083468975 11.36 3.14303936 2.194831802
Total 176.8652794 86.82602804
157
Design of Stormwater Drainage
Jose Pueblo Street 158.81m
Conduit ID(m) OD(m) Area(sq. m) Length(m) Excavation(cu. m) Backfill(cu.m)
J.PUEBLO P-1 0.3 0.326 0.083468975 20 5.53352 3.864140496
J.PUEBLO P-2 0.35 0.378 0.112220831 20 6.68168 4.437263376
J.PUEBLO P-3 0.4 0.429 0.144545463 20 7.91282 5.021910732
J.PUEBLO P-4 0.4 0.429 0.144545463 20 7.91282 5.021910732
J.PUEBLO P-5 0.55 0.582 0.266033207 20 12.23048 6.90981585
J.PUEBLO P-6 0.55 0.582 0.266033207 20 12.23048 6.90981585
J.PUEBLO P-7 0.6 0.635 0.316692174 20 13.9445 7.610656511
J.PUEBLO P-8 0.6 0.635 0.316692174 18.81 13.11480225 7.157822449
Total 79.56110225 46.933336
158
APPENDIX H: DETENTION TANK
Step 1: Identify peak discharge from site and maximum allowable peak discharge
𝐴 = 18 ℎ𝑒𝑐𝑡𝑎𝑟𝑒𝑠
𝐶𝑝𝑜𝑠𝑡 = 0.7
𝑡𝑐 = 15 𝑚𝑖𝑛𝑠
8913 8913
𝑖10 = = = 174.76𝑚𝑚/ℎ𝑟
𝑡𝑐 + 36 15 + 36
𝐶𝑝𝑜𝑠𝑡 𝑥 𝑖10 𝑥 𝐴 0.7 𝑥 174.76 𝑥 18
𝑄𝑝𝑜𝑠𝑡 = = = 6.1166𝑚3 /𝑠
360 360
𝐶𝑡𝑎𝑟𝑔𝑒𝑡 𝑥 𝑖10 𝑥 𝐴 0.55 𝑥 174.76 𝑥 18
𝑄𝑡𝑎𝑟𝑔𝑒𝑡 = = = 4.806𝑚3 /𝑠
360 360
𝐾3 = 𝑡𝑐 + 36 = 15 + 36 = 51
159
36𝐾1 𝐾3 36𝑥5199.25𝑥51
𝑡𝑥𝑚𝑎𝑥 = −𝐾3 + √ = −51 + √ = 17.363𝑚𝑖𝑛𝑠
𝐾2 2042.5625
160
Step 3: Determine detention tank configuration
𝐴𝑠𝑠𝑢𝑚𝑒 𝑑 = 6𝑚
𝑉𝑡 557.062
𝑀𝑖𝑛𝑖𝑚𝑢𝑚 𝑎𝑟𝑒𝑎 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = = = 92.844𝑚2
𝑑 6
𝜋
𝐷𝑒𝑡𝑒𝑛𝑡𝑖𝑜𝑛 𝑡𝑎𝑛𝑘 𝑎𝑟𝑒𝑎 = 𝑥𝑑 2
4
𝜋 2
92.844 = 𝑥 𝑑
4
𝑑 = 10.87𝑚 = 11𝑚m
etention tank volume=π/4 x 11^2x6=570.199m^3
𝑚3 𝜋𝑑 2 𝑑
4.806 = 0.6 𝑥 𝑥 √2 𝑥 9.81 𝑥 (5 − ( ))
𝑠 4 2
𝑑 = 1.043𝑚
161
APPENDIX I: DETENTION TANK (STRUCTURAL)
Depth of water = 4 mm
reeboard=1.3 m
H = 6 mm
iameter of tank=11 m
@ 2m from topp
=γ_w x H x D/2=9.81211/2=107.91kN/m
T 107910
Ast required = = = 830.077 mm2
σst 130
𝐏𝐫𝐨𝐯𝐢𝐝𝐞 𝟏𝟏 𝐩𝐜𝐬 − 𝟏𝟎 𝐦𝐦 𝐝𝐢𝐚𝐦𝐞𝐭𝐞𝐫 @ 𝟐𝟓𝟎 𝐦𝐦 𝐜 − 𝐜
𝐓𝐡𝐢𝐜𝐤𝐧𝐞𝐬𝐬 𝐨𝐟 𝐰𝐚𝐥𝐥l
σ_st=T/A_gtm-1A_st=323730/100 x t x 9.33-12490.231
t = 65.83 mm = 100 mm
0.24
Ast min = 𝑥 1000 𝑥 100 = 240 𝑚𝑚
100
𝐏𝐫𝐨𝐯𝐢𝐝𝐞 𝟒𝐩𝐜𝐬 − 𝟏𝟎 𝐦𝐦 𝐝𝐢𝐚𝐦𝐞𝐭𝐞𝐫 @ 𝟐𝟎𝟎 𝐦𝐦 𝐜 − 𝐜
162
APPENDIX J: FLOOD WALL (STRUCTURAL)
163
Table 4.1 Soil Factorsfor Floodwall Design
❖ 𝑦𝑤 (Freshwater) = 9.81𝐾𝑁/𝑚3
❖ Area of potential normal impact loading, 𝐶B = 0.2 (moderate upstream blocking)
❖ 𝐶Str = 0.8
❖ Expected flood velocity, V (m/sec)
Dimensional Information
Based on DPWH the floodwall height shall include freeboard, but for a large river or in the place with high wave
length, the floodwall may be higher than a man’s height, where river is not at sight. Also the height shall not
impair the scenic views, etc. The height shall have stability from structural standpoint.
❖ H = 2𝑚
❖ 𝐷𝑡 = 1.2m
❖ 𝐷 = 𝐷ℎ = 1.5m
❖ 𝑡𝑓𝑡𝑔 = 0.3m
❖ 𝐵 = 1.5m
164
❖ 𝐴ℎ = 0.6m
❖ 𝐶 = 0.5m
❖ 𝑡𝑤𝑎𝑙𝑙 = 0.4m
where:
fbuoy1 = buoyancy force due to hydrostatic pressure at the floodwall heel acting at an approximate distance of B/3 from
the heel (KN/m)
fbuoy2 = buoyancy force due to hydrostatic pressure at the floodwall toe, acting at an approximate distance of B/3 from
the toe (KN/m)
yw = specific weight of water (9.81 KN/m for fresh water and 10.05 KN/m for saltwater)
The choice of wall thickness depends on the wall material, the strength of the material, and the height of the wall.
Typical wall thicknesses are 8, 12, and 16 inches for masonry, concrete, or masonry/ concrete walls. The footing width
depends on the magnitude of the lateral forces, allowable soil bearing capacity, dead load, and the wall height. The
typical footing width is the proposed wall height. Typically, the footing is located under the wall in such a manner that
1/3 of its width forms the toe and 2/3 of the width forms the heel of the wall
165
❖ H = 2𝑚
❖ 𝐷𝑡 = 1.2m
❖ 𝐷 = 𝐷ℎ = 1.5m
❖ 𝑡𝑓𝑡𝑔 = 0.3m
Step 2: Determine dimensions
❖ 𝐵 = 1.5m
❖ 𝐴ℎ = 0.6m
❖ 𝐶 = 0.5m
❖ 𝑡𝑤𝑎𝑙𝑙 = 0.4m
Wall and footing to be reinforced concrete having unit weight (Sg )
Step 3: Calculate forces.
Since Fn acts only at a single point, we will not include loading into the uniform lateral floodwall loading. Once the
floodwall is sized, we will evaluate the wall perpendicular to flow to determine ability to resist the impact loading. If
necessary this wall will be redesigned to resist impact loads. This process will avoid overdesigning of the entire floodwall.
1 1
❖ 𝐹𝑝 = 2 [𝑘𝑝(𝑦𝑠𝑜𝑖𝑙 − 𝑦𝑤) + 𝑦𝑤 ]𝐷𝑡2 = 2
[3.68(19 − 9.81) + 9.81 ]1.22 = 31.4791𝐾𝑁/𝑚
166
❖ 𝑤𝑤ℎ = Aℎ (H − 𝑡𝑓𝑡𝑔)(𝑦𝑤) = 0.61 (2 − 0.3)(9.81) = 10.173𝐾𝑁/𝑚
❖ 𝑊𝐺 = 𝑤𝑤𝑎𝑙𝑙 + 𝑤𝑓𝑡𝑔 + 𝑤𝑠𝑡 + 𝑤𝑠ℎ + 𝑤𝑤ℎ =
❖ 𝑊𝐺 = 16.0208 + 10.602 + 8.55 + 6.727 + 10.173 = 52.0728𝐾𝑁/𝑚
52.0728𝐾𝑁 23.544𝐾𝑁
❖ 𝐹𝑣 = 𝑊𝐺 − 𝑓𝑏𝑢𝑜𝑦 = 𝑚
− 𝑚
= 75.6168𝐾𝑁/𝑚
𝑀𝑜 = 44.44𝐾𝑁𝑚m
❖ R=wwallC+twall/2+wftgC/2+wstB/2+wshB-Ah/2+ wwhB-Ah/2+Fp(Dt/3)=
0.4 0.5 1.5 0.61 1.2
❖ 𝑀𝑅 = 16.0208(0.5 + )+ 10.60( 2 ) + 8.55( 2 ) + 6.727(1.5 − )+ 31.4791( ) =
2 2 3
❖ = 53.0642𝐾𝑁𝑚m
❖ SOT=MR/MO=42.74KNm/40.9074KNm=1.2971<1.5 therefore Not OK for Over Turning
Try increasing the footing size to overcome the overturning moment. Assume B = 2m; Ah = 1.2m; and C =
0.6m. This requires revision of Steps 3 and 4 for which the results are shown below. fsta, fdif , fdh, Fsta, Fp, wwall
will not change. Recompute vertical forces.
1 1
❖ 𝐹𝑝 = 2 [𝑘𝑝(𝑦𝑠𝑜𝑖𝑙 − 𝑦𝑤) + 𝑦𝑤 ]𝐷𝑡2 = 2
[3.68(19 − 9.81) + 9.81 ]1.22 = 31.4791𝐾𝑁/𝑚
167
Step 4: Check sliding.
𝑀𝑜 = 55.802𝐾𝑁𝑚m
❖ R=wwallC+twall/2+wftgC/2+wstB/2+wshB-Ah/2+ wwhB-Ah/2+Fp(Dt/3)=
0.4 0.6 2 1.2 1.2
❖ 𝑀𝑅 = 16.0208 (0.6 + 2
) + 14.14 ( 2 ) + 10.26 (2) + 13.2336 (2 − 2
)+ 20.0124(2 − 2
)+
1.2
31.4791( ) = 86.4547𝐾𝑁𝑚
3
𝑀𝑅 86.4547𝐾𝑁𝑚
❖ 𝐹𝑆𝑂𝑇 = = 55.802𝐾𝑁𝑚 = 1.55 < 1.5 therefore OK for Over Turning
𝑀𝑂
𝐵 (𝑀𝑅−𝑀𝑂) 2 (86.4547𝐾𝑁𝑚−55.802𝐾𝑁𝑚) 7
❖ 𝑒 =( )−( ) = (2) − ( 42.2768𝐾𝑁 ) = 0.275 < 6 therefore OK
2 𝐹𝑣
𝑚
𝐻 2
❖ 𝑀𝑏 = 𝐹𝑆𝑡𝑎 ( − 𝑡𝑓𝑡𝑔) = 2.62730 ( − 0.3) = 0.9633𝐾𝑁𝑚
3 3
❖ According to ENGINEERING PRINCIPLES AND PRACTICES for Retrofitting Flood-Prone Residential
Structures, df is typically the floodwall thickness minus 0.09 m to allow a minimum of 0.08m between
the reinforcing steel and the floodwall edge.
❖ Diameter should be a multipliable by 6
168
𝑀𝑏 0.9633𝐾𝑁𝑚
❖ 𝐴𝑠 = ( 1000
)=( 1000
) = 4.1432𝑥10−4 𝑚2
7.5𝑑𝑓 7.5(0.4−0.09)
4𝐴𝑠
❖ 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 = √ = 0.0229m ≈ 22.97mm ≈ 24mm
𝜋
❖ 𝐴𝑠 = ( 1000
)=( 1000
) = 8.5796𝑥10−4 𝑚2
7.5𝑑𝑓 7.5(0.3−0.09)
4𝐴𝑠
❖ 𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 = √ = 0.0331m ≈ 33.31mm ≈ 36mm
𝜋
❖ 𝑀𝑏 = (𝑞 + 2𝑞𝑚𝑎𝑥) ( ) = ( + 2( )) ( )
6 𝑚2 𝑚2 6
= 7.3357𝐾𝑁𝑚m
❖ s=Mb/1000/7.5df=7.3357KNm/1000/7.5(0.3-0.09)=4.6576x10^-4m^2
4𝐴𝑠
𝑑𝑖𝑎𝑚𝑒𝑡𝑒𝑟 = √ = 0.0244m ≈ 24.4mm ≈ 24mm
𝜋
169
APPENDIX K: DREDGING (STRUCTURAL)
❖ Basic Conditions
Study of the backfill site was made according to following items as basic condition.
Given:
Area = 1160 m2
Height = 3m
• 𝑉 = 𝐻∗𝐴
• V = 3m*1160m2 = 3480 m3
❖ Cycle Time
170
𝑉𝑜𝑙𝑢𝑚𝑒 3480
𝑇𝑑 = = = 38.67ℎ
2 ∗ 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝑏𝑎𝑐𝑘ℎ𝑜𝑒 2 ∗ 45
• Unloading
𝑉𝑜𝑙𝑢𝑚𝑒 3480
𝑇𝑢 = = = 23.5ℎ
2 ∗ 74 2 ∗ 74
• Return trip
𝐿 645
𝑇𝑟 = = = 87.16ℎ
𝐶𝑠𝑝𝑒𝑒𝑑 7.4
• Total hour
𝑇𝑡 = 𝑇𝑑 + 𝑇𝑔 + 𝑇𝑢 + 𝑇𝑟 = 236.5ℎ
100
( 0.7 )
𝑄ℎ = = 20𝑚3 /ℎ
7
148 148
𝑁= = = 7.4 = 8
𝑄ℎ 20
171
Appendix L (Final Estimates for Stormwater Drainage)
ESTIMATE(STORMWATER DRAINAGE)
Item no. Description Quantity Unit Unit Cost Amount (₱)
TOTAL ₱ 16,895,552.92
REINFORCED CONCRETE PIPES
172
ESTIMATE(STORMWATER DRAINAGE)
Item no. Description Quantity Unit Unit Cost Amount (₱)
TOTAL ₱ 14,360,971.59
HDPE
173
ESTIMATE(STORMWATER DRAINAGE)
Item no. Description Quantity Unit Unit Cost Amount (₱)
SUB-TOTAL ₱ 3,185,169.25
TOTAL ₱ 5,640,299.42
Ductile Iron Pipe
174
Length=645m=2116.1417ft
INITIAL ESTIMATES
Unit
Item Height(Feet) Price/Length Price(Peso)
Floodwall 3 5500 11638779.35
175
INITIAL ESTIMATES
Item Height(m) Area (m^2) Unit Price/Volume Price
floodwall 3 1160 435 1500000
176
DETENTION TANK
Design Volume 468m3
Depth of Aggregate Subbase 500 mm
Depth of Pavement 300 mm
Structural Piece Detail
• Diameter 11 m
• Height 6m
• Unit Top 20 inches
• Unit Base 0 inches
• Unit Side Wall 15 inches
• Unit End Wall 15 inches
• Perimeter Wall 15 inches
Earthworks
• Excavation Cost ₱ 240,000.00
• Labor Cost (5 laborers) ₱ 6,000.00
• Equipment Cost ₱ 7,000.00
• No. of Working Days 6 days
Installation
• Transportation and Equipment ₱ 15,000.00
• Material (Precast) ₱ 1,741,646.25
• Labor Cost ₱ 14,000.00
• No. of Working Days 4 days
• Sub - Total Cost ₱ 2,023,646.25
Other Requirements
• Contigencies (5%) ₱ 101,182.31
• VAT (12%) ₱ 242,837.55
• Overall Cost ₱ 2,367,666.11
177
FINAL ESTIMATE(Floodwall)
Item Unit
Description Quantity Unit Amount (₱)
no. Cost
I. Other General Requirements ₱ 1,150,397.81
II.A. Construction survey and staking 1 55208.91 55208.91
II.B. Project Billboard 1 5812.9 5812.9
II.C. Mobilization and Demolization 2L.S. 544688 1089376
Backfilling 822.3376 cu.m 1000 0
SUB-TOTAL ₱ 12,622,270.01
TOTAL ₱ 15,077,400.18
178
ESTIMATE(Dredging)
Item no. Description Quantity Unit Unit Cost Amount (₱)
SUB-TOTAL ₱ 1,012,546.05
TOTAL ₱ 1,437,815.39
179
Cylindrical Rectangular Detention Tank
ITEM DESCRIPTION QTY UNIT UNIT COST Amount (₱)
I. Earthworks ₱ 30,594.00
· Excavation 571 m3 300 171,300
· Dump Truck 9 Hrs 900 8,100
· Backhoe 11 Hrs 1500 16,500
· Fuel, oil, lubricants 6 Lot 999 5,994
II. Concrete Works ₱ 933,679.85
· Portland Cement 2586 Bags 225 581,850.00
· Sand 143.605 m3 850 122,064.25
· Gravel G-3/4 287.207 m3 800 229,765.60
III. Rebars ₱ 1,375.00
· 10 mm dia. X 6 mts. DSB Grade
11 Pcs 125 1,375.00
33
IV. Formworks ₱ 54,720.00
· 2” x 2” x 8” Rough Good Lumber 40 pcs 120 4,800.00
· Ord. Plywood ½” x 4’ x 8’ 40 Pcs 750 30,000.00
· C.W. Nails ASSTD 40 Kilo 48 1,920.00
· G.I. Wire #16 12 Rolls 1500 18,000.00
V. Equipment ₱ 19,000.00
· Concrete Mixer 4 Hrs 2000 8,000.00
· Concrete Pump Truck 4 Hrs 2000 8,000.00
· Crane 2 Hr 1500 3,000.00
Persons/per
VI. Manpower 120 500 ₱ 60,000.00
27 days
SUB - TOTAL
₱ 1,099,368.85
COST
180
CE509 – CE PROJECTS 2
MINUTES OF THE MEETING
ATTENDANCE
PRESENT:
1. Engr. Yenko Tandoc
2. Aguillon, Edralyn
3. Barreda, Maria Claudette
4. Magboo, James Matthew
Structure:
• Detention Tank/Pipe
Final Trade-offs:
• HDPE Detention Pipe
• CSP Detention Pipe
• RCCP Detention Pipe
There being no matter to be discussed, the meeting was adjourned at 7:30 PM.
181
TECHNOLOGICAL INSTITUTE OF THE PHILIPPINES
Quezon City
CE509 – CE PROJECTS 2
MINUTES OF THE MEETING
ATTENDANCE
PRESENT:
1. Engr. Sean Lawrence Malinao
2. Aguillon, Edralyn
3. Barreda, Maria Claudette
4. Magboo, James Matthew
There being no matter to be discussed, the meeting was adjourned at 12:00 PM.
182
TECHNOLOGICAL INSTITUTE OF THE PHILIPPINES
Quezon City
CE509 – CE PROJECTS 2
MINUTES OF THE MEETING
ATTENDANCE
PRESENT:
1. Engr. Yenko Tandoc
2. Aguillon, Edralyn
3. Barreda, Maria Claudette
4. Magboo, James Matthew
There being no matter to be discussed, the meeting was adjourned at 7:30 PM.
183
TECHNOLOGICAL INSTITUTE OF THE PHILIPPINES
Quezon City
CE509 – CE PROJECTS 2
MINUTES OF THE MEETING
ATTENDANCE
PRESENT:
1. Engr. Sean Lawrence Malinao
2. Aguillon, Edralyn
3. Barreda, Maria Claudette
4. Magboo, James Matthew
There being no matter to be discussed, the meeting was adjourned at 4:00 PM.
184
TECHNOLOGICAL INSTITUTE OF THE PHILIPPINES
Quezon City
CE509 – CE PROJECTS 2
MINUTES OF THE MEETING
ATTENDANCE
PRESENT:
1. Engr. Sean Lawrence Malinao
2. Aguillon, Edralyn
3. Barreda, Maria Claudette
4. Magboo, James Matthew
185
TECHNOLOGICAL INSTITUTE OF THE PHILIPPINES
Quezon City
CE509 – CE PROJECTS 2
MINUTES OF THE MEETING
ATTENDANCE
PRESENT:
5. Engr. Sean Lawrence Malinao
6. Aguillon, Edralyn
7. Barreda, Maria Claudette
8. Magboo, James Matthew
186
CURRICULUM VITAE
187
EDRALYN AGUILLON
CIVIL ENGINEERING
CAREER OBJECTIVE
To establish a career in engineering where i can demonstrate the learning outcomes of Civil Engineering program of Technological Institute of
the Philippines, a program accredited by the US-based outcomes-oriented ABET ( Accreditation Board for Engineering Technology),
Engineering Accreditation Commission
.
DESIGN PROJECTS COMPLETED/ RESEARCHES
Having graduated from TIP with its orientation towards outcome-based education, I have acquired and can demonstrate the following student
acquire outcomes (knowledge, skills and attitudes) necessary to the practice of the computing profession:
• Analyze complex problems and identify and define the computing requirements appropriate for solution.
• Use modern techniques and tools of the computing practice in complex activities.
• Understand professional, ethical, legal, security and social issues and responsibilities relevant to professional computing.
188
OTHER SKILLS
Goal Oriented
Good Communication Skills
Adaptability to change
Multitasking
Honesty
Loyalty
Sociable
Helpful
Knowledge-Based Skills
Making a document using MS Word
Making a substantial powerpoint presentation
REFERENCES
189
MARIA CLAUDETTE BARREDA
CIVIL ENGINEERING
Technological Institute of the Philippines (TIP) QC
Address: B27 L3 PHASE 3 VILLA ST CENTRAL BICUTAN TAGUIG
Email Address: barreda.claudette@gmail.com
Cellular No.: +639195158636
CAREER OBJECTIVE
To establish a career in the field of Civil Engineering where I can demonstrate the learning outcomes of the Civil Engineering program of the
Technological Institute of the Philippines (TIP), a proram accredited by the US-based outcomes-oriented ABET (Accreditation Board for
Engineering and Technology), Computing Accreditation Commission. To learn more and continue acquiring knowledge about different
concepts and technical skills related to my program and enhance skills I have obtained from my previous experiences as a Civil Engineering
student. I want to use the knowledge I have and soon to be acquired to contribute to the welfare of our society and also be able to share my
knowledge to others.
Having graduated from TIP with its orientation towards outcome-based education, I have acquired and can demonstrate the following
student acquire outcomes (knowledge, skills and attitudes) necessary to the practice of the computing profession:
Analyze complex problems and identify and define the computing requirements appropriate for solution.
Use modern techniques and tools of the computing practice in complex activities.
Understand professional, ethical, legal, security and social issues and responsibilities relevant to professional computing.
190
OTHER SKILLS
REFERENCES
Emmanuel Lazo
Faculty Member
Technological Institute of the Philippines Quezon City emlazo_10@yahoo.com.ph +639455366909
Engr. Mico Cruzado
Faculty Member
Techonological Institute of the Philippines mico.p.cruzado@gmail.com 09989596026
191
JAMES MATTHEW MAGBOO
CIVIL ENGINEERING
Technological Institute of the Philippines (TIP) QC
Address: 2 B 14L 6-BP Towerville Gaya-Gaya San Jose del Monte Bulacan
Email Address: semajwehttam@gmail.com
Cellular No.: +639159893279
CAREER OBJECTIVE
To establish a career in information technology where I can demonstrate the learning outcomes of the Civil Engineering program of the
Technological Institute of the Philippines (TIP), a proram accredited by the US-based outcomes-oriented ABET (Accreditation Board for
Engineering and Technology), Computing Accreditation Commission.
An Evaluation of the Influence of Corn Cob Ash as an Additive Component on the Stabilization of Mud Blocks
October 2017
The Use of Chicken Bone Ash as Partial Replacement of Cement in a Concrete Mix
October 2017
Having graduated from TIP with its orientation towards outcome-based education, I have acquired and can demonstrate the following
student acquire outcomes (knowledge, skills and attitudes) necessary to the practice of the computing profession:
Analyze complex problems and identify and define the computing requirements appropriate for solution.
Use modern techniques and tools of the computing practice in complex activities.
Understand professional, ethical, legal, security and social issues and responsibilities relevant to professional computing.
192
Seminar Room A and B, Building 1, Technological Institute of the Philippines, Quezon City
August 14, 2017
Well Grounded: Withstanding Impact X Fortifying the Future. A seminar on earthquake & ground improvement
Seminar Room A and B, Building 1, Technological Institute of the Philippines, Quezon City
March 07, 2018
OTHER SKILLS
Proficient in AutoCAD
Ability to Work in different environment
Skilled in using Microsoft Office
Proficient working under pressure
Good written and verbal communication
skills
REFERENCES
193
Title Design of Storm-Water Drainage in Barangay Bambang, Pasig City
Section CE52FA1
194
195