Professional Documents
Culture Documents
Management
Assignment: Module 2
NISCHAL SINGHAL
CE18B045
What are the key risks that Public-Private Partnerships face (select as many as you can - but at
least 5)? Using real world examples taken from the class or from sources outside (books, internet,
journals etc)can you provide an instance of how each of these risks impacted a particular project
and what was/could have been done about this? (2000 Words)
These partnerships essentially work well when private sector technology and innovation
combine with public sector incentives to improve efficiency, asset allocation and complete work
on time. Although PPPs have been successful in many instances there are multiple risks
associated with each stakeholder and project. The risks pertaining to Private Public partnerships
have been discussed in this assignment.
PPPs cannot follow a common plan for all projects as the requirements and conditions vary with
location, stakeholders and projects. PPPs have injudiciously been implemented in various
instances without accounting for the risks. To identify these risks in a structured manner PESTLE
term was coined.
The various types of risks are -
1. Social Risks: PPPs are generally undertaken for building public infrastructure. The
citizens are one of the major stakeholders and at times have strong opinions about
public services and their costs. The government generally has only limited funds and is
forced to have private participation to implement multiple projects at the same time.
And the private sector is always inclined towards profits and this poses a risk if there is
no understanding about the benefits and tariffs for a project.
Risks/issues-
➔ AdT was granted exclusive rights to water resources and water provision
➔ A tariff increase of 35% was introduced through a new increasing block tariff structure
➔ The threat of charging small farmers for irrigation water
➔ Failure to involve the various stakeholders, especially the public
Impact-
For many Bolivians, the concession contract was a prime example of what was wrong with the
neo-liberal development strategy and failure to address the social risks lead to the following-
➔ Conflicts with small farmers leading to protests
➔ Calls for modification and cancellation of contracts groups by associations & political
parties
➔ Riots in February 2000, with police repression leading to 22 injuries
➔ Hostile environment leading to contract being cancelled on 10th April 2000
Risks/Issues -
➔ Design - complicated design with different sized ribs, difficult to construct
➔ Construction methods - use of epoxy-glued post-tensioned structural members was a
new techniqueand local contractors & labour were unaware and untrained
➔ Scheduling/operational risks - impractical scheduling by theorists leading to inefficiency
in construction
➔ Construction time-sensitivity - fixed deadline project
Impact -
➔ Cost overruns - 12x initial cost estimate. Initially, a $120 million project cost $1.5billion
affecting property tax and tariff rates of Montreal city
➔ Incomplete project - roof and mast deleted due to insufficient time & complexity
➔ Poor resource management - poor estimations leading to poor management of labour
and material leading to increased transportation costs
Issue/Risks
➔ The project has faced challenges on multiple fronts leading to delays
➔ Political tension and land acquisition issues leading to delay in construction
➔ Estimated cost of ticket is high, initially Rs3500, meaning there are better alternatives
available in the market
Impact-
With the delays, the one-way ticket cost required to make this project financially viable is now
Rs 4000. With the alternative of airline tickets at Rs2000 available, it is difficult to see the
project doing well once it is completed in 2027
4. Political Risk: A variety of risks come under this category. It includes payment failures
from govt bodies, resistance from opposition and termination of the project due to
change in government. The government (or a public body) is often the main sponsor for
a project and a loss of motivation or change of intent at different levels (state or centre)
can put the project at risk.
Dabhol power plant
One prime example of projects being subjected to political risk is the Power plant located in
Dabhol, Maharashtra. The 2015MW plant was to be built and operated by Enron Corporation.
Enron was a diversified service provider in the natural gas industries and had implemented
multiple power projects in developing countries in the 90s. This plant was pivotal to meet the
growing demands of electricity and encourage further private and foreign investments
Issue/risks-
➔ Market risks - Dabhol was chosen after careful analysis of multiple locations for buying
power, requirements & sustainability; Currency & inflation risks were mitigated by tying
revenue to USD
➔ Project Financing - the project financing was done through debt and equity. Having
multilateral banks onboard increased confidence in the project; PPA with MSEB for
guaranteed revenues
➔ Contractual risks - the project had exhaustive and well thought out contracts with
sponsors, lenders, boards, natural gas suppliers etc
➔ Political & regulatory risks - liberalisation of the Indian economy had happened in 1992
and along with the two electricity acts foreign and private investments were allowed in
the power sector. The project was the 1st of its kind and thus the regulatory measures
were not perfect. The opposition political parties, BJP and Shiv Sena, were apprehensive
of foreign investments in megaprojects and believed such projects should be built and
operated by Indian organisations
Impact-
Enron development corp. was successful in mitigating various risks, finalising long-term
contracts and constructing the power plant but the political risks associated proved to be
detrimental.
➔ With the BJP gaining support in Maharashtra and nationwide and eventually forming the
government, they raised several issues with the project such as the high price
agreement and lack of bidding process
➔ Eventually, after several legal deliberations and negotiations, Enron Corporation exited
and the power plant operation was shifted to the MSEB.
Risk/Issue-
Sardar Sarovar dam project was the focus of one of the world’s longest environmental and
social campaigns
➔ 10,000+ ha of forest land submerged
➔ Loss of wildlife & biodiversity and lack of regenerative methods
➔ Potential displacement of 100,000 people living in villages in submergence areas
Impact-
The project was marred by controversies and stoppages at the end costing $8billion. Some of
the key highlights were-
➔ Construction was stalled multiple times by court cases in the Supreme CourtWorld bank
after conducting an independent survey, withdrew its funding in 1994
➔ Narmada Bachao Andolan movement was born to protest against the environmental and
social effects of the project
➔ Execution of the project and raising of the height of the dam has lead to loss of forests,
biodiversity and displacement of people
Through this assignment, various risks associated with a PPP framework were studied. PPPs are
subjected to various risks which are not managed well could lead to loss of capital, resources,
time, biodiversity and at times human lives.
Although the cases seen above were of failed projects, there have been many profitable PPPs
where the risks were mitigated successfully, one such project was the Alandur sewage project.
Which faced all of the risks mentioned above but was able to mitigate them through
comprehensive planning, effective risk allocation and inclusion of all stakeholders.
The economic, social and technological conditions of a region are continuously evolving. For this
reason, the success and perception of PPPs have changed from positive to negative and vice
versa (cyclic nature) at different stages. It is necessary to understand there are advantages and
disadvantages to the PPP framework and it is not feasible to have private sector participation in
all projects and no two projects are the same. It is necessary that we learn from the successful
and unsuccessful projects of the past to implement PPPs more logically and with systematic risk
mitigation in the future.
References:
● Class slides and material
● https://www.investopedia.com/terms/p/public-private-partnerships.asp
● https://en.wikipedia.org/wiki/Sardar_Sarovar_Dam
● https://sabrangindia.in/article/environmental-impact-sardar-sarovar-dam
● https://ppp.worldbank.org/public-private-partnership/financing/risk-allocation-mitigation
● https://en.wikipedia.org/wiki/Mumbai%E2%80%93Ahmedabad_high-speed_rail_corridor
● https://www.nhsrcl.in/
● https://www.clearias.com/bullet-trains-india/
● https://ppiaf.org/sites/ppiaf.org/files/documents/toolkits/highwaystoolkit/6/pdf-version
/5-37.pdf