Professional Documents
Culture Documents
In the first phase of the project from Vizag terminal to Rajahmundry terminal two of the CP stations is
converting to SV stations (CP5,CP8)
Visakhapatnam – CH0, CP5 – CH67, CP6 – CH93, CP8 – CH135, Rajahmundry – CH181
Project activity
1.The complete 181KM of line from vizag to Rajahmundry is divided into two sections during shutdown
work which are
a) From Vizag terminal to CP6 (CH93KM)(Pigging station)
b) From CP6 to Rajahmundry
2.Before the shutdown activity the valves should be prepared as shown in below drawing and to be hydro
tested.
During Shutdown
2. After launching the pig with water, pumping will be stopped after pig travels 1km(approx.)
3. Then after with compressed air another bi-di pig will be launched.
4. Air pigging will continue till the pig reaches CP9/SV2.
5. After crossing the SV2/CP9 compressors should be stopped and valve at the SV2/CP9 will be
closed.
6. After closing the valve at SV2/CP9, air in the pipeline need to be vented by opening 2inch
connections at CP6, CP7, and CP8.
7. As air in the pipeline vented off, we can commence the works in CP8.
a) After total air vented out from the pipeline, with grainding machine need to cut the main
pipeline as per measurement.
b) After completion of cutting, 18inch valve need to be fit up and welding works will be started.