COMPOSITE WORKS AT MANGLORE
HPCL PROJECT
1. WORK DESCRIPTION
Rubble Soling is a base structure of any foundation which is located under the Plain Cement Concrete of
any type of Foundation like Footing, Raft, Road, Trimix, etc. general thickness of rubble soling is 230mm
to 300mm.
Rubble soling is done to prepare the uniform level surface on Hard Base or on backfilled surface to work
clearly and above rubble soling PCC work will be done for plain level surface. If any level difference in
base of the ground then we are doing plum concrete and rubble soling with the heap of rubble and PCC.
If hard the surface level of any foundation is too deep and structure on this building in lightweight then
needs to do rubble soling or plum concrete.
Kata Soling
Flat Soling
Leveled Soling
Random Rubble Soling
Stone Pitching
Plum Concrete
2. STANDARD IS CODE
3. WHAT TO SEE?
Following Drawings are needed to read to execute the rubble soling work at site.
Foundation Layout
Raft Layouts
Foundation Sections
Raft Section
Level Drawing (For all types of a building)
Plinth Level Drawing (For all types of the building)
COMPOSITE WORKS AT MANGLORE
HPCL PROJECT
4. WHERE WE USE!
Standard Procedure of Work (Step by Step) Rubble Soling Work (Before Start the work)
6. WORK PROCEDURE
Shift the rubble stone near working place by the use of Labour, Tough rider, tractor, lorry or
Labour, etc. Generally doesn’t use a wheelbarrow to shift the rubble stone because
wheelbarrow will damage easily, it must then use it carefully.
Start laying of stone as per your given standards, generally, all are preferred “kata Soling”
Where we need to keep all the stone vertically places, and minimum gaps are kept between
them and fix the small stone chips in the gaps of stones.
Fix Line Dori to the marked bar at the top level of Rubble soling. And lay all the area as per the
marking, if any stone height is more than your desired height then it should be cut by the
hammer.
Spread loose small and even good quality murum on rubble soling, fill all the gaps by chips and
murum. If possible use a small plate compactor on it.
Check your desired height after murum filling on rubble soling.
7. CHECKLIST
8. EQUIPMENT
Following Equipment is required to do rubble soling work.
Tractor/Tough Rider
Wheel barrow/Trolley
Line Dori and 10mm or 12mm rod
Chalk
Auto Level and measuring Staff
Hammer
Plate Compactor
COMPOSITE WORKS AT MANGLORE
HPCL PROJECT
9. HOW TO MEASURE