Check List for Inspection of Form Work (Shuttering)


Date:
PROJECT :ONSHORE TERMINAL FOR KG DWN 98/2
DEVELOPMENT PROJECT CUSTOMER: ONGC
Description of Element:
PCC Raft Slab Column Beam Shearwall Specify,if any other Element
Name of Structure : Date :

Contractor : TATA PROJECTS LTD Location : Sub Location:

Drg No. & Rev: Grid No & Level:

Element details: Qty:

Is the inspection 1st Time 2nd Time 3rd Time

Checked
Sl.No. Item Remarks
Yes No
1 Formwork design/drawing approved including
2 Correctness of formwork alignment

3 Correctness of formwork levels


4 Correctness of formwork dimensions
5 Correctness of formwork member spacing
6 Shuttering condition
7 Joints between Panels closed (no gaps)
8 Joints between Panels closed (no steps/lips)
9 Tie rod provided
10 Spacers between shutter surface tighty fitted
11 Formwork clean
12 Formwork release oil materials approved
13 Formwork release oil applied correctly
14 Safe access constructed
15 Adequate work space provided for labour / equipment
Shutter vibrators (if required) location and fixing
16
arrangement approved
Remarks :
Limits:
1. Column & Beam dimension of Cross section +12 mm & -6 mm
2. Footings in dimensions +50 mm or -12mm
3. Eccentricity 0.02 times of width of the footings or not more than 50mm
4. Thickness ± 0.05 times of the specified thickness

TPL TPI ONGC / TPCA

Format No.08.03.03/ FQ- 233 /R0 Date 25-03-2019