You are on page 1of 6

angle of 120°.

The load-bearing part is fixed by means of anchor


PLACING BOOMS bolts, either to a dedicated foundation, or to building floor slab. An
alternative option for immobilizing is possible, using counter-weights
A concrete placing boom is the final element of concrete mixture to surcharge the ends of each load-bearing beam. The load-bearing
pipeline transportation system. It is designed to deliver the concrete part is used to install the mast or tower that may be essentially a solid
mixture for discharging where and when required, therefore, similar pipe (round, square, hexagonal or octagonal) or mesh, if the height is
to cranes, it must be equipped with at least two mechanisms: boom between 10 and 45 m. During operation, the mast can be extended by
extension and rotation. The mechanisms can be both manually and telescoping, as it is provided in its design. The telescoping
hydraulically actuated, hence, booms are differentiated between mechanism can be designed as a rack-and-pinion, or using a hydraulic
mechanical (manually controlled) and hydraulically or electrically cylinder (more common). The telescoping speed is 0.5-0.8 m/min
controlled. This article aims at describing the areas for using various regardless of the method. The tower is passed through building floors
categories of concrete placing booms. using either engineering equipment openings (elevators, cable shafts,
It is known as a boom concrete pump because it uses a remote- etc.), or dedicated openings are provided that are subsequently sealed
controlled articulating robotic arm (called a boom) to place concrete by cast-in-place concrete. For heights up to 20 m, the mast is free-
accurately. Boom pumps are used on most of the larger construction standing. For greater heights, it is supported by a mounting frame,
projects as they are capable of pumping at very high volumes and installed on the floor slab and fixed to it using through bolts. The
because of the labor saving nature of the placing boom. tower’s top section contains a swivel head with the boom and
A concrete placing boom is plant incorporating an articulating boom, concrete-conveying pipe installed on a crown. The crown provides for
capable of power operated slewing and luffing to place concrete by an average rotation rate of 0.4-0.5 rpm in the horizontal direction. The
way of pumping through a pipeline attached to, or forming part of, the angle of rotation is typically up to 370°, and with some
boom of the plant. manufacturers, it is 570°. Further rotation is limited by the concrete-
Various types of concrete placing booms are available in order to conveying pipe. The crown is selected based on the static load and
meet your specific requirements: stationary, self-climbing, rail- bending moment that it is exposed to, taking into account the dynamic
mounted, floor-mounted and even ship-mounted concrete placing factor. Boom rotation mechanism is installed on a special platform
booms. The self-climbing models allow the boom climbing by itself. that is rigidly connected to the mast. Its actuator can be either
The rail-mounted are featuring the ability to meet the demands for electrical or hydraulic. Hydraulic actuators are preferable, because the
concrete placement of long span or high-rise structures and large boom extension mechanism can be only hydraulic, hence a hydraulic
surfaces. With the ship-mounted model it is easy to work in water, pack is always present. The hydraulic pack is not loaded during the
with vertical reach related to tower-body height. Mobile models boom rotation, and it is not sensible to use two types of energy.
combine excellent mobility, wide application, high utilization, high - The distribution hose on the boom is typically 3-4 m
safety and reliability, easy transportation by means of a crane. long. This ensures sufficient ease of controlling it when placing
concrete mixture, despite its rigidity and counter torque. It should be
noted that stationary mast booms are divided into two types
depending whether a boom counterweight is used or not [16]:
Concrete Placing Boom Types a. without counterweight jib;
b. with counterweight jib.
1. STATIONARY - In recent - In order to define the borderline between the two above-
years these booms have been mentioned types, information on both machine types that are
widely used in cast-in-place currently being manufactured has been collected. This information
construction of high-rise was summarized in a table (not included in this article). Similar to
structures, with large area and other boom-type cranes used in construction, the main comparison
complex configuration, together parameter was defined as the outreach of concrete mixture supply
with stationary concrete pumps. rubberized hose that always hangs vertically regardless of boom
This machine allows for position and configuration. Concrete mixture supply outreach is the
continuously supplying the distance between the axis of rotating boom section rotation and the
concrete mixture without hose centerline, horizontally measured. By analyzing the series of
wasting time for concrete loading and lifting. The mixture may be specifications for various manufacturers in terms of maximum
lifted and continuously discharged in the required location while the outreach, it was revealed that booms with an outreach of 28-36 m are
structure is being built-up vertically and horizontally. The machine is the most common (48.27%). The second important group is machines
capable of supplying an area with an outreach of 50 meters and more with an outreach of 16 to 24 m (27.58%), and a slightly smaller group
without the need to move the equipment in the horizontal direction. If is machines with an outreach of 36-52 m (24.15%). The working area
it is necessary to change the height of concrete mixture supply, the of up to 16 m is mainly served by rotary booms that have gained new
crane mast can be extended fairly quickly by means of telescoping, momentum in recent years, while the working area of over 52 m is
even when complex-shaped constructions are built, for example, oval preferable for booms installed on tower cranes.
or polygonal. It is this type of booms that was used for building the
tallest concrete structure in the world, Burg Khalifa Dubai sky- 2. MANUAL TYPE / ROTARY MECHANICAL BOOM –
scraper, and is being used now in the project of Kingdom Tower in Manual type concrete pump placing boom (cloth rod) Introduction
Jeddah, Saudi Arabia, 1,000 m high, where as many as 3 booms type Concrete pump placing boom is a new product developed to enlarge
SPB35 and 2 booms type SPB30 are installed simultaneously. the pouring range of concrete and improve the mechanization of
Globally, over 30 boom models are manufactured. However, if one pumping construction. It is a
takes into account the modifications in terms of mast height and supporting equipment of
cross-section, its telescoping method, the method of fixing the mast to concrete conveying pump,
the building’s structure, the actuator type of boom rotation which is connected with
mechanism, the method of boom folding and unfolding, this number concrete conveying pump, and
will be even greater. Currently, despite some difference in concepts, a expands the range of concrete
certain stereotype has been formed for designing these machines. The pump delivery. It effectively
machine has a load-bearing part that is essentially either two crossing solves the problem of the wall
beams (cross-piece) or three beams connected to each other at an pouring cloth, and plays an
important role in improving the construction efficiency and on a height that exceeds the specifications of the concrete pump truck.
alleviating the labor intensity. This concrete pump placing boom Concrete mixture supply booms consist of several sections that are
design is reasonable, the structure is stable and reliable, the use of hinged together. This ensures their high maneuverability, good
360° full swing arm-type fabric structure, the whole machine easy to approachability to the mixture placing location, as well as the
operate, rotating flexible, with high efficiency, energy saving, transportation function. A major benefit of applying concrete pump
economic and practical characteristics. trucks is that their design includes a screw concrete mixer. After the
- Booms of first class are used for centralized supply of concrete concrete mixture is loaded into the concrete pump truck hopper, it is
mixture via a concrete-conveying pipe fixed on the machine as a part maintained in the necessary condition throughout the entire
of its load-carrying structure, and connected with the concrete pump transportation time period and up to the time when concreting is
by a stationary pipeline. Mechanical booms are placed in the required started. The latest models of concrete pump trucks already are
location with a crane and are ready for operation without the need to equipped with an innovative system for purging the concrete-
connect additional power supplies. The entire boom or its head conveying pipe by means of an air compressor. Maximum supply
section are rotated using only a person’s muscle power. Low height of such booms can be up to 66 m, with the outreach of up to 60
resistance rotation in the central journal, small weight, sufficient m. The height and outreach will hardly be increased further, as it
length and rotary hinge locks ensure that boom sections can be easily results in certain problems with operating such trucks, namely,
turned by a single person, and precisely located in the required difficulties with efficiently controlling the truck when it is moved
position. A flexible hose is mounted on the second section end of from one construction site to another, as well as when pouring
concrete-placing boom to ensure that concrete mixture can be poured concrete, and safety issues.
into the shuttering or on the floor slab with the highest precision.

- Currently, the following types of rotary mechanical booms are DEFENITION OF TERMS
produced:
1. With the head section rotating up to 160° relative to the root  Additive: A material which is added to concrete to change the
section, in both directions of the horizontal plane; the boom is properties of the mix.
supported by a fixed three or four-post frame via the slewing
ring.  Ball Catcher: a device fitted to the delivery end of a pipeline
2. With the head section rotating up to 160° relative to the root designed to catch the sponge rubber device used for cleaning the
section, in both directions of the horizontal plane, and capable pipeline.
of lifting vertically to 3-5.5 m.
3. With the head section rotating up to 160° relative to the root  Banksman/ Spotter: A person who is competent to give directions to
section, in both directions of the horizontal plane; the boom is the operator of a vehicle-mounted concrete pump during maneuvering
supported by a column up to 3 m high mounted on a four-post of the vehicle on site by a recognized code of signals or by verbal
frame. communication.
- Type 1 booms can be installed on a rail truck mounted directly on
the horizontal reinforcement mesh behind the concreting area. During  Blanking device: A component designed by the concrete pump
operation, such booms are fixed on the rails using special clamps. manufacturer fitted securely at the outlet end of a placing or delivery
They are moved together with the concreting area, and the track is hose with a coupling or other device to prevent concrete from falling
partially disassembled. Type 1 mechanical concrete-placing booms out of the hose whilst the concrete placing boom is being moved to a
are used only for concreting horizontal floor slab areas and only when new position.
using more complex equipment for supplying the concrete mixture is
economically or technically unreasonable, for example, when  Linesman: Person supplied by Owner or Hirer trained to work with
working on a large area or on a height that exceeds the specifications concrete delivery pipelines.
of the concrete pump truck.
- These booms are produced with an outreach of 6.6 to 15 m, supply  Owner: Company, firm or person letting the concrete pump on hire,
height of up to 1.5 m and can provide a concreting area of up to 700 including their successors, assignees or personal representatives.
m2. Type 2 boom is more versatile, as it allows for pouring the
concrete mixture not only on a horizontal surface, but, thanks to its  Pipelines or Delivery Lines: Pipes, whether steel or rubber, through
slope, it can be used for constructing store walls and partitions. In this which the concrete is conveyed. They will include, pipes, bends,
case, the head section is lifted by a hydraulic cylinder using a hand- hoses, coupling connectors and any valves inserted in the line.
operated pump. Such booms have an outreach of 14 m, lifting height
 Placing Hose: A flexible hose to provide freedom of movement in
of up to 4.7 m, and a working area covered by one unit of up to 530
the final placing of concrete.
m2.

 Receiving Hopper: The area into which the mixed concrete is


3. SELF PROPELLED / TRUCK MOUNTED - These booms
discharged prior to being pumped into position.
mounted on a truck or crawler chassis are now used very widely. The
classification does not present self-propelled concrete placing booms,
 Remote Control Box: A portable control panel which is connected to
because they are all structurally similar. Concrete pump trucks consist
the concrete pump by a wired or wireless system, allowing the
of two main elements: transfer
concrete pump operator to operate the machine from a remote
pump with a hopper where the
position. The control levers / switches may operate the placing boom
concrete mixture is poured into,
movements, the concrete pump and the vehicle engine.
and the boom carrying the pipes
that supply material into the
 Safety Induction Training: Instruction given to the Hirer to
shuttering with various heights
communicate, for example, the site safety rules, safe access on the
and outreaches. Operation of a
site and the location of welfare facilities.
concrete pump truck involves
frequent change of location,
 Spotter: A person who has had training to give directions to the
therefore the boom design provides for folding it into the
concrete pump operator by a recognized code of signals or by verbal
transportation position. for example, when working on a large area or
communication.
 Sponge Rubber Cleaning Device: A piece of sponge rubber, usually - Employers have a duty to both ensure the health of their employees and to
in the shape of a ball, which is inserted into the delivery pipeline for ensure that any employee is fit to undertake the tasks they are required to
the purpose of cleaning the inside of the pipes. It is propelled along carry out.
the pipeline either by the action of the pump (forward or reverse), by 3. SPOTTER REQUIREMENTS
compressed air or by water pressure. - An appointed spotter should be able to:
I. relay signals from the placing gang to the pump operator;
 Stabilizers: Extendable structural members on the pump unit to II. direct safe movement of the concrete placing boom; and
increase the dimensions of the stability base. III. give clear and precise verbal instructions where audio equipment is
used, for example, a two-way radio.
 Trailer-mounted Concrete Pump: A concrete pump mounted on a 4. MANAGEMENT OF THE CONCRETE PUMPING
trailer that can be towed (also known as a static pump). OPERATION
- All concrete pumping pours should be planned to ensure that they
 Truck-mounted Concrete Pump: A concrete pump mounted on a are completed safely and that all significant foreseeable risks have
self-propelled lorry. been taken into account. Planning should be carried out by personnel
who have the appropriate expertise. In cases of repetitive concrete
 Wash Out Adapter: A short length of pipe with one end blanked off pours to and from one location this planning may only be necessary in
and a connection for a water/ compressed air hose for cleaning the first instance, with periodic reviews to ensure that no factors have
purposes. A secondary valve(s) should be fitted for releasing the changed. The concrete pump Owner should be able to supply a risk
pressure when necessary in addition to a working pressure gauge. assessment to the customer, detailing the generic risks in concrete
pumping.
SAFETY TIPS 5. SAFE SYSTEM OF WORK
- Following a site specific risk assessment, a safe system of work
should be established by the Hirer and this should be followed for
 The aim of this guidance is to improve standards of safety during every concrete pumping operation whether it is an individual pour or
concrete pumping and reduce the incidence of collapse of concrete a series of pours.
pump rigs and injuries due to incidents involving pressurization of - The safe system of work should cover arrangements for all aspects
pipework or other equipment. of work from the concrete pumping rigs arrival to its departure,
including:
1. SELECTION OF PERSONNEL a. the preparation of a method statement,
- The safe operation of a concrete pump relies heavily on the selection of b. the planning of the operation,
suitable personnel who are competent to carry out the required duties. c. the selection, provision and use of a suitable concrete pump and
Those responsible for the selection should ensure that an operator is boom,
efficiently organized in order to promote good teamwork in the working d. the need for additional delivery pipes in addition to the standard kit
situation. carried,
- Nobody should be selected whose efficiency is impaired by alcohol or e. the position of the concrete pump and any necessary preparation of
drugs. The Administration must issued a guidance note “Intoxicants at the site for its positioning,
Work” to avoid accidents while on work hours or when in job site or f. the site of the pour, taking into account proximity hazards, space
workplace. availability and suitability of the ground to support the weight of the
- The concrete pump operator should: concrete pump,
a) be competent; g. the provision of properly trained and competent personnel who
b) be over 18 years of age if operating a concrete pump on the site and have been made aware of their relevant responsibilities,
over 18 years of age if driving a concrete pump on the road. If driving h. the requirement for all personnel to be able to communicate
a concrete pump on the road, the operator must fulfill all necessary clearly,
requirements under road safety legislation; i. adequate supervision by competent personnel,
c) have adequate communication skills; j. ensuring that all necessary documentation is valid and available for
d) be medically and physically fit, with particular regard to eyesight, inspection,
hearing and reflexes. k. preventing unauthorized use of the concrete pump and boom,
e) be physically able to operate the concrete pump safely; l. ensuring the safety of persons not involved in the pumping
f) be able to judge distances, heights and clearances; operation,
g) be adequately trained for the class of concrete pump which he m. the provision of a clean-out area, taking into consideration all
operates. environmental issues,
h) have sufficient knowledge of the machine and its safety devices; n. the provision of an adequate piped water supply at the pump
i) be fully conversant with the duties of the spotter and should position,
understand the signals code agreed with him; o. the provision of a supply of suitable and sufficient concrete of a
j) have adequate communication skills; consistency which is readily pumped at a sustainable rate, and
k) be medically and physically fit, with particular regard to eyesight, p. adequate lighting.
hearing and reflexes (see 3.2); 6. SELECTION OF CONCRETE PUMP RIGS BEFORE
l) be physically able to operate the concrete pump safely; DEPLOYMENT
m) be able to judge distances, heights and clearances; Size and Pumping Capacity
n) be adequately trained for the class of concrete pump which he - Concrete pumps are available in a number of sizes and pumping
operates (see 2.6); capacities. The characteristics of each concrete pump should be
o) have sufficient knowledge of the machine and its safety devices; considered in relation to the job requirements.
p) be fully conversant with the duties of the spotter and should Documentation
understand the signals code agreed with him; - When the rig arrives at site the following documentation should be
q) be authorized to operate the machine; and available prior to the start of the pumping operation:
r) in the case of a mobile concrete pump operator expected to move the • Inspection Report – we recommend that the concrete pump be
pump, be qualified to drive a large goods vehicle (Class C). inspected at least annually and the information set out in appendix 3
2. MEDICAL FITNESS
be recorded during these inspections and be made available in the 3. For multiple pours, the pipeline is normally delivered to site and set
form of an inspection report. up beforehand, remaining on site until the pours have been
• Declaration of Conformity if less than 12 months old or if the pump completed. The pipeline can either be set up by Owner’s personnel or
has undergone a substantial alteration in the past 12 months. the Hirer’s personnel. The concrete pump will then come to site with
• Evidence of operator training. the operator, and possibly a linesman, to carry out each pour. It is
• Evidence of pre-delivery checks. essential that responsibility for the pipeline is agreed between the
• Daily /weekly check sheets. Evidence of the Roadworthiness Owner and Hirer.
Inspection Sheets should be supplied if requested. 4. On large contracts the Hirer may choose to supply their own
7. ARRIVAL ON SITE AND SETTING UP THE MACHINE pipeline which they will set up themselves and maintain. The Owner
- The concrete pump operator is responsible for the correct operation will then send the pump to site as required whilst the Hirer takes full
of the concrete pump in accordance with the manufacturer’s responsibility for the pipeline.
instructions and within safe systems of work. - Whichever method of supply and set up is used, it is essential that
On Arrival the operation is planned effectively and that each element of the line
- On arrival, the concrete pump operator must report to the site office. must be capable of resisting the likely maximum pressure exerted by
Site Induction the concrete pump. The installation should be inspected by a
- The concrete pump operator must attend site safety induction competent person before being taken into use, to ensure that it is safe.
training as required by the Project Supervisor for the Construction This inspection should include checks that all couplings have been
Stage (PSCS). The provider of the training may determine that the fitted with gaskets and safety pins and that flexible hoses have not
delivery of induction training on the first visit to the site is sufficient been used in place of steel bends.
but may insist on further training if site conditions change 8. Control of Noise
significantly - The combination of the noise levels from different items of plant
Authorized Access Routes may exceed the action levels in the Safety, Health & Welfare at Work
- It is the Hirer’s responsibility to assess the ground conditions and (General Application) Regulations 2007, Chapter 1 of Part 5: Control
confirm its suitability to support the equipment. The concrete pump of Noise at Work. If this excess noise level cannot be eliminated or
operator should only use authorized routes across the site. Where reduced to a safe level, the concrete pump operator should be
possible, site routes should be taken to eliminate reversing. Where supplied with appropriate ear defenders and be instructed on the use
this is not possible, the Hirer/contractor should supply a banksman/ of them in accordance with the Regulations.
spotter to assist with reversing when necessary. The use of CCTV - If operators are exposed to daily noise levels of 80 decibels (dBs) or
cameras and other visual aids should be considered to reduce the risk any instantaneous exposures of 135 dBs, his employer must make
of collisions. available to them preventive audiometric testing. If operators are
Overhead Power Lines exposed to daily noise levels of 85 dBs or any instantaneous
- Overhead power-lines must be considered when setting up the exposures of 137 dBs exposures or equivalent, they must be offered
machine; the boom must never be positioned where it might touch by their employers the services of a registered medical practitioner to
overhead lines or where electricity might arc to the boom. A safe carry out hearing checks and audiometric testing.
method of working in the vicinity of overhead cables must be 9. Remote Controls
included, if appropriate, in the overall safe system of work. - The availability of a remote control box, whether operated by cable
Proximity of Cranes and Other High Reach Equipment or by radio signals, allows the concrete pump operator to select the
- Regard should be given to the proximity of cranes or other concrete optimum position from which to operate the pump and boom. This
pump booms, especially when working areas overlap. position will vary according to the work in hand. The concrete pump
Maximum Operating Wind Speed operator should select the position that offers the safest overall
- The manufacturer of the machine specifies the maximum wind position for the job. When a remote control box is in use, any other
speed in which it is safe to operate a concrete placing boom. The controls on the machine must be effectively isolated.
pump Owner must supply this information to the Hirer. It is the 10. Use of Spotter Requirement for Spotter
responsibility of the Hirer to verify that the wind speed at the site is - If the concrete pump operator is required to position himself where
not in excess of the limit specified by the manufacturer. he cannot see the concrete placing gang, the Hirer must supply a
Pre-use Checks spotter to give appropriate signals to the concrete pump operator.
- The function of all controls and safety devices should be checked by Signal Code
the concrete pump operator for correct working before pumping - A code of signals must be agreed between the concrete pump
commences. operator and a representative of the concrete placing gang before
Guards pumping starts.
- Guards to all dangerous moving machinery must be in place at all 11. Concrete Level Monitor
times while the machine is working. - When the concrete pump operator cannot see the concrete level in
Pipelines the machine’s receiving hopper, it is the responsibility of the concrete
- Pipelines for conveying concrete from the pump to the pour position pump supplier to arrange a competent person to monitor the level of
may be supplied and set up in a number of ways: concrete in the receiving hopper and convey signals to the concrete
1. For basic single pours where the distance from the pump to the pump operator when the level is at its safe minimum. It is not
pour point does not exceed approximately 30m, the Owner will acceptable to hold the driver of the ready-mixed concrete truck
generally send the pump, operator and standard pipeline equipment to responsible for advising the concrete pump operator when the
site. The operator sets the pipeline up, with assistance from site, concrete level is low in the receiving hopper. In certain situations it
carries out the pour and removes the equipment from site. might be feasible to have mutual arrangements between drivers to
2. For basic single pours where the distance from the pump to the check the level of concrete in the hoppers. However, this must be
pour point exceeds approximately 30m, the Owner will generally agreed prior to commencing work and must be facilitated by the
send the pump and operator to site with a second person (linesman) nature of the pour.
and a vehicle containing the pipeline equipment. The operator and 12. Personnel in the Vicinity of the Concrete Pump
linesman set the pipeline up with assistance from site personnel and - Before the concrete is flowing smoothly from delivery hose, or
carry out the pour. After the pour, the equipment and pipeline is when a blockage occurs in the boom pipeline, all personnel should
removed from site. remain clear of the delivery hose and the placing boom. The danger
zone is the area around the delivery hose in which the delivery hose
can strike out. The diameter of the zone is twice the length of the persons from coming into contact with the moving machinery. The
delivery hose. interlock, a switch usually located at the hopper grille, prevents
13. Pipeline Blockages operation of the machine when dangerous moving parts inside the
- Clearing pipeline blockages is a potentially hazardous task, as hopper can be accessed. The hopper grille must be in a closed
workable concrete has such a short life. If a blockage is detected, then position at all times during the pumping operation.
it’s vital that it be cleared as quickly as possible. A clear risk
assessment and robust method statement setting out roles and
responsibilities should be in place to minimize the possibility of  SITE TRAFFIC MANAGEMENT ARRANGEMENTS
accidents. All personnel dealing with the pipeline should be trained in - The concrete pump operator must comply with the site’s traffic
what to do in the event of blockages. Whilst the concrete pump management arrangements. It is the responsibility of the Hirer to
operator may be the person on site with the most experience of ensure that alterations in the site traffic management arrangements
clearing blockages, it is unreasonable to expect him to have control necessitated by the presence of the mobile concrete pump and
over a long pipeline. It is important to remember that overall concrete-mixer lorries are adequate and implemented.
responsibility for the management of the operation will rest with the  WASHING OUT OF READY-MIX TRUCK CHUTES
Hirer. - Site managers should ensure that ready-mixed concrete trucks do
- If the concrete pump operator needs to open the delivery pipeline to not wash out their chutes into the receiving hopper of the concrete
clear a blockage, he must first release the pressure inside the pipeline pump. This can cause damage to the pump unit and affect concrete
as much as possible, for example by reversing the pumping action. quality. Washing out arrangements should be agreed between site
The pipeline must be treated as being pressurized at all times. management and ready-mix concrete suppliers.
Appropriate and adequate hand and eye protection must be worn
when opening the delivery pipeline. The Hirer/ (sub) contractor
should ensure that site personnel DO NOT under any circumstance
WORK WITH PIPELINES
open or attempt to open the delivery pipeline under pressure.  RESOURCES
- Where a blockage has to be cleared the following procedure should - The Hirer is responsible for providing adequate resources to assist
be followed: the concrete pump operator in handling pipes and accessories.
• Stop pumping immediately  SELECTION OF EQUIPMENT
• Reverse the pump until the pressure is released (DO NOT increase - Pipes and couplings must be selected in accordance with the
the pressure to clear the blockage as an alternative to the following anticipated pressure in the pipeline.
procedure)  INSPECTION
• Locate area of blockage, check the following: - The concrete pump operator/Hirer should carry out regular
o reducer (if applicable), inspections of the standard delivery pipeline supplied with the
o bends, machine, in accordance with a planned maintenance schedule to
o flexible rubber hoses, and ensure that they are fit for continued use.
o outlet of pump.  SETUP OF PIPELINES
• Establish an exclusion zone (move non-essential personnel out of - The setting up of all pipelines, not supported by the machine, should
the area) be under the direction and control of the Hirer.
• Disconnect the delivery pipeline at the safest point near to the  PIPELINE SUPPORT
blockage - All pipelines must be adequately supported.
• Clean out the blockage, re-prime and re-connect ensuring that safety  COUPLINGS
pins and clips are in place - All couplings must be in good order and correctly fitted with a good
• Recommence pumping operation to ensure blockage is clear, if not rubber seal and a securing pin. The bolts of bolted couplings must be
repeat the procedure as above capable of being tightened fully.
14. Exhaust Fumes PIPELINES FITTED TO
- Arrangements must be made to extract exhaust fumes when the
machine is operating inside a building or a confined space. SCAFFOLDING
15. Leaving the Concrete Pump Unattended  LOADINGS AND ATTACHMENT
- If the concrete pump has to be left unattended, the operation of the - Before a pipeline is fitted to a scaffold/false work, the Hirer must
boom and pump must be isolated. confirm that the scaffolding/ false work is designed and constructed
16. Maximum Hose Length to take the extra loading to be imposed. Purpose-made clips must be
- The maximum length of end hose to be suspended from the end of a used to attach the pipeline to the scaffold/ false work.
boom is specified by the manufacturer and must not be exceeded as  WORKING PLATFORMS
this may affect the strength and/or stability of the pump unit. - Working platforms, in compliance with the Safety, Health and
17. Falling Concrete Welfare at Work (General Application) Regulations 2007 Part 4
- Concrete must be prevented from falling out of the delivery hose Work at Height, must be provided for the purpose of attaching
when the boom is being maneuvered over personnel or property. pipelines to scaffolding.
Where necessary, a Blanking Device, fitted in accordance with the
manufacturer’s instructions, should be used.
18. Use of Concrete Placing Boom as a Crane CLEANING OUT THE MACHINE
- The boom must never be used as a means of hoisting/lifting - Cleaning out a concrete pump and its concrete placing boom is a
equipment or personnel. specialist operation, which is to be left to the concrete pump operator.
19. SECURING PINS If the concrete pump operator requires assistance when cleaning out
- Purpose designed securing pins must be fitted to all pipe couplings the delivery line, this must be carried out under supervision.
to prevent them from opening accidentally.  WATER SUPPLY
- The tip hose should also be fitted with safety straps/chains to - Truck-mounted concrete pumps generally carry their own supply of
prevent the hose falling in the event of pin failure. water for cleaning the boom pipes and hopper. However, in cases of
20. HOPPER more than one pour, it may be necessary for the site to provide a
- The hopper contains mixer paddles on a revolving shaft. Access water supply. Trailer or skid-mounted concrete pumps need a separate
doors and an interlocked protective grille must be fitted to prevent water supply or bowser.
 DESIGNATED WASHOUT AREAS - Other PPE should be supplied when a risk assessment deems this
- The cleaning process involves the deposit of some waste concrete necessary.
on the site. The concrete pump must only be washed out in the area
designated by the Hirer.
 ISOLATING THE PUMP
- Before working in the receiving hopper, the concrete pump operator
should always switch off the engine and remove the keys, vent the
hydraulic pressure and ensure that the agitator control lever is in the
neutral position.
 WORKING AT HEIGHT
- When considering the risk of working at height during the cleaning
process, the hierarchy of control should be followed.
 HIERARCHY OF MEASURES
a. Avoid work at height wherever possible and actively seek solutions
to facilitate this.
b. If this is not possible, use “collective” means of prevention such as
guardrails.
c. If this is not possible, use “personal” means of prevention such as
work restraint.
d. If this is not possible, use “collective” means of protection such as
air bags or nets.
e. If this is not possible, use a personal fall protection system such as
a work positioning system or fall arrest system.
 SELECTION OF PERSONAL FALL PROTECTION
EQUIPMENT
- Where a risk assessment indicates that a personal fall protection
system is required, a working positioning system should always be
used in preference to a fall arrest system. Where the use of fall arrest
personal fall protection systems is unavoidable, there will be a risk of
the wearer being left suspended following a fall and arrangements
must be made to ensure that they can be rescued in a safe and timely
manner.

LEAVING THE SITE (TRUCK-


MOUNTED PUMPS)
 STOWING
- Before leaving the site, the concrete pump operator must ensure that
the concrete placing boom is properly stowed and that all equipment
is securely loaded.
 EMPTYING THE RECEIVING HOPPER
- Concrete should not be carried in the receiving hopper on the
highway.
 CHECKING OF TYRES
- The vehicle tyres should be checked for damage, cuts, nails or
screws in the tread and material trapped between twin wheels.
 APPROPRIATE PPE
- Depending on the circumstances and the risk assessment in
operation, the PPE worn by the concrete pump operator should
generally include:
• a safety helmet to EN 397,
• footwear to EN ISO 20345,
• overalls,
• suitable eye protection to EN 166 (Mechanical strength -S -
increased robustness),
• ear defenders to EN 352,
• fall protection equipment,
• high visibility clothing to EN ISO 20471,
• impervious gloves/gauntlets to EN 374-2, and
• waterproof clothing as necessary to EN 343.
 CHARGING FOR PPE
- Concrete pump operators should not be charged a cost for PPE.
 PPE REPLACEMENT
- PPE should be replaced by the employer as necessary.
 ADDITIONAL PPE

You might also like