OM Start Time Finish Time Duration
Project OM 9.40 9.45 5 min
WBS OM 9.45 9.50 5 min
Status Change OM 10.30 10.40 10 min
20 min
Sequence Plan Start Date Plan End date Prerequisi
18 11.03.2021 11.03.2021
19 11.03.2021 11.03.2021
Year Date
ALL 11.03.2020
2020 LP 11.03.2021
2019 LP 11.03.2022
2018 LP 11.03.2023
All 11.03.2024
Year Date
2020 Pumps 11.03.2020
2018 and 2019 Pumps 11.03.2021
All 11.03.2022
All 11.03.2023
Year Date
2020 RT 11.03.2020
2019 RT 12.03.2020
2020 RT 12.03.2021
2019 RT 12.03.2022
2020 RT 12.03.2023
2019 RT 12.03.2024
Excluding 2018 related RT Projects
Year Date
All 12.03.2020
All 12.03.2021
All 12.03.2022
Method TPSL Business team TPSL D&IT Team
Through Upload Program Pankaj B SAP Team
Through Upload Program Pankaj B SAP Team