: SOP:01
C-TECH ENGINEERS PVT.LTD.
Rev. No. : 00
PROCEDURE FOR APQP Date : 01-06-2021
1. Purpose:
To establish a procedure for Manufacturing Process Development and to ensure that the new product development
activities are carried out in line with customer requirements and reduce the lead time of the development
continually. The Advanced Product Quality Planning procedure (APQP) accompanies the development of a
product and is intended to ensure that the supplier meets all of the customer's requirements on time.
2. Scope:
Applicable to all new part (Critical parts, Functional, General) development, ECN implementation.
3. Responsibility:
Overall responsibility for implementation of this procedure lies with DEVLOPMENT HEAD whereas he is assisted by Section
In charge.
4. System:
Sl. Responsibilit
Activity Input Output
No. y
PHASE – I
Received Part Drawing / Standard from Customer Part drawing /standard Review of Marketing
end. After received part drawing & standard review Customer Input
of customer inputs & material specification.
Prepare Initial Feasibility & Risk Analysis. List of Critical Feasibility & Risk Marketing
Characteristic& Analysis
Drawings, CSR
If Initial Feasibility & Risk Analysis not Feasible, Feasibility & Risk Feasibility & Risk Marketing
reply to customer for the same. Analysis Analysis Report
If Initial Feasibility & Risk Analysis Feasible Feasibility & Risk Quotation Marketing
prepares Quotation, discuss and take approval from Analysis (Customer special
top management and send to customer format)
If required, cost negotiation and spec. meeting (if Purchase Order Go to Dev. Dept. Marketing
necessary) shall be done with the customer for the
same and Receive Purchase Order to Customer and
go ahead for development department.
If Purchase Order is Feasible, Review of Phase – I Purchase Order Review of Phase–I Dev. Head
Activities. Activity (MOM)
Phase – I Activities feedback give to Development
Head and review required within two week.
Prepare Part Drawing (If Required), and get Approved Customer Drawings NPD
Approval if required. input
After Approval Issue Drawing / Standard to Concern
supplier.
PSW Submission to Customer with PPAP Level III or Production Control Level III PPAP Or NPD
Customer Specific requirement. plan, Capacity as per customer
confirmation, SPC, requirement
MSA, Spec Test
Results, Layout
inspection
After PSW Sign off with the customer, Start Status of targets and Signed PSW NPD
Ramp up Activities (Review of targets & Monitoring of process Capability
Process Stability)
QMS Review QA &
And Conduct the review of quality management Signed PSW QMS
system.
.In case of any ECN raised from customer, refer the Customer input &
Engineering Head NPD
APQP Matrix. Review of ECN within 2 Working Drawing
Change Note
Weeks Or as per Customer Requirement after
Receiving from Customer. Feasibility study of Change
Point.
1 of 1
Doc. No. : SOP:01
C-TECH ENGINEERS PVT.LTD.
Rev. No. : 00
PROCEDURE FOR APQP Date : 01-06-2021
Responsibilit
Activity Input Output
y
PHASE - V
Get feedback from customer / communicate to Feedback report Action Plan Head NPD
customer for further action at every phase.
APQP project file has been completed as per the APQP file Production Head NPD
checklist & signoff
APQP file document has been reviewed once in a Quality issue Monitoring Head NPD
year or when any customer complaint / major
process issue has been noticed.
5. Formats:-
APQP Document List
APQP/Part Development Timing plan
Responsibility
Part Development Problem History
Process Flow Diagram
PFMEA
Control Plan
Packing Standard –as per customer specific
ECN
List of special characteristics
Part Submission Warrant
Material Test Plan Certificate/Report
PFMEA Review Plan
Contract Review Form
Costing Sheet
Checking Aids
Engineering Change Request