PROJECT WORKS DAILY REPORT:

NAME OF THE PROJECT : RETROFITTING DESIGN OF METEOROLOGICAL HEAD QUARTER AT SHER-E-BANGLA NAGAR

Date : 05-10-2021
Day of Week: Tuesday

Time 8.00-11.00 12.00-15.00 16.00-18.00


Sheet No: 435 Weather Sunny Sunny Sunny
Temp 30°C 32°C 29°C
Workers Working Hour 8 hours
1) Md. Shohel Rana , Project Engineer, BSPP
Issue From:
2) Md. Nurul Alam Rony , Project Engineer, BSPP

01). Administrative & Technical Staff :

SL.No Position : No : SL : Position : No :

01) Contractor Engineer 1 05)

02) Contractor Site Manager 0 06)

03) Contractor Site Accountent 0 07)

04) Office Boy 0 08)

02). Laborer Categories :

SL.No Laborer Categories No: Hour SL. No: Laborer Categories No: Hour

01) Foreman 1 8 07) Welder 0

02) Skilled Worker 5 8 08) Site Supervisor 0

03) Semi Skilled 8 8 09) Store Keeper 0

04) Daily Labour (Unskilled) 0 8 10) Roof Crane Operator 0

05) Laborer Curing 0 Full Time

06) Electrician 0 Full Time

Total Worker = 14

03). VISITORS DETAILS :

Sl. No: Name and designation Sl. No: Name and designation

01) 06)

02) 07)

03) 08)

04) 09)

05) 10)

Page 1 of 3
04). Work Description with Location & Labor Details:
Reference to above subject ,specification and according to contract I would like to draw your attention to the following:
Worker
SL Work Description Picture Location
Details

1 Shuttering Work for Non-shrink Grout Zone-3, 2nd Floor 3

2 Rebar Cleaning Work Zone-5, 6th Floor 6

3 Re-bar fabrication work 5

Page 2 of 3
05). Request for Work Inspection :

Sl. No: Work Details: Work Location: Remarks:

01)
02)
03)
04)
05)

BSPP Engineer comments: Contractor Engineer comments:

The work progress is very slow due to the shortage of Re-bar and Non-shrink grout.
Use safety belt when work at height. Safety railing should be provided at the periphery
of working platform. The contractor should finish all repair works as soon as possible.
All workers should maintain safety measures.

Signature: Signature:
BSPP Engineer Contractor